CN107171189A - A kind of cable tunnel integrated with substation equipment basis - Google Patents

A kind of cable tunnel integrated with substation equipment basis Download PDF

Info

Publication number
CN107171189A
CN107171189A CN201710380984.4A CN201710380984A CN107171189A CN 107171189 A CN107171189 A CN 107171189A CN 201710380984 A CN201710380984 A CN 201710380984A CN 107171189 A CN107171189 A CN 107171189A
Authority
CN
China
Prior art keywords
cable
cable tunnel
switch cubicle
tunnel
switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710380984.4A
Other languages
Chinese (zh)
Inventor
马士超
李文升
蔡健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710380984.4A priority Critical patent/CN107171189A/en
Publication of CN107171189A publication Critical patent/CN107171189A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B1/00Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
    • H02B1/20Bus-bar or other wiring layouts, e.g. in cubicles, in switchyards
    • H02B1/202Cable lay-outs
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/02Installations of electric cables or lines in or on the ground or water laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

A kind of basic integrated cable tunnel of and substation equipment of the present invention, it is more than 2 meters of a cable tunnel including height, the reserved once hole in position of the top correspondence switch cubicle of cable tunnel, one time hole is used for a cable incoming-outgoing wire between cable tunnel and switch cubicle.Switch cubicle is when being arranged in pairs, a cable tunnel is arranged in pairs the underground below respective switch cabinet.Unilateral wall or double side wall in cable tunnel are provided with the cable bearer for being used for setting up cable.Secondary cable ditch, the secondary cable inlet-outlet line that secondary cable ditch is used between switch cubicle and control room are additionally provided between switch cubicle and control room.The cable tunnel that a kind of and substation equipment basis of the present invention is integrated effectively reduces the height of Switch Building in Substation, construction costs is reduced, while accelerating construction speed.Switch cubicle inlet-outlet line is directly seated in tunnel thereon, facilitates cable laying, facilitates operations staff's walkaround inspection, it is easy to cable operation maintenance.

Description

A kind of cable tunnel integrated with substation equipment basis
Technical field
The present invention relates to transformer substation construction field, more particularly to 220kV and the one-end substation and electricity of following voltage class Cable inlet-outlet line more transformer station back and forth.
Background technology
At present, the main path for cable laying is main by two kinds of cable duct and cable interlayer.Traditional cable ditch is Excavate and build by laying bricks or stones by design requirement, the sidewall weld load slotted-angle shelving of ditch is simultaneously grounded on request, and upper cover is with the underground ditch of cover plate Road.But when laying the transformer station of the more 220kV of outlet and following voltage class, generally existing cable incoming-outgoing line loop is more, The thick phenomenon in cable footpath.Cable laying and operation maintenance generally build cable clip in transformer station bottom for convenience in the design Layer.The shortcoming of cable interlayer is to need to set up a house, and the usual floor height in house is more than 2.6 meters, adds transformer station's throwing Money.And normal cable ditch mode is used, because cable duct is shallower, bending is unfavorable for cable operation maintenance, and the presence of cable duct Indoor terrace segmentation will be caused more, be unfavorable for flooring construction, cause the selection of earth material to be limited.
The content of the invention
Therefore, the technical problem to be solved in the present invention is to overcome cable interlayer of the prior art need to be in surface construction room Son, exists and invests big defect, and cable duct is too shallow, there is the defect for being unfavorable for cable operation maintenance, so as to provide one kind not Only facilitate cable operation maintenance, and the cable tunnel that a kind of small and substation equipment basis of investment is integrated.
The design of the present invention is as follows:
A kind of cable tunnel integrated with substation equipment basis, including height are more than 2 meters of a cable tunnel, institute The reserved once hole in position of the top correspondence switch cubicle of a cable tunnel is stated, a hole is used for described once electric A cable incoming-outgoing wire between cable tunnel and the switch cubicle.
Preferably, the switch cubicle is when being arranged in pairs, a cable tunnel is arranged in pairs under respective switch cabinet Square underground.
Preferably, the unilateral wall or double side wall in a cable tunnel are provided with the cable branch for being used for setting up cable Frame.
Preferably, twice channel-section steel is embedded with the top of a cable tunnel, the channel-section steel is used to install the switch Cabinet.
Preferably, secondary cable ditch is additionally provided between the switch cubicle and control room, the secondary cable ditch is used for described Secondary cable inlet-outlet line between switch cubicle and the control room.
Preferably, the secondary cable ditch includes the secondary ditch connected with the secondary cable wire inlet-outlet of the switch cubicle Groove, and it is embedded in underground, the steel pipe 7 connected with the secondary cable wire inlet-outlet of the control room, and the secondary groove Connected with the steel pipe.
Preferably, the secondary groove is vertically arranged, and the steel pipe is horizontally disposed with.
Preferably, distribution room floor one-piece casting.
Technical solution of the present invention, has the following advantages that:
1st, a kind of cable tunnel integrated with substation equipment basis, including a cable tunnel are provided in the present invention Twice channel-section steel is embedded with the top of road, a cable tunnel, the channel-section steel is used to install the switch cubicle.Cable tunnel with The integral structure of switch cubicle, overcoming original cable interlayer needs to build the house of more than 2.6 meters of floor height, and causes cost height Shortcoming, effectively reduction Switch Building in Substation height, construction costs is reduced, while accelerating construction speed.
2nd, in the present invention, the position reserved once hole, institute of the top correspondence switch cubicle of a cable tunnel The cable incoming-outgoing wire that a hole is used between a cable tunnel and the switch cubicle is stated, the switch cubicle is into During to setting, a cable tunnel is arranged in pairs the underground below respective switch cabinet.Switch cubicle inlet-outlet line is directly seated in Tunnel thereon, facilitates cable laying, facilitates operations staff's walkaround inspection, it is easy to cable operation maintenance.
3rd, the present invention uses tunnel cabling, it is to avoid during using cable duct cabling, cover plate is to flooring Segmentation;Distribution room floor one-piece casting, more easily selects earth material and construction, improves the aesthetics of flooring.
Brief description of the drawings
, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical scheme of the prior art The accompanying drawing used required in embodiment or description of the prior art is briefly described, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before creative work is not paid Put, other accompanying drawings can also be obtained according to these accompanying drawings.
The elevation that Fig. 1 is provided in the first embodiment for the present invention;
Description of reference numerals:
Cable tunnel of 1-;2- switch cubicles;Hole of 3-;4- cable beareves;
5- channel-section steels;Bis- grooves of 6-;7- steel pipes;8- secondary cable ditches.
Embodiment
Technical scheme is clearly and completely described below in conjunction with accompanying drawing, it is clear that described implementation Example is a part of embodiment of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill The every other embodiment that personnel are obtained under the premise of creative work is not made, belongs to the scope of protection of the invention.
In the description of the invention, it is necessary to explanation, term " " center ", " on ", " under ", "left", "right", " vertical ", The orientation or position relationship of the instruction such as " level ", " interior ", " outer " be based on orientation shown in the drawings or position relationship, merely to Be easy to the description present invention and simplify description, rather than indicate or imply signified device or element must have specific orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.In addition, term " first ", " second ", " the 3rd " is only used for describing purpose, and it is not intended that indicating or implying relative importance.
In the description of the invention, it is necessary to illustrate, unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;Can To be mechanical connection or electrical connection;Can be joined directly together, can also be indirectly connected to by intermediary, Ke Yishi The connection of two element internals.For the ordinary skill in the art, with concrete condition above-mentioned term can be understood at this Concrete meaning in invention.
As long as in addition, technical characteristic involved in invention described below different embodiments non-structure each other It can just be combined with each other into conflict.
Fig. 1 shows the basic integrated cable tunnel of a kind of and substation equipment that a kind of specific embodiment of the invention is provided The elevation in road.As illustrated, a kind of cable tunnel integrated with substation equipment basis, including highly it is more than the one of 2 meters Secondary cable tunnel 1, tunnel upper has been arranged in pairs 10kV switch cubicles 2, and a cable tunnel 1 is arranged in pairs in respective switch The lower section underground of cabinet 2.The integral structure of cable tunnel and switch cubicle, overcoming original cable interlayer needs to build 2.6 meters of floor height House above, and cause the high shortcoming of cost, the height of Switch Building in Substation is effectively reduced, construction costs is reduced, simultaneously Accelerate construction speed.Using tunnel cabling, it is to avoid during using cable duct cabling, cover plate divides flooring Cut;Distribution room floor one-piece casting, more easily selects earth material and construction, improves the aesthetics of flooring.
Distribution room floor one-piece casting, the position of the top correspondence switch cubicle 2 of a cable tunnel 1 is reserved with A 530mm*350mm hole 3 a, hole 3 is used between a cable tunnel 1 and the switch cubicle 2 Cable incoming-outgoing wire.It is 500mm's that single-sided side walls in cable tunnel 1, which are provided with the width for being used for setting up cable, Cable bearer 4, certainly, in other embodiments, can also be provided with bilateral side wall as needed in a cable tunnel 1 Cable bearer 4.The top of cable tunnel 1 is embedded with twice 10# channel-section steels 5, and the channel-section steel 5 is used to install the switch Cabinet 2, according to the demand of 10kV switch cubicles 2, the spacing of channel-section steel 5 is 1500mm.Switch cubicle inlet-outlet line is directly seated in tunnel thereon, side Just cable laying, facilitates operations staff's walkaround inspection, it is easy to cable operation maintenance.
Secondary cable ditch 8 is provided between the switch cubicle 2 and control room, the secondary cable ditch 8 is used for the switch cubicle 2 Secondary cable inlet-outlet line between the control room.The secondary cable ditch 8 includes entering with the secondary cable of the switch cubicle 2 The secondary groove 6 of line outlet connection, and it is embedded in underground, the pipe connected with the secondary cable wire inlet-outlet of the control room Footpath is 150mm steel pipe 7, and the secondary groove 6 connects with the steel pipe 7.The secondary groove 6 is vertically arranged, the steel Pipe 7 is horizontally disposed with.
Obviously, above-described embodiment is only intended to clearly illustrate example, and the not restriction to embodiment.It is right For those of ordinary skill in the art, can also make on the basis of the above description it is other it is various forms of change or Change.There is no necessity and possibility to exhaust all the enbodiments.And the obvious change thus extended out or Among changing still in the protection domain of the invention.

Claims (8)

1. a kind of cable tunnel integrated with substation equipment basis, it is characterised in that be more than 2 meters of once electricity including height Cable tunnel (1), reserved once hole (3) in position of the top correspondence switch cubicle (2) of a cable tunnel (1) are described The cable incoming-outgoing wire that hole (3) is used between a cable tunnel (1) and the switch cubicle (2).
2. the cable tunnel according to claim 1, it is characterised in that the switch cubicle (2) is described for when being arranged in pairs Cable tunnel (1) is arranged in pairs the underground below respective switch cabinet (2).
3. the cable tunnel according to claim 1, it is characterised in that the unilateral wall in a cable tunnel (1) Or double side wall is provided with the cable bearer (4) for being used for setting up cable.
4. the cable tunnel according to claim 1, it is characterised in that the top of a cable tunnel (1) (1) is pre- Twice channel-section steel (5) is embedded with, the channel-section steel (5) is used to install the switch cubicle (2).
5. the cable tunnel according to any one of claim 1-4, it is characterised in that the switch cubicle (2) and control Secondary cable ditch (8) is additionally provided between room, the secondary cable ditch (8) is used between the switch cubicle (2) and the control room Secondary cable inlet-outlet line.
6. the cable tunnel according to claim 5, it is characterised in that the secondary cable ditch (8) includes opening with described The secondary groove (6) of the secondary cable wire inlet-outlet connection of cabinet (2) is closed, and is embedded in underground, two with the control room The steel pipe (7) of secondary cable incoming-outgoing wire mouthful connection, and the secondary groove (6) connects with the steel pipe (7).
7. the cable tunnel according to claim 6, it is characterised in that the secondary groove (6) is vertically arranged, the steel (7) are managed to be horizontally disposed with.
8. the cable tunnel according to any one of claim 1-4, it is characterised in that distribution room floor one-piece casting.
CN201710380984.4A 2017-05-25 2017-05-25 A kind of cable tunnel integrated with substation equipment basis Pending CN107171189A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710380984.4A CN107171189A (en) 2017-05-25 2017-05-25 A kind of cable tunnel integrated with substation equipment basis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710380984.4A CN107171189A (en) 2017-05-25 2017-05-25 A kind of cable tunnel integrated with substation equipment basis

Publications (1)

Publication Number Publication Date
CN107171189A true CN107171189A (en) 2017-09-15

Family

ID=59821388

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710380984.4A Pending CN107171189A (en) 2017-05-25 2017-05-25 A kind of cable tunnel integrated with substation equipment basis

Country Status (1)

Country Link
CN (1) CN107171189A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107658829A (en) * 2017-11-14 2018-02-02 贵州电网有限责任公司 A kind of cable duct intelligent aeration dehumidification system
CN108736430A (en) * 2018-07-13 2018-11-02 安徽华电工程咨询设计有限公司 A kind of open caisson of overhanging type holder staggered floor transposition cable laying
CN109066561A (en) * 2018-09-04 2018-12-21 广东电网有限责任公司 The method of laying control cable in pre-embedded cable bracket and cable duct
CN111049089A (en) * 2019-11-29 2020-04-21 国网山东省电力公司经济技术研究院 Three-area split visual fireproof cable trench
CN111224368A (en) * 2019-12-02 2020-06-02 国网新疆电力有限公司阿勒泰供电公司 Miniature cable trench
CN114977066A (en) * 2022-06-14 2022-08-30 国网黑龙江省电力有限公司牡丹江供电公司 Support arrangement for extension cable pit is used

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100947784B1 (en) * 2009-05-11 2010-03-15 성보전기공업 주식회사 The incoming panel and switchboard where the internal parts temperature determination which leads a two-dimensional scanning is possible
CN203813215U (en) * 2014-03-28 2014-09-03 佛山电力设计院有限公司 Cable laying apparatus of prefabricated distribution box
CN204046112U (en) * 2014-09-11 2014-12-24 国家电网公司 Electric substation's secondary cable threading structure
CN204290064U (en) * 2014-11-05 2015-04-22 滁州学院 A kind of switch cubicle mounting structure
CN205677623U (en) * 2016-06-23 2016-11-09 四川电力设计咨询有限责任公司 Cable tunnel and equipment foundations compages

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100947784B1 (en) * 2009-05-11 2010-03-15 성보전기공업 주식회사 The incoming panel and switchboard where the internal parts temperature determination which leads a two-dimensional scanning is possible
CN203813215U (en) * 2014-03-28 2014-09-03 佛山电力设计院有限公司 Cable laying apparatus of prefabricated distribution box
CN204046112U (en) * 2014-09-11 2014-12-24 国家电网公司 Electric substation's secondary cable threading structure
CN204290064U (en) * 2014-11-05 2015-04-22 滁州学院 A kind of switch cubicle mounting structure
CN205677623U (en) * 2016-06-23 2016-11-09 四川电力设计咨询有限责任公司 Cable tunnel and equipment foundations compages

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107658829A (en) * 2017-11-14 2018-02-02 贵州电网有限责任公司 A kind of cable duct intelligent aeration dehumidification system
CN108736430A (en) * 2018-07-13 2018-11-02 安徽华电工程咨询设计有限公司 A kind of open caisson of overhanging type holder staggered floor transposition cable laying
CN109066561A (en) * 2018-09-04 2018-12-21 广东电网有限责任公司 The method of laying control cable in pre-embedded cable bracket and cable duct
CN111049089A (en) * 2019-11-29 2020-04-21 国网山东省电力公司经济技术研究院 Three-area split visual fireproof cable trench
CN111049089B (en) * 2019-11-29 2021-06-04 国网山东省电力公司经济技术研究院 Three-area split visual fireproof cable trench
CN111224368A (en) * 2019-12-02 2020-06-02 国网新疆电力有限公司阿勒泰供电公司 Miniature cable trench
CN114977066A (en) * 2022-06-14 2022-08-30 国网黑龙江省电力有限公司牡丹江供电公司 Support arrangement for extension cable pit is used
CN114977066B (en) * 2022-06-14 2024-03-12 国网黑龙江省电力有限公司牡丹江供电公司 Support arrangement for expand cable pit usefulness

Similar Documents

Publication Publication Date Title
CN107171189A (en) A kind of cable tunnel integrated with substation equipment basis
CN104420480B (en) The method for arranging of Collapsible Loess District comprehensive pipe network and structure
CN203420403U (en) Infilled wall construction structure based on wire box and wire tube mounting precasting building blocks
CN105971018A (en) Tubular-cross-section urban underground comprehensive pipe gallery formed by steel corrugated plates
CN2503649Y (en) Prefabricated underground box type converting station
CN106013235A (en) Corrugated steel plate city underground comprehensive pipe gallery with arch-shaped cross section
CN110424454A (en) Build together method and the structure of building together of pipe gallery and subway station
CN107893496A (en) A kind of assembly concrete integrated floor and its manufacture method
CN106058779B (en) A kind of interval strong and weak electricity arrangement structure for pipelines in tramcar engineering ground
CN207453225U (en) A kind of superstructure unit and assembly concrete integrated floor
CN104499625A (en) Profiled steel sheet and composite floor
CN110241854B (en) Utility tunnel convenient to span underground building and cabin changing method thereof
CN208803681U (en) Piping shaft and building structure
CN203800541U (en) Outdoor cable trench for intelligent substation
CN206498168U (en) A kind of distribution system of high-effective multilayer structure low level equipment
CN105089024B (en) Underground power house outlet arrangement and structure
CN204266444U (en) A kind of profiled sheet and composite floor
CN206611094U (en) A kind of outdoor GIS cable terminations fixing device
CN210658441U (en) Utility tunnel convenient to stride underground building
CN204391512U (en) A kind of control cables arrangement of intelligent substation 10kV Machine Room
CN205829120U (en) A kind of cable intermediate joint well structure
CN109149488B (en) Urban railway pipeline arrangement structure and method
CN204645358U (en) Template and floor
CN114992388B (en) Container yard three-dimensional pipe network system and layout method
CN218990261U (en) Jiang Ruodian built-up and spliced cable shaft structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170915

RJ01 Rejection of invention patent application after publication