CN107130613B - Large span tunnel is just wearing the retaining structure and its construction method of existing barricade - Google Patents

Large span tunnel is just wearing the retaining structure and its construction method of existing barricade Download PDF

Info

Publication number
CN107130613B
CN107130613B CN201710360989.0A CN201710360989A CN107130613B CN 107130613 B CN107130613 B CN 107130613B CN 201710360989 A CN201710360989 A CN 201710360989A CN 107130613 B CN107130613 B CN 107130613B
Authority
CN
China
Prior art keywords
friction pile
coupling beam
tunnel
retaining structure
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710360989.0A
Other languages
Chinese (zh)
Other versions
CN107130613A (en
Inventor
钟祖良
刘新荣
任玉琪
傅晏
杨忠平
夏彪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No5 Engineering Corp Ltd Of Cr22g
Chongqing University
Original Assignee
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University filed Critical Chongqing University
Priority to CN201710360989.0A priority Critical patent/CN107130613B/en
Publication of CN107130613A publication Critical patent/CN107130613A/en
Application granted granted Critical
Publication of CN107130613B publication Critical patent/CN107130613B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Abstract

The invention belongs to Tunnel Engineering technical fields, in particular to a kind of Large span tunnel is just wearing the retaining structure and its construction method of existing barricade, retaining structure includes two rows of friction piles, ground coupling beam, coupling beam, crown beam, diagonal brace, anchor rope structure and grouting and reinforcing body, two rows of friction piles are mounted on the outside of retaining structure, front-seat friction pile is apart from retaining structure certain distance and each other with the connection of ground coupling beam, heel row friction pile is close to retaining structure and each other with crown beam, coupling beam, the connection of ground coupling beam, it is connected with ground coupling beam with diagonal brace between two rows of friction piles, constitute integral frame structure, it is arranged on heel row friction pile to pull-type anchor rope, grouting and reinforcing is carried out by Rock And Soil of the grouting and reinforcing body to stress side around friction pile, improve the bearing capacity of Rock And Soil and retaining structure, the retaining structure is suitable for Large span tunnel and imports and exports and the hole of small deformation is required to face upward slope , not only can guarantee consolidation effect but also the operation that do not block the traffic.

Description

Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
Technical field
The invention belongs to Tunnel Engineering technical field, in particular to a kind of Large span tunnel is just wearing the retaining structure of existing barricade And its construction method.
Background technique
Since 21st century, with China express railway net, freeway net, high-grade highway net and Municipal The traffic engineering infrastructure construction of the construction of road network, China is flourished.And China, more mountainous regions, inland, house, road Etc. more adaptation to local conditions using building by the mountain after Retaining Wall Reinforcement side slope, high road network construction then frequently with tunnel structure pass through massif and The form of side slope italic, this relates to wear house, road under to tunnel's entrance and exit section and just wears asking for the existing barrier wall structure of side slope Topic.The general buried depth of Portal Section is shallower, and slope rock mass is comprehensive in crustal movement, weathering Erosion, rain drop erosion and mankind's activity etc. Act on lower crack in length and breadth, constructing tunnel inevitably disturbs slope ground body, to influence top house, traffic route Stability, meanwhile, the deformation of Rock And Soil can increase stress or even the hole of slope protection structure and tunnel lining structure with sliding again Door may cause the failure of existing barrier wall structure after abolishing, and then hole is caused to face upward slope unstability, and major landslip occurs, not only can shadow The safety for closing on building and traffic operation is rung, huge economic loss is caused, more seriously threatens staff, closes on resident and row The security of the lives and property of people.It can be seen that taking the scheme of dismounting reconstruction not to the existing barrier wall structure in slope is faced upward under such operating condition Only limitation is big, cost is more, long in time limit, and not can guarantee the normal operation of the safety for closing on building and top traffic route, more Big landslide disaster does not occur for the slope ground body that not can guarantee cranny development.Therefore, slope need to be faced upward to hole using reasonable scheme Existing barrier wall structure is reinforced, and to control the deformation and sliding of slope ground body, prevents existing structure from failing, and avoids hole sliding The generation of slope disaster.
Currently, the treatment measures for this operating condition are not described in existing tunnel specification and side slope specification, and it is real It is usually drawn using the slip casting in Slope Treatment, anchor in the engineering of border and existing structure creates the reinforcement measures such as supporting construction outside and carries out Disease Processing.Slip casting is mainly to pass through the strength characteristics for improving Rock And Soil with Reducing distortion, is suitable for cranny development, Rock And Soil pine Under the conditions of scattered, filling compaction deficiency, structural substrates drag deficiency etc., oxygen blast cyanidation, cracking and slip casting have been occurred for structure The stability that gliding mass cannot be improved increases the diseases such as sliding force instead and not only aggravates disease, municipal section road instead without effect Face mortar depositing construction had not only interfered traffic operation but also had influenced ambient enviroment.The pulling force of anchor rope (bar) is limited, larger for stress and want It asks and deforms small structure and be not suitable for, especially large deformation, which occurs, for tunnel exit and busy road slope retaining structure means to tie The destruction of structure, seriously threatens safety.Common newly-built supporting construction has bracket and friction pile, general construction party outside existing structure Just, short time limit will not interfere the operation of top road, but influence appearance, and have land occupation to require, to guarantee effect generally to each other Away from smaller, it is not suitable for long span tunnel and faces upward the supporting and retaining system of slope existing structure reinforcing.
In view of this, it is necessary to which the retaining structure and its construction method for inventing a kind of existing barricade had both adapted to the country Topographic and geologic condition reinforces existing supporting construction, ensures the supporting effectiveness of structure and closes on the normal operation of traffic, again The small spacing defect that existing ruggedized construction can be overcome imports and exports and requires the slope supporting structure of small deformation suitable for Large span tunnel Reinforcing.Meanwhile to realize that the support of this retaining structure provides a kind of construction method, to realize that long span tunnel is existing The consolidation process of supporting construction.
Summary of the invention
It can adapt to domestic topographic and geologic condition in view of this, the present invention, provides one kind to solve the above-mentioned problems, overcome The retaining structure and construction method of small spacing defect, the existing Retaining Wall Reinforcement imported and exported suitable for Large span tunnel both can guarantee and add The operation Gu effect does not block the traffic again.
In order to achieve the above objectives, the invention provides the following technical scheme:
Including retaining structure, friction pile and grouting and reinforcing body, friction pile include front-seat friction pile and with heel row friction pile, after The friction pile for arranging friction pile centre position is corresponding with front-seat friction pile, and heel row friction pile is tightly attached on retaining structure, and heel row is anti- Sliding pile is higher than front-seat friction pile, and the stake top between the stake top of the adjacent friction pile of front-seat friction pile, with front-seat friction pile is in same height Ground coupling beam is fixedly installed between the adjacent friction pile of the heel row friction pile of journey, the stake top with front-seat friction pile is on same elevation Heel row friction pile and front-seat friction pile between by coupling beam be fixedly connected, heel row friction pile top is fixedly installed with crown beam, Be fixedly installed with coupling beam between ground coupling beam in crown beam and heel row friction pile, be fixedly mounted between coupling beam and crown beam it is several be used to plus The rib column of strong retaining structure, retaining structure are equipped with the pull-type anchor rope for penetrating retaining structure and heel row friction pile, front-seat antiskid Diagonal brace is fixedly mounted with corresponding heel row friction pile top in the stake top of stake.
The utility model has the advantages that the present invention builds double friction pile on the outside of existing barricade, heel row friction pile is close to existing barricade It builds, is divided into in-rock segment and ground upper section, is built at a certain distance from front-seat friction pile is before existing barricade, predominantly embedded rock pile;Before Row's friction pile is linked together in its stake top by ground coupling beam, and is connect using diagonal brace and ground coupling beam with heel row friction pile;Heel row The ground upper section of friction pile is connected to form a whole by crown beam, coupling beam and ground coupling beam, and the thrust that retaining structure is transmitted is shared Onto each friction pile, big spacing between stake is realized;Thrust is transmitted to front-seat anti-by heel row friction pile by diagonal brace and ground coupling beam In sliding pile, to reduce the deformation of heel row friction pile, the consolidation effect and bearing capacity of enhancing structure;Crown beam on heel row friction pile Vertical rib column is set between coupling beam below, reinforces the ability of friction pile cantilever segment and crown beam resistance to deformation;Heel row antiskid Stake two sides can also add friction pile, for sharing the power in intermediate structure, to increase the bearing capacity of structure.
Several row's friction piles can also be set before front-seat friction pile of the invention, connected between adjacent each row's friction pile by ground Beam is fixedly connected, and is fixedly connected between the friction pile before front-seat friction pile and corresponding heel row friction pile by diagonal brace, multiple rows of antiskid Stake and the cooperation of diagonal brace can play the role of retaining structure further to reinforce.
Further, diagonal brace is connected to heel row friction pile far from one end of front-seat antiskid stake top and intersects with coupling beam or crown beam Position, wedge shape is formed between coupling beam and corresponding heel row friction pile between diagonal brace, front-seat friction pile and heel row friction pile Frame structure.The utility model has the advantages that diagonal brace is connected to heel row friction pile and coupling beam or crown beam far from one end of front-seat antiskid stake top The position of intersection, enable to diagonal brace to the consolidation effect of retaining structure more preferably.
Further, pull-type anchor rope penetrates existing barricade and retaining structure, and anchor rope one end is fixedly mounted by anchor pull head In heel row friction pile, the other end is fixed in basement rock supporting body by slip casting.
Further, grouting and reinforcing body is mounted on around friction pile, carries out slip casting to the Rock And Soil of stress side around friction pile It reinforces.Rock And Soil loose, cranny development before friction pile is carried out the utility model has the advantages that necessary slip casting measure can be used in the present invention It reinforces, to improve the bearing capacity of Rock And Soil and friction pile.The present invention uses advance support or pipe canopy pair before tunnel excavation Arch Rock And Soil is reinforced, and to reduce the sedimentation and surface subsidence of tunnel vault, guarantees the stabilization and traffic of existing building Normal operation.
It is real by the following technical programs that Large span tunnel, which is just wearing the construction method of the retaining structure of existing barricade, in the present invention Existing:
The Large span tunnel is just wearing the construction method of the retaining structure of existing barricade, comprising the following steps:
Step 1: preparation of construction, comprising the following steps:
1, construction survey is carried out in the area Sui Zhi by construction design drawing, survey sets out tunnel portal and its in the existing barricade of side slope On excavation contour line, center line including the main hole in tunnel at hole and peripheral sideline;
2, the tunnel portal contour line set out according to construction design drawing and survey, measures the friction pile position nearby to be built Profile, and mark the sequence of construction of friction pile;
3, the tunnel portal and friction pile position profile set out according to construction design drawing, survey, survey set out the anchor to be applied Drag-line position.
Step 2: the reinforcing retaining structure construction of the existing barricade of long span tunnel, comprising the following steps:
1, to reduce influence of the antiskid pile driving construction to the existing barricade of tunnel portal and shortening the construction period, the underground of friction pile In-rock segment uses quincunx sequence of construction, interval construction;
2, according to the position contour line for surveying the friction pile set, while between the friction pile and two sides for heel row center position of constructing Every friction pile and front-seat Center stake two sides friction pile, be all poured at the bottom surface elevation of ground coupling beam;
3, according to the position contour line for surveying the remaining stake set, the bottom surface of and then construct remaining friction pile to ground coupling beam is high At journey;
4, it has constructed after the in-rock segment of friction pile, one-piece casting ground coupling beam structure, and the cushion cap on front-seat friction pile top Locate the reinforcing bar of default diagonal brace;
5, according to the anchor rope position and anchor rope surveyed between the heel row friction pile coupling beam set out and ground coupling beam and horizontal plane Design angle, one end of pull-type anchor rope of constructing, anchor rope is fixed in basement rock supporting body using slip casting, and the other end passes through anchor Pull head is fixed in heel row friction pile;
6, after the anchor rope constructed on this section of friction pile, friction pile below one-piece casting coupling beam and coupling beam, and even The reinforcing bar of diagonal brace is preset in the junction of beam and friction pile, presets rib column reinforcing bar in coupling beam;
7, the anchor rope constructed between crown beam and coupling beam according to the method for above-mentioned construction procedure 5;
8, after completing anchor rope construction, reinforcement placing and template, friction pile, rib column and the hat on one-piece casting coupling beam top Beam;
9, according to the default reinforcing bar of design drawing and diagonal brace, the reinforcing bar and template of diagonal brace are set up, pours diagonal brace, is completed whole The construction of a retaining structure;
10, can around grouting and reinforcing friction pile power transmission carrying Rock And Soil, with the bearing capacity of enhancing structure.
Step 3: Large span tunnel construction, comprising the following steps:
1, the existing barricade in hole retaining structure construct complete, into after the maintenance stage, can carry out tunnel excavation and Liner structure applies;
2, the portal profile set according to survey, is punched on the existing barricade above arch using drilling machine, is led using small in advance Rock And Soil avoids causing Earth cave after pipe or pipe booth structure reinforcement walls to reduce Vault settlement, influences top building Safety and traffic operation, then carry out that portal is abolished, tunnel excavation and lining cutting apply;
3, the constructing tunnel after existing barricade still carries out advance support first with pipe canopy or advanced tubule, then excavates Tunnel applies liner structure in time;
4, constructing tunnel is using small drilling depth, the method for diligent measurement, fast supporting, to guarantee construction safety.
Advantage for present invention:
1, it is reinforced on the outside of existing barricade, rigid structure meets deformation requirements
Technical solution proposed by the present invention by retaining structure, friction pile, crown beam, coupling beam, coupling beam, diagonal brace, pull-type anchor draw Rope and basement rock supporting body composition, apply on the outside of existing barrier wall structure.On the basis of existing structure plays a role, antiskid is utilized Stake, diagonal brace, anchor rope formed rigid structure and crown beam, coupling beam, coupling beam formed force transfer system collective effect, thrust is passed It is delivered on the basement rock supporting body of lower section, is greatly reduced the deformation of structure and the movement of gliding mass, the small deformation in engineering can be met It is required that.
2, the engine request of big spacing between friction pile is realized
Friction pile in the present invention is connected by girder construction, realizes sharing for power, reduces the stress in single stake, and one Engineering demand can also be met by determining increasing friction pile spacing in range, outstanding for the operating condition for excavating long span tunnel between friction pile It is applicable.
3, symmetrical configuration, appearance are beautiful
Sliding-resistant system in the present invention be formed on the outside of existing barrier wall structure using friction pile, beam and diagonal brace it is similar Frame structure, symmetrical about neutral surface, appearance harmony is beautiful.
4, material is saved compared to bracket structure, practicability is stronger
For the present invention using ground coupling beam and inclined support structure instead of bracket, simple structure saves material.Meanwhile utilizing front row Structure thrust is transmitted on preferable basement rock supporting body by friction pile, also can be using the present invention even if surface layer Rock And Soil is relatively broken Supporting and retaining system reinforcing is carried out, applicability of the invention is greatly enhanced.
5, it is compact to apply arrangement, can shorten the construction period to greatest extent, reduces Coherent traffic noise
Sliding-resistant system proposed by the present invention is applied on the outside of existing barrier wall structure, easy for construction, can more friction piles it is same When the construction method adaptable with it constructing, and propose arrange compact, shorten the construction period to greatest extent, can reduce Construction infection, but can be most fast reach consolidation effect, meanwhile, the traffic operation above existing barricade will not be hindered.
Other advantages and features of the present invention determine according to practical application engineering to a certain extent, can be from reality hereafter It applies and carries out certain elaboration in example, to some introductions of those skilled in the relevant arts.
Detailed description of the invention
In order to keep the purpose of the present invention, technical scheme and beneficial effects clearer, the present invention provides following attached drawing and carries out Illustrate:
Fig. 1 is the perspective view for the retaining structure that Large span tunnel of the present invention is just wearing existing barricade;
Fig. 2 is the main view for the retaining structure that Large span tunnel of the present invention is just wearing existing barricade;
Fig. 3 is the structural schematic diagram for the retaining structure B-B section that Large span tunnel of the present invention is just wearing existing barricade;
Fig. 4 is the structural schematic diagram for the retaining structure C-C section that Large span tunnel of the present invention is just wearing existing barricade;
Fig. 5 is the structural schematic diagram for the retaining structure D-D section that Large span tunnel of the present invention is just wearing existing barricade;
Fig. 6 is the construction process figure for the retaining structure construction method that Large span tunnel of the present invention is just wearing existing barricade.
Specific embodiment
Below in conjunction with attached drawing, a preferred embodiment of the present invention will be described in detail.
Appended drawing reference in Figure of description includes:
Basement rock supporting body 1, potential slide surface 2, gliding mass 3, top of the slope road surface 4, ground line 5, retaining structure 6, friction pile 7, note Starch reinforcing body 8, coupling beam 9, stake end cushion cap 10, coupling beam 11, rib column 12, anchor rope 13, anchor pull head 14, crown beam 15, diagonal brace 16, even Encircle tunnel partition wall 17, advanced tubule 18, tunnel lining structure 19, tunnel portal 20.
As shown in Figure 1, Figure 2, Fig. 3, Fig. 4 and Large span tunnel shown in fig. 5 are just wearing the retaining structure of existing barricade, and the present embodiment is Certain multiple-arch tunnel outlet section wears the town road of heavy traffic under tunnel, and hole mileage ZK5+494.461 and YK5+495 are worn The more existing barricade of road slope.Cover artificial plain fill and silty clay on Portal Section, 3.90~15.20m of thickness, in the Jurassic system that underlies System sandy soil stabilizer mud stone, sandstone, ground interface are steeper.Rock layer surface has the highly weathered rock mass of 0.9~2.7m thickness, relatively broken, The harm such as it may cause chip off-falling after tunnel excavation, collapse.The high about 18.8m in slope is faced upward at hole, mainly by plain fill and highly weathered rock mass Composition.Tunnel list hole is three lanes large-span structure, and after excavating and abolishing portal barricade, existing barrier wall structure may lost effect, Leading to face upward the slope soil body may destroy along rock soil interface or the interior slip that bankets, and threaten construction personnel, road above equipment and side slope Road, structures safety.On the basis of engineering demand, through checking, it was demonstrated that can be used sliding-resistant system provided by the present invention and Construction method is faced upward progress scheme outside the existing barricade in slope in this long span tunnel and is applied.
The operating condition for facing upward the existing barricade in slope is just being worn to the Large span tunnel using sliding-resistant system of the invention, specific technical solution It is as follows:
Embodiment sliding-resistant system according to the invention using 8 having a size of 2000 × 3000 friction pile 7, heel row friction pile It is 5, front-seat friction pile is 3 corresponding with the centre 3 of heel row friction pile.
5 friction piles 7 of heel row friction pile are connected with the crown beam 15, coupling beam 11 and ground coupling beam 9 that size is 1500 × 3000 It connects, ground upper section is all 18m, intermediate friction pile build-in 19.25m, the equal build-in 14.25m of 4 piles of intermediate friction pile two sides.
The front-seat equal build-in 15.75m of 3 friction piles, each other with the ground coupling beam 9 having a size of 1500 × 3000 in its friction pile 7 tops link together.
Front two rows friction pile is with the ground coupling beam 9 having a size of 2000 × 1500 and having a size of 2000 × 2000 and anti-with heel row The diagonal brace 16 that sliding pile angle is 45 ° connects, and constitutes integral frame structure.
The anchor rope 13 being arranged on heel row friction pile, intermediate friction pile top is arranged one, with horizontal plane at 30 ° of angles; Two are respectively set on close to the two sides friction pile 7 of central pile, with horizontal plane at 20 ° of angles;On the friction pile 7 in two outsides respectively Setting 4, with horizontal plane at 20 ° of angles.
Grouting and reinforcing is carried out to the Rock And Soil on front side of front-seat friction pile, to reinforce the carrying energy of Rock And Soil and retaining structure Power, and then Reducing distortion.
Large span tunnel as shown in FIG. 6 is just wearing the construction method of the retaining structure of existing barricade, comprising the following steps:
Step 1: preparation of construction
1, construction survey is carried out in the area Sui Zhi by construction design drawing, survey sets out tunnel portal 20 and its in the existing gear of side slope Excavation contour line on wall, including the center line in the main hole in two tunnels at hole or so and peripheral sideline;
2, to be built friction pile 7 are measured near tunnel contour line at the hole measured according to construction design drawing It sets, and marks its sequence of construction;
3, according to the position profile of construction design drawing and the heel row friction pile measured, survey sets out anchor rope 13 to be applied Position.
Step 2: the ruggedized construction construction of the existing barricade in hole
1, position is set according to the survey of friction pile 7, while four friction piles 7 of front and rear row two sides of constructing and heel row center A friction pile 7 to ground coupling beam 9 bottom surface elevation at;
2, and then a friction pile 7 of the front-seat center position of construction and remaining two friction piles 7 of heel row connect to ground At 9 bottom surface elevation of beam;
3, the reinforcing bar for setting up ground coupling beam 9, presets 16 reinforcing bar of diagonal brace at stake end cushion cap 10, and support ground 9 template of coupling beam is whole The stake end cushion cap 10 for pouring ground 9 component of coupling beam and front-seat friction pile stake end, makes front and rear row friction pile form an overall structure;
4, the position of the anchor rope 13 set according to survey, the anchor rope 13 between construction ground coupling beam 9 and coupling beam 11, ground lower end are logical It crosses slip casting to be fixed in basement rock supporting body 1,7 end of friction pile is fixed with anchor pull head 14;
5, reinforcement placing presets 16 steel of diagonal brace in the junction of the corresponding heel row friction pile of front-seat friction pile and coupling beam 11 Muscle, support shuttering, one-piece casting coupling beam 11 and friction pile 7 below;
6, continue the anchor rope 13 constructed between crown beam 15 and coupling beam 11, ground lower end by slip casting and basement rock supporting body 1 or Middle Wall of Multi-Arch Highway Tunnel 17 is fixed, and 7 end of friction pile is fixed with anchor pull head 14;
7, reinforcement placing, the template of construction friction pile 7, rib column 12 and crown beam 15, one-piece casting concrete form whole knot Structure;
8, the template of construction diagonal brace 16, lays reinforcing bar, and casting concrete completes the construction of entire retaining structure;
9, after front-seat friction pile reaches intensity requirement, grouting and reinforcing can be carried out to the Rock And Soil in front of it.
Step 3: tunnel portal construction
1, multiple-arch tunnel is excavated inside rock mass to from the barricade of hole using central drift method in the present embodiment;
2, middle drift is first excavated when constructing tunnel, advanced 5~10m of tunnel tunnel face applies interim liner structure and tunnel Mid-board;
3, advanced tubule 18 or pipe booth structure are applied before tunnel excavation in vault Rock And Soil, to the power of vault Rock And Soil Learning performance is improved, its intensity, Reducing distortion are enhanced;
4, after tunnel is excavated using benching tunneling method, tunnel lining structure 19 is applied in time, forms closed ring structure, It is mobile with the Rock And Soil sedimentation and the gliding mass 3 that reduce top;
5, tunnel structure all applies face upward slope supporting and retaining system and be linked to be entirety with existing supporting and retaining system after, first abolish pilot tunnel portal and timely Crack is blocked, then tunnel portal barricade is abolished again and applies tunnel structure in time, blocks crack, the portal for completing tunnel is applied Work;
6, after tunnel structure evagination certain distance, tunnel portal 20 is applied, completes the construction that barricade is just being worn in tunnel.
Example proves that the retaining structure construction method that Large span tunnel of the invention is just wearing existing barricade is suitable for Large span tunnel The operating condition of the existing barricade in the hole slope Zheng Chuanyang.The retaining structure design that Large span tunnel in the present invention is just wearing existing barricade is simple, Consumptive material is less, and appearance is beautiful, easy for construction, and construction method arranges compact, can effectively shorten the duration, realize long span tunnel The supporting and retaining system for facing upward the existing barricade on slope is reinforced, and control slope sliding and deformation reduce construction disturbance and to the shadow for closing on traffic operation It rings, reduces construction risk, save project cost.
Finally, it is stated that preferred embodiment above is only used to illustrate the technical scheme of the present invention and not to limit it, although logical It crosses above preferred embodiment the present invention is described in detail, however, those skilled in the art should understand that, can be Various changes are made to it in form and in details, without departing from claims of the present invention limited range.

Claims (5)

1. the retaining structure that Large span tunnel is just wearing existing barricade, which is characterized in that including retaining structure (6), friction pile (7) and note It starches reinforcing body (8), the friction pile includes front-seat friction pile and with heel row friction pile, the friction pile at position among heel row friction pile Corresponding with front-seat friction pile, heel row friction pile is tightly attached on retaining structure, and heel row friction pile is higher than front-seat friction pile, and front row is anti- The adjacent friction pile of heel row friction pile of the stake top in same elevation between the stake top of the adjacent friction pile of sliding pile, with front-seat friction pile Between be fixedly installed with ground coupling beam (9), with heel row friction pile on same elevation of the stake top of front-seat friction pile and front-seat antiskid It is fixedly connected between stake by ground coupling beam, heel row friction pile top is fixedly installed with crown beam (15), crown beam and heel row antiskid Coupling beam (11) are fixedly installed between ground coupling beam in stake, be fixedly mounted between the coupling beam and crown beam it is several be used to reinforce supporting and retaining system The rib column (12) of structure, the retaining structure are equipped with the pull-type anchor rope for penetrating retaining structure and heel row friction pile, and front row is anti- Diagonal brace (16) are fixedly mounted with corresponding heel row friction pile top in the stake top of sliding pile, the one end of diagonal brace far from front-seat antiskid stake top It is connected to the position that heel row friction pile intersects with coupling beam or crown beam, is connected between diagonal brace, front-seat friction pile and heel row friction pile Wedge-shaped frame structure is formed between beam and corresponding heel row friction pile, the pull-type anchor rope penetrates existing barricade and supporting and retaining system knot Structure, described anchor rope one end are fixedly mounted in heel row friction pile by anchor pull head (14), and the other end is fixed on base by slip casting In rock supporting body (1), the grouting and reinforcing body (8) is mounted on around friction pile, to the Rock And Soil of stress side around friction pile into Row grouting and reinforcing.
2. the construction method that a kind of Large span tunnel is just wearing the retaining structure of existing barricade, which is characterized in that work progress include with Lower step:
Step 1: preparation of construction, comprising the following steps:
1) according to design drawing, survey sets out center line and outer contour of the tunnel portal on existing barricade;
2) it combines design drawing and surveys outer contour of the tunnel portal set out on existing barricade, determine the position of friction pile And its contour line, and mark sequence of construction;
3) it combines design drawing and surveys the tunnel portal and friction pile position contour line set out, survey sets out setting for pull-type anchor rope Seated position, and mark;
Step 2: the reinforcing retaining structure construction of the existing barricade of long span tunnel, comprising the following steps:
1) the friction pile position profile that sets is surveyed according to step 1, according to quincuncial sequence of construction interval construction friction pile to company Soffit elevation;
2) integral erection reinforcing bar and template, one-piece casting coupling beam and front-seat friction pile top cushion cap, and preset at cushion cap The reinforcing bar of diagonal brace;
3) the anchor rope position for setting out and marking is surveyed according to step 1, the anchor rope between coupling beam of constructing and ground coupling beam integrally pours Build coupling beam and friction pile below;
4) the anchor rope position for setting out and marking is surveyed according to step 1, the anchor rope between crown beam of constructing and coupling beam, one-piece casting Crown beam and friction pile below, rib column;
5) inclined support structure is applied, the construction of entire retaining structure is completed;
6) grouting and reinforcing is carried out to the Rock And Soil before friction pile, to improve the bearing capacity of Rock And Soil and retaining structure;
Step 3: Large span tunnel construction, comprising the following steps:
1) the retaining structure construction of existing barricade described in step 2 is completed after entering the maintenance stage, can carry out constructing tunnel;
2) according to the portal profile that sets of survey, punched on the existing barricade above arch using drilling machine, using advanced tubule or Rock And Soil after pipe booth structure reinforcement walls, then carry out that portal is abolished, tunnel excavation and lining cutting apply;
3) advance support is carried out to tunnel vault Rock And Soil using advanced tubule or pipe booth structure before tunnel excavation;
4) constructing tunnel is using small drilling depth, the method for diligent measurement, fast supporting, to guarantee construction safety.
3. the construction method that Large span tunnel as claimed in claim 2 is just wearing the retaining structure of existing barricade, which is characterized in that step In rapid two 1) described in friction pile quincunx sequence of construction, refer to according to the position contour line of friction pile set is surveyed, first construct The friction pile of heel row center position and the friction pile at two sides interval and front-seat friction pile not corresponding therewith, are all poured into ground At the bottom surface elevation of coupling beam, remaining friction pile is and then constructed at the bottom surface elevation of ground coupling beam.
4. the construction method that Large span tunnel as claimed in claim 3 is just wearing the retaining structure of existing barricade, which is characterized in that step In rapid two 3) described in one-piece casting coupling beam, refer to and preset the reinforcing bar of diagonal brace in coupling beam and heel row friction pile junction, in coupling beam Preset the reinforcing bar of rib column in upside.
5. the construction method that Large span tunnel as claimed in claim 4 is just wearing the retaining structure of existing barricade, which is characterized in that step In rapid two 3) and 4) described in anchor rope construction, refer to that, by drilling, anchor rope passes through existing barrier wall structure, and one end passes through slip casting It is fixed in basement rock supporting body, the other end is fixed in anti-slide pile structure using anchor pull head.
CN201710360989.0A 2017-05-19 2017-05-19 Large span tunnel is just wearing the retaining structure and its construction method of existing barricade Active CN107130613B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710360989.0A CN107130613B (en) 2017-05-19 2017-05-19 Large span tunnel is just wearing the retaining structure and its construction method of existing barricade

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710360989.0A CN107130613B (en) 2017-05-19 2017-05-19 Large span tunnel is just wearing the retaining structure and its construction method of existing barricade

Publications (2)

Publication Number Publication Date
CN107130613A CN107130613A (en) 2017-09-05
CN107130613B true CN107130613B (en) 2019-06-07

Family

ID=59732530

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710360989.0A Active CN107130613B (en) 2017-05-19 2017-05-19 Large span tunnel is just wearing the retaining structure and its construction method of existing barricade

Country Status (1)

Country Link
CN (1) CN107130613B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108487299B (en) * 2018-02-07 2020-05-15 重庆大学 Hollow triangular arc-shaped retaining wall
CN108396666A (en) * 2018-02-14 2018-08-14 重庆恩光科技有限公司 Slope treatment security protection system
CN108385993A (en) * 2018-02-14 2018-08-10 重庆交通大学 Junk prevention for building damps catching device
CN108194095A (en) * 2018-03-20 2018-06-22 上海市城市建设设计研究总院(集团)有限公司 The prefabricated superposed type vehicle driving passage structure of subterranean tunnel or gallery
CN109811773B (en) * 2019-03-01 2023-12-26 中铁十九局集团第五工程有限公司 Bias tunnel portal excavation protection structure and construction method thereof
CN110029685A (en) * 2019-04-16 2019-07-19 中铁建设集团有限公司 A kind of pile drawing anchor barricade fabricated construction
CN110205889B (en) * 2019-06-11 2021-03-02 兰州铁道设计院有限公司 Method for carrying out existing line roadbed slope width transformation by adopting combined pile slab wall structure
CN110344833A (en) * 2019-08-16 2019-10-18 招商局重庆交通科研设计院有限公司 Tunnel excavation support structure and method for tunnel construction
CN111305237A (en) * 2020-03-05 2020-06-19 中煤科工集团重庆设计研究院有限公司 Slope supporting structure and construction method
CN112502188B (en) * 2020-12-10 2022-03-22 河南博源电力设备股份有限公司 Power communication comprehensive pipe rack in easy-to-slide area and construction method thereof
CN113957815B (en) * 2021-11-30 2022-10-04 中铁二十局集团第五工程有限公司 Construction method for medium-large-diameter double-hole steel corrugated pipe culvert of highway
CN114922200B (en) * 2022-01-17 2023-11-24 兰州交通大学 Existing-newly-built combined retaining structure of wide road embankment and construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08121086A (en) * 1994-10-26 1996-05-14 Kenzo Murakami Concrete wall structure and manufacture thereof
CN202989932U (en) * 2012-12-05 2013-06-12 昆明理工大学 H-shaped double-row pile structure with large inclined angle prestressed anchor cables
CN203514328U (en) * 2013-07-22 2014-04-02 深圳市工勘岩土工程有限公司 Combined anti-slide structure
CN104389628A (en) * 2014-11-21 2015-03-04 山西省交通科学研究院 Landslide section tunnel reinforcing device and reinforcing construction method
CN105840207A (en) * 2016-03-24 2016-08-10 杭州江润科技有限公司 Cross shallow buried bias pressure loose accumulation body large-span tunnel comprehensive entrance structure construction method
CN106049512A (en) * 2016-06-21 2016-10-26 重庆交通大学 Design and calculation method for double-row pile foundation-bearing platform-retaining wall combined supporting and retaining structure
CN106499413A (en) * 2016-11-19 2017-03-15 中铁十二局集团有限公司 A kind of Shallow-buried section tunnel stratum consolidation construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08121086A (en) * 1994-10-26 1996-05-14 Kenzo Murakami Concrete wall structure and manufacture thereof
CN202989932U (en) * 2012-12-05 2013-06-12 昆明理工大学 H-shaped double-row pile structure with large inclined angle prestressed anchor cables
CN203514328U (en) * 2013-07-22 2014-04-02 深圳市工勘岩土工程有限公司 Combined anti-slide structure
CN104389628A (en) * 2014-11-21 2015-03-04 山西省交通科学研究院 Landslide section tunnel reinforcing device and reinforcing construction method
CN105840207A (en) * 2016-03-24 2016-08-10 杭州江润科技有限公司 Cross shallow buried bias pressure loose accumulation body large-span tunnel comprehensive entrance structure construction method
CN106049512A (en) * 2016-06-21 2016-10-26 重庆交通大学 Design and calculation method for double-row pile foundation-bearing platform-retaining wall combined supporting and retaining structure
CN106499413A (en) * 2016-11-19 2017-03-15 中铁十二局集团有限公司 A kind of Shallow-buried section tunnel stratum consolidation construction method

Also Published As

Publication number Publication date
CN107130613A (en) 2017-09-05

Similar Documents

Publication Publication Date Title
CN107130613B (en) Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN106223989B (en) Excavate safeguard structure and construction method in unsymmetrial loading tunnel hole
CN104452809B (en) A kind of super shallow tunnel cover and cut construction method
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN105839643A (en) Tunnel in-hole construction method adopting foundation pit support
CN103206219A (en) Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method
CN103161476B (en) Mechanical shaft-forming method of shield cutterhead maintenance shaft in tunnel and underground construction
CN102748040B (en) Main structure for metro long-span station and pillar arching construction method thereof
CN103883328B (en) The dark construction method of half lid half of high steep V-type coombe biased segment is worn under separate tunnel
Chen et al. Recent advances in high slope reinforcement in China: Case studies
CN105862930B (en) A kind of protection structure to creating existing tunnel below underground engineering
CN109914456A (en) A kind of bridge and subway tunnel adjoin newly-built or with design and construction method when building
CN108487911A (en) The compound crossing method construction method of longspan tunnel bilateral wall under complex geological condition
CN204941545U (en) Station boring construction system
CN108412502B (en) A kind of deep tunnel passes through upper-soft lower-hard ground construction method
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN108843333A (en) Collapsible Loess District tunneling double-arched tunnel passes through the construction method of existing railway
CN113565525A (en) Construction protection system and construction method for newly-built shield tunnel super-close ultra-shallow buried upper-span existing tunnel
CN107965325B (en) A kind of small interval shallow tunnel just branch arch replacement construction method
CN107288642A (en) PBA construction technologies
CN106050262A (en) Composite lining structure for super-large-span pile-foundation-joist-based bearing arched tunnel and construction method thereof
CN105863650A (en) Tunneling construction method with first wall construction and second tunneling construction
CN108979659A (en) The ruggedized construction and method of structures are worn under weak soil rich water large cross-section tunnel group
Yao et al. Numerical analysis of the influence of isolation piles in metro tunnel construction of adjacent buildings
CN103572680B (en) The roadbed filling construction method of coal mine gob

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191213

Address after: 400044 Shapingba street, Shapingba District, Chongqing, No. 174

Co-patentee after: No.5 Engineering Corporation Limited of CR22G

Patentee after: Chongqing University

Address before: 400044 Shapingba street, Shapingba District, Chongqing, No. 174

Patentee before: Chongqing University