CN113565533A - Arch subway station building connection structure and construction method - Google Patents

Arch subway station building connection structure and construction method Download PDF

Info

Publication number
CN113565533A
CN113565533A CN202110609900.6A CN202110609900A CN113565533A CN 113565533 A CN113565533 A CN 113565533A CN 202110609900 A CN202110609900 A CN 202110609900A CN 113565533 A CN113565533 A CN 113565533A
Authority
CN
China
Prior art keywords
existing
subway station
connection
newly
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110609900.6A
Other languages
Chinese (zh)
Inventor
雷升祥
黄欣
冀国栋
赵静波
张京京
陈一夫
岳长城
陈霞飞
彭澍
高飞鹏
丁正全
邹春华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
China Railway Construction Corp Ltd CRCC
Original Assignee
China Railway 18th Bureau Group Co Ltd
China Railway Construction Corp Ltd CRCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, China Railway Construction Corp Ltd CRCC filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN202110609900.6A priority Critical patent/CN113565533A/en
Publication of CN113565533A publication Critical patent/CN113565533A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses an arch subway station building and connecting structure which comprises an existing subway station, a newly-built transfer passage, an existing arch top edge beam, existing subway station side walls, a transfer passage primary support, a transfer passage top plate, a transfer passage bottom plate, a reinforcing column and a reinforcing ring beam. The bottom of the newly-built transfer passage is connected with the side wall of the existing subway station, and two first connecting points are arranged at the connecting position; the top of the newly-built transfer passage is connected with the existing arch edge beam, and two connection points II are arranged at the connection position; two parallel reinforcing columns are arranged between the first two connection points and the second two connection points, and a closed ring frame structure is arranged between the first two connection points, the second two connection points and the two reinforcing columns. The closed ring frame structure can effectively reduce the construction risk of communicating and plugging new and old structures of the underground engineering, and can be popularized and applied to underground engineering construction; the construction process is relatively simple, the construction period is short, and a large amount of labor and time expenditure on site are saved.

Description

Arch subway station building connection structure and construction method
Technical Field
The invention relates to the related technical field of subway engineering building, in particular to an arched subway station building connection structure and a construction method.
Background
In recent years, with the acceleration of urbanization progress in China, a large number of people are poured into cities, so that the degree of urban population gathering is rapidly increased, some subways built and put into operation at early stage gradually have the problem that the requirements of passenger traveling and transfer cannot be met, and the targeted building of the subways is a fundamental method for solving the problems. The subway construction inevitably involves the problems of the removal of the existing structure, the connection of the existing structure and a newly-built structure and the like. The peripheral environment of subway engineering is generally complex, the requirements for controlling the deformation of the earth surface and the existing structure are strict, and the problem of safety risk is easily caused by repeated conversion of a stress system in the building construction process. If the building method is improper, the existing structure can be damaged, and serious engineering accidents can be caused.
CN 102943678B an arch subway station is new and old building and is linked up structure, in this technical scheme, the existing station of A number line links up with the newly-built station of B number line and forms the transfer station, and the opening in the side wall of the existing station of A number line forms the communicating passway of the newly-built station of B number line, includes: the tunnel comprises a tunnel opening, an arched top-bottom beam, a profile steel pull rod, a chemical screw and a wedge-shaped steel plate. A plurality of groups of chemical screw rods are oppositely arranged on the inner sides of the arched top and bottom beams in the range of the opening on the side wall of the existing station, a plurality of section steel pull rods with wedge-shaped steel plates fixed at two ends are fixedly connected with the corresponding chemical screw rods through the wedge-shaped steel plates, and the section steel pull rods are connected and fixed between the arched top and bottom beams at two sides of the arched top; a reinforcing ring beam is cast in situ between the outer side of the arched top-bottom beam in the opening range and the newly-built structure, the arched top-bottom beam and the reinforcing ring beam are fixedly connected by using chemical embedded bars, and the reinforcing ring beam forms a closed ring beam in the newly-built structure along the edge of the opening; after the side wall of the existing station of the line A is provided with a hole, a reinforced concrete beam bottom reinforcing layer is arranged below the bottom surface of the arched top-bottom beam and is combined with the bottom surface of the arched top-bottom beam into a whole; a section of side wall is reserved between two rectangular holes in the side wall of the existing station, a reinforced concrete column is attached to the newly built station, the upper end and the lower end of the reinforced concrete column are connected with the reinforcing ring beam, and the reserved side wall and the attached reinforced concrete column are combined to form the reinforcing column. The method for breaking the side wall of the existing station opening area in a segmented mode comprises the following steps: temporarily plugging the existing line station transfer section, transforming the pipeline on the upper part of the suspended ceiling of the existing line transfer section, and applying a profile steel pull rod at the foot part of the vault; constructing a primary support and a secondary lining of a station of the No. B line to the outer side of the side wall of the No. A line and tightly jacking the side wall of the No. A line; the side wall is divided into a plurality of areas at intervals, concrete protective layers on the inner side and the outer side of the side wall of the area I are chiseled, reserved steel bars needed by glass are chiseled, and concrete in the area 1 is cut in sequence according to the chiseling sequence.
Constructing a beam bottom reinforcing layer of the existing arched top and bottom beam in the area I; a temporary support system is additionally arranged by a scaffold, a reinforcing column is poured, and the scaffold is firmly anchored with a newly-built structure; after the structure I reaches the design strength, chiseling the concrete protective layers on the inner side and the outer side of the side wall of the area II, stripping off the required reserved reinforcing steel bars, and sequentially cutting the concrete of the area 2 according to the chiseling sequence; reserving temporary support of the area I, constructing a beam bottom reinforcing layer of an existing arched top-bottom beam in the area II, and erecting the temporary support of the area II by using a scaffold; after the structure of the area II reaches the design strength, sequentially performing hole opening and constructing a beam bottom reinforcing layer of the existing arched top-bottom beam on the area III in the same steps as the steps (4) and (5); the temporary support of each area is reserved, the existing line side wall structures of the IV area and the V area are excavated in sequence with the construction sequence of other areas, the existing arch top-bottom beam is reinforced as required, and the concrete of the No. A line side wall is cut into a size capable of being carried in a blocking mode through the static force of a diamond rope saw; and after the second lining of the underground excavation section structure is constructed, removing the temporary support after the concrete structure reaches the design strength.
In the prior art, a medium-sized steel pull rod needs to be constructed in an existing station, and normal operation of the station can be influenced; the construction process of the reinforced ring beam is complex, and the difficulty of erecting the template support is high, so that the pouring effect is difficult to ensure; meanwhile, the lateral deformation of the side wall of the existing station to the hole opening part cannot be effectively controlled in the existing scheme; the construction steps are complicated, the construction period is long, and the cost of consumed labor time is high.
Disclosure of Invention
The invention aims to overcome the defects of the prior art, and provides an arch subway station building connection structure and a construction method, which can realize the connection of a newly-built structure and an existing arch subway station and reduce the construction cost on the basis of ensuring the connection construction safety.
The invention adopts the technical scheme that the building and connecting structure for the arched subway station comprises an existing subway station, a newly-built transfer passage, an existing top arched edge beam, existing subway station side walls, a transfer passage primary support, a transfer passage top plate, a transfer passage bottom plate, a reinforcing column and a reinforcing ring beam.
The existing subway station is an existing PBA station, the existing top arch edge beam is a top arch structure of the existing subway station, and the existing subway station side wall is a lower structure of the existing subway station.
The bottom of the newly-built transfer passage is connected with the side wall of the existing subway station, and two first connecting points are arranged at the connecting position; the top of the newly-built transfer passage is connected with the existing arch edge beam, and two connection points II are arranged at the connection position;
two parallel reinforcing columns are arranged between the first two connection points and the second two connection points, the first connection point is of a reinforcing column and embedded steel bar connecting structure of an existing arch edge beam, the second connection point is of a reinforcing column and embedded steel bar connecting structure of an existing station side wall, and a closed ring frame structure is arranged between the first two connection points, the second two connection points and the two reinforcing columns.
Furthermore, the bottom and the top of the newly-built transfer channel are both provided with a transfer channel primary support, the transfer channel primary support at the bottom is provided with a transfer channel bottom plate, and the transfer channel primary support at the top is provided with a transfer channel top plate.
Furthermore, the reinforcing columns at the first connecting point and the second connecting point are fixedly connected with the existing arch edge beam and the existing side wall at the lower part of the station through embedded bars.
Furthermore, the newly-built transfer channel is of a single-span vault vertical wall section structure.
Compared with the prior art, the invention provides an arch subway station extension and connection structure and a construction method, wherein a closed ring frame structure is formed by connecting reinforcing columns with existing arch top side beams and lower side wall embedded bars, so that the communication and connection construction risk of new and old structures of underground engineering can be effectively reduced, and the arch subway station extension and connection structure and the construction method can be popularized and applied to underground engineering extension and construction; the invention provides an arched subway station building connection structure and a construction method, which are relatively simple in construction process and short in construction period, and save a large amount of labor and time expenditure on site.
Drawings
Fig. 1 is a schematic structural view of the present invention.
Fig. 2 is a schematic diagram of waterproof lap joint of a new structure and an old structure.
Fig. 3 is a schematic view of the reinforcement of the connection site of the present invention.
Fig. 4 is a partial sectional view of the connection site.
Detailed Description
The invention is described in further detail below with reference to the figures and the embodiments.
As shown in fig. 1-4, the invention provides an arch subway station building and connecting structure, which comprises an existing subway station 1, a newly-built transfer passage 2, an existing arch-shaped edge beam 3, existing subway station side walls 4, a transfer passage primary support 5, a transfer passage top plate 6, a transfer passage bottom plate 7, a reinforcing column 8 and a reinforcing ring beam 9.
The existing subway station 1 is an existing PBA station, the existing arch side beam 3 is an arch structure of the existing subway station 1, and the existing subway station side wall 4 is a lower structure of the existing subway station 1; the newly-built transfer passage 2 is of a single-span vault straight wall section structure, and the newly-built transfer passage 2 is constructed by adopting an underground excavation CRD method;
the bottom of the newly-built transfer passage 2 is connected with the side wall 4 of the existing subway station, and two connection points I are arranged at the connection position; the top of the newly-built transfer passage 2 is connected with the existing arch edge beam 3, and two connection points II are arranged at the connection position;
two parallel reinforcing columns 8 are arranged between the first two connection points and the second two connection points, the first connection point is of a reinforcing column 8 and embedded steel bar connecting structure of the existing arch-shaped edge beam 3, the second connection point is of a reinforcing column 8 and embedded steel bar connecting structure of the existing station side wall 4, and a closed ring frame structure is arranged between the first two connection points and the second two connection points and between the two reinforcing columns 8. And the two first connecting points and the two second connecting points are arranged along the length direction of the newly-built transfer passage 2.
Furthermore, the bottom and the top of the newly-built transfer channel 2 are provided with a transfer channel primary support 5, the transfer channel primary support 5 at the bottom is provided with a transfer channel bottom plate 7, and the transfer channel primary support 5 at the top is provided with a transfer channel top plate 6.
Further, the reinforcing columns 8 at the first connection point and the second connection point are fixedly connected with the existing arch edge beam 3 and the existing station lower side wall 4 through embedded bars 17.
The concrete construction steps are as follows:
s1, excavating the newly-built transfer channel 2 by adopting a subsurface excavation CRD method, and constructing the primary support 5 of the transfer channel to the outer side of the side wall 4 of the existing subway station;
s2, dismantling the temporary middle partition wall of the newly-built transfer channel 2 in sections, constructing a waterproof layer 10 of the newly-built transfer channel 2, and reserving a waterproof joint; constructing a secondary lining of the newly-built transfer passage 2 to a deformation joint position, and reserving a steel bar connector for connecting the waterproof of a connection part and the connection of a new structure and an old structure of the secondary lining;
s3, according to the construction sequence of the newly-built transfer passage pilot tunnel, the side piles 11 of the existing subway station 1 are broken in blocks from top to bottom. After the removal, the waterproof layer 10 of the newly-built transfer passage 2 is partially overlapped with the waterproof layer 12 of the existing subway station 1, the overlapping range extends beyond the deformation joint 13 (the length is 300mm), and the sealing is carried out by adopting building sealant; a water-swelling water stop strip 14 is arranged at the lap joint part of the waterproof layer to form a waterproof partition; the connection part of the new and old structure is provided with a water-swelling water stop strip 14 and a grouting pipe 15;
s4, determining the position of the connection hole 16 at the connection position of the new and old structure according to the design drawing, and constructing reinforcing columns 8 at two sides of the connection hole 16. The reinforcing column 8 is fixedly connected with the existing arch top edge beam 3 and the existing station lower side wall 4 through embedded bars 17 to form a closed ring frame structure;
s5, breaking the existing station side wall 4 corresponding to the range of the connection hole 16 in a partitioning and blocking manner, and penetrating through the existing subway station 1 and the newly-built transfer passage 2;
and (4) performing chiseling and bar planting 18 on the top and the bottom of the finished connecting hole 16 of S5, pouring to form a reinforcing ring beam 9, and then applying the residual structure of the transfer passage.
The invention provides an arch subway station building and connecting structure and a construction method, wherein a closed ring frame structure is formed by connecting reinforcing columns with existing arch top edge beams and lower side wall embedded bars, so that the risk of underground engineering new and old structure communication and connection construction can be effectively reduced, and the arch subway station building and connecting structure and the construction method can be popularized and applied to underground engineering building and construction; the invention provides an arched subway station building connection structure and a construction method, which are relatively simple in construction process and short in construction period, and save a large amount of labor and time expenditure on site.

Claims (7)

1. An arch-shaped subway station extension connection structure is characterized in that an existing subway station is an existing PBA (Poly Butylene Acrylonitrile butadiene styrene) station, an existing top arch edge beam is a top arch structure of the existing subway station, and a side wall of the existing subway station is a lower structure of the existing subway station; the method is characterized in that: the bottom of the newly-built transfer passage is connected with the side wall of the existing subway station, and two first connecting points are arranged at the connecting position; the top of the newly-built transfer passage is connected with the existing arch edge beam, and two connection points II are arranged at the connection position;
two parallel reinforcing columns are arranged between the first two connection points and the second two connection points, the first connection point is of a reinforcing column and embedded steel bar connecting structure of an existing arch edge beam, the second connection point is of a reinforcing column and embedded steel bar connecting structure of an existing station side wall, and a closed ring frame structure is arranged between the first two connection points, the second two connection points and the two reinforcing columns.
2. The arched subway station building connection structure as claimed in claim 1, wherein: the bottom and the top of the new transfer channel are provided with a transfer channel primary support, the transfer channel primary support at the bottom is provided with a transfer channel bottom plate, and the transfer channel primary support at the top is provided with a transfer channel top plate.
3. The arched subway station building connection structure as claimed in claim 1, wherein: and the reinforcing columns at the first connection point and the second connection point are fixedly connected with the existing arch edge beam and the existing lower side wall of the station through embedded bars.
4. The arched subway station building connection structure as claimed in claim 1, wherein: the newly-built transfer passage is of a single-span vault vertical wall section structure.
5. A construction method using the arched subway station connection structure as claimed in any one of claims 1 to 4, characterized in that: determining the position of a connection hole at the connection part of the new and old structures according to a design drawing, and constructing reinforcing columns on two sides of the connection hole; the reinforcing column is fixedly connected with the existing arch edge beam and the existing lower side wall of the station through embedded bars to form a closed ring frame structure.
6. Construction method according to claim 5, characterized in that: the method also includes the steps of:
s1, excavating a newly-built transfer channel by adopting a subsurface excavation CRD method, and constructing a primary support of the transfer channel to the outer side of the side wall of the existing subway station;
s2, removing temporary middle partition walls of the newly-built transfer channel in sections, constructing a waterproof layer of the newly-built transfer channel, and reserving a waterproof joint; constructing a secondary lining of the newly-built transfer passage to a deformation joint position, and reserving a steel bar connector for connecting the waterproof of a connection part and the connection of a new structure and an old structure of the secondary lining;
s3, according to the construction sequence of the newly-built transfer channel pilot tunnel, breaking side piles of the existing subway station in blocks from top to bottom; after the removal, the waterproof layer of the newly-built transfer passage is partially overlapped with the waterproof layer of the existing subway station, the overlapping range extends beyond the deformation joint, and building sealant is adopted for sealing; a water-swelling water stop strip is arranged at the lap joint part of the waterproof layer to form a waterproof partition; the connection part of the new and old structure is provided with a water-swelling water stop strip and a grouting pipe;
s4, constructing a closed ring frame structure;
and S5, breaking the side wall of the existing station corresponding to the range of the connection hole in a partitioning and blocking manner, and penetrating the existing subway station and the newly-built transfer passage.
7. The construction method according to claim 6, which is characterized in that: and (4) performing chiseling and bar planting on the top and the bottom of the connection hole finished in the step S5, pouring to form a reinforced ring beam, and constructing a residual structure of the newly-built transfer channel after finishing.
CN202110609900.6A 2021-06-01 2021-06-01 Arch subway station building connection structure and construction method Pending CN113565533A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110609900.6A CN113565533A (en) 2021-06-01 2021-06-01 Arch subway station building connection structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110609900.6A CN113565533A (en) 2021-06-01 2021-06-01 Arch subway station building connection structure and construction method

Publications (1)

Publication Number Publication Date
CN113565533A true CN113565533A (en) 2021-10-29

Family

ID=78161650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110609900.6A Pending CN113565533A (en) 2021-06-01 2021-06-01 Arch subway station building connection structure and construction method

Country Status (1)

Country Link
CN (1) CN113565533A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114294007A (en) * 2022-01-04 2022-04-08 北京市政建设集团有限责任公司 Interface construction process and equipment for existing subway line

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH646491A5 (en) * 1977-05-17 1984-11-30 Matraaljai Szenbanyak Tunnelling and tunnel lining equipment
CN107119711A (en) * 2017-07-06 2017-09-01 中国铁路设计集团有限公司 A kind of connected structure and construction method for abutting existing transfer station on a large scale
CN108385721A (en) * 2018-02-22 2018-08-10 中铁第勘察设计院集团有限公司 The construction unicom system and its construction method at new subway line station and building up station
CN111395390A (en) * 2020-03-18 2020-07-10 广州地铁设计研究院股份有限公司 Reinforcing structure and method for existing structure opening and new structure connection node
CN111706350A (en) * 2020-05-07 2020-09-25 中铁十八局集团有限公司 Plugging side wall breaking method for communication of newly-built transfer hall and existing tunnel
CN111828016A (en) * 2020-08-12 2020-10-27 北京市政建设集团有限责任公司 Construction process for connecting underground excavated tunnel with existing line side wall
CN215108944U (en) * 2021-06-01 2021-12-10 中铁十八局集团有限公司 Arch subway station is opened up and is built structure of plugging into

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH646491A5 (en) * 1977-05-17 1984-11-30 Matraaljai Szenbanyak Tunnelling and tunnel lining equipment
CN107119711A (en) * 2017-07-06 2017-09-01 中国铁路设计集团有限公司 A kind of connected structure and construction method for abutting existing transfer station on a large scale
CN108385721A (en) * 2018-02-22 2018-08-10 中铁第勘察设计院集团有限公司 The construction unicom system and its construction method at new subway line station and building up station
CN111395390A (en) * 2020-03-18 2020-07-10 广州地铁设计研究院股份有限公司 Reinforcing structure and method for existing structure opening and new structure connection node
CN111706350A (en) * 2020-05-07 2020-09-25 中铁十八局集团有限公司 Plugging side wall breaking method for communication of newly-built transfer hall and existing tunnel
CN111828016A (en) * 2020-08-12 2020-10-27 北京市政建设集团有限责任公司 Construction process for connecting underground excavated tunnel with existing line side wall
CN215108944U (en) * 2021-06-01 2021-12-10 中铁十八局集团有限公司 Arch subway station is opened up and is built structure of plugging into

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114294007A (en) * 2022-01-04 2022-04-08 北京市政建设集团有限责任公司 Interface construction process and equipment for existing subway line
CN114294007B (en) * 2022-01-04 2023-08-22 北京市政建设集团有限责任公司 Interface construction process and equipment for existing subway line

Similar Documents

Publication Publication Date Title
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN110306593A (en) A kind of station construction method
CN109555535B (en) Lower-way truss type prestressed pipe curtain structure and construction method
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
CN210086295U (en) Compound assembled underground structure
CN110469341A (en) A kind of assembly of Underground Subway Station combines integrated morphology and construction method with pouring
CN112681374A (en) Shallow-buried underground-excavated channel cover excavation top-down construction method under complex conditions
KR100313720B1 (en) Composite Underground Structure Construction Method
CN115821985A (en) Integrated construction method for auxiliary structure of subway open cut station
CN114352289A (en) Air shaft duct and method for breaking shield tunnel segment in mine construction section
CN215108944U (en) Arch subway station is opened up and is built structure of plugging into
CN111022076A (en) Split self-propelled construction method for large-span subway tunnel secondary lining vault
CN113565533A (en) Arch subway station building connection structure and construction method
CN112921986A (en) Assembled underground structure and integrated construction method of assembled underground structure and foundation pit
CN116145729B (en) Subway layered station structure in sea-land connection area and construction method thereof
CN110486062B (en) Method for mechanically underground excavating multi-layer multi-span underground engineering in soft soil
CN108571010B (en) Method for integrating open cut method engineering prefabricated main structure and supporting structure
CN116398165A (en) New tunnel penetrating through existing station at zero distance and construction method thereof
CN115450221B (en) Construction method for subway crossing river channel
CN114109402B (en) Large-section construction method of underground excavated crossover line implemented by interval tunnel organization
CN110735641A (en) Construction method of transfer passage of underpass pipeline
CN113863968B (en) Anti-floating construction method for pipe jacking method assembly type subway station
CN108979645B (en) Under-bridge compound curve double-layer comprehensive pipe gallery traffic ring gallery underground excavation and reverse construction process
AU2016102393A4 (en) A Method of constructing a column, a tunnel, and a tunnel made from the method
RU2565314C2 (en) Subway station erection method (yurkevich(s method)

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20211029