CN107166092B - A kind of pipeline underwater mating method - Google Patents
A kind of pipeline underwater mating method Download PDFInfo
- Publication number
- CN107166092B CN107166092B CN201710487673.8A CN201710487673A CN107166092B CN 107166092 B CN107166092 B CN 107166092B CN 201710487673 A CN201710487673 A CN 201710487673A CN 107166092 B CN107166092 B CN 107166092B
- Authority
- CN
- China
- Prior art keywords
- pipe laying
- pipeline
- butt end
- underwater mating
- fixture
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/26—Repairing or joining pipes on or under water
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The present invention provides a kind of pipeline underwater mating methods, comprising the following steps: S1: being lifted the butt end of pipe laying using air bag, and installs drawing device and limiting device;S2: the blind plate and sandboard for removing the butt end of pipe laying carry out sedimentation of pouring water to pipe laying;S3: it treats pipe laying and carries out sedimentation of pouring water;S4: in the butt end installs fixture of the pipeline to be installed, the fixture is equipped with idler wheel;S5: the fixture of the steel wire penetrating of hoist engine pipeline butt end to be installed is simultaneously connect with the drawing device of pipe laying butt end;S6: the wirerope of tensioning hoisting machine makes pipeline to be installed fit with pipe laying;S7: coarse positioning is carried out by ring flange of the steel screw rod to both ends;S8: the matched fixing bolt of mounting flange is simultaneously tightened;S9: air bag is sequentially discharged from pipe laying direction, sinking pipeline completes pipeline docking.
Description
Technical field
The present invention relates to submarine pipelines to be laid with field more particularly to a kind of pipeline underwater mating method.
Background technique
High density polyethylene pipe (hereinafter referred to as HDPE pipe) is widely used in defeated to (drawing) water system, drainage system and combustion gas
The multiple fields such as send.When carrying out the installation of underwater HDPE pipe, frequently with segmentation installation, the technique of underwater mating, traditional HDPE pipe
Underwater mating technology still is limited to minor diameter (630mm or less) pipeline section, and for major diameter or even super-large diameter HDPE pipeline, this
The applicability of a little underwater mating technologies is poor.With the development of economy, the application of major diameter HDPE pipeline certainly will be more extensive, because
This needs to research and develop a kind of underwater mating method suitable for major diameter HDPE pipeline.
Summary of the invention
In order to solve the problems in the prior art, the present invention provides a kind of structures simply, the convenient pipeline of docking is underwater
Interconnection method.
The present invention provides a kind of pipeline underwater mating methods, including pipe laying, pipeline to be installed and barge, described
Barge is equipped with crawler crane and hoist engine, and the butt end of the pipe laying and the butt end of pipeline to be installed are equipped with flange
Disk, further comprising the steps of:
The butt end of pipe laying: being lifted by S1 using air bag, is installed in the butt end of the pipe laying
Drawing device and limiting device;
S2: the blind plate and sandboard for removing the butt end of pipe laying carry out sedimentation of pouring water to pipe laying;
S3: it treats pipe laying and carries out pouring water sedimentation and its pipeline to be installed and pipe laying are made by the crawler crane
Height it is corresponding;
S4: in the butt end installs fixture of the pipeline to be installed, the fixture is equipped with idler wheel;
S5: the fixture of the steel wire penetrating of hoist engine pipeline butt end to be installed and the drawing with pipe laying butt end
Device connection;
S6: the wirerope of tensioning hoisting machine, drawing pipeline to be installed it is close to pipe laying and by limiting device into
Row pipeline laterally and axially positions until pipeline to be installed fits with pipe laying;
S7: coarse positioning is carried out by ring flange of the steel screw rod to both ends;
S8: the matched fixing bolt of mounting flange is simultaneously tightened;
S9: air bag is sequentially discharged from pipe laying direction, sinking pipeline completes pipeline docking.
As a further improvement of the present invention, the air bag is 70m models that are multiple and being arranged in pipe laying butt end
In enclosing, multiple air bags guarantee that pipe laying butt end is lifted 1.5m after sedimentation of pouring water for this.
As a further improvement of the present invention, the butt end of the pipe laying two sides be equipped with concrete anchor block, it is described
Pipe laying butt end is fixed on the concrete anchor block by hawser, and the butt end of pipe laying is equipped with multiple ballasts
Block, the drawing device are two and are symmetrically set in the two sides of first kentledge of pipe laying.
As a further improvement of the present invention, the method for the ring flange of pipe laying butt end and pipeline butt end to be installed
Contraposition adjustment wirerope is equipped between blue disk.
As a further improvement of the present invention, the limiting device is pairs that are multiple and being evenly arranged in pipe laying
It connects on the ring flange at end.
As a further improvement of the present invention, in step S9, fixing bolt is fastened again after sinking twenty four hours,
And it tests to docking end face gap.
The beneficial effects of the present invention are: the present invention can conveniently complete subaqueous pipe using the simple device of structure
The docking in road can be adapted for the underwater mating of major diameter high-density polytene pipeline, dock high-efficient, applicable depth of water range
Extensively, easily operated.
Detailed description of the invention
Fig. 1 is the device layout schematic diagram of inventive pipeline underwater mating method;
Fig. 2 is the device layout schematic diagram of another angle of inventive pipeline underwater mating method;
Fig. 3 is the scheme of installation of the drawing device of inventive pipeline underwater mating method;
Fig. 4 is the structural schematic diagram of the drawing device of inventive pipeline underwater mating method;
Fig. 5 is the scheme of installation of the limiting device of inventive pipeline underwater mating method;
Fig. 6 is the layout drawing of the contraposition wirerope of inventive pipeline underwater mating method.
Appended drawing reference: 1- pipe laying;2- pipeline to be installed;3- barge;4- crawler crane;5- hoist engine;6- air bag;7-
Concrete anchor block;9- kentledge;10- drawing device;11- limiting device;12- contraposition adjustment wirerope;101- support plate;102-
First fixed plate;The second fixed plate of 103-;104- link.
Specific embodiment
As shown in Figures 1 to 6, the invention discloses a kind of pipeline underwater mating methods, including pipe laying 1, wait pacify
Tubulature road 2 and barge 3, the barge 3 are equipped with crawler crane 4 and hoist engine 5, and the butt end of the pipe laying 1 is equipped with flange
The butt end of disk, pipeline 2 to be installed is equipped with ring flange, further comprising the steps of: S1: using air bag 6 by pipe laying 1
Butt end is lifted, and installs drawing device 10 and limiting device 11 in the butt end of the pipe laying 1;S2: it removes
The blind plate and sandboard of the butt end of pipe laying 1 carry out sedimentation of pouring water to pipe laying 1;S3: the progress of pipe laying 2 is treated
It pours water and settles and keep its pipeline 2 to be installed corresponding with the height of pipe laying 1 by the crawler crane 4;S4: it is described to
The butt end installs fixture of pipe laying 2, the fixture are equipped with idler wheel;S5: the steel wire penetrating of hoist engine 5 pipeline 2 to be installed
The fixture of butt end is simultaneously connect with the drawing device 10 of 1 butt end of pipe laying;S6: the wirerope of tensioning hoisting machine 5, drawing
Pipeline 2 to be installed is close to pipe laying 1 and is laterally and axially positioned by the progress pipeline of limiting device 11 until to be installed
Pipeline 2 fits with pipe laying 1;S7: coarse positioning is carried out by ring flange of the steel screw rod to both ends;S8: mounting flange
Matched fixing bolt is simultaneously tightened;S9: air bag 6 is sequentially discharged from 1 direction of pipe laying, sinking pipeline completes pipeline docking.
Air bag 6 is bound within the scope of the about 70m of the butt end of pipe laying 1, pipe laying 1 is sling using 6 multiple spot of air bag
Butt end, making the segment pipe, away from bottom about 1.5m, barge 3 is docked in the top of pipe laying 1, distance for lifting after sedimentation of pouring water
Butt end about 15m, the air bag 6 under barge 3 are bound in 1 two sides of pipe laying.
Concrete anchor block 7,1 butt end of pipe laying are equipped at the 1 butt end two sides about 5m of pipe laying
It is fixed on the concrete anchor block 7 by hawser, so that docking pipeline is maintained a relatively stable state, pipe laying 1
Butt end is equipped with multiple kentledges 9, and the drawing device 10 is two and is symmetrically set in first ballast of pipe laying 1
The two sides of block 9.
Contraposition adjustment is equipped between the ring flange of 2 butt end of the ring flange of 1 butt end of pipe laying and pipeline to be installed
Wirerope 12, contraposition adjustment wirerope 12 are being installed when pipeline 2 to be installed is close to 1 certain distance of pipe laying,
Hole location check and correction can be carried out to the flange hole at both ends.
The drawing device 10 includes support plate 101, the first fixed plate 102 and the second fixed plate 103, and described first is fixed
Plate 102 is set to described 101 one end of support plate, and 101 other end of support plate is equipped with the link for connecting 5 wirerope of hoist engine
104, second fixed plate 103 is equipped with sliding slot, and second fixed plate 103 is bolted on the support plate 101
On, the bolt passes through sliding slot, the second fixed plate 103 and support plate 101 are fixed, the second fixed plate 103 adjustable in this way
Position, the easy disassembly drawing device 10.
The limiting device 11 is multiple and is evenly arranged on the ring flange of the butt end of pipe laying 1.
In step s 9, fixing bolt is fastened again after sinking twenty four hours, and to docking end face gap
It tests, until inspection result complies with standard.
The present invention first passes through air bag 6 and the pipe laying of sinking is carried out lifting certain distance, and needs will have been installed
Pipeline within the scope of pipeline 170m is lifted, and can make the lifting angle of pipe laying 1 gentler in this way, rising height
In 1.5m or so, the docking in later period is facilitated to operate, and position restriction is carried out by the concrete anchor block 7 at both ends, then
Drawing device 10 and limiting device 11 are installed in the butt end of pipe laying 1, drawing device 10 is used for the steel of wire rope hoist 5
Cord, limiting device 11 are used to play axial positioning in docking, then pass through air bag 6 again for the docking of pipeline 2 to be installed
End is lifted, and rising height and the rising height of 1 butt end of pipe laying are essentially identical, and by crawler crane 4 to it
The micro-adjustment of axial location is carried out, guarantees that smoothly docking, the wirerope of hoist engine 5 initially pass through the folder of 2 butt end of pipeline to be installed
It is fixed on drawing device 10 again after tool, pipe laying 2 can be treated by hoist engine 5 in this way and carry out drawing, carried out simultaneously
Band hangs 4 hanging supports and lives right above pipeline to be installed 2, to facilitate docking, when 2 butt end of pipeline to be installed is close to limiting device 11
Before coverage, binding contraposition adjustment wirerope 12, for adjusting flange screw dislocation;Then hoist engine 5 and crawler crane 4 are mutual
It matches, adjusts pipeline butt end to be pacified and enter 11 coverage of limiting device, realize position-limiting action, when docking pipeline pastes completely
Close and flange the ring disk device to hole it is consistent after, along circumferential uniformly 8~10 steel screw rods of insertion of ring flange and fasten, steel screw rod connection procedure
In, constantly adjustment docking pipeline section and continuous observation end face of flange gap, until ring flange connection error within the allowable range,
After steel screw rod slightly connects, the matched fixing bolt of ring flange symmetrically is penetrated, wherein hole location shared by steel screw rod is replaced one by one
At fixing bolt.After often penetrating a fixing bolt, flange bolt is screwed to design torque;Fixing bolt is installed it
Afterwards, Cong Yian pipeline section bends up end and starts, and sequence discharges air bag 6, completes pipeline seat bottom sinking;After flanged joint is completed 24 hours,
Flange fixing bolt need to fasten again, while use the gap of 2mm clearance gauge inspection docking end face, if passed examination, pipeline pair
Construction is connect to be fully completed;If inspection is unqualified, Ying Zaici is fastened and fixed bolt and checks, until passed examination.
The present invention can conveniently complete the docking of submarine pipeline using the simple device of structure, can be applicable in
In the underwater mating of major diameter high-density polytene pipeline, it is wide, easily operated to dock high-efficient, applicable depth of water range.
The above content is a further detailed description of the present invention in conjunction with specific preferred embodiments, and it cannot be said that
Specific implementation of the invention is only limited to these instructions.For those of ordinary skill in the art to which the present invention belongs, exist
Under the premise of not departing from present inventive concept, a number of simple deductions or replacements can also be made, all shall be regarded as belonging to of the invention
Protection scope.
Claims (6)
1. a kind of pipeline underwater mating method, including pipe laying, pipeline to be installed and barge, the barge is equipped with crawler crane
And hoist engine, the butt end of the pipe laying and the butt end of pipeline to be installed are equipped with ring flange, which is characterized in that packet
Include following steps:
The butt end of pipe laying: being lifted by S1 using air bag, installs drawing in the butt end of the pipe laying
Device and limiting device;
S2: the blind plate and sandboard for removing the butt end of pipe laying carry out sedimentation of pouring water to pipe laying;
S3: it treats pipe laying and carries out pouring water sedimentation and its pipeline to be installed and the height of pipe laying are made by the crawler crane
It spends corresponding;
S4: in the butt end installs fixture of the pipeline to be installed, the fixture is equipped with idler wheel;
S5: the fixture of the steel wire penetrating of hoist engine pipeline butt end to be installed and the drawing device with pipe laying butt end
Connection;
S6: the wirerope of tensioning hoisting machine, drawing pipeline to be installed is close to pipe laying and carries out pipe by limiting device
Road laterally and axially positions until pipeline to be installed fits with pipe laying;
S7: coarse positioning is carried out by ring flange of the steel screw rod to both ends;
S8: the matched fixing bolt of mounting flange is simultaneously tightened;
S9: air bag is sequentially discharged from pipe laying direction, sinking pipeline completes pipeline docking.
2. pipeline underwater mating method according to claim 1, it is characterised in that: the air bag is multiple and is arranged in
Within the scope of the 70m of pipe laying butt end, multiple air bags guarantee that pipe laying butt end is lifted after sedimentation of pouring water for this
Rise 1.5m.
3. pipeline underwater mating method according to claim 1, it is characterised in that: the butt end of the pipe laying two sides
Equipped with concrete anchor block, the butt end of pipe laying is fixed on the concrete anchor block by hawser, described to have installed
Pipeline butt end is equipped with multiple kentledges, and the drawing device is two and is symmetrically set in first ballast of pipe laying
The two sides of block.
4. pipeline underwater mating method according to claim 1, it is characterised in that: the ring flange of pipe laying butt end
Contraposition adjustment wirerope is equipped between the ring flange of pipeline butt end to be installed.
5. pipeline underwater mating method according to claim 4, it is characterised in that: the limiting device is multiple and equal
It is even to be arranged on the ring flange of the butt end of pipe laying.
6. pipeline underwater mating method according to claim 1, it is characterised in that: small in sinking 24 in step S9
When after fixing bolt is fastened again, and to docking end face gap test.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710487673.8A CN107166092B (en) | 2017-06-23 | 2017-06-23 | A kind of pipeline underwater mating method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710487673.8A CN107166092B (en) | 2017-06-23 | 2017-06-23 | A kind of pipeline underwater mating method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107166092A CN107166092A (en) | 2017-09-15 |
CN107166092B true CN107166092B (en) | 2019-07-05 |
Family
ID=59820225
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710487673.8A Active CN107166092B (en) | 2017-06-23 | 2017-06-23 | A kind of pipeline underwater mating method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107166092B (en) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107606306B (en) * | 2017-09-18 | 2019-07-12 | 金丹 | Road rain water pipeline construction method |
CN107387870B (en) * | 2017-09-18 | 2019-07-26 | 金丹 | A kind of automatic pipe-laying equipment |
CN108050301B (en) * | 2017-11-01 | 2019-08-16 | 中交第四航务工程局有限公司 | A kind of great diameter and long HDPE pipeline immersing method |
CN111692427B (en) * | 2020-05-19 | 2021-08-13 | 中交第四航务工程局有限公司 | Underwater positioning method for large-diameter overlong HDPE (high-density polyethylene) pipeline |
CN111692429A (en) * | 2020-05-19 | 2020-09-22 | 中交第四航务工程局有限公司 | Underwater closure method for large-diameter HDPE (high-density polyethylene) pipeline |
CN112212074B (en) * | 2020-09-23 | 2021-08-03 | 中交第四航务工程局有限公司 | Large-diameter overlong HDPE pipeline closure method |
CN114960901A (en) * | 2022-05-19 | 2022-08-30 | 佛山市市政建设工程有限公司 | Rainwater pipeline automatic alignment installation device |
CN115929990B (en) * | 2022-12-29 | 2023-07-25 | 中交第四航务工程局有限公司 | Method for installing submarine pipeline in deep sea section |
CN116576301A (en) * | 2023-05-31 | 2023-08-11 | 中国建筑第二工程局有限公司 | Municipal pipeline installation equipment and method based on BIM model technology |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NO325701B1 (en) * | 2005-12-02 | 2008-07-07 | Norsk Hydro Produksjon As | Method and arrangement for preventing water ingress into critical umbilical linings between preferably an underwater production and processing plant and an onshore or platform control room |
CN101649928A (en) * | 2009-06-17 | 2010-02-17 | 钟爱民 | Method for installing pipelines assisted by air bags |
CN104344078B (en) * | 2014-08-12 | 2016-03-02 | 山东科技大学 | Deep underwater pipes clamp-press type mechanical connector Intelligent Installation device and using method thereof |
CN105952967B (en) * | 2016-06-01 | 2018-09-14 | 天津市城安热电有限公司 | A kind of immersed tube operational method using floating ball sinking pipeline |
CN105909865B (en) * | 2016-06-15 | 2018-10-02 | 青岛理工大学 | Underwater air bag balances submarine pipeline prosthetic device |
CN106704705B (en) * | 2017-01-12 | 2019-12-17 | 中交天航南方交通建设有限公司 | overwater pipeline assembling operation method and system |
-
2017
- 2017-06-23 CN CN201710487673.8A patent/CN107166092B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN107166092A (en) | 2017-09-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107166092B (en) | A kind of pipeline underwater mating method | |
AU2017202003B2 (en) | Pipe-laying vessel and method of laying a pipeline | |
US10288194B2 (en) | Marine reel lay method pipeline installation vessel and methods | |
US9506586B2 (en) | Pipe connection guide arrangement | |
CN104989875A (en) | Submarine pipeline flange underwater abutting joint installation method | |
CN104631602B (en) | Sewage deep sea emission engineering marine site pipeline construction method | |
AU2014300717A1 (en) | Foundations for subsea pipeline accessories | |
CN105605315B (en) | A kind of three node pipes neck formula J-type paving system | |
US4335752A (en) | Flanged pipe | |
ATE423289T1 (en) | SYSTEM FOR LAYING UNDERWATER PIPES AND LIFTING DEVICE | |
US5181798A (en) | Double pipe turntable and stinger | |
US9874295B2 (en) | Clamp assembly for pipe-laying vessel and method of laying a pipeline | |
US3739592A (en) | Conical stabbing guide and clamp system for riser pipe installation | |
CN104006216B (en) | A kind of crude oil of offshore platform standpipe maintain and replace method and apparatus | |
CN109185558B (en) | Method for underwater installation of large-diameter GRP pipeline | |
RU2008136202A (en) | INSTALLATION OF THE PIPELINE USING THE CRANE | |
US20090223673A1 (en) | Offshore Riser Retrofitting Method and Apparatus | |
RU188233U1 (en) | SHAFT TYPE SEALING CHAMBER | |
CN205578897U (en) | Deep water J type is system of laying fast | |
KR20130068431A (en) | Tensioner of pipe-laying on vessels having clamp extention apparatus | |
CN205896386U (en) | Marine pipeline lays quick knock off joint | |
CN114458830B (en) | HDPE water intake pipeline laying method and pipe laying ship for power plant gas unit extension project | |
CN204752046U (en) | On --spot hoist and mount are with two steps of towers | |
NL2030951B1 (en) | Rapid fixing device of optical fiber sensor for deep-sea mixed transportation riser and laying method | |
RU213497U1 (en) | Device for repair work on an underground pipeline |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20190625 Address after: 510290 No. 368 Lijiao Road, Haizhu District, Guangzhou City, Guangdong Province Applicant after: CCCC Fourth Harbor Engineering Co., Ltd. Address before: 510231 No. 163 Qianjin Road, Haizhu District, Guangzhou City, Guangdong Province Applicant before: The Second Engineering Company of CCCC Fourth Harbor Engineering Co.,Ltd. |