CN107150761A - The water surface of large-scale floating body builds installation method - Google Patents
The water surface of large-scale floating body builds installation method Download PDFInfo
- Publication number
- CN107150761A CN107150761A CN201710295013.XA CN201710295013A CN107150761A CN 107150761 A CN107150761 A CN 107150761A CN 201710295013 A CN201710295013 A CN 201710295013A CN 107150761 A CN107150761 A CN 107150761A
- Authority
- CN
- China
- Prior art keywords
- water surface
- floating body
- installation method
- connection cable
- scale floating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B75/00—Building or assembling floating offshore structures, e.g. semi-submersible platforms, SPAR platforms or wind turbine platforms
Abstract
Installation method, including step are built the invention discloses a kind of water surface of large-scale floating body:Step 1: in building inflatable mounting platform on the water surface;Step 2: on the platform of step one formation, closing up fixed structure thing using closing device;Step 3: on the works of step 2 formation, honeycomb board is installed using mobile device, so as to form floating body.The invention provides a stabilised platform, superstructure module can be built as land on the platform.
Description
Technical field
Installation method is built the present invention relates to a kind of water surface of large-scale floating body.
Background technology
The construction of large-scale boat structure thing is generally carried out on land or dock.Each component build permitted by group, middle group, it is big
In the group stage, on the one hand need to take larger place, further need exist for often moving, increase process.Closing up on land can be by
Road, traffic and the limitation of place size.Land has to pass through the lower water operation of complexity after the completion of closing up, risk is high.In ship
Depressed place closes up, and the occupancy depressed place phase is longer, costly, and dock length and width (especially in terms of width) are by larger limitation.Using normal
The large-scale boat structure thing that rule method is closed up farther out, is transported by channel width and depth limit typically all from target water.It is logical
Often when works closes up, it is fixed using a large amount of temporary components are welded.Welding, sanding operation cause certain journey to structure
The injury of degree.Live interim operation is difficult to ensure that welding quality, easily causes trueness error and accident.
The content of the invention
The present invention is in order to solve the above technical problems, the water surface for providing a kind of large-scale floating body builds installation method.
To realize object above, the present invention is achieved through the following technical solutions:
The water surface of large-scale floating body builds installation method, including step:
Step 1: in building inflatable mounting platform on the water surface;
Step 2: on the platform of step one formation, closing up fixed structure thing using closing device;
Step 3: on the works of step 2 formation, honeycomb board is installed using mobile device, so as to form floating body.
According to one embodiment of the invention, described step one includes step:Step a, assembling steel structure frame;Step
Rapid b, some air bags and inflate in being be arranged in parallel in steel structure frame;Step c, in steel structure frame top fix work put down
Face.
According to one embodiment of the invention, described closing device includes:Rotor, connection cable, tension equipment and
Anchor, wherein, rotor is respectively welded on works to be closed up, connection cable is set around rotor, and tension equipment is to even
Connecing hawser application pretightning force is tensioned connection cable, and anchor is used for the connection cable of fixed tensioning.
According to one embodiment of the invention, described mobile device includes:Guide rail and locomotive, wherein, guide rail can
Releasably it is arranged on works, locomotive is transported to installation site peace in being movably disposed on guide rail, and by honeycomb board
Dress.
According to one embodiment of the invention, described locomotive includes:Body, handling mechanism, grabbing device and turn
Wheel, wherein, the lower section of body is used to accommodate grabbing device and honeycomb board to be moved provided with receiving space, and handling mechanism is set
It is connected in the top of body and with grabbing device, the power for providing grabbing device raising and lowering, grabbing device is used to grab
Honeycomb board to be moved is taken, runner is arranged at the bottom of body and on guide rail.
The present invention reduces the land transport problem of large structure in building inflatable mounting platform on the water surface, saves land
The place lease expenses of ground, saves the engineering ship lease expenses such as barge.Close up fixed structure thing using closing device, in knot
Structure thing is good rotor welding when manufacturing, it is to avoid danger and quality problems that live temporary weld is likely to result in.The works closed up
Saving material can be reused.Pretightning force is applied by machinery, easy to operate.Only need to control the accurate of rotor mounting location
Degree, less rigging error adds up factor.Honeycomb board is installed using mobile device, convenient transport is laborsaving time saving, installs accurate,
Less alignment error, less labor strength., on the platform can be such as land the invention provides a stabilised platform
Equally build superstructure module.
Brief description of the drawings
Fig. 1 is the top view of step one inflatable mounting platform;
Fig. 2 is the front view of step one inflatable mounting platform;
Fig. 3 is the left view of step one inflatable mounting platform;
Fig. 4 is step 2 closing device floor plan;
Fig. 5 is step 2 closing device side arrangement figure;
Fig. 6 is step 3 mobile device schematic diagram;
Fig. 7 is locomotive structural representation.
Embodiment
The present invention is described in detail below in conjunction with the accompanying drawings:
The water surface of the present embodiment large-scale floating body builds installation method, including step:
As shown in Figure 1, Figure 2 and Figure 3, Step 1: in building inflatable mounting platform on the water surface:
Including step:Step a, assembling steel structure frame 3;Step b, in some air bags 1 that be arranged in parallel in steel structure frame 3
And inflate;Step c, the top fixation working face 2 in steel structure frame 3.
In building inflatable mounting platform on the water surface, the land transport problem of large structure is reduced, land is saved
Place lease expenses, saves the engineering ship lease expenses such as barge.
As shown in Figure 4 and Figure 5, Step 2: on the platform of step one formation, closing up fixed structure thing using closing device
4;Closing device includes:Rotor 5, connection cable 6, tension equipment 7 and anchor 8, wherein, divide on works 4 to be closed up
Other welded disc turbine rotor 5, connection cable 6 is set around rotor 5, and tension equipment 7 applies pretightning force to connection cable 6 makes connection cable 6
Tensioning, anchor 8 is used for the connection cable 6 of fixed tensioning.Connection cable 6 uses wirerope.
Close up fixed structure thing 4 using closing device, rotor 5 is welded when works 4 is manufactured, it is to avoid scene is interim
Weld the danger being likely to result in and quality problems.The works 4 closed up can reuse saving material.Pretightning force passes through machinery
Apply, it is easy to operate.Only need to control the accuracy of the installation site of rotor 5, less rigging error adds up factor.
As shown in Figure 6 and Figure 7, Step 3: on the works 4 of step 2 formation, cellular board is installed using mobile device
Material, so as to form floating body.
Mobile device includes:Guide rail 9 and locomotive 10, wherein, guide rail 9 is removable installed on works 4, locomotive
10 are movably disposed on guide rail 9, and honeycomb board is transported into installation site installation.
Described locomotive 10 includes:Body 11, handling mechanism 12, grabbing device 13 and runner 14, wherein, body 11
Lower section is used to accommodate grabbing device 13 and honeycomb board 15 to be moved provided with receiving space, and handling mechanism 12 is arranged at body 11
Top and be connected with grabbing device 13, the power for providing the raising and lowering of grabbing device 13, grabbing device 13 be used for grab
Honeycomb board 15 to be moved is taken, runner 14 is arranged at the bottom of body 11 and on guide rail 9.
In use, grabbing device 13 captures honeycomb board 15 to be moved in laydown area, handling mechanism 12 makes grabbing device
13 rise, and locomotive 10 is in being moved to installation site on guide rail 9, handling mechanism 12 makes grabbing device 13 decline release honeycomb board
15。
Honeycomb board 15 is installed using mobile device, convenient transport is laborsaving time saving, installs accurate, less alignment error, compared with
Few labor strength.
The part used in the present embodiment is built in factory building.
Embodiment in the present invention is only used for that the present invention will be described, and is not construed as limiting the scope of claims limitation,
Other substantial equivalent replacements that those skilled in that art are contemplated that, all fall in the scope of protection of the present invention.
Claims (5)
1. a kind of water surface of large-scale floating body builds installation method, it is characterised in that including step:
Step 1: in building inflatable mounting platform on the water surface;
Step 2: on the platform of step one formation, closing up fixed structure thing using closing device;
Step 3: on the works of step 2 formation, honeycomb board is installed using mobile device, so as to form floating body.
2. the water surface of large-scale floating body according to claim 1 builds installation method, it is characterised in that described step one is wrapped
Include step:Step a, assembling steel structure frame;Step b, some air bags and inflate in being be arranged in parallel in steel structure frame;Step c,
Working face is fixed in the top of steel structure frame.
3. the water surface of large-scale floating body according to claim 1 or 2 builds installation method, it is characterised in that described closes up
Device includes:Rotor, connection cable, tension equipment and anchor, wherein, rotor is respectively welded on works to be closed up,
Connection cable is set around rotor, and tension equipment applies pretightning force to connection cable is tensioned connection cable, and anchor is used for
The connection cable of fixed tensioning.
4. the water surface of large-scale floating body according to claim 1 builds installation method, it is characterised in that described mobile device
Including:Guide rail and locomotive, wherein, guide rail is removable installed on works, locomotive in being movably disposed on guide rail,
And honeycomb board is transported to installation site installation.
5. the water surface of large-scale floating body according to claim 4 builds installation method, it is characterised in that described locomotive bag
Include:Body, handling mechanism, grabbing device and runner, wherein, the lower section of body provided with receiving space be used to accommodating grabbing device and
Honeycomb board to be moved, handling mechanism is arranged at the top of body and is connected with grabbing device, for providing grabbing device
The power for rising and declining, grabbing device is used to capture honeycomb board to be moved, and runner is arranged at the bottom of body and is located at and leads
On rail.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710295013.XA CN107150761B (en) | 2017-04-28 | 2017-04-28 | The water surface of large-scale floating body builds installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710295013.XA CN107150761B (en) | 2017-04-28 | 2017-04-28 | The water surface of large-scale floating body builds installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107150761A true CN107150761A (en) | 2017-09-12 |
CN107150761B CN107150761B (en) | 2019-04-12 |
Family
ID=59793991
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710295013.XA Active CN107150761B (en) | 2017-04-28 | 2017-04-28 | The water surface of large-scale floating body builds installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107150761B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111470001A (en) * | 2019-01-22 | 2020-07-31 | 中集海洋工程研究院有限公司 | Method for building ultra-large ship |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07187066A (en) * | 1993-12-28 | 1995-07-25 | Hitachi Zosen Corp | Assembly method for floating structure |
EP1980486A1 (en) * | 2006-02-03 | 2008-10-15 | Open Joint-Stock Company "Central Design Bureau" 'Corall' | Method for assembling a waterborne ship hull and a device for carrying out said method |
CN201132590Y (en) * | 2007-10-26 | 2008-10-15 | 黄锐明 | Base for building floating house on water |
CN102582799A (en) * | 2012-04-11 | 2012-07-18 | 广新海事重工股份有限公司 | Buoyancy tank and afloat buoyancy tank joining process |
CN104608887A (en) * | 2015-01-20 | 2015-05-13 | 上海海事大学 | Air bag filling type truss used for large ocean platform |
CN205801445U (en) * | 2016-07-14 | 2016-12-14 | 蔡修坤 | In-water foundation carrier module |
CN206031709U (en) * | 2016-07-11 | 2017-03-22 | 中诚国际海洋工程勘察设计有限公司 | Gasbag formula platform |
-
2017
- 2017-04-28 CN CN201710295013.XA patent/CN107150761B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07187066A (en) * | 1993-12-28 | 1995-07-25 | Hitachi Zosen Corp | Assembly method for floating structure |
EP1980486A1 (en) * | 2006-02-03 | 2008-10-15 | Open Joint-Stock Company "Central Design Bureau" 'Corall' | Method for assembling a waterborne ship hull and a device for carrying out said method |
CN201132590Y (en) * | 2007-10-26 | 2008-10-15 | 黄锐明 | Base for building floating house on water |
CN102582799A (en) * | 2012-04-11 | 2012-07-18 | 广新海事重工股份有限公司 | Buoyancy tank and afloat buoyancy tank joining process |
CN104608887A (en) * | 2015-01-20 | 2015-05-13 | 上海海事大学 | Air bag filling type truss used for large ocean platform |
CN206031709U (en) * | 2016-07-11 | 2017-03-22 | 中诚国际海洋工程勘察设计有限公司 | Gasbag formula platform |
CN205801445U (en) * | 2016-07-14 | 2016-12-14 | 蔡修坤 | In-water foundation carrier module |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111470001A (en) * | 2019-01-22 | 2020-07-31 | 中集海洋工程研究院有限公司 | Method for building ultra-large ship |
Also Published As
Publication number | Publication date |
---|---|
CN107150761B (en) | 2019-04-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2021524419A (en) | Devices and methods for lifting objects from the deck of motion-affected vessels | |
CN108773455B (en) | Bulb bow reform technology | |
CN103057663B (en) | Underwater installation process of removable deck of million-ton roll-on-roll-off ship | |
CN106223303A (en) | A kind of ship booster supporting compartment installation method | |
CN107150761A (en) | The water surface of large-scale floating body builds installation method | |
CN108891527A (en) | A kind of rudder blade mounting tool and installation method | |
CN105523477A (en) | Method for carrying out pile leg connection by utilizing 3000t floating crane | |
JP6313613B2 (en) | Crane equipment and work boat | |
CN105480387B (en) | Ship-building gantry crane entirety shipping methods | |
JP6636955B2 (en) | Portal scraper with carrier structure based on truss structure | |
CN104060592B (en) | Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles | |
CN209290620U (en) | Large-scale component lifting transport installation integrated ship | |
CN103395478B (en) | A kind of marine wind turbine whole machine is transported and installs complete special equipment | |
CN206070516U (en) | The construction system of over-water bored pile is carried out based on pushing tow mobile platform | |
CN102564792A (en) | Loading device for entirely applying simulative load to ocean work-over rig | |
JP2001048012A (en) | Mobile scaffold device for inspection in tunnel construction work | |
CN103171911B (en) | Ship loader installation technology | |
CN106703031A (en) | Pile press for architectural engineering | |
CN203007843U (en) | Variable amplitude deck derrick crane | |
CN103174093A (en) | Mounting device and mounting method of steel box girder in support zone | |
WO2008085061A1 (en) | Tool carrier and method for carrying tools for cutting elongated structures | |
CN208897265U (en) | A kind of novel rudder paddle mounting tool | |
KR101256526B1 (en) | Apparatus for fixing unloader | |
KR20190034817A (en) | Transportation ship for heavy | |
CN109533209A (en) | Large-scale component lifting transport installation integrated ship and construction technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20201013 Address after: 215200, Changan Road, Wujiang economic and Technological Development Zone, Jiangsu, Suzhou province (Science and Technology Pioneer Park) Patentee after: SUZHOU YUNYI AVIATION COMPOSITE MATERIAL STRUCTURE Co.,Ltd. Address before: Beike Building No. 1077 Shenzhen Nanshan District City, Guangdong province 518067 merchants Street Nanhai Road 5 layer 502 Patentee before: SHENZHEN BLUE OCEAN ENGINEERING DEVELOPMENT Co.,Ltd. |
|
TR01 | Transfer of patent right |