CN107150761A - The water surface of large-scale floating body builds installation method - Google Patents

The water surface of large-scale floating body builds installation method Download PDF

Info

Publication number
CN107150761A
CN107150761A CN201710295013.XA CN201710295013A CN107150761A CN 107150761 A CN107150761 A CN 107150761A CN 201710295013 A CN201710295013 A CN 201710295013A CN 107150761 A CN107150761 A CN 107150761A
Authority
CN
China
Prior art keywords
water surface
floating body
installation method
connection cable
scale floating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710295013.XA
Other languages
Chinese (zh)
Other versions
CN107150761B (en
Inventor
俞麒峰
艾玉忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU YUNYI AVIATION COMPOSITE MATERIAL STRUCTURE Co.,Ltd.
Original Assignee
Shenzhen Blue Ocean Engineering Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Blue Ocean Engineering Development Co Ltd filed Critical Shenzhen Blue Ocean Engineering Development Co Ltd
Priority to CN201710295013.XA priority Critical patent/CN107150761B/en
Publication of CN107150761A publication Critical patent/CN107150761A/en
Application granted granted Critical
Publication of CN107150761B publication Critical patent/CN107150761B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B75/00Building or assembling floating offshore structures, e.g. semi-submersible platforms, SPAR platforms or wind turbine platforms

Abstract

Installation method, including step are built the invention discloses a kind of water surface of large-scale floating body:Step 1: in building inflatable mounting platform on the water surface;Step 2: on the platform of step one formation, closing up fixed structure thing using closing device;Step 3: on the works of step 2 formation, honeycomb board is installed using mobile device, so as to form floating body.The invention provides a stabilised platform, superstructure module can be built as land on the platform.

Description

The water surface of large-scale floating body builds installation method
Technical field
Installation method is built the present invention relates to a kind of water surface of large-scale floating body.
Background technology
The construction of large-scale boat structure thing is generally carried out on land or dock.Each component build permitted by group, middle group, it is big In the group stage, on the one hand need to take larger place, further need exist for often moving, increase process.Closing up on land can be by Road, traffic and the limitation of place size.Land has to pass through the lower water operation of complexity after the completion of closing up, risk is high.In ship Depressed place closes up, and the occupancy depressed place phase is longer, costly, and dock length and width (especially in terms of width) are by larger limitation.Using normal The large-scale boat structure thing that rule method is closed up farther out, is transported by channel width and depth limit typically all from target water.It is logical Often when works closes up, it is fixed using a large amount of temporary components are welded.Welding, sanding operation cause certain journey to structure The injury of degree.Live interim operation is difficult to ensure that welding quality, easily causes trueness error and accident.
The content of the invention
The present invention is in order to solve the above technical problems, the water surface for providing a kind of large-scale floating body builds installation method.
To realize object above, the present invention is achieved through the following technical solutions:
The water surface of large-scale floating body builds installation method, including step:
Step 1: in building inflatable mounting platform on the water surface;
Step 2: on the platform of step one formation, closing up fixed structure thing using closing device;
Step 3: on the works of step 2 formation, honeycomb board is installed using mobile device, so as to form floating body.
According to one embodiment of the invention, described step one includes step:Step a, assembling steel structure frame;Step Rapid b, some air bags and inflate in being be arranged in parallel in steel structure frame;Step c, in steel structure frame top fix work put down Face.
According to one embodiment of the invention, described closing device includes:Rotor, connection cable, tension equipment and Anchor, wherein, rotor is respectively welded on works to be closed up, connection cable is set around rotor, and tension equipment is to even Connecing hawser application pretightning force is tensioned connection cable, and anchor is used for the connection cable of fixed tensioning.
According to one embodiment of the invention, described mobile device includes:Guide rail and locomotive, wherein, guide rail can Releasably it is arranged on works, locomotive is transported to installation site peace in being movably disposed on guide rail, and by honeycomb board Dress.
According to one embodiment of the invention, described locomotive includes:Body, handling mechanism, grabbing device and turn Wheel, wherein, the lower section of body is used to accommodate grabbing device and honeycomb board to be moved provided with receiving space, and handling mechanism is set It is connected in the top of body and with grabbing device, the power for providing grabbing device raising and lowering, grabbing device is used to grab Honeycomb board to be moved is taken, runner is arranged at the bottom of body and on guide rail.
The present invention reduces the land transport problem of large structure in building inflatable mounting platform on the water surface, saves land The place lease expenses of ground, saves the engineering ship lease expenses such as barge.Close up fixed structure thing using closing device, in knot Structure thing is good rotor welding when manufacturing, it is to avoid danger and quality problems that live temporary weld is likely to result in.The works closed up Saving material can be reused.Pretightning force is applied by machinery, easy to operate.Only need to control the accurate of rotor mounting location Degree, less rigging error adds up factor.Honeycomb board is installed using mobile device, convenient transport is laborsaving time saving, installs accurate, Less alignment error, less labor strength., on the platform can be such as land the invention provides a stabilised platform Equally build superstructure module.
Brief description of the drawings
Fig. 1 is the top view of step one inflatable mounting platform;
Fig. 2 is the front view of step one inflatable mounting platform;
Fig. 3 is the left view of step one inflatable mounting platform;
Fig. 4 is step 2 closing device floor plan;
Fig. 5 is step 2 closing device side arrangement figure;
Fig. 6 is step 3 mobile device schematic diagram;
Fig. 7 is locomotive structural representation.
Embodiment
The present invention is described in detail below in conjunction with the accompanying drawings:
The water surface of the present embodiment large-scale floating body builds installation method, including step:
As shown in Figure 1, Figure 2 and Figure 3, Step 1: in building inflatable mounting platform on the water surface:
Including step:Step a, assembling steel structure frame 3;Step b, in some air bags 1 that be arranged in parallel in steel structure frame 3 And inflate;Step c, the top fixation working face 2 in steel structure frame 3.
In building inflatable mounting platform on the water surface, the land transport problem of large structure is reduced, land is saved Place lease expenses, saves the engineering ship lease expenses such as barge.
As shown in Figure 4 and Figure 5, Step 2: on the platform of step one formation, closing up fixed structure thing using closing device 4;Closing device includes:Rotor 5, connection cable 6, tension equipment 7 and anchor 8, wherein, divide on works 4 to be closed up Other welded disc turbine rotor 5, connection cable 6 is set around rotor 5, and tension equipment 7 applies pretightning force to connection cable 6 makes connection cable 6 Tensioning, anchor 8 is used for the connection cable 6 of fixed tensioning.Connection cable 6 uses wirerope.
Close up fixed structure thing 4 using closing device, rotor 5 is welded when works 4 is manufactured, it is to avoid scene is interim Weld the danger being likely to result in and quality problems.The works 4 closed up can reuse saving material.Pretightning force passes through machinery Apply, it is easy to operate.Only need to control the accuracy of the installation site of rotor 5, less rigging error adds up factor.
As shown in Figure 6 and Figure 7, Step 3: on the works 4 of step 2 formation, cellular board is installed using mobile device Material, so as to form floating body.
Mobile device includes:Guide rail 9 and locomotive 10, wherein, guide rail 9 is removable installed on works 4, locomotive 10 are movably disposed on guide rail 9, and honeycomb board is transported into installation site installation.
Described locomotive 10 includes:Body 11, handling mechanism 12, grabbing device 13 and runner 14, wherein, body 11 Lower section is used to accommodate grabbing device 13 and honeycomb board 15 to be moved provided with receiving space, and handling mechanism 12 is arranged at body 11 Top and be connected with grabbing device 13, the power for providing the raising and lowering of grabbing device 13, grabbing device 13 be used for grab Honeycomb board 15 to be moved is taken, runner 14 is arranged at the bottom of body 11 and on guide rail 9.
In use, grabbing device 13 captures honeycomb board 15 to be moved in laydown area, handling mechanism 12 makes grabbing device 13 rise, and locomotive 10 is in being moved to installation site on guide rail 9, handling mechanism 12 makes grabbing device 13 decline release honeycomb board 15。
Honeycomb board 15 is installed using mobile device, convenient transport is laborsaving time saving, installs accurate, less alignment error, compared with Few labor strength.
The part used in the present embodiment is built in factory building.
Embodiment in the present invention is only used for that the present invention will be described, and is not construed as limiting the scope of claims limitation, Other substantial equivalent replacements that those skilled in that art are contemplated that, all fall in the scope of protection of the present invention.

Claims (5)

1. a kind of water surface of large-scale floating body builds installation method, it is characterised in that including step:
Step 1: in building inflatable mounting platform on the water surface;
Step 2: on the platform of step one formation, closing up fixed structure thing using closing device;
Step 3: on the works of step 2 formation, honeycomb board is installed using mobile device, so as to form floating body.
2. the water surface of large-scale floating body according to claim 1 builds installation method, it is characterised in that described step one is wrapped Include step:Step a, assembling steel structure frame;Step b, some air bags and inflate in being be arranged in parallel in steel structure frame;Step c, Working face is fixed in the top of steel structure frame.
3. the water surface of large-scale floating body according to claim 1 or 2 builds installation method, it is characterised in that described closes up Device includes:Rotor, connection cable, tension equipment and anchor, wherein, rotor is respectively welded on works to be closed up, Connection cable is set around rotor, and tension equipment applies pretightning force to connection cable is tensioned connection cable, and anchor is used for The connection cable of fixed tensioning.
4. the water surface of large-scale floating body according to claim 1 builds installation method, it is characterised in that described mobile device Including:Guide rail and locomotive, wherein, guide rail is removable installed on works, locomotive in being movably disposed on guide rail, And honeycomb board is transported to installation site installation.
5. the water surface of large-scale floating body according to claim 4 builds installation method, it is characterised in that described locomotive bag Include:Body, handling mechanism, grabbing device and runner, wherein, the lower section of body provided with receiving space be used to accommodating grabbing device and Honeycomb board to be moved, handling mechanism is arranged at the top of body and is connected with grabbing device, for providing grabbing device The power for rising and declining, grabbing device is used to capture honeycomb board to be moved, and runner is arranged at the bottom of body and is located at and leads On rail.
CN201710295013.XA 2017-04-28 2017-04-28 The water surface of large-scale floating body builds installation method Active CN107150761B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710295013.XA CN107150761B (en) 2017-04-28 2017-04-28 The water surface of large-scale floating body builds installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710295013.XA CN107150761B (en) 2017-04-28 2017-04-28 The water surface of large-scale floating body builds installation method

Publications (2)

Publication Number Publication Date
CN107150761A true CN107150761A (en) 2017-09-12
CN107150761B CN107150761B (en) 2019-04-12

Family

ID=59793991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710295013.XA Active CN107150761B (en) 2017-04-28 2017-04-28 The water surface of large-scale floating body builds installation method

Country Status (1)

Country Link
CN (1) CN107150761B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111470001A (en) * 2019-01-22 2020-07-31 中集海洋工程研究院有限公司 Method for building ultra-large ship

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07187066A (en) * 1993-12-28 1995-07-25 Hitachi Zosen Corp Assembly method for floating structure
EP1980486A1 (en) * 2006-02-03 2008-10-15 Open Joint-Stock Company "Central Design Bureau" 'Corall' Method for assembling a waterborne ship hull and a device for carrying out said method
CN201132590Y (en) * 2007-10-26 2008-10-15 黄锐明 Base for building floating house on water
CN102582799A (en) * 2012-04-11 2012-07-18 广新海事重工股份有限公司 Buoyancy tank and afloat buoyancy tank joining process
CN104608887A (en) * 2015-01-20 2015-05-13 上海海事大学 Air bag filling type truss used for large ocean platform
CN205801445U (en) * 2016-07-14 2016-12-14 蔡修坤 In-water foundation carrier module
CN206031709U (en) * 2016-07-11 2017-03-22 中诚国际海洋工程勘察设计有限公司 Gasbag formula platform

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07187066A (en) * 1993-12-28 1995-07-25 Hitachi Zosen Corp Assembly method for floating structure
EP1980486A1 (en) * 2006-02-03 2008-10-15 Open Joint-Stock Company "Central Design Bureau" 'Corall' Method for assembling a waterborne ship hull and a device for carrying out said method
CN201132590Y (en) * 2007-10-26 2008-10-15 黄锐明 Base for building floating house on water
CN102582799A (en) * 2012-04-11 2012-07-18 广新海事重工股份有限公司 Buoyancy tank and afloat buoyancy tank joining process
CN104608887A (en) * 2015-01-20 2015-05-13 上海海事大学 Air bag filling type truss used for large ocean platform
CN206031709U (en) * 2016-07-11 2017-03-22 中诚国际海洋工程勘察设计有限公司 Gasbag formula platform
CN205801445U (en) * 2016-07-14 2016-12-14 蔡修坤 In-water foundation carrier module

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111470001A (en) * 2019-01-22 2020-07-31 中集海洋工程研究院有限公司 Method for building ultra-large ship

Also Published As

Publication number Publication date
CN107150761B (en) 2019-04-12

Similar Documents

Publication Publication Date Title
JP2021524419A (en) Devices and methods for lifting objects from the deck of motion-affected vessels
CN108773455B (en) Bulb bow reform technology
CN103057663B (en) Underwater installation process of removable deck of million-ton roll-on-roll-off ship
CN106223303A (en) A kind of ship booster supporting compartment installation method
CN107150761A (en) The water surface of large-scale floating body builds installation method
CN108891527A (en) A kind of rudder blade mounting tool and installation method
CN105523477A (en) Method for carrying out pile leg connection by utilizing 3000t floating crane
JP6313613B2 (en) Crane equipment and work boat
CN105480387B (en) Ship-building gantry crane entirety shipping methods
JP6636955B2 (en) Portal scraper with carrier structure based on truss structure
CN104060592B (en) Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles
CN209290620U (en) Large-scale component lifting transport installation integrated ship
CN103395478B (en) A kind of marine wind turbine whole machine is transported and installs complete special equipment
CN206070516U (en) The construction system of over-water bored pile is carried out based on pushing tow mobile platform
CN102564792A (en) Loading device for entirely applying simulative load to ocean work-over rig
JP2001048012A (en) Mobile scaffold device for inspection in tunnel construction work
CN103171911B (en) Ship loader installation technology
CN106703031A (en) Pile press for architectural engineering
CN203007843U (en) Variable amplitude deck derrick crane
CN103174093A (en) Mounting device and mounting method of steel box girder in support zone
WO2008085061A1 (en) Tool carrier and method for carrying tools for cutting elongated structures
CN208897265U (en) A kind of novel rudder paddle mounting tool
KR101256526B1 (en) Apparatus for fixing unloader
KR20190034817A (en) Transportation ship for heavy
CN109533209A (en) Large-scale component lifting transport installation integrated ship and construction technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201013

Address after: 215200, Changan Road, Wujiang economic and Technological Development Zone, Jiangsu, Suzhou province (Science and Technology Pioneer Park)

Patentee after: SUZHOU YUNYI AVIATION COMPOSITE MATERIAL STRUCTURE Co.,Ltd.

Address before: Beike Building No. 1077 Shenzhen Nanshan District City, Guangdong province 518067 merchants Street Nanhai Road 5 layer 502

Patentee before: SHENZHEN BLUE OCEAN ENGINEERING DEVELOPMENT Co.,Ltd.

TR01 Transfer of patent right