CN207032282U - A kind of connected structure for abutting existing transfer station on a large scale - Google Patents

A kind of connected structure for abutting existing transfer station on a large scale Download PDF

Info

Publication number
CN207032282U
CN207032282U CN201720810149.5U CN201720810149U CN207032282U CN 207032282 U CN207032282 U CN 207032282U CN 201720810149 U CN201720810149 U CN 201720810149U CN 207032282 U CN207032282 U CN 207032282U
Authority
CN
China
Prior art keywords
station
reinforcement
plate
minus
newly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201720810149.5U
Other languages
Chinese (zh)
Inventor
李凤涛
王国光
阮剑辉
周文涛
吕宝伟
杨松龄
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
China Railway Design Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp filed Critical China Railway Design Corp
Priority to CN201720810149.5U priority Critical patent/CN207032282U/en
Application granted granted Critical
Publication of CN207032282U publication Critical patent/CN207032282U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses a kind of connected structure for abutting existing transfer station on a large scale to include the building up station of A lines and the newly-built station of B lines, the two joining place forms transfer station, continuously punched on the side wall of A line building up station, form the multiple passways communicated with the newly-built station of B lines, the passway includes the hole at existing structure, back timber at negative one layer hole, back timber at minus two layers of hole, pillar at negative one layer hole, pillar at minus two layers of hole, the temporary support column and full hall scaffold of axle power can be applied, back-up sand steel pipe column inside at newly-built structure, steel pipe column slab column connection reinforcement ring, steel pipe column reinforcement welding reinforcing ring, steel pipe column baseplate reinforcing bar welds reinforcing ring, the recessed ring beam of back plate connections and plate.The utility model improves water resistance by adding infiltration path at the recessed longeron growth bottom deformation seam of bottom plate, and the deformation of control existing structure and internal force conversion are highly beneficial.

Description

A kind of connected structure for abutting existing transfer station on a large scale
Technical field
The utility model belongs to subway engineering field, and in particular to a kind of connected structure for abutting existing transfer station on a large scale.
Background technology
Build subway and have become and solve the problems, such as one of effective way of Modern Traffic, with metro construction scale Constantly increase, transfer station occupy increasingly consequence in Urban Rail Transit.The transfer of the old and new's subway line And the connection problem of subway station and existing subway station is not built in same period construction after necessarily referring to.Designer first builds subway in design During station, transfer interface can be typically reserved, so that follow-up Station Design is constructed.
Due to Modern Urban Development excessive velocities, subway gauze is constantly in adjustment state, sometimes in not reserved transfer Also transfer station occurs in the case of condition, such as Metro Line 1 in Nanjing and No. 4 line transfer stops drum tower station.In such engineering, If do not take the deformation of control building up station and cut measure and the method for existing structure, it will to the safety of existing subway station Produce totally unfavorable influence.Especially when the later stage builds, subway horizontal span is big, surrounding enviroment are complicated, can not utilize temporary support The station of existing structure deformation is controlled, it is slightly unreasonable that it is connected design and construction scheme, it will causing existing structure to produce can not Inverse destruction, causes engineering accident what is more, jeopardizes the Metro Passenger security of the lives and property.
Utility model content
The utility model proposes that the purpose is to provided a kind of a wide range of adjoining both to solve the problems, such as that prior art is present There is the connected structure of transfer station.
The technical solution of the utility model is:A kind of connected structure for abutting existing transfer station on a large scale, including A lines Building up station and B lines newly-built station, the two joining place formed transfer station, connect on the side wall of A line building up station It is continuous to punch, form the multiple passways communicated with the newly-built station of B lines, the passway includes hole at existing structure, born Back timber at one layer of hole, back timber at minus two layers of hole, pillar at negative one layer hole, pillar at minus two layers of hole, axle power can be applied Temporary support column and full hall scaffold, newly-built structure inside back-up sand steel pipe column, steel pipe column slab column connection reinforcement ring, Steel pipe column reinforcement welding reinforcing ring, steel pipe column baseplate reinforcing bar welding reinforcing ring, the recessed ring beam of back plate connections and plate, it is described interim Temporary support column in support post and full hall scaffold is steel pipe support, among it equipped with jack, can remove side wall When put in time at side wall, steel pipe column reinforcement welding reinforcing ring is the annular slab that is welded of steel plate, and newly-built station structure is indulged Beam and crossbeam reinforcing bar are welded on reinforcing ring, ensure reinforcing steel bar bear;Back plate connections in the recessed ring beam of back plate connections and plate Recessed ring beam is the beam that is poured under newly-built structure bottom plate, and it can be against in existing building enclosure, complete horizontal direction power transmission and Water expandable waterstop can be added inside, strengthen waterproof slab ability.
The top plate of the building up station, middle plate, at building up station bottom plate outside respectively with the cast-in-place reinforcement longeron of newly-built structure, The reinforcement longeron include negative one layer reinforcement longeron and connecting plate, minus two layers of reinforcement longeron and connecting plate, bottom plate reinforcement longeron and connecting plate, Movement joint, implantation reinforcing bar, cast-in-place negative one layer reinforcement pillar, minus two layers of reinforcement pillar at the reinforcement longeron, built in reverse hierarchical Reinforcement pillar reinforcing bar is connected by reinforcing bar connector in journey.
The connected structure applies station according to site condition construction fender post, back-up sand steel tube column foundation, back-up sand steel pipe column Negative one layer reinforcement longeron and connecting plate complete top plate connection, reserve negative one layer reinforcement pillar reinforcing bar interface by reinforcing bar connector, treat After top plate reaches design strength, earthing is backfilled, makees successively earth excavation, construct newly-built station negative one layer side wall, middle plate to subinverse And minus two layers of reinforcement longeron and connecting plate, negative one layer reinforcement pillar, minus two layers of reinforcement pillar reinforcing bar is reserved by reinforcing bar connector and connect Mouthful;After middle plate reaches design strength, make successively earth excavation to subinverse, construction station minus two layers of side wall, bottom plate, bottom plate is recessed Longeron and connecting plate, minus two layers of reinforcement pillar;After bottom plate reaches design strength, set in building up station negative one layer and minus two layer frame Temporary support column and full hall scaffold, then segmentation abolish, the side wall in tunnel opening area building up station region.
The beneficial effects of the utility model are as follows:
(1)It is strict to control building up station deformation using newly-built structure lateral rigidity using top-down invers method.
(2)Connection existing structure is layered by top-down invers method so that existing structure internal force change substep is changed, and stress is more Rationally.
(3)First apply reinforced structure and interim upright supports, the vertical deformation of strict guarantee existing structure and safety.
(4)Staged and layered abolishes existing structure, stronger to existing structure stress check calculation.
(5)Scheme is abolished using static(al), noise pollution is small.
(6)Using top-down invers method, surrounding enviroment are influenceed and traffic impact is small.
Brief description of the drawings
Fig. 1 is the position view of newly-built structure and existing structure in the utility model;
Fig. 2 is the sectional view in O-O sections in Fig. 1;
Fig. 3 is the assembling schematic diagram of back-up sand steel pipe column in the utility model;
Fig. 4 is the structural representation of steel pipe column slab column connection reinforcement ring in the utility model;
Fig. 5 is the structural representation of steel pipe column reinforcement welding reinforcing ring in the utility model;
Fig. 6 is the structural representation of steel pipe column baseplate reinforcing bar welding reinforcing ring in the utility model;
Fig. 7 is newly-built structure longeron and crossbeam reinforcing bar and steel column welding schematic diagram in the utility model;
Fig. 8 ~ 17 are the working procedure figures of construction method in the utility model;
Wherein:
Back timber at 2 minus two layers of hole of back timber at 1 negative one layer hole
Pillar at the negative one layer hole of 3 building up station bottom plate 4
The negative one layer reinforcement longeron of pillar 6 and connecting plate at 5 minus two layers of hole
7 minus two layers of reinforcement longeron and the bottom plate reinforcement longeron of connecting plate 8 and connecting plate
9 negative one layer reinforcement pillar, 10 minus two layers of reinforcement pillar
The back-up sand steel pipe column of 11 movement joint 12
The recessed ring beam of 13 back plate connections and the building up station structural envelope structure of plate 14
The steel pipe column reinforcement welding reinforcing ring of 15 steel pipe column slab column connection reinforcement ring 16
17 steel pipe column baseplate reinforcing bars welding reinforcing ring 18 is implanted into reinforcing bar
The slightly expanded concrete beam of 19 reinforcing bar connector 20
Plate in the newly-built structure of 21 newly-built structure top plate 22
23 newly-built structure bottom plates
24 temporary support columns and full hall scaffold
The back-up sand steel tube column foundation of 25 water expandable waterstop 26
0 hole.
Embodiment
Hereinafter, the utility model is described in detail with embodiment referring to the drawings:
As shown in Fig. 1 ~ 7, a kind of connected structure for abutting existing transfer station on a large scale, include the building up station of A lines With the newly-built station of B lines, the two joining place forms transfer station, continuously punched on the side wall of A line building up station, is formed The multiple passways communicated with the newly-built station of B lines, the passway include hole 0 at existing structure, at negative one layer hole Back timber 2 at back timber 1, minus two layers of hole, pillar 4 at negative one layer hole, pillar 5 at minus two layers of hole, the interim of axle power can be applied Back-up sand steel pipe column 12, steel pipe column slab column connection reinforcement ring 15 inside at support post and full hall scaffold 24, newly-built structure, Steel pipe column reinforcement welding reinforcing ring 16, steel pipe column baseplate reinforcing bar welding reinforcing ring 17, the recessed ring beam of back plate connections and plate 13, institute It is steel pipe support to state the temporary support column in temporary support column and full hall scaffold 24, can be among it equipped with jack Put in time at side wall when removing side wall, steel pipe column reinforcement welding reinforcing ring 16 is the annular slab that steel plate is welded, newly-built Station structure longeron and crossbeam reinforcing bar are welded on reinforcing ring, ensure reinforcing steel bar bear;In the recessed ring beam of back plate connections and plate 13 The recessed ring beam of back plate connections be the beam that is poured under newly-built structure bottom plate, it can be against in existing building enclosure, complete water Square to power transmission and water expandable waterstop 25 can be added inside, strengthen waterproof slab ability.
The top plate of the building up station, middle plate, outside is indulged with the cast-in-place reinforcement of newly-built structure respectively at building up station bottom plate 3 Beam, the reinforcement longeron include negative one layer reinforcement longeron and connecting plate 6, minus two layers of reinforcement longeron and connecting plate 7, bottom plate reinforcement longeron and Connecting plate 8, movement joint 11, implantation reinforcing bar 18, cast-in-place negative one layer reinforcement pillar 9, minus two layers of reinforcement pillar 10 at the reinforcement longeron, Reinforcement pillar reinforcing bar is connected by reinforcing bar connector 19 during reverse hierarchical is built.
The connected structure applies according to site condition construction fender post, back-up sand steel tube column foundation 26, back-up sand steel pipe column 12 Station negative one layer reinforcement longeron and connecting plate 6 complete top plate connection, and the reinforcing bar of negative one layer reinforcement pillar 9 is reserved by reinforcing bar connector 19 Interface, after top plate reaches design strength, backfills earthing, makees successively earth excavation, newly-built station negative one layer side of constructing to subinverse Wall, middle plate and minus two layers of reinforcement longeron and connecting plate 7, negative one layer reinforcement pillar 9, minus two layers of reinforcement is reserved by reinforcing bar connector 19 The reinforcing bar interface of pillar 10;After middle plate reaches design strength, make successively earth excavation to subinverse, the minus two layers of side wall in station of constructing, The recessed longeron of bottom plate, bottom plate and connecting plate 13, minus two layers of reinforcement pillar 10;After bottom plate reaches design strength, in building up station Negative one layer and minus two layer frame set temporary support column and full hall scaffold 24, then segmentation abolish, tunnel opening area building up station area The side wall in domain.
As shown in Fig. 8 ~ 17, a kind of construction method for the connected structure for abutting existing transfer station on a large scale, including it is following Step:
(ⅰ)Site preparation, builds that station stanchion is basic and embedded back-up sand steel pipe column 12 the construction later stage;As shown in Figure 8.
(ⅱ)Excavate on the soil body to newly-built structure top plate 21, cut building up station structural envelope structure 14 and agent structure top Plate part concrete simultaneously retains its reinforcing bar, is implanted into implantation reinforcing bar 18 in building up station top plate, as shown in Figure 9.
(ⅲ)Excavate soil layer to newly-built structure top plate 21 under, laying the later stage build station top plate, beam, post reinforcing bar, apply with Existing structure connecting portion side wall opening position negative one layer reinforcement longeron and connecting plate 6, negative one layer reinforcement pillar 9, and reserved steel bar connects 19 are refuted, movement joint 11, casting concrete are set, completion is connected with building up station structure roof, treats that concrete strength reaches design It is required that backfill top plate earth-covering, station top surface recovers normal, as shown in Figure 10.
(ⅳ)Soil layer is excavated into newly-built structure under plate 22, the construction later stage builds plate in station, in existing building enclosure Tick slot, plate bottom portion space in being filled using slightly expanded concrete beam 20, builds station and building up station building enclosure after connection, Horizontal direction power transmission at plate in guarantee, as shown in figure 11.
(ⅴ)Plate above building up station structural envelope structure 14 in newly-built station is cut, is applied and existing structure connecting portion The minus two layers of reinforcement longeron of side wall opening position and connecting plate 7, negative one layer reinforcement longeron and connecting plate 6 and the steel for reserving minus two layers of reinforcement pillar Muscle connector 19, movement joint 11, casting concrete are set, completion is connected with plate in building up station agent structure, as shown in figure 12.
(ⅵ)Treat step(ⅴ)Middle board concrete reach design strength after, excavate soil layer to newly-built structure bottom plate 23 under, Construction newly-built structure bottom plate 23, the tick slot in building up station building enclosure, the recessed ring beam of construction back plate connections and plate 13, it is embedded In building up station building enclosure, ensure horizontal direction power transmission at bottom plate, as shown in figure 13.
(ⅶ)Newly-built station bottom plate above building up station building enclosure is cut, is applied and existing structure connecting portion side wall position Place's bottom plate reinforcement longeron and connecting plate 8, minus two layers of reinforcement pillar 10 are put, movement joint 11 is set, casting concrete, completed and existing car Station owner's body structure base slab connects, as shown in figure 14.
(ⅷ)Temporary support column and full hall scaffold 24 are set up inside building up station, as shown in figure 15.
(ⅸ)After connected structure concrete strength reaches design requirement intensity, segmentation cuts existing structure negative one layer side Wall, retain wall and beam column position reinforcing bar at reserved reinforcement pillar, apply back timber 1 at negative one layer hole, as shown in figure 16.
(ⅹ)After negative one layer back timber concrete reaches design requirement intensity, segmentation cuts the minus two layers of side wall of existing structure, Retain wall and beam column position reinforcing bar at reserved reinforcement pillar, apply back timber 2 at minus two layers of hole, treat minus two layer concretes intensity knot Temporary support column and full hall scaffold 24 are removed after to design requirement, completion is connected with existing A lines, as shown in figure 17.
Embodiment 1
It is used in the design and construction of certain subway Line 1 and No. 4 line transfer stops.Because rail network adjusts, No. 4 lines and 1 Number line is changed under the conditions of the reserved transfer in drum tower station, therefore is needed large area to abolish existing Line 1 side wall and carried out transfer company It is logical.Line 1 is existing F3/B3 station, and No. 4 lines are the newly-built stop of underground two.Line 1 building enclosure uses digging hole filling pile, main The long 210.7m of body structure, wide 23.05m, deep 21m box concrete structure.No. 4 line joining place foundation ditches wide 49.4m, long 112m.
Technical difficult points are:1. it is closely connected between main body open excavation section and existing Line 1 structure, such as take direct excavation pit Then the structure of existing Line 1 can be adversely affected;2. the processing between new and old structure, including linking, change between concrete structure Shape, which seams, puts with structurally waterproof etc.;3. large area abolishes Line 1 existing structure side wall and the structure at Line 1 station and operation will be produced Raw certain influence, therefore how to refine the Design of Reinforcement for solving Line 1 structure and transformation will be to increase economic results in society, drop The influence degree of low Line 1 operation is then most important.
After excessive kind of demonstration design, design and construction use utility model illustrated herein.Building enclosure is using stake+anchor cable Support form, it is 26m that lid, which digs segment length, and the disconnected length of open cut is 86m.Site operation experience, Monitoring Data and building up station operation Monitoring Data fully proves:Can strictly it be controlled using newly-built structure lateral rigidity and layering interconnection technique using top-down invers method method Building up station deformation gauge structure safety;Reinforce existing structure in advance using reinforced structure, set temporary support column, segmentation to abolish The displacement that punches can be controlled, avoids structure from destroying;Embedding re-bar technique and reserved steel bar joint technology are ripe, can guarantee that construction quality; It is small using static(al) cutting scheme noise, favorable environment protection and civilized construction.
The utility model can be widely popularized into the reconstruction and extension project of subway station, the especially suitable newly-built station work of large span Journey, engineering can be made safer, economical.

Claims (3)

1. a kind of connected structure for abutting existing transfer station on a large scale, including the newly-built car of the building up station of A lines and B lines Stand, the two joining place forms transfer station, is continuously punched on the side wall of A line building up station, is formed and the newly-built station of B lines The multiple passways communicated, it is characterised in that:The passway includes the hole at existing structure(0), push up at negative one layer hole Beam(1), back timber at minus two layers of hole(2), pillar at negative one layer hole(4), pillar at minus two layers of hole(5), axle power can be applied Temporary support column and full hall scaffold(24), at newly-built structure inside back-up sand steel pipe column(12), steel pipe column slab column connect Connect reinforcing ring(15), steel pipe column reinforcement welding reinforcing ring(16), steel pipe column baseplate reinforcing bar welding reinforcing ring(17), back plate connections Recessed ring beam and plate(13), the temporary support column and full hall scaffold(24)In temporary support column be steel pipe support, It is furnished with jack among it, can be put in time at side wall when removing side wall, steel pipe column reinforcement welding reinforcing ring(16)For steel The annular slab that plate weld forms, newly-built station structure longeron and crossbeam reinforcing bar are welded on reinforcing ring, ensure reinforcing steel bar bear;Bottom plate The recessed ring beam in junction and plate(13)In the recessed ring beam of back plate connections be the beam that is poured under newly-built structure bottom plate, it can be supported In existing building enclosure, complete horizontal direction power transmission and water expandable waterstop can be added inside(25), strengthen waterproof slab Ability.
A kind of 2. connected structure for abutting existing transfer station on a large scale according to claim 1, it is characterised in that:It is described The top plate of building up station, middle plate, building up station bottom plate(3)Place outside respectively with the cast-in-place reinforcement longeron of newly-built structure, the reinforcement Longeron includes negative one layer reinforcement longeron and connecting plate(6), minus two layers of reinforcement longeron and connecting plate(7), bottom plate reinforcement longeron and connecting plate (8), movement joint(11), implantation reinforcing bar(18), cast-in-place negative one layer reinforcement pillar at the reinforcement longeron(9), minus two layers of reinforcement post Son(10), pass through reinforcing bar connector during reverse hierarchical is built(19)Connect reinforcement pillar reinforcing bar.
A kind of 3. connected structure for abutting existing transfer station on a large scale according to claim 1, it is characterised in that:It is described Connected structure is according to site condition construction fender post, back-up sand steel tube column foundation(26), back-up sand steel pipe column(12), apply station negative one Layer reinforcement longeron and connecting plate(6)Top plate connection is completed, passes through reinforcing bar connector(19)Reserved negative one layer reinforcement pillar(9)Reinforcing bar connects Mouthful, after top plate reaches design strength, earthing is backfilled, makees successively earth excavation to subinverse, newly-built station negative one layer side wall of constructing, Middle plate and minus two layers of reinforcement longeron and connecting plate(7), negative one layer reinforcement pillar(9), pass through reinforcing bar connector(19)It is reserved minus two layers Reinforcement pillar(10)Reinforcing bar interface;After middle plate reaches design strength, make successively earth excavation to subinverse, minus two layers of station of constructing The recessed longeron of side wall, bottom plate, bottom plate and connecting plate(13), minus two layers of reinforcement pillar(10);After bottom plate reaches design strength, Building up station negative one layer and minus two layer frame set temporary support column and full hall scaffold(24), then segmentation abolish, tunnel opening area The side wall in building up station region.
CN201720810149.5U 2017-07-06 2017-07-06 A kind of connected structure for abutting existing transfer station on a large scale Withdrawn - After Issue CN207032282U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720810149.5U CN207032282U (en) 2017-07-06 2017-07-06 A kind of connected structure for abutting existing transfer station on a large scale

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720810149.5U CN207032282U (en) 2017-07-06 2017-07-06 A kind of connected structure for abutting existing transfer station on a large scale

Publications (1)

Publication Number Publication Date
CN207032282U true CN207032282U (en) 2018-02-23

Family

ID=61465834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720810149.5U Withdrawn - After Issue CN207032282U (en) 2017-07-06 2017-07-06 A kind of connected structure for abutting existing transfer station on a large scale

Country Status (1)

Country Link
CN (1) CN207032282U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119711A (en) * 2017-07-06 2017-09-01 中国铁路设计集团有限公司 A kind of connected structure and construction method for abutting existing transfer station on a large scale
CN111878095A (en) * 2020-08-11 2020-11-03 中铁十八局集团有限公司 Construction method for existing underground structure of newly-built channel connection without reserved interface

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119711A (en) * 2017-07-06 2017-09-01 中国铁路设计集团有限公司 A kind of connected structure and construction method for abutting existing transfer station on a large scale
CN107119711B (en) * 2017-07-06 2022-09-06 中国铁路设计集团有限公司 Connecting structure for large-range adjacent existing transfer station and construction method
CN111878095A (en) * 2020-08-11 2020-11-03 中铁十八局集团有限公司 Construction method for existing underground structure of newly-built channel connection without reserved interface

Similar Documents

Publication Publication Date Title
CN107119711A (en) A kind of connected structure and construction method for abutting existing transfer station on a large scale
CN108060683B (en) A kind of middle weathering geology top-down construction method
CN206800412U (en) The foundation pit enclosure structure that a kind of steel-pipe pile is combined with Larsen steel sheet pile fore shaft
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN108868778B (en) Non-excavation construction method for large underground structure
CN109914456A (en) A kind of bridge and subway tunnel adjoin newly-built or with design and construction method when building
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN105350526B (en) Method for setting up steel platform
CN109958445A (en) The frame construction method in Large Underground space is buried for an ultra shallow
CN112647956A (en) Construction method for shield tunneling of water-rich composite stratum to closely pass through subway station
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN207032282U (en) A kind of connected structure for abutting existing transfer station on a large scale
CN106480891B (en) A kind of shaft construction method
CN112982481A (en) Structure construction method for crossing subway intersection node on pipe gallery
CN109989407B (en) Roadbed pile tube curtain supporting structure behind newly-added two-line platform of railway
CN107574836A (en) Cross the constructing structure and construction method of urban road underpass
CN105986830B (en) The tunneling method of construction of roadside strip underground garage
CN110486062A (en) A kind of method of mechanical tunneling multilayer multispan underground engineering in weak soil
CN106498951B (en) A kind of shaft excavation construction method
CN214787427U (en) Tunnel arch bridge type tunnel bottom structure
CN112627002B (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof
CN111851515B (en) Adjacent foundation pit cooperative construction enclosure structure and construction method thereof
CN207062996U (en) Cross the constructing structure of urban road underpass
CN211312225U (en) Pile-column integrated structure based on bridge transformed from existing road surface

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20180223

Effective date of abandoning: 20220906

AV01 Patent right actively abandoned

Granted publication date: 20180223

Effective date of abandoning: 20220906

AV01 Patent right actively abandoned