CN107178391A - A kind of construction method of armored concrete fire dam and application - Google Patents
A kind of construction method of armored concrete fire dam and application Download PDFInfo
- Publication number
- CN107178391A CN107178391A CN201710446967.6A CN201710446967A CN107178391A CN 107178391 A CN107178391 A CN 107178391A CN 201710446967 A CN201710446967 A CN 201710446967A CN 107178391 A CN107178391 A CN 107178391A
- Authority
- CN
- China
- Prior art keywords
- formwork
- vertical
- holes
- sides
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 35
- 239000004567 concrete Substances 0.000 title claims description 7
- 238000009415 formwork Methods 0.000 claims abstract description 103
- 230000002787 reinforcement Effects 0.000 claims abstract description 27
- 238000000034 method Methods 0.000 claims abstract description 17
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 17
- 239000011464 hollow brick Substances 0.000 claims abstract description 15
- 239000004568 cement Substances 0.000 claims abstract description 12
- 239000011449 brick Substances 0.000 claims abstract description 11
- 238000005065 mining Methods 0.000 claims abstract description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 56
- 239000010959 steel Substances 0.000 claims description 56
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 50
- 229910052742 iron Inorganic materials 0.000 claims description 25
- 238000005429 filling process Methods 0.000 claims description 6
- 239000002002 slurry Substances 0.000 claims description 6
- 239000004744 fabric Substances 0.000 claims description 5
- 235000008331 Pinus X rigitaeda Nutrition 0.000 claims description 3
- 235000011613 Pinus brutia Nutrition 0.000 claims description 3
- 241000018646 Pinus brutia Species 0.000 claims description 3
- 239000002023 wood Substances 0.000 claims description 3
- 239000004566 building material Substances 0.000 abstract description 2
- 239000002994 raw material Substances 0.000 abstract description 2
- 239000000463 material Substances 0.000 description 5
- 238000005457 optimization Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 239000011398 Portland cement Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000003912 environmental pollution Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000003756 stirring Methods 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/02—Supporting means, e.g. shuttering, for filling-up materials
- E21F15/04—Stowing mats; Goaf wire netting; Partition walls
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明公开了一种钢筋混凝土密闭墙的施工方法及其应用,其包括打立模孔、布筋孔;配筋;立模板;装排水管;砌水泥砖墙、抹浆;设置墙撑等步骤,可用于下向水平分层进路式胶结充填采矿法采空区充填时密闭墙的构筑。本发明中构筑密闭墙的原材料为常用建材,且不需要特殊加工,施工工艺简单,对施工人员的专业技能要求不高,可操作性强,所使用的材料运输到现场,2名工人在8小时内可完成构筑密闭墙的施工(不包括空心砖筑砌封顶),解决了目前密闭墙施工时费力费时,安全可靠性差,经济成本高,不能快速有效地遏制突发事故蔓延的问题。
The invention discloses a construction method and application of a reinforced concrete airtight wall, which comprises the steps of making vertical formwork holes and laying reinforcement holes; reinforcement; vertical formwork; installing drainage pipes; building cement brick walls and plastering; setting wall supports, etc. The method can be used for the construction of the airtight wall when the goaf is filled in the downward horizontal layered approach type cemented filling mining method. The raw materials for constructing the airtight wall in the present invention are commonly used building materials, and no special processing is required, the construction process is simple, the professional skills of the construction personnel are not high, and the operability is strong. The construction of the airtight wall can be completed within hours (excluding the hollow brick roofing), which solves the current problems of laborious and time-consuming construction of the airtight wall, poor safety and reliability, high economic cost, and the inability to quickly and effectively contain the spread of sudden accidents.
Description
技术领域technical field
本发明涉及矿井下安全施工技术领域,尤其涉及一种钢筋混凝土密闭墙的施工方法及应用。The invention relates to the technical field of mine safety construction, in particular to a construction method and application of a reinforced concrete airtight wall.
背景技术Background technique
充填采矿方法因作业安全、矿石贫损小、可延缓甚至防止地表沉降及深部岩爆等工程地质灾害等优点,在矿山生产实际中应用越来越多。而在充填采矿工艺中,充填挡墙的构筑是充填前必须完成的一项重要准备工作。充填挡墙施工质量的好坏,直接影响充填作业的效率、成本和充填质量。部分矿山因挡墙构筑不当,充填过程中经常出现过跑浆、漏砂等问题,严重的出现挡墙整体垮塌等事故,导致井下环境污染,漏沙处理困难等问题。也有部分矿山为了提高充填挡墙安全性,加大挡墙的厚度,导致充填材料消耗加大,构筑时间加长,进而导致采充作业效率低下。因此,简化充填挡墙的构筑工艺,设计合适的挡墙结构及尺寸,可降低矿山充填成本、提高采充效率和充填质量,进而提高矿山生产的安全性及经济效益。Due to the advantages of safe operation, small ore loss, delay or even prevention of engineering geological disasters such as surface subsidence and deep rockburst, filling mining method is more and more used in actual mine production. In the filling mining process, the construction of the filling retaining wall is an important preparatory work that must be completed before filling. The construction quality of filling retaining wall directly affects the efficiency, cost and filling quality of filling operation. Due to improper construction of the retaining wall in some mines, problems such as slurry running and sand leakage often occurred during the filling process, and serious accidents such as the overall collapse of the retaining wall occurred, resulting in underground environmental pollution and difficulties in handling sand leakage. In order to improve the safety of the filling retaining wall, some mines increase the thickness of the retaining wall, resulting in increased consumption of filling materials and longer construction time, which in turn leads to low efficiency of mining and filling operations. Therefore, simplifying the construction process of the filling retaining wall and designing a suitable retaining wall structure and size can reduce mine filling costs, improve mining and filling efficiency and filling quality, and then improve the safety and economic benefits of mine production.
发明内容Contents of the invention
本发明的目的在于提供一种施工简单、高效的钢筋混凝土密闭墙施工方法,以解决上述现有技术中的问题。The object of the present invention is to provide a simple and efficient construction method for reinforced concrete airtight walls, so as to solve the above-mentioned problems in the prior art.
为解决上述问题,本发明采用如下技术方案:In order to solve the above problems, the present invention adopts the following technical solutions:
本发明提供了一种钢筋混凝土密闭墙的施工方法,包括如下步骤:The invention provides a construction method for a reinforced concrete airtight wall, comprising the steps of:
步骤1:打立模孔、布筋孔Step 1: Drill holes for vertical formwork and fabric reinforcement
在要浇灌密闭墙位置的两侧边帮钻立模孔,每侧从下往上分为多排,每排两个同平面的立模孔,并在竖直方向上形成两列孔,最下方一排距浇灌位置底板0.3m,立模孔的上下间距为0.9-1.1m,在边帮两侧的两列立模孔中间位置布置筋孔,两侧由下至上均设置等间距60-80cm的筋孔,且最下方筋孔距浇灌位置底板0.3m,其中所述立模孔孔深为50-70cm,筋孔孔深为70-90cm;Drill vertical formwork holes on both sides of the airtight wall to be poured, each side is divided into multiple rows from bottom to top, each row has two vertical formwork holes on the same plane, and forms two columns of holes in the vertical direction, finally The lower row is 0.3m away from the bottom plate of the pouring position, the vertical distance between the vertical formwork holes is 0.9-1.1m, and the rib holes are arranged in the middle of the two rows of vertical formwork holes on both sides of the side, and the two sides are set at equal intervals of 60- 80cm reinforcement hole, and the bottommost reinforcement hole is 0.3m away from the bottom plate of the pouring position, wherein the hole depth of the vertical formwork is 50-70cm, and the depth of the reinforcement hole is 70-90cm;
步骤2:配筋Step 2: Reinforcement
在两侧边帮的筋孔内均插入螺纹钢,相交部分用铁丝固定,接着按间距25-35cm在螺纹钢一侧等间距布置竖向钢筋,并用铁丝将钢筋与螺纹钢固定;Insert rebars into the reinforcement holes on both side sides, and fix the intersecting parts with iron wires, then arrange vertical rebars at equal intervals on one side of rebars at intervals of 25-35 cm, and fix the rebars and rebars with iron wires;
步骤3:立模板Step 3: Formwork
在边帮两边的底部第一和第二排的立模孔内插入螺纹钢,并在两侧边帮的螺纹钢上套长空心钢管,同排两根长空心钢管相交处用铁丝固定好,之后在长空心钢管内侧每隔60-70cm竖向固定长空心钢管形成立模架,接着在立模架内部将模板由下往上横着叠放至第二排立模孔高处,在模板内侧每隔75-85cm等间距竖向设置钢筋,并将钢筋用铁丝固定在长空心钢管上压紧固定模板,将搅拌好的混凝土注入模板内,铺平压实至模板所铺设的高度,然后将上面一排立模孔内同样插入螺纹钢和长空心钢管并用铁丝固定好,继续叠加模板并浇注混凝土直至距离顶板55-65cm处,完成立模;Insert threaded steel into the first and second rows of vertical formwork holes at the bottom of both sides of the sides, and put long hollow steel pipes on the rebars of both side sides, and fix the intersection of two long hollow steel pipes in the same row with iron wire. Then vertically fix the long hollow steel pipes at intervals of 60-70cm inside the long hollow steel pipes to form a vertical formwork frame, and then stack the formwork horizontally from bottom to top inside the vertical formwork frame to the height of the second row of vertical formwork holes. Install steel bars vertically at equal intervals of 75-85cm, and fix the steel bars on long hollow steel pipes with iron wires to press and fix the formwork, pour the mixed concrete into the formwork, pave and compact it to the height of the formwork, and then place Insert threaded steel and long hollow steel pipes into the upper row of vertical formwork holes and fix them with iron wires, continue to stack the formwork and pour concrete until the distance from the top plate is 55-65cm, and complete the vertical formwork;
步骤4:排水管Step 4: Drain Pipe
所述立模板的过程中在底板中部设置一排水管,在距离底板1.7-1.9m处设置第二根排水管,在距底板2.6-2.8m处设置第三根排水管,而后每隔18-22cm竖直间距埋设一根排水管;In the process of erecting the formwork, a drain pipe is set in the middle of the bottom plate, a second drain pipe is set at a distance of 1.7-1.9m from the bottom plate, a third drain pipe is set at a distance of 2.6-2.8m from the bottom plate, and then every 18- A drainage pipe is buried at a vertical interval of 22cm;
步骤5:砌水泥砖墙、抹浆Step 5: Laying cement brick walls and plastering
拆除模板后砌水泥砖墙,并用空心砖筑砌封顶,中间预留观察孔;空心砖墙面要抹浆,保证充填过程不跑浆;After the formwork is removed, cement brick walls are built, and hollow bricks are used to build the roof, and observation holes are reserved in the middle; the hollow brick walls should be plastered to ensure that the filling process does not run out of slurry;
步骤6:设置墙撑Step 6: Setting Up Wall Braces
取墙撑六根,竖向等距设置三根竖撑,中间横向放置一根横撑,并使所述横撑两边抵住两侧竖撑,最后在两侧横撑和竖撑的相交位置各打一斜撑。Take six wall braces, set three vertical braces vertically and equidistantly, place a horizontal brace in the middle, and make the two sides of the horizontal brace against the vertical braces on both sides, and finally place a punch at the intersection of the horizontal braces and vertical braces on both sides. A diagonal brace.
作为本发明对上述技术方案的优选,所述步骤1中立模孔由下至上分为三排,孔深60cm,筋孔孔深80cm,立模孔上下孔间距为1m,两列立模孔水平间距为40-60cm,每侧筋孔由下至上设有五个,且上下孔间距为70cm。As the present invention's optimization of the above-mentioned technical scheme, in the step 1, the vertical mold holes are divided into three rows from bottom to top, the hole depth is 60cm, the rib hole is 80cm deep, the upper and lower hole spacing of the vertical mold holes is 1m, and the two columns of vertical mold holes are horizontal The spacing is 40-60cm, and there are five rib holes on each side from bottom to top, and the spacing between the upper and lower holes is 70cm.
作为本发明对上述技术方案的优选,所述步骤2中模板由两边帮处向中部铺设,使得模板与边帮的接合处无间隙,如果模板中部存在间隙,则在间隙处铺设竖向模板填充。As the present invention's optimization of the above technical solution, in the step 2, the formwork is laid from the sides to the middle, so that there is no gap at the joint between the formwork and the sideways. If there is a gap in the middle of the formwork, a vertical formwork is laid at the gap to fill the gap. .
作为本发明对上述技术方案的优选,所述步骤2中立模完毕后,养护36h。As the present invention's optimization of the above-mentioned technical solution, in the step 2, after the mold is set up, it is cured for 36 hours.
作为本发明对上述方案的优选,所述步骤6中墙撑为干松木。As a preferred embodiment of the above solution in the present invention, the wall support in step 6 is dry pine wood.
本发明还提供了上述钢筋混凝土密闭墙的施工方法的应用,其用于下向水平分层进路式胶结充填采矿法采空区充填时密闭墙的构筑。The present invention also provides the application of the construction method of the reinforced concrete airtight wall, which is used for the construction of the airtight wall when filling the goaf with the downward horizontal layering approach type cemented filling mining method.
本发明的有益效果在于:The beneficial effects of the present invention are:
1)构筑密闭墙的原材料为常用建材,且不需要特殊加工,本方案所用到的钢筋、水泥、铁丝、空心砖及木头等是矿山采矿作业及支护过程中普遍使用的材料,其来源广泛,成本相对较低且可有效控制;1) The raw materials for constructing the airtight wall are commonly used building materials and do not require special processing. The steel bars, cement, iron wire, hollow bricks and wood used in this scheme are materials commonly used in mine mining operations and support processes, and their sources are extensive. The cost is relatively low and can be effectively controlled;
(2)施工工艺简单,对施工人员的专业技能要求不高,除了钻立模孔及布筋孔需要专业的凿岩机操作工外,其他步骤普通工人只要按作业要求操作也能胜任;(2) The construction process is simple, and the professional skills of the construction personnel are not high. In addition to drilling vertical formwork holes and reinforcement holes, professional rock drill operators are required, and ordinary workers can also perform other steps as long as they operate according to the job requirements;
(3)所需要的施工人员少,效率高,只要立模孔及筋孔预先打好,所使用的材料运输到现场,2名工人在8小时内可完成构筑密闭墙的施工(不包括空心砖筑砌封顶)。(3) Less construction workers are required and the efficiency is high. As long as the vertical formwork holes and reinforcement holes are pre-drilled, and the materials used are transported to the site, 2 workers can complete the construction of the closed wall within 8 hours (excluding hollow bricks) build roof).
(4)可操作性强,不需要特殊的机械施工设备,而且当空区断面的形状及尺寸发生变化时,通过适当调整施工工艺参数,上述使用的施工方案和材料同样可用。(4) Strong operability, no special mechanical construction equipment is required, and when the shape and size of the void section change, the construction scheme and materials used above can also be used by properly adjusting the construction process parameters.
附图说明Description of drawings
图1为实施例1中所述钢筋混凝土密闭墙的立模架结构示意图;Fig. 1 is the vertical formwork frame structural representation of reinforced concrete airtight wall described in embodiment 1;
图2为实施例1所述钢筋混凝土密闭墙的截面布筋示意图;Fig. 2 is the cross-sectional reinforcement schematic diagram of the reinforced concrete airtight wall described in embodiment 1;
图3为实施例1所述钢筋混凝土密闭墙的墙撑结构示意图;Fig. 3 is the wall support structure schematic diagram of the reinforced concrete airtight wall described in embodiment 1;
其中,1—立模孔,2—螺纹钢,3—长空心钢管,4—钢筋,5—边帮,6—筋孔,7—排水管,8—混凝土,9—空心砖,10—竖撑,11—横撑,12—斜撑。Among them, 1—vertical hole, 2—rebar, 3—long hollow steel pipe, 4—steel bar, 5—side support, 6—reinforcing hole, 7—drainage pipe, 8—concrete, 9—hollow brick, 10—vertical support , 11—horizontal brace, 12—diagonal brace.
具体实施方式detailed description
为使本发明实现的技术手段、创作特征、达成目的与功效易于明白了解,下面结合具体实施方式,进一步阐述本发明。In order to make the technical means, creative features, goals and effects achieved by the present invention easy to understand, the present invention will be further described below in conjunction with specific embodiments.
实施例中所用的材料规格为:模板(长2m,宽10-20cm,厚2.5cm及5cm若干)、直径28mm的螺纹钢(1.5m、3m)、直径12mm钢筋(3m)、2寸的长空心钢管(3m、3.5m)、8号铁丝(粗)、14号铁丝(细)、规格400mm×200mm×200mm空心砖若干、3包42.5#普通硅酸盐水泥、干松木墙撑6根(长4m直径15cm-30cm)The material specifications used in the embodiment are: formwork (long 2m, wide 10-20cm, thick 2.5cm and 5cm some), diameter 28mm rebar (1.5m, 3m), diameter 12mm steel bar (3m), 2 cun long Hollow steel pipe (3m, 3.5m), No. 8 iron wire (coarse), No. 14 iron wire (thin), several hollow bricks with specifications of 400mm×200mm×200mm, 3 packs of 42.5# ordinary Portland cement, 6 dry pine wall supports (long 4m diameter 15cm-30cm)
实施例1Example 1
一种钢筋混凝土密闭墙的施工方法,其包括如下步骤:A construction method for a reinforced concrete airtight wall, comprising the steps of:
步骤1:打立模孔1、布筋孔6Step 1: Drill vertical formwork hole 1, fabric reinforcement hole 6
如图1及图2所示,在要浇灌密闭墙位置的两侧边帮5钻立模孔1,每侧从下往上分为三排,每排两个同平面的立模孔1,并在竖直方向上形成两列孔,两列立模孔1的水平间距取50cm,最下方一排距浇灌位置底板0.3m,每排立模孔1的上下间距为1m,在边帮5两侧的两列立模孔1中间位置布置筋孔6,两侧由下至上均设置等间距为70cm的五个筋孔4,且最下方筋孔6距浇灌位置底板0.3m,且所述立模孔1孔深为60cm,筋孔6孔深为80cm;As shown in Fig. 1 and Fig. 2, the vertical mold holes 1 are drilled on the side walls 5 on both sides of the airtight wall to be poured, and each side is divided into three rows from bottom to top, and each row has two vertical mold holes 1 on the same plane. And form two rows of holes in the vertical direction, the horizontal distance between the two rows of vertical mold holes 1 is 50cm, the bottom row is 0.3m away from the bottom plate of the pouring position, and the vertical distance between each row of vertical mold holes 1 is 1m. Rib holes 6 are arranged in the middle of the two rows of vertical formwork holes 1 on both sides, and five rib holes 4 with an equal distance of 70 cm are arranged on both sides from bottom to top, and the bottom rib holes 6 are 0.3m away from the bottom plate of the pouring position, and the The depth of hole 1 of vertical formwork is 60cm, and the depth of hole 6 of rib is 80cm;
步骤2:配筋Step 2: Reinforcement
如图2在两侧边帮5的筋孔6内均插入3m的螺纹钢2,相交部分用8号铁丝固定,接着按间距30cm在螺纹钢2一侧等间距竖向布置钢筋4,并用8号铁丝将钢筋4与螺纹钢2固定;As shown in Figure 2, 3m rebar 2 is inserted in the rib holes 6 of both side sides 5, and the intersecting part is fixed with No. Steel bar 4 and threaded steel 2 are fixed by No. 1 iron wire;
步骤3:立模板Step 3: Formwork
在边帮5两边的底部第一和第二排的立模孔1内插入1.5m的螺纹钢2,并在两侧边帮5的螺纹钢2上套3m的长空心钢管3,同排两根长空心钢管3相交处用铁丝固定好,之后在3m长空心钢管3内侧每隔65cm竖向固定3.5m的长空心钢管3形成立模架,接着在立模架内部将模板由下往上横着叠放至第二排立模孔1高处,在模板内侧每隔80cm等间距竖向设置钢筋4,并将钢筋4用8号铁丝固定在长空心钢管3上压紧固定模板,将搅拌好的混凝土10注入模板内,铺平压实至模板所铺设的高度,然后将上面一排立模孔1内同样插入螺纹钢2和长空心钢管3并用8号铁丝固定好,继续叠加模板直至距离顶板60cm处,完成立模;Insert the threaded steel 2 of 1.5m in the bottom first and second rows of vertical mold holes 1 on both sides of the side rail 5, and cover the long hollow steel pipe 3 of 3m on the threaded steel 2 of the side rails 5 on both sides. The intersections of the root-length hollow steel pipes 3 are fixed with iron wires, and then 3.5m long hollow steel pipes 3 are vertically fixed at intervals of 65cm inside the 3m-long hollow steel pipes 3 to form a formwork frame, and then the formwork is placed inside the formwork frame from bottom to top Stack horizontally to the height of the second row of vertical formwork holes 1, set steel bars 4 vertically at equal intervals of 80cm inside the formwork, and fix the steel bars 4 on the long hollow steel pipe 3 with No. 8 iron wire to press and fix the formwork, and stir The good concrete 10 is poured into the formwork, paved and compacted to the height of the formwork, and then the upper row of vertical formwork holes 1 are also inserted into the threaded steel 2 and the long hollow steel pipe 3 and fixed with No. 8 iron wires, and the formwork is continued until At a distance of 60cm from the top plate, the vertical mold is completed;
步骤4:排水管Step 4: Drain Pipe
所述立模板的过程中在底板中部设置一排水管7,在距离底板1.8m处设置第二根排水管7,在距底板2.7m处设置第三根排水管7,而后每隔20cm竖直间距埋设一根排水管7;In the process of erecting the formwork, a drainpipe 7 is set in the middle of the bottom plate, the second drainpipe 7 is set at 1.8m from the bottom plate, the third drainpipe 7 is set at 2.7m from the bottom plate, and then every 20cm vertical Buried a drainage pipe 7 at intervals;
步骤5:砌水泥砖墙、抹浆Step 5: Laying cement brick walls and plastering
拆除模板后砌水泥砖墙,并用空心砖9筑砌封顶,中间预留观察孔;空心砖墙面要抹浆,保证充填过程不跑浆;After removing the formwork, build a cement brick wall, and use hollow bricks 9 to build and seal the roof, and reserve an observation hole in the middle; the hollow brick wall surface should be plastered to ensure that the filling process does not run out of slurry;
步骤6:设置墙撑Step 6: Setting Up Wall Braces
如图3所示取墙撑六根,竖向等距设置三根竖撑10,中间横向放置一根横撑11,并使所述横撑11两边抵住两侧竖撑10,最后在两侧横撑11和竖撑10的相交位置各打一斜撑12。As shown in Figure 3, take six wall braces, set three vertical braces 10 vertically and equidistantly, place a horizontal brace 11 horizontally in the middle, and make the two sides of the horizontal brace 11 resist the vertical braces 10 on both sides, and finally place a horizontal brace 11 on both sides. The intersecting position of support 11 and vertical support 10 makes a diagonal support 12 respectively.
实施例2Example 2
一种钢筋混凝土密闭墙的施工方法,其包括如下步骤:A construction method for a reinforced concrete airtight wall, comprising the steps of:
步骤1:打立模孔、布筋孔Step 1: Drill holes for vertical formwork and fabric reinforcement
在要浇灌密闭墙位置的两侧边帮钻立模孔,每侧从下往上分为三排,每排两个同平面的立模孔,并在竖直方向上形成两列孔,两列立模孔的水平间距取40cm,最下方一排距浇灌位置底板0.3m,每排立模孔的上下间距为0.9m,在边帮两侧的两列立模孔中间位置布置筋孔,两侧由下至上均设置等间距为60cm的五个筋孔,且最下方筋孔距浇灌位置底板0.3m,且所述立模孔孔深为50cm,筋孔孔深为70cm;Drill vertical formwork holes on both sides of the airtight wall to be poured, each side is divided into three rows from bottom to top, each row has two vertical formwork holes on the same plane, and forms two columns of holes in the vertical direction, two The horizontal distance between the vertical formwork holes in a row is 40cm, and the bottom row is 0.3m away from the bottom plate of the pouring position. Five rib holes with an equal distance of 60cm are set on both sides from bottom to top, and the bottom rib hole is 0.3m away from the bottom plate of the pouring position, and the hole depth of the vertical formwork is 50cm, and the depth of the hole hole is 70cm;
步骤2:配筋Step 2: Reinforcement
在两侧边帮的筋孔内均插入3m的螺纹钢,相交部分用8号铁丝固定,接着按间距25cm在螺纹钢一侧等间距竖向布置钢筋,并用8号铁丝将钢筋与螺纹钢固定;Insert 3m of rebar into the reinforcement holes of both side sides, fix the intersecting part with No. 8 iron wire, then arrange the rebar vertically at equal intervals on one side of the rebar at a distance of 25cm, and fix the rebar and rebar with No. 8 iron wire ;
步骤3:立模板Step 3: Formwork
在边帮两边的底部第一和第二排的立模孔内插入1.5m的螺纹钢,并在两侧边帮的螺纹钢上套3m的长空心钢管,同排两根长空心钢管相交处用铁丝固定好,之后在3m的长空心钢管内侧每隔60cm竖向固定3.5m的长空心钢管形成立模架,接着在立模架内部将模板由下往上横着叠放至第二排立模孔高处,在模板内侧每隔75cm等间距竖向设置钢筋,并将钢筋用8号铁丝固定在长空心钢管上压紧固定模板,将搅拌好的混凝土注入模板内,铺平压实至模板所铺设的高度,然后将上面一排立模孔内同样插入螺纹钢和长空心钢管并用8号铁丝固定好,继续叠加模板直至距离顶板55cm处,完成立模;Insert 1.5m of rebar into the first and second rows of vertical mold holes at the bottom of both sides of the sides, and put 3m long hollow steel pipes on the rebars of both side sides, at the intersection of two long hollow steel pipes in the same row Fix it with iron wire, and then vertically fix 3.5m long hollow steel pipes every 60cm inside the 3m long hollow steel pipes to form the vertical formwork frame, and then stack the formwork horizontally from bottom to top to the second row of vertical formwork frames inside the vertical formwork frame. At the height of the mold hole, vertically set steel bars at equal intervals of 75cm inside the formwork, and fix the steel bars on the long hollow steel pipe with No. Then insert threaded steel and long hollow steel pipes into the upper row of vertical formwork holes and fix them with No. 8 iron wire. Continue to stack the formwork until it is 55cm away from the top plate to complete the vertical formwork;
步骤4:排水管Step 4: Drain Pipe
所述立模板的过程中在底板中部设置一排水管,在距离底板1.7m处设置第二根排水管,在距底板2.6m处设置第三根排水管,而后每隔18cm竖直间距埋设一根排水管;In the process of erecting the formwork, a drain pipe is set in the middle of the base plate, a second drain pipe is set at a distance of 1.7m from the base plate, a third drain pipe is set at a distance of 2.6m from the base plate, and then a drain pipe is buried every 18cm vertical interval. root drainage pipe;
步骤5:砌水泥砖墙、抹浆Step 5: Laying cement brick walls and plastering
拆除模板后砌水泥砖墙,并用空心砖筑砌封顶,中间预留观察孔;空心砖墙面要抹浆,保证充填过程不跑浆;After the formwork is removed, cement brick walls are built, and hollow bricks are used to build the roof, and observation holes are reserved in the middle; the hollow brick walls should be plastered to ensure that the filling process does not run out of slurry;
步骤6:设置墙撑Step 6: Setting Up Wall Braces
取墙撑六根,竖向等距设置三根竖撑,中间横向放置一根横撑,并使所述横撑两边抵住两侧竖撑,最后在两侧横撑和竖撑的相交位置各打一斜撑。Take six wall braces, set three vertical braces vertically and equidistantly, place a horizontal brace in the middle, and make the two sides of the horizontal brace against the vertical braces on both sides, and finally place a punch at the intersection of the horizontal braces and vertical braces on both sides. A diagonal brace.
实施例3Example 3
一种钢筋混凝土密闭墙的施工方法,其包括如下步骤:A construction method for a reinforced concrete airtight wall, comprising the steps of:
步骤1:打立模孔、布筋孔Step 1: Drill holes for vertical formwork and fabric reinforcement
在要浇灌密闭墙位置的两侧边帮钻立模孔,每侧从下往上分为三排,每排两个同平面的立模孔,并在竖直方向上形成两列孔,两列立模孔的水平间距取60cm,最下方一排距浇灌位置底板0.3m,每排立模孔的上下间距为1.1m,在边帮两侧的两列立模孔中间位置布置筋孔,两侧由下至上均设置等间距为80cm的五个筋孔,且最下方筋孔距浇灌位置底板0.3m,且所述立模孔孔深为70cm,筋孔孔深为90cm;Drill vertical formwork holes on both sides of the airtight wall to be poured, each side is divided into three rows from bottom to top, each row has two vertical formwork holes on the same plane, and forms two columns of holes in the vertical direction, two The horizontal distance between the vertical formwork holes in the row is 60cm, the bottom row is 0.3m away from the bottom plate of the pouring position, the vertical distance between each row of vertical formwork holes is 1.1m, and the reinforcement holes are arranged in the middle of the two columns of vertical formwork holes on both sides of the side. Five rib holes with an equal distance of 80cm are set on both sides from bottom to top, and the bottom rib hole is 0.3m away from the bottom plate of the pouring position, and the hole depth of the vertical formwork is 70cm, and the depth of the hole hole is 90cm;
步骤2:配筋Step 2: Reinforcement
在两侧边帮的筋孔内均插入3m的螺纹钢,相交部分用8号铁丝固定,接着按间距35cm在螺纹钢一侧等间距竖向布置钢筋,并用8号铁丝将钢筋与螺纹钢固定;Insert 3m of rebar into the rib holes on both side sides, fix the intersecting part with No. 8 iron wire, then arrange the rebar vertically at equal intervals on one side of the rebar at a distance of 35cm, and fix the rebar and rebar with No. 8 iron wire ;
步骤3:立模板Step 3: Formwork
在边帮两边的底部第一和第二排的立模孔内插入1.5m的螺纹钢,并在两侧边帮的螺纹钢上套3m的长空心钢管,同排两根长空心钢管相交处用铁丝固定好,之后在3m的长空心钢管内侧每隔70cm竖向固定3.5m的长空心钢管形成立模架,接着在立模架内部将模板由下往上横着叠放至第二排立模孔高处,在模板内侧每隔85cm等间距竖向设置钢筋,并将钢筋用8号铁丝固定在长空心钢管上压紧固定模板,将搅拌好的混凝土注入模板内,铺平压实至模板所铺设的高度,然后将上面一排立模孔内同样插入螺纹钢和长空心钢管并用8号铁丝固定好,继续叠加模板直至距离顶板65cm处,完成立模;Insert 1.5m of rebar into the first and second rows of vertical mold holes at the bottom of both sides of the sides, and put 3m long hollow steel pipes on the rebars of both side sides, at the intersection of two long hollow steel pipes in the same row Fix it with iron wire, and then vertically fix 3.5m long hollow steel pipes at intervals of 70cm inside the 3m long hollow steel pipes to form the vertical formwork frame, and then stack the formwork horizontally from bottom to top to the second row of vertical formwork frames inside the vertical formwork frame. At the height of the mold hole, vertically set steel bars at equal intervals of 85cm inside the formwork, and fix the steel bars on the long hollow steel pipe with No. Then insert threaded steel and long hollow steel pipes into the upper row of vertical mold holes and fix them with No. 8 iron wire. Continue to stack the template until it is 65cm away from the top plate to complete the vertical mold;
步骤4:排水管Step 4: Drain Pipe
所述立模板的过程中在底板中部设置一排水管,在距离底板1.9m处设置第二根排水管,在距底板2.8m处设置第三根排水管,而后每隔22cm竖直间距埋设一根排水管;In the process of erecting the formwork, a drainage pipe is set in the middle of the bottom plate, a second drainage pipe is set at a distance of 1.9m from the bottom plate, a third drainage pipe is set at a distance of 2.8m from the bottom plate, and then a drainage pipe is buried every 22cm vertical interval. root drainage pipe;
步骤5:砌水泥砖墙、抹浆Step 5: Laying cement brick walls and plastering
拆除模板后砌水泥砖墙,并用空心砖筑砌封顶,中间预留观察孔;空心砖墙面要抹浆,保证充填过程不跑浆;After the formwork is removed, cement brick walls are built, and hollow bricks are used to build the roof, and observation holes are reserved in the middle; the hollow brick walls should be plastered to ensure that the filling process does not run out of slurry;
步骤6:设置墙撑Step 6: Setting Up Wall Braces
取墙撑六根,竖向等距设置三根竖撑,中间横向放置一根横撑,并使所述横撑两边抵住两侧竖撑,最后在两侧横撑和竖撑的相交位置各打一斜撑。Take six wall braces, set three vertical braces vertically and equidistantly, place a horizontal brace in the middle, and make the two sides of the horizontal brace against the vertical braces on both sides, and finally place a punch at the intersection of the horizontal braces and vertical braces on both sides. A diagonal brace.
本技术领域中的普通技术人员应当认识到,以上的实施例仅是用来说明本发明,而并非用作为对本发明的限定,只要在本发明的实质精神范围内,对以上所述实施例的变化、变型都将落在本发明的权利要求范围内。Those of ordinary skill in the art should recognize that the above embodiments are only used to illustrate the present invention, rather than as a limitation to the present invention, as long as within the scope of the spirit of the present invention, the above-described embodiments Changes and modifications will fall within the scope of the claims of the present invention.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710446967.6A CN107178391B (en) | 2017-06-14 | 2017-06-14 | A kind of construction method and application of armored concrete fire dam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710446967.6A CN107178391B (en) | 2017-06-14 | 2017-06-14 | A kind of construction method and application of armored concrete fire dam |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN107178391A true CN107178391A (en) | 2017-09-19 |
| CN107178391B CN107178391B (en) | 2018-12-28 |
Family
ID=59836624
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710446967.6A Expired - Fee Related CN107178391B (en) | 2017-06-14 | 2017-06-14 | A kind of construction method and application of armored concrete fire dam |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN107178391B (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110863856A (en) * | 2019-12-02 | 2020-03-06 | 江西理工大学 | A kind of access-type cemented filling and sealing wall and its construction method |
| CN111980749A (en) * | 2020-08-23 | 2020-11-24 | 昆明理工大学 | Novel detachable recycling filling retaining wall construction device and method |
| CN112922668A (en) * | 2021-03-01 | 2021-06-08 | 中色国际矿业股份有限公司帕鲁特金矿 | Underground filling retaining wall for mine and construction method thereof |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5167474A (en) * | 1991-12-06 | 1992-12-01 | John Kennedy Metal Products & Buildings | Form for making a permanent concrete mine stopping |
| CN201288586Y (en) * | 2008-10-22 | 2009-08-12 | 中国矿业大学 | Structure for preventing slipping of filled wall body along spatially keeping lane |
| CN101864987A (en) * | 2010-06-13 | 2010-10-20 | 中国矿业大学 | A construction method for filling wall of gob-side entry retaining in high-inclination coal seam |
| CN103696803A (en) * | 2013-12-06 | 2014-04-02 | 西北矿冶研究院 | Be used for mine underground tailings cemented filling barricade device |
| CN103806938A (en) * | 2014-03-10 | 2014-05-21 | 长沙矿山研究院有限责任公司 | Framework for fixing fillers in filling mining and building method |
| CN106837418A (en) * | 2016-12-28 | 2017-06-13 | 中国矿业大学 | A kind of trapezoidal fire dam of mine anti-explosion and its construction method |
-
2017
- 2017-06-14 CN CN201710446967.6A patent/CN107178391B/en not_active Expired - Fee Related
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5167474A (en) * | 1991-12-06 | 1992-12-01 | John Kennedy Metal Products & Buildings | Form for making a permanent concrete mine stopping |
| CN201288586Y (en) * | 2008-10-22 | 2009-08-12 | 中国矿业大学 | Structure for preventing slipping of filled wall body along spatially keeping lane |
| CN101864987A (en) * | 2010-06-13 | 2010-10-20 | 中国矿业大学 | A construction method for filling wall of gob-side entry retaining in high-inclination coal seam |
| CN103696803A (en) * | 2013-12-06 | 2014-04-02 | 西北矿冶研究院 | Be used for mine underground tailings cemented filling barricade device |
| CN103806938A (en) * | 2014-03-10 | 2014-05-21 | 长沙矿山研究院有限责任公司 | Framework for fixing fillers in filling mining and building method |
| CN106837418A (en) * | 2016-12-28 | 2017-06-13 | 中国矿业大学 | A kind of trapezoidal fire dam of mine anti-explosion and its construction method |
Non-Patent Citations (1)
| Title |
|---|
| 唐子波 等: "泡沫混凝土防火防爆密闭墙设计及其施工技术", 《煤矿现代化》 * |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110863856A (en) * | 2019-12-02 | 2020-03-06 | 江西理工大学 | A kind of access-type cemented filling and sealing wall and its construction method |
| CN111980749A (en) * | 2020-08-23 | 2020-11-24 | 昆明理工大学 | Novel detachable recycling filling retaining wall construction device and method |
| CN112922668A (en) * | 2021-03-01 | 2021-06-08 | 中色国际矿业股份有限公司帕鲁特金矿 | Underground filling retaining wall for mine and construction method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| CN107178391B (en) | 2018-12-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103410332B (en) | A kind of concrete hollow block reinforcement wall construction technology | |
| CN101906768B (en) | Panel construction method of concrete faced rock-fill dam | |
| CN108266191B (en) | An optimized construction method for multi-arch tunnels | |
| CN111206698A (en) | Construction method of assembled wallboard | |
| CN108278115A (en) | A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop | |
| CN104405062A (en) | Integrated column-equipped heat preservation wallboard, production and building techniques and matched equipment | |
| CN109209389B (en) | Construction method for entering semi-open and semi-closed tunnel | |
| CN106638940A (en) | Fabricated high-rise residence precast concrete component construction method | |
| CN107059920A (en) | Loess formation piping lane construction technology | |
| CN206737417U (en) | A kind of PC prefabricated outer wall panels grouting typified form | |
| CN106870001A (en) | Tunnel is layered pocket type self-support filling counterfort construction method | |
| CN110656959A (en) | Large-section loess tunnel primary support limit-invasion arch-changing construction method | |
| CN106968692B (en) | Tunnel excavation supporting structure and construction method thereof | |
| CN110847929A (en) | Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting | |
| CN111042569B (en) | Construction method for additionally building linear accelerator machine room in limited space of hospital basement | |
| CN210117716U (en) | Trapezoidal foundation ditch lateral wall concrete typical forms of elevartor shaft | |
| CN107178391A (en) | A kind of construction method of armored concrete fire dam and application | |
| CN108374663B (en) | Twice-molding construction method for sandy gravel geological tunnel | |
| CN211499326U (en) | Synchronous construction structures of concrete infilled wall and cast-in-place structure | |
| CN106988339A (en) | Sandy gravel stratum piping lane construction technology | |
| CN105862897A (en) | Original-groove casting construction method for shallow foundation of sandy mudstone foundation | |
| CN212272234U (en) | A high-strength composite formwork for the open channel section of a large-section inclined well | |
| CN104746521B (en) | The application of oversized cross-section slope cushion layer constructing structure | |
| CN106401276A (en) | Construction method for wall column binding bars of frame type building block enclosing wall | |
| CN208122041U (en) | A kind of IPS Cast-in-place concrete shear wall structure of self-heat preservation system system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181228 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |