CN204457791U - A kind ofly meet the interim air channel structure that large-diameter shield first passes through subway station - Google Patents
A kind ofly meet the interim air channel structure that large-diameter shield first passes through subway station Download PDFInfo
- Publication number
- CN204457791U CN204457791U CN201520081190.4U CN201520081190U CN204457791U CN 204457791 U CN204457791 U CN 204457791U CN 201520081190 U CN201520081190 U CN 201520081190U CN 204457791 U CN204457791 U CN 204457791U
- Authority
- CN
- China
- Prior art keywords
- air duct
- shield
- pile
- air channel
- passes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 abstract description 15
- 238000009412 basement excavation Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 4
- 239000002689 soil Substances 0.000 description 4
- 241001023788 Cyttus traversi Species 0.000 description 3
- 230000005641 tunneling Effects 0.000 description 3
- 230000002787 reinforcement Effects 0.000 description 2
- 239000002002 slurry Substances 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
本实用新型涉及一种满足大直径盾构先穿越地铁车站的临时风道结构,其包括竖井、导洞、钻孔灌注桩、桩顶冠梁、风道、盾构井以及风道围护桩;其中,所述导洞水平设置,并和竖井连通;于所述导洞的底部设有所述钻孔灌注桩;所述桩顶冠梁浇筑于钻孔灌注桩的顶部;所述盾构井设置在风道内,并位于桩顶冠梁的下方;所述风道围护桩位于风道的两侧。本实用新型的满足大直径盾构先穿越地铁车站的临时风道结构能较好解决地铁区间隧道和车站施工筹划冲突,盾构可直接穿越车站风道,可以保证地铁区间隧道和车站施工筹划完全相互独立,整个工程筹划以区间隧道为主线,能尽早实现“洞通”的目标。
The utility model relates to a temporary air duct structure that meets the requirement that a large-diameter shield tunnel first passes through a subway station, which includes a vertical shaft, a pilot hole, a bored pile, a crown beam at the top of a pile, an air duct, a shield well and an air duct surrounding protection pile ; Wherein, the pilot hole is arranged horizontally and communicated with the shaft; the bottom of the pilot hole is provided with the bored pile; the pile top crown beam is poured on the top of the bored pile; the shield The well is arranged in the air duct and is located under the crown beam of the pile top; the air duct surrounding protection piles are located on both sides of the air duct. The utility model meets the requirement that the large-diameter shield first passes through the temporary air duct structure of the subway station, which can better solve the construction planning conflict between the tunnel in the subway section and the station. Independent of each other, the entire project planning is based on the interval tunnel as the main line, which can realize the goal of "hole opening" as soon as possible.
Description
【技术领域】【Technical field】
本实用新型涉及一种地铁车站的组成结构,具体涉及一种满足大直径盾构先穿越地铁车站的临时风道结构,属于轨道交通工程技术领域。The utility model relates to a composition structure of a subway station, in particular to a temporary air duct structure for a large-diameter shield to pass through the subway station first, and belongs to the technical field of rail transit engineering.
【背景技术】【Background technique】
地铁区间隧道和车站均采用大直径盾构掘进,一次形成单洞双线隧道,车站在盾构隧道基础上进行扩挖。这种施工方法及工程筹划能较好解决目前常规的地铁工程筹划所遇到的困难。但是采用这种工程筹划方式一般都要求在盾构到达车站前完成车站两端的风道结构施工、加强环梁施工及风道侧壁土体加固后才能具备接收盾构或提供盾构穿越风道的条件。Large-diameter shield tunneling is used for tunnels and stations in the subway section, forming a single-hole and double-track tunnel at one time, and the stations are expanded and excavated on the basis of shield tunnels. This construction method and engineering planning can better solve the difficulties encountered in the current conventional subway engineering planning. However, this kind of project planning method generally requires the completion of the construction of the air duct structure at both ends of the station, the strengthening of the ring beam construction, and the reinforcement of the soil on the side wall of the air duct before the shield machine arrives at the station. conditions of.
然而,风道为暗挖大断面高边墙结构,施工工序繁杂,施工周期长,由于盾构掘进速度快,而车站风道施工受地面拆迁、管线改移等因素制约,在盾构到达前很难满足设计要求的盾构接收与始发条件,盾构只能放慢掘进速度或到站后等待,影响盾构施工效率和“洞通目标”的实现。However, the air duct is an underground excavation large-section high-side wall structure, the construction process is complicated, and the construction period is long. Due to the fast excavation speed of the shield machine, the construction of the air duct of the station is restricted by factors such as ground demolition and pipeline relocation. It is difficult to meet the shield receiving and starting conditions required by the design, and the shield tunneling speed can only be slowed down or waited after arriving at the station, which affects the shield construction efficiency and the realization of the "hole opening goal".
因此,为解决上述技术问题,确有必要提供一种创新的满足大直径盾构先穿越地铁车站的临时风道结构,以克服现有技术中的所述缺陷。Therefore, in order to solve the above technical problems, it is indeed necessary to provide an innovative temporary air duct structure that allows the large-diameter shield to pass through the subway station first, so as to overcome the defects in the prior art.
【实用新型内容】【Content of utility model】
为解决上述问题,本实用新型的目的在于提供一种满足大直径盾构先穿越地铁车站的临时风道结构,其可在大盾构先过站后再建造。In order to solve the above problems, the purpose of this utility model is to provide a temporary air duct structure that meets the needs of large-diameter shields passing through subway stations first, which can be constructed after the large shields pass through the station first.
为实现上述目的,本实用新型采取的技术方案为:一种满足大直径盾构先穿越地铁车站的临时风道结构,其包括竖井、导洞、钻孔灌注桩、桩顶冠梁、风道、盾构井以及风道围护桩;其中,所述导洞水平设置,并和竖井连通;于所述导洞的底部设有所述钻孔灌注桩;所述桩顶冠梁浇筑于钻孔灌注桩的顶部;所述盾构井设置在风道内,并位于桩顶冠梁的下方;所述风道围护桩位于风道的两侧。In order to achieve the above purpose, the technical solution adopted by the utility model is: a temporary air duct structure that meets the needs of large-diameter shield tunnels passing through the subway station first, which includes shafts, pilot holes, bored piles, pile top crown beams, and air ducts. , shield wells and air duct surrounding protection piles; wherein, the pilot tunnel is set horizontally and communicates with the shaft; the bottom of the pilot tunnel is provided with the bored cast-in-place pile; The top of the cast-in-situ pile; the shield well is arranged in the air duct and is located below the crown beam of the pile top; the air duct surrounding protection piles are located on both sides of the air duct.
本实用新型的满足大直径盾构先穿越地铁车站的临时风道结构进一步为:所述钻孔灌注桩的直径为800mm。The temporary air channel structure of the utility model that satisfies the need for the large-diameter shield to pass through the subway station first is as follows: the diameter of the bored pile is 800 mm.
本实用新型的满足大直径盾构先穿越地铁车站的临时风道结构还可为:所述风道围护桩呈等间距的竖直排布。In the present invention, the temporary air duct structure satisfying that the large-diameter shield first passes through the subway station can also be: the air duct enclosing piles are vertically arranged at equal intervals.
与现有技术相比,本实用新型具有如下有益效果:本实用新型的满足大直径盾构先穿越地铁车站的临时风道结构能较好解决地铁区间隧道和车站施工筹划冲突,盾构可直接穿越车站风道,可以保证地铁区间隧道和车站施工筹划完全相互独立,整个工程筹划以区间隧道为主线,能尽早实现“洞通”的目标。Compared with the prior art, the utility model has the following beneficial effects: the utility model meets the requirement that the large-diameter shield first passes through the temporary air duct structure of the subway station, which can better solve the construction planning conflict between the tunnel in the subway section and the station, and the shield can directly Passing through the station air duct can ensure that the subway section tunnel and station construction planning are completely independent of each other. The entire project planning takes the section tunnel as the main line, and can realize the goal of "opening" as soon as possible.
【附图说明】【Description of drawings】
图1是施工本实用新型的步骤1)的施工图。Fig. 1 is the construction drawing of step 1) of constructing the utility model.
图2是施工本实用新型的步骤2)的施工图。Fig. 2 is the construction drawing of step 2) of constructing the utility model.
图3是本实用新型的满足大直径盾构先穿越地铁车站的临时风道结构的结构示意图。Fig. 3 is a structural schematic diagram of the temporary air duct structure of the utility model that satisfies the requirement that the large-diameter shield first passes through the subway station.
【具体实施方式】【Detailed ways】
请参阅说明书附图1所示,本实用新型为一种满足大直径盾构先穿越地铁车站的临时风道结构,其由竖井1、导洞2、钻孔灌注桩3、桩顶冠梁4、风道6、盾构井5以及风道围护桩7等几部分组成。Please refer to the accompanying drawing 1 of the specification. The utility model is a temporary air duct structure that meets the needs of large-diameter shield tunnels passing through subway stations first. , air duct 6, shield shaft 5 and air duct enclosure pile 7 and other parts.
其中,所述导洞2水平设置,并和竖井1连通。于所述导洞2的底部设有所述钻孔灌注桩3。所述钻孔灌注桩3的直径为800mm。Wherein, the pilot tunnel 2 is arranged horizontally and communicates with the vertical shaft 1 . The bored pile 3 is arranged at the bottom of the pilot hole 2 . The diameter of the bored pile 3 is 800mm.
所述桩顶冠梁4浇筑于钻孔灌注桩3的顶部。The pile crown beam 4 is poured on the top of the bored pile 3 .
所述盾构井5设置在风道6内,并位于桩顶冠梁4的下方。The shield well 5 is arranged in the air duct 6 and is located below the pile top crown beam 4 .
所述风道围护桩7位于风道6的两侧,其呈等间距的竖直排布。The air duct surrounding protection piles 7 are located on both sides of the air duct 6 and arranged vertically at equal intervals.
本实用新型的满足大直径盾构先穿越地铁车站的临时风道结构的施工方法如下:The construction method of the utility model that satisfies the large-diameter shield first passing through the temporary air duct structure of the subway station is as follows:
1),如图1所示,以竖井1作为施工通道,在竖井侧壁开马头门,并对马头门部位的土体进行注浆加固,马头门部位的三榀格栅密排。小导洞2采用短台阶法进行开挖,并留核心土,每次开挖步距不大于0.75m,两个小导洞之间应保持不低于5m的距离,每循环开挖前应对拱部土体采用超前小导管进行注浆加固,注浆浆液采用水泥浆,若地层含水,应注水泥水玻璃双液浆;1), as shown in Figure 1, take the shaft 1 as the construction channel, open the horse head gate on the side wall of the shaft, and carry out grouting reinforcement to the soil at the horse head gate, and the three grids at the horse head gate are closely arranged . The small pilot tunnel 2 is excavated by the short step method, and the core soil is left. The step distance of each excavation is not greater than 0.75m. The soil in the arch part is reinforced by grouting with advanced small conduits, and the grouting grout is cement slurry. If the stratum contains water, it should be filled with cement-water glass double-fluid slurry;
2),如图2所示,在导洞内施作钻孔灌注桩3,桩的直径为800mm,但大直径盾构穿越风道部位的导洞内钻孔灌注桩不施工,并在大盾构穿越风道部位的导洞内各增加1根钻孔桩,在小导洞内施作桩顶冠梁4,大直径盾构穿越风道部位的桩顶冠梁尺寸适当加大,并考虑盾构穿越工况的荷载,对冠梁的弯矩、剪力等进行核算;2), as shown in Figure 2, the bored cast-in-place pile 3 is constructed in the pilot tunnel, and the diameter of the pile is 800mm, but the bored cast-in-place pile is not constructed in the pilot tunnel where the large-diameter shield crosses the air duct, and the bored pile is not constructed in the large-diameter shield tunnel. One drilled pile is added in each guide hole where the shield machine passes through the air duct, and the pile crown beam 4 is constructed in the small guide hole. Consider the load of the shield tunneling condition, and calculate the bending moment and shear force of the crown beam;
3),如图3所示,在冠梁强度达到设计强度后,大盾构直接穿越风道6后形成盾构井5;在大盾构穿越后再进行风道6土方开挖及风道围护桩7施工。3), as shown in Figure 3, after the strength of the crown beam reaches the design strength, the large shield directly passes through the air duct 6 to form the shield well 5; after the large shield passes through, the earthwork excavation of the air duct 6 and the air duct Construction of enclosure pile 7.
以上的具体实施方式仅为本创作的较佳实施例,并不用以限制本创作,凡在本创作的精神及原则之内所做的任何修改、等同替换、改进等,均应包含在本创作的保护范围之内。The specific implementation above is only a preferred embodiment of this creation, and is not intended to limit this creation. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of this creation should be included in this creation. within the scope of protection.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520081190.4U CN204457791U (en) | 2015-02-04 | 2015-02-04 | A kind ofly meet the interim air channel structure that large-diameter shield first passes through subway station |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520081190.4U CN204457791U (en) | 2015-02-04 | 2015-02-04 | A kind ofly meet the interim air channel structure that large-diameter shield first passes through subway station |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204457791U true CN204457791U (en) | 2015-07-08 |
Family
ID=53664693
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520081190.4U Expired - Fee Related CN204457791U (en) | 2015-02-04 | 2015-02-04 | A kind ofly meet the interim air channel structure that large-diameter shield first passes through subway station |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204457791U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107191198A (en) * | 2017-04-05 | 2017-09-22 | 中铁二十二局哈尔滨铁路建设集团有限责任公司 | The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes |
| CN108868814A (en) * | 2018-08-24 | 2018-11-23 | 中铁西安勘察设计研究院有限责任公司 | Collapsible loess combination land pebble stratum tunneling air duct connects the ventilating shaft of shield tunnel |
| CN113006813A (en) * | 2020-04-01 | 2021-06-22 | 中铁十四局集团有限公司 | Layout and mechanized rapid construction method for fusing subway station and section in single section |
-
2015
- 2015-02-04 CN CN201520081190.4U patent/CN204457791U/en not_active Expired - Fee Related
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107191198A (en) * | 2017-04-05 | 2017-09-22 | 中铁二十二局哈尔滨铁路建设集团有限责任公司 | The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes |
| CN108868814A (en) * | 2018-08-24 | 2018-11-23 | 中铁西安勘察设计研究院有限责任公司 | Collapsible loess combination land pebble stratum tunneling air duct connects the ventilating shaft of shield tunnel |
| CN108868814B (en) * | 2018-08-24 | 2023-12-29 | 中铁西安勘察设计研究院有限责任公司 | Air shaft of underground excavation air duct shield tunnel of collapsible loess combined pebble soil stratum |
| CN113006813A (en) * | 2020-04-01 | 2021-06-22 | 中铁十四局集团有限公司 | Layout and mechanized rapid construction method for fusing subway station and section in single section |
| CN113006813B (en) * | 2020-04-01 | 2022-07-29 | 中铁十四局集团有限公司 | Layout and mechanized rapid construction method for fusing subway station and section in single section |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105041349B (en) | A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel | |
| CN105003272B (en) | Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways | |
| CN105064397B (en) | Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation | |
| CN101963060B (en) | Tunnel construction method based on steel pipe arch rib support structure | |
| CN103452561B (en) | Vertical in-tunnel construction method of multilayer transverse channel of underground excavation station of metro, and construction method on east side and west side | |
| CN104632235A (en) | Method for expanding excavation of large-diameter shield tunnel for subway station construction through pile arch wall support | |
| CN105822310B (en) | A fast and low-risk subway station tunnel construction method | |
| CN104653188B (en) | A kind of large-diameter shield that arranges in tunneling air channel receives and the method for starting well | |
| CN104295301B (en) | The construction method in a kind of shallow buried covered excavation cracked rock mass subway tunnel crosspoint | |
| CN105298501A (en) | Construction method for auxiliary air duct structure of underground excavation station | |
| CN104712343B (en) | A kind of big shield is built the shield of air channel structure again and is missed the stop method after first missing the stop | |
| CN101086209A (en) | Shield tunneling and shallow tunneling combined construction method for building underground station | |
| CN106703814A (en) | Mined metro station hole pile construction method | |
| CN204457789U (en) | A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build | |
| CN103114857A (en) | Shield tunnel construction method | |
| CN105089670B (en) | Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel | |
| CN106223976B (en) | Shield well end steel tube shed reinforcement system based on agent structure and its construction method | |
| CN204457792U (en) | A kind ofly dig large diameter shield tunnel with many pilot tunnel methods and the subway station of building | |
| CN107975383B (en) | Construction method for excavation and support of T-shaped intersection in underground cavern | |
| CN103993885A (en) | Construction method for underground excavation tunnel side-direction hole opening supporting system | |
| CN103867209A (en) | Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro | |
| CN204457791U (en) | A kind ofly meet the interim air channel structure that large-diameter shield first passes through subway station | |
| CN205422733U (en) | High side wall of large -span side hole is detained and is encircleed substation rank subway station supporting construction | |
| CN104047607A (en) | Construction method for lifting out shield tunneling machine under condition of envelop enclosure | |
| CN108222945B (en) | Construction method for excavating underground excavation station of subway with super-large section by using main and auxiliary layered tunnels |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150708 Termination date: 20160204 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |