CN107120714B - A year-round comprehensive utilization energy-saving system - Google Patents

A year-round comprehensive utilization energy-saving system Download PDF

Info

Publication number
CN107120714B
CN107120714B CN201710352036.XA CN201710352036A CN107120714B CN 107120714 B CN107120714 B CN 107120714B CN 201710352036 A CN201710352036 A CN 201710352036A CN 107120714 B CN107120714 B CN 107120714B
Authority
CN
China
Prior art keywords
water
heat
pump
way valve
enters
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710352036.XA
Other languages
Chinese (zh)
Other versions
CN107120714A (en
Inventor
王海超
端木琳
李祥立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian University of Technology
Original Assignee
Dalian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian University of Technology filed Critical Dalian University of Technology
Priority to CN201710352036.XA priority Critical patent/CN107120714B/en
Publication of CN107120714A publication Critical patent/CN107120714A/en
Application granted granted Critical
Publication of CN107120714B publication Critical patent/CN107120714B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/18Hot-water central heating systems using heat pumps
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/34Chemical or biological purification of waste gases
    • B01D53/46Removing components of defined structure
    • B01D53/48Sulfur compounds
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/34Chemical or biological purification of waste gases
    • B01D53/74General processes for purification of waste gases; Apparatus or devices specially adapted therefor
    • B01D53/80Semi-solid phase processes, i.e. by using slurries
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22STEAM GENERATION
    • F22DPREHEATING, OR ACCUMULATING PREHEATED, FEED-WATER FOR STEAM GENERATION; FEED-WATER SUPPLY FOR STEAM GENERATION; CONTROLLING WATER LEVEL FOR STEAM GENERATION; AUXILIARY DEVICES FOR PROMOTING WATER CIRCULATION WITHIN STEAM BOILERS
    • F22D11/00Feed-water supply not provided for in other main groups
    • F22D11/02Arrangements of feed-water pumps
    • F22D11/06Arrangements of feed-water pumps for returning condensate to boiler
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23JREMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J15/00Arrangements of devices for treating smoke or fumes
    • F23J15/02Arrangements of devices for treating smoke or fumes of purifiers, e.g. for removing noxious material
    • F23J15/04Arrangements of devices for treating smoke or fumes of purifiers, e.g. for removing noxious material using washing fluids
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23JREMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J15/00Arrangements of devices for treating smoke or fumes
    • F23J15/06Arrangements of devices for treating smoke or fumes of coolers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D2258/00Sources of waste gases
    • B01D2258/02Other waste gases
    • B01D2258/0283Flue gases
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23JREMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J2215/00Preventing emissions
    • F23J2215/20Sulfur; Compounds thereof
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/12Hot water central heating systems using heat pumps
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/30Technologies for a more efficient combustion or heat usage

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Analytical Chemistry (AREA)
  • Thermal Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Biomedical Technology (AREA)
  • Combustion & Propulsion (AREA)
  • Water Supply & Treatment (AREA)
  • Treating Waste Gases (AREA)

Abstract

本发明提供了一种热电厂锅炉烟气余热用于集中供热或加热锅炉给水的全年化综合利用节能系统,属于热电厂锅炉烟气余热回收与利用技术领域。该烟气余热回收系统的烟气余热回收分为两个部分,首先回收湿式脱硫塔内由脱硫浆液和烟气直接接触换热形成的高温水的热量,采用的设备为吸收式热泵,高位驱动能源来自汽轮机抽汽;初步升温后的水进入设置于除尘器之前的气水换热器,其内有足够的蛇形管道,水从管道流动吸收高温的烟气余热,得到进一步的加热。余热的利用也分为两个部分,采暖季主要用于加热热网回水,若此时水温度能够达到热网要求,则不需进入热网加热器,否则进入热网加热器加热到热网所需的温度。非采暖季则用于提高热电厂锅炉给水温度。

The invention provides an energy-saving system for annual comprehensive utilization of boiler flue gas waste heat in a thermal power plant for centralized heating or boiler feed water heating, and belongs to the technical field of recovery and utilization of boiler flue gas waste heat in a thermal power plant. The flue gas waste heat recovery of the flue gas waste heat recovery system is divided into two parts. First, the heat of high-temperature water formed by the direct contact heat exchange between the desulfurization slurry and the flue gas in the wet desulfurization tower is recovered. The equipment used is an absorption heat pump, driven by a high position. The energy comes from the steam extraction of the steam turbine; the water after initial heating enters the air-water heat exchanger installed in front of the dust collector, and there are enough serpentine pipes in it, and the water flows from the pipes to absorb the high-temperature waste heat of the flue gas for further heating. The use of waste heat is also divided into two parts. In the heating season, it is mainly used to heat the return water of the heating network. If the water temperature can meet the requirements of the heating network at this time, it does not need to enter the heating network heater. The desired temperature of the net. In the non-heating season, it is used to increase the temperature of boiler feed water in thermal power plants.

Description

一种全年化综合利用节能系统A year-round comprehensive utilization energy-saving system

技术领域technical field

本发明涉及热电厂锅炉烟气余热回收与利用领域,尤其涉及到烟气余热直接用于集中供热或加热锅炉给水的全年化综合利用节能系统。The invention relates to the field of recovery and utilization of boiler flue gas waste heat in a thermal power plant, in particular to an annual comprehensive utilization energy-saving system in which the flue gas waste heat is directly used for central heating or boiler feed water heating.

背景技术Background technique

目前热电厂锅炉的烟气余热很少用于回收,而烟气损失一项在锅炉损失中占有最大的比重,因此如果能够回收该项余热,采暖季用于集中供热,非采暖季用于加热锅炉给水将会真正实现热电厂烟气余热的全年化综合利用,在不多耗煤的前提下提高热电厂的效率,从而达到节能减排的目的。热电厂中湿法脱硫应用广泛,如钙法和镁法是最常用的方法,他们的共同点是采用脱硫塔脱硫,脱硫塔内部烟气和脱硫浆液进行直接接触进行热质交换,一方面脱除烟气中的硫和进一步除尘,另一方面将烟气中的显热和部分潜热交换到脱硫浆液中,从而大幅降低烟气出口温度,同时脱硫浆液的温度也将升高到45℃左右,如此高的温度是非常理想的热泵低位热源,远优于其他低位热源,因此回收这部分热量很有必要,结合高温烟气侧的气水换热器,将会提高锅炉效率和热电厂能效,并减少污染物的排放。At present, the waste heat of the flue gas of the thermal power plant boiler is rarely used for recovery, and the flue gas loss accounts for the largest proportion of the boiler loss. Therefore, if the waste heat can be recovered, it can be used for central heating in the heating season and for heating in the non-heating season Boiler feed water will truly realize the year-round comprehensive utilization of waste heat from flue gas in thermal power plants, and improve the efficiency of thermal power plants on the premise of less coal consumption, so as to achieve the purpose of energy saving and emission reduction. Wet desulfurization is widely used in thermal power plants. For example, calcium method and magnesium method are the most commonly used methods. What they have in common is that the desulfurization tower is used for desulfurization. The flue gas inside the desulfurization tower is in direct contact with the desulfurization slurry for heat and mass exchange. Sulfur in the flue gas and further dust removal, on the other hand, the sensible heat and part of the latent heat in the flue gas are exchanged into the desulfurization slurry, thereby greatly reducing the outlet temperature of the flue gas, and the temperature of the desulfurization slurry will also increase to about 45 ° C. Such a high temperature is an ideal low-level heat source for heat pumps, which is far superior to other low-level heat sources. Therefore, it is necessary to recover this part of heat. Combined with the gas-water heat exchanger on the high-temperature flue gas side, it will improve boiler efficiency and thermal power plant energy efficiency, and Reduce pollutant emissions.

发明内容Contents of the invention

本发明的技术方案:Technical scheme of the present invention:

一种热电厂锅炉烟气余热用于集中供热或加热锅炉给水的全年化综合利用节能系统,分为脱硫塔集水池和氧化池一体的烟气余热全年化综合梯级利用系统与脱硫塔集水池和氧化池分开设置的烟气余热全年化综合梯级利用系统两种;An annual comprehensive energy-saving system for boiler flue gas waste heat in a thermal power plant used for central heating or heating boiler feed water, which is divided into an annual comprehensive cascade utilization system for flue gas waste heat integrated with a desulfurization tower sump and an oxidation pool and a desulfurization tower set There are two kinds of year-round comprehensive cascade utilization systems for flue gas waste heat, which are set separately for the water pool and oxidation pool;

脱硫塔集水池和氧化池一体的烟气余热全年化综合梯级利用系统,包括锅炉1、汽轮机2、冷凝设备3、除氧水箱4、锅炉回水泵5、凝结水箱6、低压加热器7、高压加热器8、减温减压器9、气水换热器10、除尘器11、脱硫塔12、烟囱13、吸收式热泵14、脱硫浆液循环泵15、工艺水泵16、脱硫剂输送泵17、风机18、脱硫副产品输送泵19、吹灰控制器28、集水池29和氧化池30;The year-round comprehensive cascade utilization system of flue gas waste heat integrating the desulfurization tower sump and oxidation pool, including boiler 1, steam turbine 2, condensing equipment 3, deoxygenated water tank 4, boiler return pump 5, condensed water tank 6, low-pressure heater 7, High-pressure heater 8, temperature and pressure reducer 9, air-water heat exchanger 10, dust collector 11, desulfurization tower 12, chimney 13, absorption heat pump 14, desulfurization slurry circulation pump 15, process water pump 16, desulfurization agent delivery pump 17 , fan 18, desulfurization by-product delivery pump 19, soot blowing controller 28, water collection tank 29 and oxidation tank 30;

在采暖期,热网回水通过第四三通阀门27进入吸收式热泵14,热网回水在吸收式热泵14中被初次加热至50~65℃;经过初次加热的热网回水从吸收式热泵14出来依次通过第三三通阀门25和第二三通阀门24,再进入气水换热器10 实现二次加热至55~68℃;从气水换热器10出来的二次加热水体经过第一三通阀门22后,依次经过低压加热器7和高压加热器8,使水体被加热至当前集中供热所需的温度,以此实现热网供水;In the heating period, the return water of the heating network enters the absorption heat pump 14 through the fourth three-way valve 27, and the return water of the heating network is heated to 50-65°C for the first time in the absorption heat pump 14; The heat pump 14 passes through the third three-way valve 25 and the second three-way valve 24 in turn, and then enters the air-water heat exchanger 10 to realize secondary heating to 55-68°C; the secondary heating from the air-water heat exchanger 10 After the water body passes through the first three-way valve 22, it passes through the low-pressure heater 7 and the high-pressure heater 8 in sequence, so that the water body is heated to the temperature required by the current central heating, so as to realize the water supply of the heating network;

在非采暖期,热网回水吸收余热的流程不运行,即不经过吸收式热泵14和气水换热器10的二次加热,无需向热网供水;此时冷凝设备3中的冷凝水分为两部分,一部分进入除氧水箱4进行除氧,经过除氧的水通过锅炉回水泵5再次回到锅炉1内使用;另一部分通过第三三通阀门25进入吸收式热泵14,冷凝水在吸收式热泵14中被初步加热之后依次通过第四三通阀门27和第二三通阀门24再进入气水换热器10实现二次加热;从气水换热器10出来的二次加热冷凝水经过第一三通阀门22后,进入除氧水箱4进行除氧,经过除氧的水通过锅炉回水泵5再次回到锅炉1内使用;In the non-heating period, the process of absorbing waste heat by returning water to the heating network does not run, that is, it does not go through the secondary heating of the absorption heat pump 14 and the air-water heat exchanger 10, and does not need to supply water to the heating network; at this time, the condensed water in the condensing device 3 is Two parts, one part enters the deaeration water tank 4 for deaeration, and the deaerated water returns to the boiler 1 again through the boiler return water pump 5 for use; the other part enters the absorption heat pump 14 through the third three-way valve 25, and the condensed water is absorbed After being initially heated in the heat pump 14, it passes through the fourth three-way valve 27 and the second three-way valve 24 and then enters the air-water heat exchanger 10 to realize secondary heating; the secondary heating condensed water coming out of the air-water heat exchanger 10 After passing through the first three-way valve 22, it enters the deaeration water tank 4 for deaeration, and the deaeration water returns to the boiler 1 again for use through the boiler return water pump 5;

锅炉1产生的蒸汽分为两部分,一部分通过减温减压器9进入热网高压加热器8,换热之后进入凝结水箱6;另一部分进入汽轮机2,之后又分为乏汽和抽汽两部分,乏汽进入冷凝设备3,实现冷凝;抽汽分为两部分,第一部分抽汽经过第一阀门20进入热网低压加热器7,换热之后进入凝结水箱6,第二部分抽汽经过第二阀门21进入吸收式热泵14作为驱动热源,之后也进入凝结水箱6;The steam generated by the boiler 1 is divided into two parts, one part enters the heat network high-pressure heater 8 through the temperature and pressure reducer 9, and enters the condensed water tank 6 after heat exchange; the other part enters the steam turbine 2, and then is divided into exhaust steam and extraction steam. part, the exhausted steam enters the condensing equipment 3 to realize condensation; the extraction steam is divided into two parts, the first part of the extraction steam enters the low-pressure heater 7 of the heat network through the first valve 20, and enters the condensate tank 6 after heat exchange, and the second part of the extraction steam passes through The second valve 21 enters the absorption heat pump 14 as a driving heat source, and then also enters the condensed water tank 6;

脱硫塔12内的脱硫浆液通过浆液泵15进入吸收式热泵14,将其热量释放到热网回水之后,降低温度的脱硫浆液再次进入脱硫塔12的喷淋系统,吸收烟气余热并进行脱硫,由此连续产生高温脱硫浆液并再次回到吸收式热泵14;The desulfurization slurry in the desulfurization tower 12 enters the absorption heat pump 14 through the slurry pump 15, releases its heat to the return water of the heat network, and then the desulfurization slurry with reduced temperature enters the spray system of the desulfurization tower 12 again to absorb the waste heat of the flue gas and perform desulfurization , thereby continuously producing high-temperature desulfurization slurry and returning to the absorption heat pump 14 again;

脱硫塔12从上到下依次设置工艺水泵16、脱硫剂输送泵17和脱硫副产品输送泵19,工艺水泵16用于向脱硫塔12内供水,脱硫剂输送泵17用于向脱硫塔12中添加脱硫剂,脱硫塔12内的副产品从脱硫副产品输送泵19排出;脱硫塔12上设有风机18,加速脱硫副产品沉淀;The desulfurization tower 12 is provided with a process water pump 16, a desulfurization agent delivery pump 17 and a desulfurization by-product delivery pump 19 in sequence from top to bottom. The process water pump 16 is used to supply water to the desulfurization tower 12, and the desulfurization agent delivery pump 17 is used to add Desulfurization agent, the by-products in the desulfurization tower 12 are discharged from the desulfurization by-product delivery pump 19; the desulfurization tower 12 is provided with a fan 18 to accelerate the precipitation of the desulfurization by-products;

脱硫塔12内经过脱硫和热质交换后降温的干净烟气进入烟囱13内;The clean flue gas cooled after desulfurization and heat and mass exchange in the desulfurization tower 12 enters the chimney 13;

锅炉1的烟道内首先设置气水换热器10,与热网回水换热后,经过除尘器 11除尘,再进入脱硫塔12进行脱硫处理;In the flue of the boiler 1, an air-water heat exchanger 10 is first arranged, and after exchanging heat with the return water of the heating network, the dust is removed by the dust collector 11, and then enters the desulfurization tower 12 for desulfurization treatment;

气水换热器10连接吹灰控制器28;The air-water heat exchanger 10 is connected to the soot blowing controller 28;

第四阀门26设置于第三三通阀门25和第四三通阀门27之间,当吸收式热泵14进行检修时,关闭第三三通阀门25和第四三通阀门27,热网回水直接通过第四阀门26进入后续流程;The fourth valve 26 is set between the third three-way valve 25 and the fourth three-way valve 27. When the absorption heat pump 14 is overhauled, the third three-way valve 25 and the fourth three-way valve 27 are closed, and the return water of the heating network Directly enter the follow-up process through the fourth valve 26;

第三阀门23设置于第一三通阀门22和第二三通阀门24之间,当气水换热器10进行检修时,关闭第一三通阀门22和第二三通阀门24,热网回水直接通过第三阀门23进入后续流程。The third valve 23 is arranged between the first three-way valve 22 and the second three-way valve 24. When the air-water heat exchanger 10 is overhauled, the first three-way valve 22 and the second three-way valve 24 are closed, and the heating network The return water directly enters the subsequent process through the third valve 23 .

脱硫塔集水池和氧化池分开设置的烟气余热全年化综合梯级利用系统包括锅炉1、汽轮机2、冷凝设备3、除氧水箱4、锅炉回水泵5、凝结水箱6、低压加热器7、高压加热器8、减温减压器9、气水换热器10、除尘器11、脱硫塔 12、烟囱13、吸收式热泵14、脱硫浆液循环泵15、工艺水泵16、脱硫剂输送泵17、风机18、脱硫副产品输送泵19、吹灰控制器28、集水池29和氧化池30;The year-round comprehensive cascade utilization system of flue gas waste heat, which is set separately from the desulfurization tower sump and oxidation tank, includes boiler 1, steam turbine 2, condensing equipment 3, deoxygenated water tank 4, boiler return pump 5, condensed water tank 6, low-pressure heater 7, High-pressure heater 8, temperature and pressure reducer 9, air-water heat exchanger 10, dust collector 11, desulfurization tower 12, chimney 13, absorption heat pump 14, desulfurization slurry circulation pump 15, process water pump 16, desulfurization agent delivery pump 17 , fan 18, desulfurization by-product delivery pump 19, soot blowing controller 28, water collection tank 29 and oxidation tank 30;

在采暖期,热网回水通过第四三通阀门27进入吸收式热泵14,热网回水在吸收式热泵14中被初次加热至50~65℃;经过初次加热的热网回水从吸收式热泵14出来依次通过第三三通阀门25和第二三通阀门24,再进入气水换热器10 实现二次加热至55~68℃;从气水换热器10出来的二次加热水体经过第一三通阀门22后,依次经过低压加热器7和高压加热器8,使水体被加热至当前集中供热所需的温度,以此实现热网供水;In the heating period, the return water of the heating network enters the absorption heat pump 14 through the fourth three-way valve 27, and the return water of the heating network is heated to 50-65°C for the first time in the absorption heat pump 14; The heat pump 14 passes through the third three-way valve 25 and the second three-way valve 24 in turn, and then enters the air-water heat exchanger 10 to realize secondary heating to 55-68°C; the secondary heating from the air-water heat exchanger 10 After the water body passes through the first three-way valve 22, it passes through the low-pressure heater 7 and the high-pressure heater 8 in sequence, so that the water body is heated to the temperature required by the current central heating, so as to realize the water supply of the heating network;

在非采暖期,热网回水吸收余热的流程不运行,即不经过吸收式热泵14和气水换热器10的二次加热,无需向热网供水;此时冷凝设备3中的冷凝水分为两部分,一部分进入除氧水箱4进行除氧,经过除氧的水通过锅炉回水泵5再次回到锅炉1内使用;另一部分通过第三三通阀门25进入吸收式热泵14,冷凝水在吸收式热泵14中被初步加热之后依次通过第四三通阀门27和第二三通阀门24再进入气水换热器10实现二次加热;从气水换热器10出来的二次加热冷凝水经过第一三通阀门22后,进入除氧水箱4进行除氧,经过除氧的水通过锅炉回水泵5再次回到锅炉1内使用;In the non-heating period, the process of absorbing waste heat by returning water to the heating network does not run, that is, it does not go through the secondary heating of the absorption heat pump 14 and the air-water heat exchanger 10, and does not need to supply water to the heating network; at this time, the condensed water in the condensing device 3 is Two parts, one part enters the deaeration water tank 4 for deaeration, and the deaerated water returns to the boiler 1 again through the boiler return water pump 5 for use; the other part enters the absorption heat pump 14 through the third three-way valve 25, and the condensed water is absorbed After being initially heated in the heat pump 14, it passes through the fourth three-way valve 27 and the second three-way valve 24 and then enters the air-water heat exchanger 10 to realize secondary heating; the secondary heating condensed water coming out of the air-water heat exchanger 10 After passing through the first three-way valve 22, it enters the deaeration water tank 4 for deaeration, and the deaeration water returns to the boiler 1 again for use through the boiler return water pump 5;

锅炉1产生的蒸汽分为两部分,一部分通过减温减压器9进入热网高压加热器8,换热之后进入凝结水箱6;另一部分进入汽轮机2,之后又分为乏汽和抽汽两部分,乏汽进入冷凝设备3,实现冷凝;抽汽分为两部分,第一部分抽汽经过第一阀门20进入热网低压加热器7,换热之后进入凝结水箱6,第二部分抽汽经过第二阀门21进入吸收式热泵14作为驱动热源,之后也进入凝结水箱6;The steam generated by the boiler 1 is divided into two parts, one part enters the heat network high-pressure heater 8 through the temperature and pressure reducer 9, and enters the condensed water tank 6 after heat exchange; the other part enters the steam turbine 2, and then is divided into exhaust steam and extraction steam. part, the exhausted steam enters the condensing equipment 3 to realize condensation; the extraction steam is divided into two parts, the first part of the extraction steam enters the low-pressure heater 7 of the heat network through the first valve 20, and enters the condensate tank 6 after heat exchange, and the second part of the extraction steam passes through The second valve 21 enters the absorption heat pump 14 as a driving heat source, and then also enters the condensed water tank 6;

脱硫塔12内的脱硫浆液进入集水池29,集水池29出水通过浆液泵15进入吸收式热泵14,将其热量释放到热网回水之后,降低温度的出水再次进入脱硫塔12的喷淋系统;The desulfurization slurry in the desulfurization tower 12 enters the sump 29, and the outlet water of the sump 29 enters the absorption heat pump 14 through the slurry pump 15, releases its heat to the return water of the heat network, and the lowered outlet water enters the spray system of the desulfurization tower 12 again ;

脱硫塔12上设置工艺水泵16,用于向脱硫塔12内供水;A process water pump 16 is arranged on the desulfurization tower 12 for supplying water to the desulfurization tower 12;

脱硫剂输送泵17用于向集水池29中添加脱硫剂;The desulfurizing agent delivery pump 17 is used to add desulfurizing agent to the sump 29;

风机18和脱硫副产品输送泵19设置在氧化池30上,集水池29内的副产品通过氧化池30氧化处理后经脱硫副产品输送泵19排出;风机18加速脱硫副产品沉淀;The fan 18 and the desulfurization by-product delivery pump 19 are arranged on the oxidation tank 30, and the by-products in the sump 29 are oxidized by the oxidation tank 30 and then discharged through the desulfurization by-product delivery pump 19; the fan 18 accelerates the desulfurization by-product precipitation;

脱硫塔12内经过脱硫和热质交换后降温的干净烟气进入烟囱13内;The clean flue gas cooled after desulfurization and heat and mass exchange in the desulfurization tower 12 enters the chimney 13;

锅炉1的烟道内首先设置气水换热器10,与热网回水换热后,经过除尘器 11除尘,再进入脱硫塔12进行脱硫处理;In the flue of the boiler 1, an air-water heat exchanger 10 is first arranged, and after exchanging heat with the return water of the heating network, the dust is removed by the dust collector 11, and then enters the desulfurization tower 12 for desulfurization treatment;

气水换热器10连接吹灰控制器28;The air-water heat exchanger 10 is connected to the soot blowing controller 28;

第四阀门26设置于第三三通阀门25和第四三通阀门27之间,当吸收式热泵14进行检修时,关闭第三三通阀门25和第四三通阀门27,热网回水直接通过第四阀门26进入后续流程;The fourth valve 26 is set between the third three-way valve 25 and the fourth three-way valve 27. When the absorption heat pump 14 is overhauled, the third three-way valve 25 and the fourth three-way valve 27 are closed, and the return water of the heating network Directly enter the follow-up process through the fourth valve 26;

第三阀门23设置于第一三通阀门22和第二三通阀门24之间,当气水换热器10进行检修时,关闭第一三通阀门22和第二三通阀门24,热网回水直接通过第三阀门23进入后续流程。The third valve 23 is arranged between the first three-way valve 22 and the second three-way valve 24. When the air-water heat exchanger 10 is overhauled, the first three-way valve 22 and the second three-way valve 24 are closed, and the heating network The return water directly enters the subsequent process through the third valve 23 .

本发明的有益效果:本发明提出的系统能够对热电厂烟气余热进行充分的全年化综合梯级利用,增大热电厂的供热能力,有效降低了热电厂的能耗,提高了能源利用效率,降低了热电厂的环境影响。Beneficial effects of the present invention: the system proposed by the present invention can fully utilize the waste heat of the flue gas of the thermal power plant for a full year and comprehensively cascade, increase the heat supply capacity of the thermal power plant, effectively reduce the energy consumption of the thermal power plant, improve energy utilization efficiency, reduce environmental impact of thermal power plants.

附图说明Description of drawings

图1是脱硫塔集水池和氧化池一体的烟气余热全年化综合梯级利用系统。Figure 1 is a year-round comprehensive cascade utilization system of flue gas waste heat integrated with the desulfurization tower sump and oxidation pool.

图2是脱硫塔集水池和氧化池分开设置的烟气余热全年化综合梯级利用系统。Figure 2 is a year-round comprehensive cascade utilization system of flue gas waste heat that is set separately from the desulfurization tower water collection pool and oxidation pool.

图中:1锅炉;2汽轮机;3冷凝设备;4除氧水箱;5锅炉回水泵;6凝结水箱; 7低压加热器;8高压加热器;9减温减压器;10气水换热器;11除尘器; 12脱硫塔;13烟囱;14吸收式热泵;15脱硫浆液循环泵;16工艺水泵; 17脱硫剂输送泵;18风机;19脱硫副产品输送泵;20、21、23、26阀门;22、24、25、27三通阀门;28吹灰控制器;29集水池;30氧化池。In the figure: 1 boiler; 2 steam turbine; 3 condensing equipment; 4 deoxygenated water tank; 5 boiler return pump; 6 condensed water tank; 7 low pressure heater; 8 high pressure heater; ;11 dust collector; 12 desulfurization tower; 13 chimney; 14 absorption heat pump; 15 desulfurization slurry circulation pump; 16 process water pump; 17 desulfurization agent delivery pump; 18 fan; ; 22, 24, 25, 27 three-way valve; 28 soot blowing controller; 29 pool; 30 oxidation pool.

具体实施方式Detailed ways

以下结合附图和技术方案,进一步说明本发明的具体实施方式。The specific implementation manners of the present invention will be further described below in conjunction with the accompanying drawings and technical solutions.

图1所述系统中,在采暖季,三通阀门(22)、(24)、(25)和(27)与热网回水联通。温度为Th的供热回水先流经吸收式热泵(14),回收脱硫塔(12) 内高温水的热量,温度上升ΔT1,之后经过初步升温的热网回水进入除尘器之前的高温烟气侧气水换热器(10),通过吸收高温烟气的显热使得温度上升ΔT2。若(Th+ΔT1+ΔT2)≥Tg,即水温达到了当前采暖阶段的供水温度要求,则关闭阀门 20,此时集中供热系统热量完全由烟气余热供给。当室外气温降低,烟气余热量不足以满足供热需求时,即(Th+ΔT1+ΔT2)<Tg,则开启阀门20,启动热网加热器(7),对热网回水进一步加热,但加热量仅需要满足温升Tg-(Th+ΔT1+ΔT2) 即可,因此可以大幅减少热网加热器的抽汽量。In the system described in Fig. 1, in the heating season, the three-way valves (22), (24), (25) and (27) are connected with the backwater of the heating network. The heating return water with a temperature of T h first flows through the absorption heat pump (14) to recover the heat of the high-temperature water in the desulfurization tower (12), and the temperature rises by ΔT 1 . The gas-water heat exchanger (10) on the flue gas side increases the temperature by ΔT 2 by absorbing the sensible heat of the high-temperature flue gas. If (T h +ΔT 1 +ΔT 2 )≥Tg, that is, the water temperature reaches the water supply temperature requirement in the current heating stage, then the valve 20 is closed, and the heat of the central heating system is completely supplied by the waste heat of the flue gas. When the outdoor air temperature drops and the residual heat of the flue gas is insufficient to meet the heating demand, that is, (T h +ΔT 1 +ΔT 2 )<Tg, then open the valve 20, start the heating network heater (7), and return water to the heating network Further heating, but the heating amount only needs to meet the temperature rise Tg-(T h +ΔT 1 +ΔT 2 ), so the steam extraction amount of the heating network heater can be greatly reduced.

图1所述系统中,在非采暖季,若凝结水温度高于脱硫浆液温度,则三通阀(22)、(24)、(25)和(27)与凝结水联通。凝结水先流经吸收式热泵(14),回收脱硫塔(12)内高温水的热量,之后经过初步升温的凝结水进入除尘器之前的高温烟气侧气水换热器(10),通过吸收高温烟气的显热使得温度进一步上升。之后送回除氧器,由于锅炉给水获得了额外的温升,因此在锅炉内所需要的热量减少,提高了锅炉的效率。In the system described in Fig. 1, in the non-heating season, if the temperature of the condensed water is higher than the temperature of the desulfurized slurry, the three-way valves (22), (24), (25) and (27) communicate with the condensed water. The condensed water first flows through the absorption heat pump (14) to recover the heat of the high-temperature water in the desulfurization tower (12), and then the condensed water that has been preliminarily heated enters the high-temperature flue gas side gas-water heat exchanger (10) before the dust collector. The sensible heat of the high-temperature flue gas makes the temperature rise further. After that, it is sent back to the deaerator. Because the boiler feed water has an additional temperature rise, the heat required in the boiler is reduced, which improves the efficiency of the boiler.

由于热电厂运行方式和参数不同,若凝结水温度低于脱硫浆液温度,则关闭阀门(21),采用直接的水水换热方式吸收脱硫内水的热量;如果两者温度相差不多,则关闭阀门(21),打开阀门(26),关闭三通阀门(25)和(27)与热泵的连接,这样凝结水将直接进入气水换热器(10)吸收高温烟气的热量,然后返回除氧器。Due to the different operating modes and parameters of thermal power plants, if the condensate temperature is lower than the desulfurization slurry temperature, close the valve (21), and use direct water-to-water heat exchange to absorb the heat of desulfurization internal water; if the two temperatures are similar, close the valve (21), open the valve (26), close the connection between the three-way valves (25) and (27) and the heat pump, so that the condensed water will directly enter the air-water heat exchanger (10) to absorb the heat of the high-temperature flue gas, and then return to the oxygenator.

Claims (1)

1. a kind of thermal power plant boiler fume afterheat is for the whole yearization of central heating or heating boiler feed water comprehensive utilization energy conservation system System, for the comprehensive gradient utilization system of fume afterheat whole yearization that desulfurizing tower collecting-tank and oxidation pond are provided separately, feature exists In the comprehensive gradient utilization system of the fume afterheat whole yearization that the desulfurizing tower collecting-tank and oxidation pond are provided separately includes boiler (1), steam turbine (2), condensing plant (3), deoxygenation water tank (4), boiler blow-down water pump (5), condensate tank (6), low-pressure heater (7), high-pressure heater (8), temperature-decreased pressure reducer (9), air-water heat exchanger (10), deduster (11), desulfurizing tower (12), chimney (13), absorption heat pump (14), desulfurization slurry circulating pump (15), technique water pump (16), desulfurizing agent delivery pump (17), blower (18), desulfuration byproduct delivery pump (19), soot-blowing control device (28), collecting-tank (29) and oxidation pond (30);
In Heating Period, heat supply network return water enters absorption heat pump (14) by the 4th three-way valve (27), and heat supply network return water is absorption Heat pump is heated to 50~65 DEG C in (14) for the first time;It is come out successively by the heat supply network return water heated for the first time from absorption heat pump (14) By third three-way valve (25) and the second three-way valve (24), enter back into air-water heat exchanger (10) realize reheating to 55~ 68℃;The reheating water body come out from air-water heat exchanger (10) successively adds by low pressure after the first three-way valve (22) Hot device (7) and high-pressure heater (8), temperature needed for making water body be heated to current central heating realize that heat supply network supplies water with this;
In non-heating period, the process that heat supply network return water absorbs waste heat is not run, i.e., exchanges heat without absorption heat pump (14) and air water The reheating of device (10), without supplying water to heat supply network;At this time the condensed moisture in condensing plant (3) be two parts, a part into Enter deoxygenation water tank (4) and carry out deoxygenation, the water by deoxygenation is turned again in boiler (1) by boiler blow-down water pump (5) and used;It is another Part enters absorption heat pump (14) by third three-way valve (25), and condensed water is tentatively heated in absorption heat pump (14) The 4th three-way valve (27) is passed sequentially through later and the second three-way valve (24) enters back into air-water heat exchanger (10) and realizes secondary add Heat;The reheating condensed water come out from air-water heat exchanger (10) is after the first three-way valve (22), into deoxygenation water tank (4) Deoxygenation is carried out, the water by deoxygenation is turned again in boiler (1) by boiler blow-down water pump (5) and used;
The steam that boiler (1) generates is divided into two parts, and a part enters heat supply network high-pressure heater (8) by temperature-decreased pressure reducer (9), Enter condensate tank (6) after heat exchange;Another part enters steam turbine (2), is divided into steam exhaust and steam extraction two parts, steam exhaust again later Into condensing plant (3), condensation is realized;Steam extraction is divided into two parts, and first part's steam extraction enters heat supply network by the first valve (20) Low-pressure heater (7) enters condensate tank (6) after heat exchange, and second part steam extraction enters absorption by the second valve (21) Heat pump (14) is used as driving heat source, also enters condensate tank (6) later;
Desulfurization slurry in desulfurizing tower (12) enters collecting-tank (29), and collecting-tank (29) water outlet is entered by slurries pump (15) to be absorbed Formula heat pump (14), after its heat is discharged into heat supply network return water, the water outlet for reducing temperature is again introduced into the spray of desulfurizing tower (12) System;
Technique water pump (16) are set on desulfurizing tower (12), for supplying water into desulfurizing tower (12);
Desulfurizing agent delivery pump (17) is used to add desulfurizing agent into collecting-tank (29);
Blower (18) and desulfuration byproduct delivery pump (19) are arranged on oxidation pond (30), and the byproduct in collecting-tank (29) passes through It is discharged after oxidation pond (30) oxidation processes through desulfuration byproduct delivery pump (19);Blower (18) accelerates desulfuration byproduct precipitating;
The clean flue gas to cool down after desulfurization and caloic exchange in desulfurizing tower (12) enters in chimney (13);
Air-water heat exchanger (10) are set first in the flue of boiler (1), after the heat exchange of heat supply network return water, are removed by deduster (11) Dirt enters back into desulfurizing tower (12) and carries out desulfurization process;
Air-water heat exchanger (10) connects soot-blowing control device (28);
4th valve (26) is set between third three-way valve (25) and the 4th three-way valve (27), when absorption heat pump (14) When being overhauled, closes third three-way valve (25) and the 4th three-way valve (27), heat supply network return water directly pass through the 4th valve (26) enter follow-up process;
Third valve (23) is set between the first three-way valve (22) and the second three-way valve (24), when air-water heat exchanger (10) When being overhauled, closes the first three-way valve (22) and the second three-way valve (24), heat supply network return water directly pass through third valve (23) enter follow-up process.
CN201710352036.XA 2017-05-18 2017-05-18 A year-round comprehensive utilization energy-saving system Active CN107120714B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710352036.XA CN107120714B (en) 2017-05-18 2017-05-18 A year-round comprehensive utilization energy-saving system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710352036.XA CN107120714B (en) 2017-05-18 2017-05-18 A year-round comprehensive utilization energy-saving system

Publications (2)

Publication Number Publication Date
CN107120714A CN107120714A (en) 2017-09-01
CN107120714B true CN107120714B (en) 2019-08-09

Family

ID=59728340

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710352036.XA Active CN107120714B (en) 2017-05-18 2017-05-18 A year-round comprehensive utilization energy-saving system

Country Status (1)

Country Link
CN (1) CN107120714B (en)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108151045A (en) * 2017-12-20 2018-06-12 广东也节能科技有限公司 A kind of flue gas heat recovery system
CN108704463B (en) * 2018-07-25 2024-03-08 北京京诚科林环保科技有限公司 A comprehensive treatment system and process for sintering flue gas desulfurization, denitrification and flue gas whitening elimination
CN109681281B (en) * 2019-01-25 2024-01-26 清华大学 A biomass cogeneration system that can simultaneously recover spent steam and flue gas waste heat
CN109945277A (en) * 2019-03-25 2019-06-28 大连理工大学 An energy-saving system using electric heat pump to deeply recover waste heat from flue gas of thermal power plant for central heating
CN109974062A (en) * 2019-03-25 2019-07-05 大连理工大学 A deep recovery system of flue gas waste heat using absorption heat pump and two-stage heat exchanger
CN109945278A (en) * 2019-03-25 2019-06-28 大连理工大学 An energy-saving system using absorption heat pump for deep recovery of flue gas waste heat for central heating
US11821637B2 (en) 2019-03-25 2023-11-21 Dalian University Of Technology Energy-saving system using electric heat pump to deeply recover flue gas waste heat from heat power plant for district heating
CN110118359B (en) * 2019-04-16 2020-11-27 天津大学 A fuel-electric complementary heating peak-shaving system for thermal power stations
CN110425512A (en) * 2019-08-27 2019-11-08 华能国际电力股份有限公司 Device and method for recycling flue gas waste heat of power plant by utilizing cascade
CN110425567A (en) * 2019-08-27 2019-11-08 华能国际电力股份有限公司 Device and method for preheating air by recycling flue gas waste heat of power plant
CN110894954B (en) * 2019-12-18 2025-08-29 台州临港热电有限公司 A high-temperature tail gas purification and waste heat recovery system
CN112023639A (en) * 2020-08-26 2020-12-04 山东国舜建设集团有限公司 Device and method for recycling latent heat in flue gas treatment of coal-fired power plant
CN112197325A (en) * 2020-10-05 2021-01-08 大连理工大学 Thermoelectric peak regulation integrated system for promoting renewable energy consumption and waste heat recovery
CN112833382A (en) * 2021-03-23 2021-05-25 西安热工研究院有限公司 Device and method for comprehensive utilization of multi-stage waste heat in power plant
CN113339872A (en) * 2021-05-27 2021-09-03 山东京清节能环保科技有限公司 Slurry waste heat recycling system
CN115046238B (en) * 2022-08-16 2022-11-04 石家庄诚峰热电有限公司 Cold and hot dual-supply system
CN116202075A (en) * 2023-03-13 2023-06-02 杭州蕴泽环境科技有限公司 System and method for recycling exhausted waste heat of a back-pressure thermal power unit
CN119554878B (en) * 2024-11-29 2025-12-26 中铝山东有限公司 A waste heat utilization system and method based on alumina production

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2182296A2 (en) * 2008-10-28 2010-05-05 Oy Scancool Ab District heating arrangement and method
CN102519068A (en) * 2011-12-02 2012-06-27 西安交通大学 Smoke water condensing and waste heat recovering device
CN103691260A (en) * 2013-12-23 2014-04-02 北京国电清新环保技术股份有限公司 Heat recovery water-saving system for desulfuration by wet process and process thereof
CN205137624U (en) * 2015-11-17 2016-04-06 北京慧峰仁和科技股份有限公司 Boiler waste heat heating system economizer

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61122428A (en) * 1984-11-19 1986-06-10 Mitsubishi Corp Two-stage cycle absorption heat pump type floor heating system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2182296A2 (en) * 2008-10-28 2010-05-05 Oy Scancool Ab District heating arrangement and method
CN102519068A (en) * 2011-12-02 2012-06-27 西安交通大学 Smoke water condensing and waste heat recovering device
CN103691260A (en) * 2013-12-23 2014-04-02 北京国电清新环保技术股份有限公司 Heat recovery water-saving system for desulfuration by wet process and process thereof
CN205137624U (en) * 2015-11-17 2016-04-06 北京慧峰仁和科技股份有限公司 Boiler waste heat heating system economizer

Also Published As

Publication number Publication date
CN107120714A (en) 2017-09-01

Similar Documents

Publication Publication Date Title
CN107120714B (en) A year-round comprehensive utilization energy-saving system
CN107178814A (en) A kind of thermal power plant boiler fume afterheat is used for the energy conserving system of central heating
CN101900347B (en) System for high-grade recycling waste heat of smoke discharged from boiler of power station
WO2018014768A1 (en) Residual heat reuse system for turbine-boiler integrated heat energy circulation
CN109945278A (en) An energy-saving system using absorption heat pump for deep recovery of flue gas waste heat for central heating
CN101709879A (en) System for deep cooling and waste heat recovery of smoke gas in boiler
CN204254934U (en) A kind of heating system utilizing compression heat pump to realize the recovery of the residual heat from boiler fume degree of depth
CN204593428U (en) Boiler low-temperature fume waste-heat recovery device
CN203823787U (en) Comprehensive smoke waste heat utilization system
CN103062754A (en) Power station machine furnace integrated cold end comprehensive optimization system
CN211011316U (en) Steam turbine boiler waste heat utilization system for coal-fired power plant
CN102269401A (en) Low-temperature flue gas waste heat recovery utilization method
CN109737446A (en) A thermal power plant boiler exhaust waste heat recovery and flue gas whitening system
CN206347555U (en) A kind of economic benefits and social benefits supplementary heat exchanger system for MGGH
CN109974062A (en) A deep recovery system of flue gas waste heat using absorption heat pump and two-stage heat exchanger
CN106996571A (en) A kind of coal-fired hot-water boiler fume afterheat depth recovery system and its method
CN104006401A (en) Power station boiler smoke waste heat deep recycling and emission reducing system
CN109945277A (en) An energy-saving system using electric heat pump to deeply recover waste heat from flue gas of thermal power plant for central heating
CN201827875U (en) Low-temperature flue gas waste heat recovery device
CN102213438A (en) Smoke exhaust system for realizing energy conservation by using coal-fired boiler flue-gas waste heat recovery and water conservation by using wet desulphurization
CN108679637A (en) A kind of energy saving white device that disappears of boiler smoke
CN206846764U (en) A kind of coal-fired hot-water boiler fume afterheat depth recovery system
CN108458334A (en) A kind of device and method of novel thermal power plant&#39;s low temperature heat and eliminating white smoke
CN201779684U (en) High-grade recycling system for exhaust heat of power station boiler
CN105757645A (en) Efficient low-grade residual heat resource utilization system for coal-fired power plant

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant