CN107130603B - It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side - Google Patents

It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side Download PDF

Info

Publication number
CN107130603B
CN107130603B CN201710524953.1A CN201710524953A CN107130603B CN 107130603 B CN107130603 B CN 107130603B CN 201710524953 A CN201710524953 A CN 201710524953A CN 107130603 B CN107130603 B CN 107130603B
Authority
CN
China
Prior art keywords
concrete
boom
column
waterborne
pump line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710524953.1A
Other languages
Chinese (zh)
Other versions
CN107130603A (en
Inventor
梁昆
张文锋
宋晓龙
丁俊吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201710524953.1A priority Critical patent/CN107130603B/en
Publication of CN107130603A publication Critical patent/CN107130603A/en
Application granted granted Critical
Publication of CN107130603B publication Critical patent/CN107130603B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention discloses a kind of construction method for refuting using idle side and assembling boom and pouring concrete waterborne, belongs to technical field of building construction, including step 1, assembles boom;Step 2, boom casting concrete.The present invention uses boom+ground pump+construction technology just refuted, it is more significant to pour concrete effect waterborne, improve construction efficiency, accelerate construction speed, it is ensured that concrete Quality Control, it is especially waterborne when pouring cast-in-place pile concrete, its effect is more prominent, it ensure that pile foundation concrete pouring quality, in turn ensure site safety, the limited shock for reducing ship to operation platform.

Description

It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side
Technical field
The present invention relates to a kind of construction methods of concrete, and in particular to a kind of to be poured using idle square assembling boom of refuting The construction method of concrete waterborne, belongs to technical field of building construction.
Background technique
Previous long piled wharf sea casting concrete is all made of concrete mixer vessel mixed concrete, its main feature is that concrete stirs It ship rental charge and dispatches with high, scene is higher using matched correlative charges;If offshore is relatively close and when can not dispatch mixer ship Harbour project, general use side, which refutes loop wheel machine and adds, hangs the technique for pouring into mould, its main feature is that ship chartering is costly, speed of application Slowly, the concrete indices of cast in situs are required high.
Summary of the invention
Water is poured using idle square assembling boom of refuting in view of the above existing problems in the prior art, the present invention provides a kind of The construction method of upper concrete, can timely, quickly under the premise of guaranteeing safety and quality using existing ship machine equipment Completion offshore concrete pour task, and construction cost is low.
To achieve the goals above, it refutes assembling boom and pours concrete waterborne in the idle side of a kind of utilization that the present invention uses Construction method, specifically include following steps,
Step 1 assembles boom;
1) it selects space to meet the place of requirement on piling boat deck first, places truss upright-column pedestal, pedestal With deck reinforcement of weld;
2) assembly of truss upright-column is carried out, is equipped with several spreaders one in column, column is lifted to upright post base using high Strength bolt reinforcement by connection installs pump line in column, while multiple tracks bearing diagonal is arranged in column middle position, and bearing diagonal uses type Steel welded armor steel plate and column;
3) assembled complete girder is sling, the pivoting support of girder lower part is saved into top connecting hole in alignment with support, so Bolt fastening is used afterwards, this connection is non-directional, installs horizontal tower by pivoting support on the top of column, Heng Tashang is provided with spreader Two, then horizontal tower bearing diagonal one and horizontal tower bearing diagonal two install ballast box in one end of horizontal tower, the other end installs wirerope;
4) after ballast box lifts, the pump line on cantilever is unfolded by wirerope at this time, by the vertical pump in support section Pipe is connect with girder feeding bent pipe, and interface uses rubber ring seal;
5) test run tears place open with curved among big rope control concrete discharge port and lever arm, runs one in its maximum effect range Week;
6) ground pump concrete pump pipe is fixed with 90 ° of bend pipes below boom with pipe clamp, in adapter tube, checks pump line Inside whether clean up, interface checks bolt fastening situation after using rubber washer, pump line to connect, and so far completes boom Installment work;
Step 2, boom casting concrete;
1) pile driving barge stays position, and pile driving barge is equipped with the tugboat scene of carrying out and stays position;
2) casting concrete;
1. whether the basic performance of reinspection boom meets the requirements, can start to construct after meeting the requirements;
2. getting out the signal lamp and intercom of concreting;
3. washing away delivery pipe after ten minutes in feeding front pump slurry extraction, concrete can progress into magazine feed, and mortar is slow Slowly it is reduced in right amount, works normally after ten minutes;
4. discharge port changes position, outlet is encased with a gunnysack, avoids commerical ready-mixed concrete from falling on the ground, arrives It is unlocked again on another unloading position;
5. after commerical ready-mixed concrete pours, pump line is cleaned up with mortar and clear water.
As an improvement, the top of the column is equipped with reinforcement channel steel.
As an improvement, the specification of the ballast box is 1020 × 1020 × 800mm.
It goes on board compared to the pump truck in traditional technology and enters mould construction with cage, the method for the present invention has the advantage that
1. side, which refutes, has pile driving barge by oneself using company, foreign payment lease expenses is not needed;
2. ground pump is own equipment, do not need separately to purchase;
3. pile driving barge has 7 mouthfuls of windlass, for carrying out concreting, ship overall stability is good, it is not easy to hit The component poured, is conducive to finished product protection;
4. good compared with pump truck stability of going on board since the boom side of being fixed on is refuted, safety coefficient is high when construction;
5, it constructs compared to cage, speed of application can be greatly speeded up, reduce the construction period.
It is more significant that the present invention using boom pours concrete effect waterborne, improves construction efficiency, accelerates construction Progress, it is ensured that concrete Quality Control.Especially waterborne effect is more prominent when pouring cast-in-place pile concrete, that is, guarantees Pile foundation concrete pouring quality in turn ensures site safety, the limited shock for reducing ship to operation platform.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of truss upright-column in the present invention;
In figure: 1, column, 2, spreader one, 3, bearing diagonal, 4, pump line, 5, ballast box, 6, spreader two, 7, Heng Ta, 8, Heng Ta Bearing diagonal one, 9, horizontal tower bearing diagonal two, 10, wirerope, 11, pivoting support, 12, channel steel.
Specific embodiment
In order to make the objectives, technical solutions and advantages of the present invention clearer, right below by attached drawing and embodiment The present invention is further elaborated.However, it should be understood that specific embodiment described herein is only used to explain this hair Range that is bright, being not intended to restrict the invention.
Unless otherwise defined, all technical terms and scientific terms used herein are led with technology of the invention is belonged to The normally understood meaning of the technical staff in domain is identical, and term as used herein in the specification of the present invention is intended merely to retouch State the purpose of specific embodiment, it is not intended that in the limitation present invention.
It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side, following steps are specifically included,
Step 1 assembles boom;
1) it selects space to meet the place of requirement on piling boat deck first, places truss upright-column pedestal, pedestal With deck reinforcement of weld;
2) assembly of truss upright-column is carried out, as shown in Figure 1, being equipped with several spreaders 1 in column 1, column 1 is lifted to vertical Column pedestal uses high-strength bolt reinforcement by connection, pump line 4 is installed, while in column 1 in order to ensure the stabilization of truss upright-column, vertical Multiple tracks bearing diagonal 3 is arranged in 1 middle position of column, and bearing diagonal 3 is using fashioned iron welding deck plating and column 1;
3) assembled complete girder is sling, the pivoting support of girder lower part is saved into top connecting hole in alignment with support, so Bolt fastening is used afterwards, this connection is non-directional, installs horizontal tower 7 by pivoting support 11 on the top of column 1, is arranged on horizontal tower 7 There are spreader 26, horizontal tower bearing diagonal 1 and horizontal tower bearing diagonal 29, ballast box 5, other end peace then are installed in one end of horizontal tower 7 Steel loading cord 10;
4) after the lifting of ballast box 5 is good, the pump line 4 on cantilever is unfolded by wirerope 10 at this time, by hanging down in support section Straight pump line is connect with girder feeding bent pipe, and interface uses rubber ring seal, and concrete pump pipe should reexamine spiral shell after connecting Whether bolt fastening situation tightens, and is rechecked when necessary using torque spanner;
5) test run tears place open with curved among big rope control concrete discharge port and lever arm, runs one in its maximum effect range Week, boom stability, safety, cloth range etc. meet the requirements;
6) ground pump concrete pump pipe is fixed with 90 ° of bend pipes below boom with pipe clamp, in adapter tube, it is necessary to total Check whether clean up in pump line, interface must use rubber washer, and pump line should reexamine bolt fastening feelings after connecting Condition;
After the completion of above-mentioned work, that is, the installment work of boom is completed, then connect with concrete pumping pipeline, assembled Safety inspection group inspects for acceptance after the completion, and acceptance(check) can put into cloth after providing each group member's signature of record of acceptance Expect operation.
Wherein, assembling boom material requested is as shown in table 1 below.
Table 1 assembles boom material requested
Serial number Title Specification Unit Quantity
1 Column 56 × 56 × 5.0 angle steel 8000mm 4
2 Spreader one 50 × 50 × 4.0 angle steel 600mm 32
3 Bearing diagonal 40 × 40 × 4.0 angle steel 800mm 32
4 Pump line 125mm pump line 8000mm 1
5 Ballast box 1020×1020×800mm 1
6 Spreader two 14# channel steel 300mm 14
7 Horizontal tower 16# channel steel 10869mm 2
8 Horizontal tower bearing diagonal one 50 × 50 × 4mm angle steel 2700mm 2
9 Horizontal tower bearing diagonal two 50 × 50 × 4mm angle steel 5700mm 2
10 Wirerope ∅:12mm 20m 1
11 Pivoting support 315 bearings 1
12 Channel steel 160×60×4mm 4000mm 4
Step 2, boom casting concrete;
1) pile driving barge is equipped with the special tugboat scene of carrying out and stays position, and position should be according to needing pouring structure planar dimension, piping feelings Condition etc. considers, it is desirable that apparatus for distributing should be able to cover total plane, and can uniformly, promptly carry out cloth, equipment should securely, Stablize and do not influence the normal operating of other processes;
When using fixed boom operation, ship machine, which stays position, should will pour position as much as possible in fixed boom In working range, avoiding carrying out secondary position of staying can complete to pour;
2) casting concrete;
Boom construction point:
1. whether the basic performance of reinspection boom meets the requirements, with big rope control commerical ready-mixed concrete discharge port and lever arm Centre is curved to tear place open, runs one week in its maximum effect range, can start to construct after meeting the requirements;
2. getting out the signal lamp and intercom of concreting, it is ensured that the lamp pump that goes out stops, halt it is vertical stop, foreground pours a little 4 seconds must be shifted to an earlier date to halt, turn off the light, communication must set special messenger's progress, and when carrying on construction work at night, the people for controlling concrete must mix hand Electricity sees concreting height and concrete quality clearly;
3. washing away delivery pipe after ten minutes in feeding front pump slurry extraction, concrete can progress into magazine feed, and mortar is slow Slowly it is reduced in right amount, can work normally within 10 minutes or so;
4. discharge port changes position, outlet is encased with a gunnysack, avoids commerical ready-mixed concrete from falling on the ground, to separately It is unlocked again on one unloading position;
After 5. commerical ready-mixed concrete pours, it is necessary to clean up pump line with mortar and clear water, avoid pipe inner concrete Plugging phenomenon occurs for condensation.
As the improvement of embodiment, the top of the column 1 is equipped with reinforcement channel steel 12, and overall structural strength is high, consolidates Property is good.
It is compared through analysis, boom casting concrete technique of the invention is gone on board compared with concrete mixer hangs filling work with loop wheel machine Skill saves equipment leasing expense, while also saving the time that ship repeatedly stays position, greatly improves casting concrete casting speed Degree, the duration of pouring significantly reduce, and the casting quality of concrete is effectively guaranteed.
Secondly, refuting assembling boom using idle side, to pour concrete engineering method construction efficiency waterborne high, safe and reliable, economical Benefit is evident;Boom assembling is quick and easy, adapts to most harbour over-water construction projects, especially Cambodia area There is a serious shortage in the supply for the ships such as mixer ship machine equipment, dispatches from domestic or other countries costly.Therefore, it refutes and sets using existing idle side Standby to design and be transformed by reasonable, the construction task of completion Wharf Engineering concreting waterborne that can be more outstanding is right Correlation engineering has certain reference directive function.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modification, equivalent replacement or improvement etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (3)

1. a kind of refute the construction method that assembling boom pours concrete waterborne using idle side, which is characterized in that specifically include Following steps,
Step 1 assembles boom;
1) it selects space to meet the place of requirement on piling boat deck first, places truss upright-column pedestal, pedestal and first Plate reinforcement of weld;
2) assembly of truss upright-column is carried out, is equipped with several spreaders one (2) in column (1), column (1) lifting to upright post base is adopted With high-strength bolt reinforcement by connection, pump line (4) are installed in column (1), while multiple tracks bearing diagonal is set in column (1) middle position (3), bearing diagonal (3) is using fashioned iron welding deck plating and column (1);
3) assembled complete girder is sling, the pivoting support of girder lower part is saved into top connecting hole in alignment with support, is then used Bolt fastening, this connection is non-directional, horizontal tower (7) is installed by pivoting support (11) on the top of column (1), on horizontal tower (7) It is provided with spreader two (6), horizontal tower bearing diagonal one (8) and horizontal tower bearing diagonal two (9), counterweight then is installed in one end of Heng Ta (7) Case (5), the other end install wirerope (10);
4) after ballast box (5) lifting is good, the pump line on cantilever (4) is unfolded by wirerope (10) at this time, will be in support section Vertical pump line is connect with girder feeding bent pipe, and interface uses rubber ring seal;
5) test run is torn place open with curved among big rope control concrete discharge port and lever arm, is run one week in its maximum effect range;
6) ground pump concrete pump pipe is fixed with 90 ° of bend pipes below boom with pipe clamp, in adapter tube, checking in pump line is No to clean up, interface checks bolt fastening situation after using rubber washer, pump line to connect, and so far completes the peace of boom Fill work;
Step 2, boom casting concrete;
1) pile driving barge stays position, and pile driving barge is equipped with the tugboat scene of carrying out and stays position;
2) casting concrete;
1. whether the basic performance of reinspection boom meets the requirements, can start to construct after meeting the requirements;
2. getting out the signal lamp and intercom of concreting;
3. washing away delivery pipe after ten minutes in feeding front pump slurry extraction, concrete can progress into magazine feed, and mortar slowly subtracts It is few to arrive in right amount, it works normally after ten minutes;
4. discharge port changes position, outlet is encased with a gunnysack, avoids commerical ready-mixed concrete from falling on the ground, arrives another It is unlocked again on a unloading position;
5. after commerical ready-mixed concrete pours, pump line is cleaned up with mortar and clear water.
2. the construction method that assembling boom pours concrete waterborne is refuted by the idle side of a kind of utilization according to claim 1, It is characterized in that, the top of the column (1) is equipped with reinforcement with channel steel (12).
3. the construction method that assembling boom pours concrete waterborne is refuted by the idle side of a kind of utilization according to claim 1, It is characterized in that, the specification of the ballast box (5) is 1020 × 1020 × 800mm.
CN201710524953.1A 2017-06-30 2017-06-30 It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side Active CN107130603B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710524953.1A CN107130603B (en) 2017-06-30 2017-06-30 It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710524953.1A CN107130603B (en) 2017-06-30 2017-06-30 It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side

Publications (2)

Publication Number Publication Date
CN107130603A CN107130603A (en) 2017-09-05
CN107130603B true CN107130603B (en) 2019-10-11

Family

ID=59737271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710524953.1A Active CN107130603B (en) 2017-06-30 2017-06-30 It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side

Country Status (1)

Country Link
CN (1) CN107130603B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162279A (en) * 2018-10-09 2019-01-08 长江勘测规划设计研究有限责任公司 With the distribution device that can continuously put in storage and its construction method of tower crane cooperation
CN112478100B (en) * 2020-12-18 2023-06-27 览越工程管理咨询有限公司 Method for constructing concrete spherical aquatic building

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08170343A (en) * 1994-12-16 1996-07-02 Fujita Corp Finishing construction method of underwater rubble mound
CN2285337Y (en) * 1996-08-23 1998-07-01 建设部长沙建设机械研究院 Manual concrete distributing lover
JP2000017644A (en) * 1998-07-01 2000-01-18 Kansai Electric Power Co Inc:The Installation method of underwater structure
CN201730053U (en) * 2010-04-15 2011-02-02 上海建工(集团)总公司 Symmetric concrete casting device for box girder over water
CN104060545A (en) * 2014-07-10 2014-09-24 中交二航局第四工程有限公司 Overwater suspension cable trestle capable of being used for pumping concrete and construction method and application thereof
CN206143774U (en) * 2016-10-15 2017-05-03 中铁四局集团有限公司 Assembling wharf boat overwater operation platform

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08170343A (en) * 1994-12-16 1996-07-02 Fujita Corp Finishing construction method of underwater rubble mound
CN2285337Y (en) * 1996-08-23 1998-07-01 建设部长沙建设机械研究院 Manual concrete distributing lover
JP2000017644A (en) * 1998-07-01 2000-01-18 Kansai Electric Power Co Inc:The Installation method of underwater structure
CN201730053U (en) * 2010-04-15 2011-02-02 上海建工(集团)总公司 Symmetric concrete casting device for box girder over water
CN104060545A (en) * 2014-07-10 2014-09-24 中交二航局第四工程有限公司 Overwater suspension cable trestle capable of being used for pumping concrete and construction method and application thereof
CN206143774U (en) * 2016-10-15 2017-05-03 中铁四局集团有限公司 Assembling wharf boat overwater operation platform

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
工程方驳改搅拌船的技术思路及工艺;程旭东 等;《中国水运》;20130831;第13卷(第8期);第1-2页 *
混凝土水上浇筑技术在柬埔寨上丁湄公河大桥施工中的应用;曹正亮;《建筑施工》;20130925;第35卷(第9期);第837-838页 *

Also Published As

Publication number Publication date
CN107130603A (en) 2017-09-05

Similar Documents

Publication Publication Date Title
CN101619630B (en) Mounting method of steel chimney and implementary jacking device
CN106677258B (en) A kind of mounting process of power plant sea water intake caisson
CN101832049A (en) Concrete-structured conjoined cylindrical shell construction device and method therefor
CN107130603B (en) It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side
CN104975719A (en) Novel material distribution device and construction method for pouring floor concrete by using same
CN101858059A (en) Construction method of erecting prestressed concrete beam on river
CN211849244U (en) Novel assembled high-pile beam-slab wharf structure
CN104649039B (en) Concrete transporter
CN202689016U (en) Cofferdam assembling and lifting platform for double-wall steel cofferdam construction of deep-water bridge pier
CN108570974A (en) A kind of prefabricated fish pass slot of bottom plate
CN110172995B (en) Grouting construction system and method for large-diameter single-pile steel pipe pile interpolation transition section
CN209795746U (en) novel assembled is tied and is leaned on ship device
CN209469875U (en) A kind of concrete pump pipe bending place support device
CN107719583B (en) Equipment base and manhole cover combined device convenient to disassemble and examine
CN112412154B (en) Ultra-high voltage transmission line construction process with floating type overwater platform as operation surface
CN105822128A (en) Interior masonry and exterior sliding construction process method for chimney
CN210341975U (en) Major diameter single pile steel-pipe pile interpolation changeover portion grouting construction system
CN201762737U (en) Shallow plate loading test modified device
CN214738234U (en) Modular breakwater dyke head navigation light stake foundation structure
CN106192767B (en) A kind of device and construction method that can improve bottom concrete bearing capacity
CN210763974U (en) Be suitable for reverse construction method to get soil mouthful and pass suspension type electric hoist for material
CN113431081A (en) Integral ship-leaning anti-collision structure of offshore wind power multi-pile foundation and construction method
CN202899035U (en) Assembling type gabion gravity anchor casting and unmooring device
CN206070380U (en) A kind of device that can improve bottom concrete bearing capacity
CN208328869U (en) A kind of prefabricated fish pass slot of bottom plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant