CN107119711A - A kind of connected structure and construction method for abutting existing transfer station on a large scale - Google Patents

A kind of connected structure and construction method for abutting existing transfer station on a large scale Download PDF

Info

Publication number
CN107119711A
CN107119711A CN201710545302.0A CN201710545302A CN107119711A CN 107119711 A CN107119711 A CN 107119711A CN 201710545302 A CN201710545302 A CN 201710545302A CN 107119711 A CN107119711 A CN 107119711A
Authority
CN
China
Prior art keywords
station
plate
building
reinforcement
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710545302.0A
Other languages
Chinese (zh)
Other versions
CN107119711B (en
Inventor
李凤涛
王国光
阮剑辉
周文涛
吕宝伟
杨松龄
杨立新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
China Railway Design Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp filed Critical China Railway Design Corp
Priority to CN201710545302.0A priority Critical patent/CN107119711B/en
Publication of CN107119711A publication Critical patent/CN107119711A/en
Application granted granted Critical
Publication of CN107119711B publication Critical patent/CN107119711B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a kind of connected structure and construction method for abutting existing transfer station on a large scale, reinforcement longeron and post are concrete cast-in-situ structure, make it be combined with existing structure by embedding re-bar technique to link together, set movement joint to complete the connection of new and old structure between reinforced structure and newly-built structure afterwards, the safety that measure ensures existing structure thing such as abolish finally by reinforced structure, segmentation static(al).By the newly-built station of a wide range of adjacent part of top-down invers method, interconnection technique is layered, lateral support is provided in time, can strictly control building up station deformation to ensure existing structure safety.Simultaneously, the present invention also substantially increases water resistance by adding infiltration path at the recessed longeron growth bottom deformation seam of bottom plate, and the deformation of control existing structure and internal force conversion are highly beneficial, and be particularly suitable for use in adjacent engineering on a large scale and the complicated engineering of surrounding enviroment.

Description

A kind of connected structure and construction method for abutting existing transfer station on a large scale
Technical field
The invention belongs to subway engineering field, and in particular to it is a kind of on a large scale abut existing transfer station connected structure and Construction method.
Background technology
Build subway and have become and solve the problems, such as one of effective way of Modern Traffic, with metro construction scale Constantly increase, transfer station occupies increasingly consequence in Urban Rail Transit.The transfer of the old and new's subway line And the connection problem of subway station and existing subway station is not built in same period construction after necessarily referring to.Designer first builds subway in design During station, transfer interface can be typically reserved, so that follow-up Station Design is constructed.
Due to Modern Urban Development excessive velocities, subway gauze is constantly in adjustment state, is not reserving transfer sometimes Also transfer station, such as Metro Line 1 in Nanjing and No. 4 line transfer stops drum tower station occur in the case of condition.In such engineering, If not taking the deformation of control building up station and cutting measure and the method for existing structure, it will to the safety of existing subway station Produce totally unfavorable influence.Especially when later stage construction subway horizontal span is big, surrounding enviroment are complicated, it is impossible to utilize temporary support The station of existing structure deformation is controlled, it is slightly unreasonable that it is connected design and construction scheme, it will causing existing structure to produce can not Inverse destruction, causes engineering accident what is more, jeopardizes the Metro Passenger security of the lives and property.
The content of the invention
The present invention proposes to solve the problem of prior art is present, and the purpose is to provide a kind of adjacent on a large scale existing change The connected structure and construction method of boarding station.
The technical scheme is that:A kind of connected structure for abutting existing transfer station on a large scale, including A lines were both There are station and the newly-built station of B lines, the two joining place formation transfer station is continuously opened on the side wall of A line building up station Hole, forms the multiple passways communicated with the newly-built station of B lines, and the passway includes the hole at existing structure, negative one layer Back timber at hole, back timber at minus two layers of hole, pillar at negative one layer hole, pillar at minus two layers of hole, facing for axle power can be applied When support post and full hall scaffold, newly-built structure inside back-up sand steel pipe column, steel pipe column slab column connection reinforcement ring, steel pipe Post reinforcement welding reinforcing ring, steel pipe column baseplate reinforcing bar welding reinforcing ring, the recessed ring beam of back plate connections and plate, the temporary support Temporary support column in column and full hall scaffold is steel pipe support, is furnished with jack in the middle of it, can when removing side wall and When put at side wall, steel pipe column reinforcement welding reinforcing ring is the annular slab that is welded of steel plate, newly-built station structure longeron and Crossbeam reinforcing bar is welded on reinforcing ring, it is ensured that reinforcing steel bar bear;Back plate connections in the recessed ring beam of back plate connections and plate are recessed Ring beam is the beam that is poured under newly-built structure bottom plate, and it can be against in existing building enclosure, completes horizontal direction power transmission and can be Water expandable waterstop is inside added, strengthens waterproof slab ability.
The top plate of the building up station, middle plate, at building up station bottom plate outside respectively with the cast-in-place reinforcement longeron of newly-built structure, The reinforcement longeron include negative one layer reinforcement longeron and connecting plate, minus two layers of reinforcement longeron and connecting plate, bottom plate reinforcement longeron and connecting plate, Cast-in-place negative one layer reinforcement pillar, minus two layers of reinforcement pillar, built in reverse hierarchical at movement joint, implantation reinforcing bar, the reinforcement longeron Reinforcement pillar reinforcing bar is connected by reinforcing bar connector in journey.
The connected structure applies station according to site condition construction fender post, back-up sand steel tube column foundation, back-up sand steel pipe column Negative one layer reinforcement longeron and connecting plate complete top plate connection, reserve negative one layer reinforcement pillar reinforcing bar interface by reinforcing bar connector, treat Top plate is reached after design strength, backfills earthing, and successively earth excavation is made to subinverse, construct newly-built station negative one layer side wall, middle plate And minus two layers of reinforcement longeron and connecting plate, negative one layer reinforcement pillar, minus two layers of reinforcement pillar reinforcing bar is reserved by reinforcing bar connector and connect Mouthful;After middle plate reaches design strength, successively earth excavation is made to subinverse, construction station minus two layers of side wall, bottom plate, bottom plate is recessed Longeron and connecting plate, minus two layers of reinforcement pillar;After bottom plate reaches design strength, set in building up station negative one layer and minus two layer frame Temporary support column and full hall scaffold, then segmentation abolish, the side wall in tunnel opening area building up station region.
A kind of construction method of above-mentioned connected structure for abutting existing transfer station on a large scale, comprises the following steps:
(ⅰ)Site preparation, builds that station stanchion is basic and embedded back-up sand steel pipe column the construction later stage;
(ⅱ)Excavate on the soil body to newly-built structure top plate, cut building up station structural envelope main structure body structure roof part coagulation Soil simultaneously retains its reinforcing bar, in building up station top plate implantation implantation reinforcing bar;
(ⅲ)Excavate under soil layer to newly-built structure top plate, the laying later stage builds station top plate, beam, post reinforcing bar, applies and existing knot Negative one layer reinforcement longeron and connecting plate, negative one layer reinforcement pillar at structure connecting portion side wall position, and reserved steel bar plugs into, and sets and becomes Shape is stitched, casting concrete, and completion is connected with building up station structure roof, is treated that concrete strength reaches design requirement, is backfilled top plate Earthing, station top surface recovers normal;
(ⅳ)Soil layer is excavated into newly-built structure under plate, the construction later stage builds plate in station, the tick slot in existing building enclosure makes Plate bottom portion space in being filled with slightly expanded concrete beam, builds station and building up station building enclosure, it is ensured that middle plate after connection Locate horizontal direction power transmission;
(ⅴ)Plate above building up station structural envelope structure in newly-built station is cut, is applied and existing structure connecting portion side wall position The reinforcing bar of the minus two layers of reinforcement longeron in the place of putting and connecting plate, negative one layer reinforcement longeron and connecting plate and reserved minus two layers of reinforcement pillar is plugged into Device, sets movement joint, and casting concrete, completion is connected with plate in building up station agent structure;
(ⅵ)Treat step(ⅴ)Middle board concrete reach after design strength that excavate under soil layer to newly-built structure bottom plate, construction is new Structure base slab is built, the tick slot in building up station building enclosure, the construct recessed ring beam of back plate connections and plate, embedded building up station encloses In protection structure, it is ensured that horizontal direction power transmission at bottom plate;
(ⅶ)Cut newly-built station bottom plate above building up station building enclosure, apply with existing structure connecting portion side wall position Bottom plate reinforcement longeron and connecting plate, minus two layers of reinforcement pillar, set movement joint, and casting concrete is completed and building up station body junction Structure bottom plate is connected;
(ⅷ)Temporary support column and full hall scaffold are set up inside building up station;
(ⅸ)After connected structure concrete strength reaches design requirement intensity, segmentation cuts existing structure negative one layer side wall, protects Wall and beam column position reinforcing bar at reserved reinforcement pillar are stayed, back timber at negative one layer hole is applied;
(ⅹ)After negative one layer back timber concrete reaches design requirement intensity, segmentation cuts the minus two layers of side wall of existing structure, retains Wall and beam column position reinforcing bar at reserved reinforcement pillar, apply back timber at minus two layers of hole, treat minus two layer concretes intensity knot to setting Meter removes temporary support column and full hall scaffold after requiring, completion is connected with existing A lines.
Beneficial effects of the present invention are as follows:
(1)Using top-down invers method, using newly-built structure lateral rigidity, strict control building up station deformation.
(2)Pass through top-down invers method layering connection existing structure so that existing structure internal force change substep is changed, and stress is more Rationally.
(3)First apply reinforced structure and interim upright supports, the vertical deformation of strict guarantee existing structure and safety.
(4)Staged and layered abolishes existing structure, stronger to existing structure stress check calculation.
(5)Scheme is abolished using static(al), noise pollution is small.
(6)It is small on surrounding enviroment influence and traffic impact using top-down invers method.
Brief description of the drawings
Fig. 1 is the position view of newly-built structure and existing structure in the present invention;
Fig. 2 is the sectional view in O-O sections in Fig. 1;
Fig. 3 is the assembling schematic diagram of back-up sand steel pipe column in the present invention;
Fig. 4 is the structural representation of steel pipe column slab column connection reinforcement ring in the present invention;
Fig. 5 is the structural representation of steel pipe column reinforcement welding reinforcing ring in the present invention;
Fig. 6 is the structural representation of steel pipe column baseplate reinforcing bar welding reinforcing ring in the present invention;
Fig. 7 is newly-built structure longeron and crossbeam reinforcing bar and steel column welding schematic diagram in the present invention;
Fig. 8 ~ 17 are the working procedure figures of construction method in the present invention;
Wherein:
Back timber at 2 minus two layers of hole of back timber at 1 negative one layer hole
Pillar at the negative one of 3 building up station bottom plate 4 layer hole
The negative one of pillar 6 layer reinforcement longeron and connecting plate at 5 minus two layers of hole
7 minus two layers of reinforcement longeron and the bottom plate reinforcement longeron of connecting plate 8 and connecting plate
The minus two layers of reinforcement pillar of 9 negative ones layer reinforcement pillar 10
The back-up sand steel pipe column of 11 movement joint 12
The recessed ring beam of 13 back plate connections and the building up station structural envelope structure of plate 14
The steel pipe column reinforcement welding reinforcing ring of 15 steel pipe column slab column connection reinforcement ring 16
The 17 steel pipe column baseplate reinforcing bars welding implantation reinforcing bar of reinforcing ring 18
The slightly expanded concrete beam of 19 reinforcing bar connector 20
Plate in the newly-built structure of 21 newly-built structure top plate 22
23 newly-built structure bottom plates
24 temporary support columns and full hall scaffold
The back-up sand steel tube column foundation of 25 water expandable waterstop 26
0 hole.
Embodiment
Hereinafter, referring to the drawings and embodiment the present invention is described in detail:
As shown in Fig. 1 ~ 7, a kind of connected structure for abutting existing transfer station on a large scale, including the building up station of A lines and No. B The newly-built station of line, the two joining place formation transfer station, continuously punches on the side wall of A line building up station, is formed and No. B Multiple passways that the newly-built station of line is communicated, the passway include existing structure at hole 0, negative one layer hole at back timber 1, Back timber 2 at minus two layers of hole, pillar 4 at negative one layer hole, pillar 5 at minus two layers of hole, the temporary support that can apply axle power are stood Back-up sand steel pipe column 12, steel pipe column slab column connection reinforcement ring 15, steel pipe column inside at post and full hall scaffold 24, newly-built structure Reinforcement welding reinforcing ring 16, steel pipe column baseplate reinforcing bar welding reinforcing ring 17, the recessed ring beam of back plate connections and plate 13, it is described interim Temporary support column in support post and full hall scaffold 24 is steel pipe support, and it is middle equipped with jack, can remove side Put in time at side wall during wall, steel pipe column reinforcement welding reinforcing ring 16 is the annular slab that steel plate is welded, newly-built station knot Structure longeron and crossbeam reinforcing bar are welded on reinforcing ring, it is ensured that reinforcing steel bar bear;Bottom plate in the recessed ring beam of back plate connections and plate 13 The recessed ring beam in junction is the beam poured under newly-built structure bottom plate, and it can be against in existing building enclosure, completes horizontal direction Power transmission and water expandable waterstop 25 can be added inside, strengthen waterproof slab ability.
The top plate of the building up station, middle plate, outside is vertical with the cast-in-place reinforcement of newly-built structure respectively at building up station bottom plate 3 Beam, the reinforcement longeron include negative one layer reinforcement longeron and connecting plate 6, minus two layers of reinforcement longeron and connecting plate 7, bottom plate reinforcement longeron and Cast-in-place negative one layer reinforcement pillar 9, minus two layers of reinforcement pillar 10 at connecting plate 8, movement joint 11, implantation reinforcing bar 18, the reinforcement longeron, Reinforcement pillar reinforcing bar is connected by reinforcing bar connector 19 during reverse hierarchical is built.
The connected structure is applied according to site condition construction fender post, back-up sand steel tube column foundation 26, back-up sand steel pipe column 12 Station negative one layer reinforcement longeron and connecting plate 6 complete top plate connection, and the reinforcing bar of negative one layer reinforcement pillar 9 is reserved by reinforcing bar connector 19 Interface, after top plate reaches design strength, backfills earthing, successively earth excavation is made to subinverse, newly-built station negative one layer side of constructing Wall, middle plate and minus two layers of reinforcement longeron and connecting plate 7, negative one layer reinforcement pillar 9, minus two layers of reinforcement is reserved by reinforcing bar connector 19 The reinforcing bar interface of pillar 10;After middle plate reaches design strength, successively earth excavation is made to subinverse, the minus two layers of side wall in station of constructing, The recessed longeron of bottom plate, bottom plate and connecting plate 13, minus two layers of reinforcement pillar 10;After bottom plate reaches design strength, in building up station Negative one layer and minus two layer frame set temporary support column and full hall scaffold 24, then segmentation abolish, tunnel opening area building up station area The side wall in domain.
As shown in Fig. 8 ~ 17, a kind of construction method for the connected structure for abutting existing transfer station on a large scale, including it is following Step:
(ⅰ)Site preparation, builds that station stanchion is basic and embedded back-up sand steel pipe column 12 the construction later stage;As shown in Figure 8.
(ⅱ)Excavate on the soil body to newly-built structure top plate 21, cut building up station structural envelope structure 14 and agent structure top Plate part concrete simultaneously retains its reinforcing bar, is implanted into reinforcing bar 18 in the implantation of building up station top plate, as shown in Figure 9.
(ⅲ)Excavate soil layer to newly-built structure top plate 21 under, laying the later stage build station top plate, beam, post reinforcing bar, apply with Negative one layer reinforcement longeron and connecting plate 6, negative one layer reinforcement pillar 9 at existing structure connecting portion side wall position, and reserved steel bar connects 19 are refuted, movement joint 11 is set, casting concrete, completion is connected with building up station structure roof, treats that concrete strength reaches design It is required that, top plate earth-covering is backfilled, station top surface recovers normal, as shown in Figure 10.
(ⅳ)Soil layer is excavated into newly-built structure under plate 22, the construction later stage builds plate in station, in existing building enclosure Tick slot, plate bottom portion space in being filled using slightly expanded concrete beam 20, builds station and building up station building enclosure after connection, Horizontal direction power transmission at plate in guarantee, as shown in figure 11.
(ⅴ)Plate above building up station structural envelope structure 14 in newly-built station is cut, is applied and existing structure connecting portion Minus two layers of reinforcement longeron and connecting plate 7, negative one layer reinforcement longeron and connecting plate 6 and the steel for reserving minus two layers of reinforcement pillar at side wall position Muscle connector 19, sets movement joint 11, and casting concrete, completion is connected with plate in building up station agent structure, as shown in figure 12.
(ⅵ)Treat step(ⅴ)Middle board concrete reach after design strength, excavate soil layer to newly-built structure bottom plate 23 under, Construction newly-built structure bottom plate 23, the tick slot in building up station building enclosure, the construction recessed ring beam of back plate connections and plate 13, it is embedded In building up station building enclosure, it is ensured that horizontal direction power transmission at bottom plate, as shown in figure 13.
(ⅶ)Newly-built station bottom plate above building up station building enclosure is cut, is applied and existing structure connecting portion side wall position Place's bottom plate reinforcement longeron and connecting plate 8, minus two layers of reinforcement pillar 10 are put, movement joint 11 is set, casting concrete is completed and existing car Station owner's body structure base slab is connected, as shown in figure 14.
(ⅷ)Temporary support column and full hall scaffold 24 are set up inside building up station, as shown in figure 15.
(ⅸ)After connected structure concrete strength reaches design requirement intensity, segmentation cuts existing structure negative one layer side Wall, retains wall and beam column position reinforcing bar at reserved reinforcement pillar, applies back timber 1 at negative one layer hole, as shown in figure 16.
(ⅹ)After negative one layer back timber concrete reaches design requirement intensity, segmentation cuts the minus two layers of side wall of existing structure, Retain wall and beam column position reinforcing bar at reserved reinforcement pillar, apply back timber 2 at minus two layers of hole, treat minus two layer concretes intensity knot Temporary support column and full hall scaffold 24 are removed after to design requirement, completion is connected with existing A lines, as shown in figure 17.
Embodiment 1
In the design and construction for being used in certain subway Line 1 and No. 4 line transfer stops.Due to rail network adjustment, No. 4 lines and Line 1 Changed under the conditions of not reserving transfer at drum tower station, therefore need large area to abolish existing Line 1 side wall and carry out transfer connection.1 Number line is existing F3/B3 station, and No. 4 lines are the newly-built stop of underground two.Line 1 building enclosure uses digging hole filling pile, body junction The long 210.7m of structure, width 23.05m, depth 21m box concrete structure.No. 4 line joining place foundation ditches wide 49.4m, long 112m.
Technical difficult points are:1. it is closely connected between main body open excavation section and existing Line 1 structure, such as take direct excavation pit Then the structure to existing Line 1 can be adversely affected;2. the processing between new and old structure, including linking, change between concrete structure Shape, which is seamed, puts with structurally waterproof etc.;3. large area abolishes Line 1 existing structure side wall and the structure at Line 1 station and operation will be produced Raw certain influence, therefore how to refine the Design of Reinforcement for solving Line 1 structure and transformation will be to increase economic results in society, drop The influence degree of low Line 1 operation is then most important.
After excessive kind of demonstration design, design and construction use inventive method illustrated herein.Building enclosure is using stake+anchor cable Support form, it is 26m that lid, which digs segment length, and open cut breaks length for 86m.Site operation experience, Monitoring Data and building up station operation Monitoring Data is fully proved:Can strictly it be controlled using newly-built structure lateral rigidity and layering interconnection technique using top-down invers method method Building up station deformation gauge structure safety;Reinforce existing structure in advance using reinforced structure, set temporary support column, segmentation to abolish The displacement that punches can be controlled, it is to avoid structure is destroyed;Embedding re-bar technique and reserved steel bar joint technology are ripe, can guarantee that construction quality; It is small using static(al) cutting scheme noise, favorable environment protection and civilized construction.
The present invention can be widely popularized into the reconstruction and extension project of subway station, the especially suitable newly-built Station Project of large span, It can make that engineering is safer, economy.

Claims (4)

1. a kind of connected structure for abutting existing transfer station on a large scale, includes the building up station and the newly-built car of B lines of A lines Stand, the two joining place formation transfer station continuously punches on the side wall of A line building up station, formed and the newly-built station of B lines The multiple passways communicated, it is characterised in that:The passway includes the hole at existing structure(0), negative one layer hole at push up Beam(1), back timber at minus two layers of hole(2), negative one layer hole at pillar(4), pillar at minus two layers of hole(5), axle power can be applied Temporary support column and full hall scaffold(24), at newly-built structure inside back-up sand steel pipe column(12), steel pipe column slab column connect Connect reinforcing ring(15), steel pipe column reinforcement welding reinforcing ring(16), steel pipe column baseplate reinforcing bar welding reinforcing ring(17), back plate connections Recessed ring beam and plate(13), the temporary support column and full hall scaffold(24)In temporary support column be steel pipe support, It is furnished with jack in the middle of it, can be put in time at side wall when removing side wall, steel pipe column reinforcement welding reinforcing ring(16)For steel The annular slab of plate weld, newly-built station structure longeron and crossbeam reinforcing bar are welded on reinforcing ring, it is ensured that reinforcing steel bar bear;Bottom plate The recessed ring beam in junction and plate(13)In the recessed ring beam of back plate connections be the beam that is poured under newly-built structure bottom plate, it can be supported In existing building enclosure, complete horizontal direction power transmission and water expandable waterstop can be added inside(25), strengthen waterproof slab Ability.
2. a kind of connected structure for abutting existing transfer station on a large scale according to claim 1, it is characterised in that:It is described The top plate of building up station, middle plate, building up station bottom plate(3)Place outside respectively with the cast-in-place reinforcement longeron of newly-built structure, the reinforcement Longeron includes negative one layer reinforcement longeron and connecting plate(6), minus two layers of reinforcement longeron and connecting plate(7), bottom plate reinforcement longeron and connecting plate (8), movement joint(11), implantation reinforcing bar(18), cast-in-place negative one layer reinforcement pillar at the reinforcement longeron(9), minus two layers of reinforcement post Son(10), pass through reinforcing bar connector during reverse hierarchical is built(19)Connect reinforcement pillar reinforcing bar.
3. a kind of connected structure for abutting existing transfer station on a large scale according to claim 1, it is characterised in that:It is described Connected structure is according to site condition construction fender post, back-up sand steel tube column foundation(26), back-up sand steel pipe column(12), apply station negative one Layer reinforcement longeron and connecting plate(6)Top plate connection is completed, passes through reinforcing bar connector(19)Reserved negative one layer reinforcement pillar(9)Reinforcing bar connects Mouthful, after top plate reaches design strength, earthing is backfilled, successively earth excavation is made to subinverse, newly-built station negative one layer side wall of constructing, Middle plate and minus two layers of reinforcement longeron and connecting plate(7), negative one layer reinforcement pillar(9), pass through reinforcing bar connector(19)It is reserved minus two layers Reinforcement pillar(10)Reinforcing bar interface;After middle plate reaches design strength, successively earth excavation is made to subinverse, minus two layers of station of constructing The recessed longeron of side wall, bottom plate, bottom plate and connecting plate(13), minus two layers of reinforcement pillar(10);After bottom plate reaches design strength, Building up station negative one layer and minus two layer frame set temporary support column and full hall scaffold(24), then segmentation abolish, tunnel opening area The side wall in building up station region.
4. a kind of construction method for the connected structure for abutting existing transfer station on a large scale according to claim 1 ~ 3, it is special Levy and be:Comprise the following steps:
(ⅰ)Site preparation, builds that station stanchion is basic and embedded back-up sand steel pipe column the construction later stage(12);
(ⅱ)The soil body is excavated to newly-built structure top plate(21)On, cut building up station structural envelope structure(14)And agent structure top Plate part concrete simultaneously retains its reinforcing bar, in building up station top plate implantation implantation reinforcing bar(18);
(ⅲ)Soil layer is excavated to newly-built structure top plate(21)Under, laying the later stage build station top plate, beam, post reinforcing bar, apply with both There are negative one layer reinforcement longeron and connecting plate at the side wall position of structural connection position(6), negative one layer reinforcement pillar(9), and reserved steel bar Plug into(19), movement joint is set(11), casting concrete, completion be connected with building up station structure roof, treat that concrete strength reaches To design requirement, top plate earth-covering is backfilled, station top surface recovers normal;
(ⅳ)Excavate soil layer plate into newly-built structure(22)Under, the construction later stage builds plate in station, is picked in existing building enclosure Groove, uses slightly expanded concrete beam(20)Station and building up station building enclosure are built in filling after plate bottom portion space, connection, Horizontal direction power transmission at plate in guarantee;
(ⅴ)Cut plate above building up station structural envelope structure in newly-built station(14), apply and existing structure connecting portion side Minus two layers of reinforcement longeron and connecting plate at wall displacement(7), negative one layer reinforcement longeron and connecting plate(6)And reserve minus two layers of reinforcement pillar Reinforcing bar connector(19), movement joint is set(11), casting concrete, completion be connected with plate in building up station agent structure;
(ⅵ)Treat step(ⅴ)Middle board concrete reach after design strength, excavate soil layer to newly-built structure bottom plate(23)Under, apply Work newly-built structure bottom plate(23), the tick slot in building up station building enclosure, the construct recessed ring beam of back plate connections and plate(13), it is embedding Enter in building up station building enclosure, it is ensured that horizontal direction power transmission at bottom plate;
(ⅶ)Cut newly-built station bottom plate above building up station building enclosure, apply with existing structure connecting portion side wall position Bottom plate reinforcement longeron and connecting plate(8), minus two layers of reinforcement pillar(10), movement joint is set(11), casting concrete, complete with it is existing Station agent structure bottom plate connection;
(ⅷ)Temporary support column and full hall scaffold are set up inside building up station(24);
(ⅸ)After connected structure concrete strength reaches design requirement intensity, segmentation cuts existing structure negative one layer side wall, protects Wall and beam column position reinforcing bar at reserved reinforcement pillar are stayed, back timber at negative one layer hole is applied(1);
(ⅹ)After negative one layer back timber concrete reaches design requirement intensity, segmentation cuts the minus two layers of side wall of existing structure, retains Wall and beam column position reinforcing bar at reserved reinforcement pillar, apply back timber at minus two layers of hole(2), treat that minus two layer concretes intensity knot is arrived Temporary support column and full hall scaffold are removed after design requirement(24), complete to be connected with existing A lines.
CN201710545302.0A 2017-07-06 2017-07-06 Connecting structure for large-range adjacent existing transfer station and construction method Active CN107119711B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710545302.0A CN107119711B (en) 2017-07-06 2017-07-06 Connecting structure for large-range adjacent existing transfer station and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710545302.0A CN107119711B (en) 2017-07-06 2017-07-06 Connecting structure for large-range adjacent existing transfer station and construction method

Publications (2)

Publication Number Publication Date
CN107119711A true CN107119711A (en) 2017-09-01
CN107119711B CN107119711B (en) 2022-09-06

Family

ID=59730869

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710545302.0A Active CN107119711B (en) 2017-07-06 2017-07-06 Connecting structure for large-range adjacent existing transfer station and construction method

Country Status (1)

Country Link
CN (1) CN107119711B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110159270A (en) * 2019-05-07 2019-08-23 中铁隧道集团二处有限公司 Existing subway station transfer node tunneling section lifts construction method
CN111206943A (en) * 2020-02-21 2020-05-29 上海市城市建设设计研究总院(集团)有限公司 Micro-interference post-repair underground excavation interface connecting component and construction method thereof
CN111878095A (en) * 2020-08-11 2020-11-03 中铁十八局集团有限公司 Construction method for existing underground structure of newly-built channel connection without reserved interface
CN111910786A (en) * 2020-08-10 2020-11-10 上海万科企业有限公司 Construction method for clinging deformation joint of TOD upper cover plate structural column
CN113404083A (en) * 2021-04-08 2021-09-17 中铁十六局集团有限公司 Construction method of T-shaped communication structure
CN113565533A (en) * 2021-06-01 2021-10-29 中铁十八局集团有限公司 Arch subway station building connection structure and construction method
CN114294007A (en) * 2022-01-04 2022-04-08 北京市政建设集团有限责任公司 Interface construction process and equipment for existing subway line
CN114934543A (en) * 2022-06-07 2022-08-23 广州地铁设计研究院股份有限公司 Station transfer node structure and construction method thereof
CN116290102A (en) * 2023-05-17 2023-06-23 中国铁路设计集团有限公司 Construction method for layer-adding transformation of operation underground station
CN116464098A (en) * 2023-06-20 2023-07-21 中国铁路设计集团有限公司 Construction method of continuous ultra-wide side-leaning hole-opening structure of subway station board

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202689036U (en) * 2012-05-28 2013-01-23 上海市政工程设计研究总院(集团)有限公司 Connecting structure between main body structure and accessory structure in fully-covered waterproof underground structure
CN103866701A (en) * 2012-12-14 2014-06-18 上海市政工程设计研究总院(集团)有限公司 Construction method for reserved laterally widened structure of underground box culvert structure
CN104088296A (en) * 2014-06-24 2014-10-08 上海市城市建设设计研究总院 Soft soil area basement layer adding construction method
CN104099944A (en) * 2014-07-24 2014-10-15 武汉市汉阳市政建设集团公司 Construction method for connecting subway station and long-span accessory structure
KR101467147B1 (en) * 2014-05-16 2014-11-28 주식회사 삼안 Subway platform construction method using semi-rigid connection
CN204282399U (en) * 2014-11-14 2015-04-22 广州地铁设计研究院有限公司 A kind of subway space enclosing structure
CN105951844A (en) * 2016-06-21 2016-09-21 中铁第四勘察设计院集团有限公司 Roof node structure adopting cover-excavation method and construction method of roof node structure
CN106013241A (en) * 2016-07-12 2016-10-12 中铁第勘察设计院集团有限公司 Crown beam foundation trench upright construction and cover-excavation method station combination structural system and construction method
CN207032282U (en) * 2017-07-06 2018-02-23 中国铁路设计集团有限公司 A kind of connected structure for abutting existing transfer station on a large scale

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202689036U (en) * 2012-05-28 2013-01-23 上海市政工程设计研究总院(集团)有限公司 Connecting structure between main body structure and accessory structure in fully-covered waterproof underground structure
CN103866701A (en) * 2012-12-14 2014-06-18 上海市政工程设计研究总院(集团)有限公司 Construction method for reserved laterally widened structure of underground box culvert structure
KR101467147B1 (en) * 2014-05-16 2014-11-28 주식회사 삼안 Subway platform construction method using semi-rigid connection
CN104088296A (en) * 2014-06-24 2014-10-08 上海市城市建设设计研究总院 Soft soil area basement layer adding construction method
CN104099944A (en) * 2014-07-24 2014-10-15 武汉市汉阳市政建设集团公司 Construction method for connecting subway station and long-span accessory structure
CN204282399U (en) * 2014-11-14 2015-04-22 广州地铁设计研究院有限公司 A kind of subway space enclosing structure
CN105951844A (en) * 2016-06-21 2016-09-21 中铁第四勘察设计院集团有限公司 Roof node structure adopting cover-excavation method and construction method of roof node structure
CN106013241A (en) * 2016-07-12 2016-10-12 中铁第勘察设计院集团有限公司 Crown beam foundation trench upright construction and cover-excavation method station combination structural system and construction method
CN207032282U (en) * 2017-07-06 2018-02-23 中国铁路设计集团有限公司 A kind of connected structure for abutting existing transfer station on a large scale

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110159270A (en) * 2019-05-07 2019-08-23 中铁隧道集团二处有限公司 Existing subway station transfer node tunneling section lifts construction method
CN111206943A (en) * 2020-02-21 2020-05-29 上海市城市建设设计研究总院(集团)有限公司 Micro-interference post-repair underground excavation interface connecting component and construction method thereof
CN111910786A (en) * 2020-08-10 2020-11-10 上海万科企业有限公司 Construction method for clinging deformation joint of TOD upper cover plate structural column
CN111878095A (en) * 2020-08-11 2020-11-03 中铁十八局集团有限公司 Construction method for existing underground structure of newly-built channel connection without reserved interface
CN113404083A (en) * 2021-04-08 2021-09-17 中铁十六局集团有限公司 Construction method of T-shaped communication structure
CN113565533A (en) * 2021-06-01 2021-10-29 中铁十八局集团有限公司 Arch subway station building connection structure and construction method
CN114294007A (en) * 2022-01-04 2022-04-08 北京市政建设集团有限责任公司 Interface construction process and equipment for existing subway line
CN114294007B (en) * 2022-01-04 2023-08-22 北京市政建设集团有限责任公司 Interface construction process and equipment for existing subway line
CN114934543A (en) * 2022-06-07 2022-08-23 广州地铁设计研究院股份有限公司 Station transfer node structure and construction method thereof
CN116290102A (en) * 2023-05-17 2023-06-23 中国铁路设计集团有限公司 Construction method for layer-adding transformation of operation underground station
CN116464098A (en) * 2023-06-20 2023-07-21 中国铁路设计集团有限公司 Construction method of continuous ultra-wide side-leaning hole-opening structure of subway station board
CN116464098B (en) * 2023-06-20 2023-09-05 中国铁路设计集团有限公司 Construction method of continuous ultra-wide side-leaning hole-opening structure of subway station board

Also Published As

Publication number Publication date
CN107119711B (en) 2022-09-06

Similar Documents

Publication Publication Date Title
CN107119711A (en) A kind of connected structure and construction method for abutting existing transfer station on a large scale
CN108060683B (en) A kind of middle weathering geology top-down construction method
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN108868778B (en) Non-excavation construction method for large underground structure
CN105003272B (en) Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways
CN109914456B (en) Design and construction method for adjacent and simultaneous construction of bridge and subway tunnel
CN107740426A (en) A kind of assembled arcading wall base pit supporting construction and construction technology
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN108868814B (en) Air shaft of underground excavation air duct shield tunnel of collapsible loess combined pebble soil stratum
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN105350526B (en) Method for setting up steel platform
CN105370288A (en) Construction method of shallow-buried large-span tunnels
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN112647956A (en) Construction method for shield tunneling of water-rich composite stratum to closely pass through subway station
CN106480891B (en) A kind of shaft construction method
CN104894926B (en) Retaining structure and its construction method on the high embankment of existing railway
CN207032282U (en) A kind of connected structure for abutting existing transfer station on a large scale
CN107574836A (en) Cross the constructing structure and construction method of urban road underpass
CN105986830B (en) The tunneling method of construction of roadside strip underground garage
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN107905795A (en) Subway station is inverse under a kind of operation condition widens method
CN110486062A (en) A kind of method of mechanical tunneling multilayer multispan underground engineering in weak soil
CN106498951B (en) A kind of shaft excavation construction method
CN113266362B (en) Top pipe cover excavation construction method for penetrating through existing dense anchor cable area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant