CN109162279A - With the distribution device that can continuously put in storage and its construction method of tower crane cooperation - Google Patents
With the distribution device that can continuously put in storage and its construction method of tower crane cooperation Download PDFInfo
- Publication number
- CN109162279A CN109162279A CN201811171827.3A CN201811171827A CN109162279A CN 109162279 A CN109162279 A CN 109162279A CN 201811171827 A CN201811171827 A CN 201811171827A CN 109162279 A CN109162279 A CN 109162279A
- Authority
- CN
- China
- Prior art keywords
- bend pipe
- cloth tube
- shaped bend
- pipe
- tower crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a kind of distribution devices that can continuously put in storage with tower crane cooperation, including the first cloth tube, second cloth tube, first U-shaped bend pipe, second U-shaped bend pipe, feed pipe and fixed bracket, first cloth tube is equipped with the lifting rope for connecting with crane hook, one end of first cloth tube is connect with the both ends of the first U-shaped bend pipe by anchor tip respectively with one end of the second cloth tube, the other end of second cloth tube is connect with one end of the second U-shaped bend pipe by anchor tip, the feed pipe is mounted on fixed bracket, the feeding side of the feed pipe with concrete pump machine for connecting, the discharge end of the feed pipe is arranged straight up and is connect with the other end of the second U-shaped bend pipe by swivel joint, the first U-shaped bend pipe and the second U-shaped bend pipe are connected by two 90 degree of bend pipes by swivel joint It connects.The present invention has the characteristics that simple structure, convenient for disassembly and assembly, strong operability, intensity of putting in storage are high, construction is continuous quick.
Description
Technical field
The present invention relates to the realm of building construction, and in particular to a kind of distribution device that can continuously put in storage of the cooperation with tower crane and
Its construction method.
Background technique
It during construction of hydro project, is poured through the mode frequently with pump concrete, conventional pump concrete puts in storage
And distributing mode (is laying of markstone) in concreting process in the large volume of vertical ascent (concrete dam), applicability is poor, and
There are certain safety, quality hidden danger, process intersection reduces construction efficiency repeatedly.Therefore, taking the reasonable mode of putting in storage is to protect
Demonstrate,prove pump mass concrete construction quality, safety and the key for ensuring construction speed.In conventional pumping concrete construction
There are problems that the following:
1, concrete pump pipe terminal discharge point, which directly passes through tower crane placer and is arranged in, pours in storehouse, accounts for pressure and pours one in storehouse
Fixed space to concrete distributing and pours the incorporation to vibrate in the presence of certain influence and influence block stone.
2, manually to tear pump line open frequent for peace in storehouse, big to labour demand intensity and there are some potential safety problemss.
3, it puts in storage discontinuous, the chance high temperature period is easy to appear cold seam of construction and other issues.
4, structure is complicated for traditional tower crane placer, and dismounting and transport are all extremely inconvenient.
Summary of the invention
The purpose of the invention is to overcome the shortcomings of above-mentioned background technique, a kind of can continuously entering for cooperation with tower crane is provided
The distribution device in storehouse.
In order to achieve the goal above, a kind of distribution device that can continuously put in storage with tower crane cooperation provided by the invention, packet
Include the first cloth tube, the second cloth tube, the first U-shaped bend pipe, the second U-shaped bend pipe, feed pipe and fixed bracket, first cloth
Pipe is equipped with lifting rope for connecting with crane hook, one end of one end of first cloth tube and the second cloth tube respectively with
The both ends of first U-shaped bend pipe are connected by anchor tip, and one end of the other end of second cloth tube and the second U-shaped bend pipe is logical
Anchor tip connection is crossed, the feed pipe is mounted on fixed bracket, and the feeding side of the feed pipe is used for and concrete pump machine
Connection, the discharge end of the feed pipe are arranged straight up and are connect with the other end of the second U-shaped bend pipe by swivel joint, institute
It states the first U-shaped bend pipe and the second U-shaped bend pipe and is formed by connecting by two 90 degree of bend pipes by swivel joint.
In above scheme, the other end of first cloth tube is connected with rubber hose by anchor tip.
In above scheme, first cloth tube and the second cloth tube are spliced by the straight pump line of more piece by anchor tip
At.
In above scheme, the fixed bracket is set up by shelf pipe.
A kind of construction method with the distribution device that can continuously put in storage of tower crane cooperation provided by the invention, including walk as follows
It is rapid:
1) set up fixed bracket in the storehouse surface adjacent with storehouse is poured, by discharge nozzle be mounted on fixed bracket and and coagulation
Native pump machine connection;
2) after being completed the first cloth tube, the second cloth tube, the first U-shaped bend pipe and the second U-shaped bend pipe, match in tower crane
The lower connection for completing the second U-tube and the pipe end that discharges is closed, realizes the connection of entire pipeline;
3) move back and forth the area of cloth of adjustment distribution device by the revolution of control tower crane boom and trolley, tower crane is hung
The lifting of hook can drive the swivel joint of the second U-tube, and then adjust cloth height;
4) repeating step 3) can be realized to pouring pouring without dead angle for storehouse storehouse surface.
Technical solution provided by the invention has the benefit that
The present invention has the characteristics that simple structure, convenient for disassembly and assembly, strong operability, intensity of putting in storage are high, construction is continuous quick.
Detailed description of the invention
Fig. 1 is fabric construction schematic diagram in distal end of the present invention;
Fig. 2 is fabric construction schematic diagram in proximal end of the present invention;
Fig. 3 is the first U-shaped bend pipe and its distressed structure schematic diagram;
Fig. 4 is the second U-shaped bend pipe and its distressed structure schematic diagram.
In figure: the first cloth tube 1, lifting rope 1a, rubber hose 1b, the second cloth tube 2, first 3,90 degree of bend pipes of U-shaped bend pipe
3a, second 4,90 degree of bend pipe 4a of U-shaped bend pipe, feed pipe 5, fixed bracket 6, swivel joint 7.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and embodiments.
A kind of distribution device that can continuously put in storage of and tower crane cooperation as shown in Figure 1, including the first cloth tube 1, second
Cloth tube 2, the first U-shaped bend pipe 3, the second U-shaped bend pipe 4, feed pipe 5 and fixed bracket 6, first cloth tube 1, which is equipped with, to be used
In the lifting rope 1a being connect with crane hook, one end of one end of first cloth tube 1 and the second cloth tube 2 respectively with the first U
The both ends of type bend pipe 3 are connected by anchor tip, and the other end of second cloth tube 2 and one end of the second U-shaped bend pipe 4 pass through
Anchor tip connection, the feed pipe 5 are mounted on fixed bracket 6, and the feeding side of the feed pipe 5 is used for and concrete pump machine
Connection, the discharge end of the feed pipe 5 are arranged straight up and are connected with the other end of the second U-shaped bend pipe 4 by swivel joint 7
It connects, the first U-shaped bend pipe 3 and the second U-shaped bend pipe 4 are formed by connecting by two 90 degree of bend pipes 3a, 4a by swivel joint 7.
The other end of above-mentioned first cloth tube 1 is connected with rubber hose 1b by anchor tip.
Above-mentioned first cloth tube 1 and the second cloth tube 2 are spliced by the straight pump line of more piece by anchor tip.
Above-mentioned fixed bracket 6 is set up by shelf pipe.
The above-mentioned construction method with the distribution device that can continuously put in storage of tower crane cooperation, includes the following steps:
1) set up fixed bracket in the storehouse surface adjacent with storehouse is poured, by discharge nozzle be mounted on fixed bracket and and coagulation
Native pump machine connection;
2) after being completed the first cloth tube, the second cloth tube, the first U-shaped bend pipe and the second U-shaped bend pipe, match in tower crane
The lower connection for completing the second U-tube and the pipe end that discharges is closed, realizes the connection of entire pipeline;
3) move back and forth the area of cloth of adjustment distribution device by the revolution of control tower crane boom and trolley, tower crane is hung
The lifting of hook can drive the swivel joint of the second U-tube, and then adjust cloth height;
4) repeating step 3) can be realized to pouring pouring without dead angle for storehouse storehouse surface.
Design principle of the invention are as follows:
The fixation bracket that the present invention is set up by using shelf pipe, it is convenient for disassembly and assembly, moreover it is possible to make full use of building site current material;
The U-shaped bend pipes of swivel joint are had by using two, and are matched with tower crane, can carry out cloth in different zones and height
Material, substantially increases the flexibility of cloth under conditions of making full use of building site existing utility.
Other unspecified parts belong to the prior art.
Claims (5)
1. the distribution device that can continuously put in storage with tower crane cooperation, it is characterised in that: including the first cloth tube (1), the second cloth
Manage (2), the first U-shaped bend pipe (3), the second U-shaped bend pipe (4), feed pipe (5) and fixed bracket (6), first cloth tube (1)
It is equipped with lifting rope (1a) for connecting with crane hook, the one of one end of first cloth tube (1) and the second cloth tube (2)
End is connect with the both ends of the first U-shaped bend pipe (3) by anchor tip respectively, the other end and the 2nd U of second cloth tube (2)
One end of type bend pipe (4) is connected by anchor tip, and the feed pipe (5) is mounted on fixed bracket (6), the feed pipe
(5) feeding side for being connect with concrete pump machine, the discharge end of the feed pipe (5) arrange straight up and with it is second U-shaped
The other end of bend pipe (4) is connected by swivel joint (7), and the first U-shaped bend pipe (3) and the second U-shaped bend pipe (4) are by two
90 degree of bend pipe (3a;4a) it is formed by connecting by swivel joint (7).
2. the distribution device according to claim 1 that can continuously put in storage with tower crane cooperation, it is characterised in that: described first
The other end of cloth tube (1) is connected with rubber hose (1b) by anchor tip.
3. the distribution device according to claim 1 or 2 that can continuously put in storage with tower crane cooperation, it is characterised in that: described
First cloth tube (1) and the second cloth tube (2) are spliced by the straight pump line of more piece by anchor tip.
4. the distribution device according to claim 3 that can continuously put in storage with tower crane cooperation, it is characterised in that: the fixation
Bracket (6) is set up by shelf pipe.
5. the distribution device that can continuously put in storage cooperated described in any one of claims 1 to 4 claim of constructing with tower crane
Method, which comprises the steps of:
1) set up fixed bracket in the storehouse surface adjacent with storehouse is poured, by discharge nozzle be mounted on fixed bracket and and concrete pump
Machine connection;
2) after being completed the first cloth tube, the second cloth tube, the first U-shaped bend pipe and the second U-shaped bend pipe, under tower crane cooperation
The connection for completing the second U-tube and the pipe end that discharges, realizes the connection of entire pipeline;
3) move back and forth the area of cloth of adjustment distribution device by the revolution of control tower crane boom and trolley, crane hook
Lifting can drive the swivel joint of the second U-tube, and then adjust cloth height;
4) repeating step 3) can be realized to pouring pouring without dead angle for storehouse storehouse surface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811171827.3A CN109162279A (en) | 2018-10-09 | 2018-10-09 | With the distribution device that can continuously put in storage and its construction method of tower crane cooperation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811171827.3A CN109162279A (en) | 2018-10-09 | 2018-10-09 | With the distribution device that can continuously put in storage and its construction method of tower crane cooperation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109162279A true CN109162279A (en) | 2019-01-08 |
Family
ID=64877595
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811171827.3A Pending CN109162279A (en) | 2018-10-09 | 2018-10-09 | With the distribution device that can continuously put in storage and its construction method of tower crane cooperation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109162279A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914809A (en) * | 2019-04-11 | 2019-06-21 | 长沙赛搏机器智能有限公司 | A kind of concrete arm tail house and concrete pumping equipment |
CN110528525A (en) * | 2019-09-30 | 2019-12-03 | 贵州水务建设工程有限公司 | A kind of big storehouse surface all standing distribution device of casting of concrete in mass and assemble method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204212431U (en) * | 2014-10-17 | 2015-03-18 | 中国十七冶集团有限公司 | Concrete pump distribution device |
US20150361681A1 (en) * | 2013-01-31 | 2015-12-17 | Huan DAO | Combination of concrete spreader and crane tower |
CN205153553U (en) * | 2015-12-03 | 2016-04-13 | 中国长江三峡集团公司 | Multipurpose combination equipment of pouring |
CN107130603A (en) * | 2017-06-30 | 2017-09-05 | 中交第航务工程局有限公司 | It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side |
CN206971224U (en) * | 2017-06-22 | 2018-02-06 | 中国建筑第八工程局有限公司 | Suitable for the concrete self-flowing pastefill pipe of deep basal pit |
CN209114472U (en) * | 2018-10-09 | 2019-07-16 | 长江勘测规划设计研究有限责任公司 | With the distribution device that can continuously put in storage of tower crane cooperation |
-
2018
- 2018-10-09 CN CN201811171827.3A patent/CN109162279A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150361681A1 (en) * | 2013-01-31 | 2015-12-17 | Huan DAO | Combination of concrete spreader and crane tower |
CN204212431U (en) * | 2014-10-17 | 2015-03-18 | 中国十七冶集团有限公司 | Concrete pump distribution device |
CN205153553U (en) * | 2015-12-03 | 2016-04-13 | 中国长江三峡集团公司 | Multipurpose combination equipment of pouring |
CN206971224U (en) * | 2017-06-22 | 2018-02-06 | 中国建筑第八工程局有限公司 | Suitable for the concrete self-flowing pastefill pipe of deep basal pit |
CN107130603A (en) * | 2017-06-30 | 2017-09-05 | 中交第航务工程局有限公司 | It is a kind of to refute the construction method that assembling boom pours concrete waterborne using idle side |
CN209114472U (en) * | 2018-10-09 | 2019-07-16 | 长江勘测规划设计研究有限责任公司 | With the distribution device that can continuously put in storage of tower crane cooperation |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914809A (en) * | 2019-04-11 | 2019-06-21 | 长沙赛搏机器智能有限公司 | A kind of concrete arm tail house and concrete pumping equipment |
CN110528525A (en) * | 2019-09-30 | 2019-12-03 | 贵州水务建设工程有限公司 | A kind of big storehouse surface all standing distribution device of casting of concrete in mass and assemble method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109736353A (en) | Construction method of composite single-side formwork deep foundation pit basement outer wall | |
CN206233596U (en) | Building block exterior wall constructional column concrete casting device | |
CN109162279A (en) | With the distribution device that can continuously put in storage and its construction method of tower crane cooperation | |
CN214658892U (en) | High-low grade concrete intercepting device | |
CN208136909U (en) | A kind of anti-levitating device of filling concrete pile cages fluking type | |
CN209114472U (en) | With the distribution device that can continuously put in storage of tower crane cooperation | |
CN107806114A (en) | Basement roof closes late poured band structure and construction method in advance | |
CN207419261U (en) | A kind of stayed bridge pylon cable concrete distributing device | |
CN207549111U (en) | One kind is suitable for cement grout agitator | |
CN207597882U (en) | A kind of vibrator for being suitable for deep narrow concrete structure position construction | |
CN206667234U (en) | Concrete pile head breaking supplementary structure | |
CN206636574U (en) | A kind of fully-automatic intelligent wet shotcreting spraying machine | |
CN212866902U (en) | Inclined three-way pipe for pouring concrete in funnel tank | |
CN208267393U (en) | Electrical wire tube one-time reserved pre-buried finished product protection device | |
CN213539753U (en) | Assembled construction is with quick cloth machine | |
CN201567793U (en) | Simple material distributing device for high-rise concrete pouring construction | |
CN210767793U (en) | Detachable pre-embedded structure for fixing safety rope | |
CN205502574U (en) | Swift formula hangs mould | |
CN209066887U (en) | Concrete component constructing device | |
CN204098505U (en) | New concrete material distributing machine | |
CN208088357U (en) | A kind of basement roof closes late poured band structure in advance | |
CN207228652U (en) | Support Spraying System for Beam Spraying Maintenance | |
CN206830191U (en) | A kind of refractory gunning equipment for wet shotcreting | |
CN205955216U (en) | Special hydraulic pressure slip casting machine of earthen archaeological site protection anchor | |
CN207111176U (en) | Tunnel pipeline supporting construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |