CN110306593A - A kind of station construction method - Google Patents
A kind of station construction method Download PDFInfo
- Publication number
- CN110306593A CN110306593A CN201910595962.9A CN201910595962A CN110306593A CN 110306593 A CN110306593 A CN 110306593A CN 201910595962 A CN201910595962 A CN 201910595962A CN 110306593 A CN110306593 A CN 110306593A
- Authority
- CN
- China
- Prior art keywords
- concrete
- construction
- plate
- pile
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 55
- 238000009412 basement excavation Methods 0.000 claims abstract description 18
- 238000000034 method Methods 0.000 claims abstract description 14
- 239000004567 concrete Substances 0.000 claims description 45
- 229910000831 Steel Inorganic materials 0.000 claims description 24
- 239000010959 steel Substances 0.000 claims description 24
- 238000009415 formwork Methods 0.000 claims description 15
- 238000005553 drilling Methods 0.000 claims description 13
- 230000002787 reinforcement Effects 0.000 claims description 13
- 238000005086 pumping Methods 0.000 claims description 11
- 230000003014 reinforcing Effects 0.000 claims description 10
- 238000001556 precipitation Methods 0.000 claims description 9
- 239000011150 reinforced concrete Substances 0.000 claims description 6
- 238000011065 in-situ storage Methods 0.000 claims description 5
- 239000011230 binding agent Substances 0.000 claims description 3
- 238000007493 shaping process Methods 0.000 claims description 3
- 238000009416 shuttering Methods 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances data:image/svg+xml;base64,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 data:image/svg+xml;base64,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 O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 2
- 210000003205 Muscles Anatomy 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 230000005641 tunneling Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 230000001815 facial Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/04—Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
- E02D5/187—Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/36—Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
Abstract
The present invention relates to a kind of station construction methods, it includes the operation of layering excavation of foundation pit, stratified body building operation and the backfill operation of parallel sectional alternately, wherein, single section construction operation, along construction method, specifically includes layering excavation of foundation pit operation, stratified body building operation, backfill job step using open cut.Single section described in this station construction method is since both ends, to intermediate two-way parallel excavation.This station construction method, sectional level substantially increase construction efficiency to capable construction process;Stage excavation cooperates foundation pit, main structure alternately operating mode, ensure that Work sectors foundation pit digs the stability in face and main structure;With excavate, with go along with sb. to guard him, with build, with remove, with the section construction of backfill, reduce the influence to public transport.
Description
Technical field
The present invention relates to city track traffic engineering technical field of construction, in particular to one kind can be improved construction efficiency,
Ensure that foundation pit digs the stability in face and main structure, reduces the station construction method that construction influences public transport.
Background technique
With the fast development in China city, wall is increasingly gathered around in the traffic of large- and-medium size cities, has seriously affected city dweller's
Quality of life, accelerating Urban Rail Transit Project becomes the common recognition in more and more cities.Underground tunneling subway station conduct
The important component of city track traffic engineering, because having many advantages, such as not influence traffic above-ground, moving that change pipeline less, in wagon flow
With the more inner city of pipeline using relatively broad.Existing station construction method mainly has open cut and two kinds of tunneling, due to station
Need to build entrance as the interface channel between subway station and ground, thus it is general all or part of using open-cut
Method, that there are construction efficiency is low for existing unidirectional open-cut method, foundation pit digs the main structure that facial contour is unstable and comes to it
Building road pavement public transport unstable, long in time limit influences headlight defect.
Summary of the invention
The technical problem to be solved in the present invention is intended to provide one kind and can be improved construction efficiency, ensures that foundation pit digs face and main body
The stability of structure reduces the station construction method that construction influences public transport.
In order to solve the above technical problems, this station construction method includes the layering excavation of foundation pit of parallel sectional alternately
Operation, stratified body building operation and backfill operation, wherein single section construction operation, along construction method, is specifically wrapped using open cut
Include following steps,
S1 --- layering excavation of foundation pit operation: (1) perform diaphram wall, interim column pile foundation, dewatering well;(2) it opens
It digs to 1m under first of support center line, then first of concrete support is installed;(3) precipitation is excavated in second support
0.5m under heart line installs second concrete support, applies prestressing force;(4) precipitation is excavated under third road support center line
0.5m simultaneously installs third road concrete support;Precipitation is excavated to final excavation face;
S2 --- stratified body constructs operation: (1) performing under bottom plate and part side wall waterproof layer;Pour station bottom plate, low
Beam, part side wall and column concrete;Remove the support of third road;(2) two layers of underground part interior wall, middle plate are poured;Remove second
Road support;(3) basement one interior wall, column, top beam are poured;Waterproof roofing layer is performed, capping beam of constructing;Remove first
Support, interim column and steel binder;
S3 --- backfill operation: (1) remove temporary structure above ground-connecting-wall;(2) bottom surface is backfilled to resume traffic.
Diaphram wall described in this station construction method and step S1 cooperates hydraulic grooving machine grooving, crawler crane using impact drill
Steel reinforcement cage is put, double duct underwater grouting concrete is at wall;Wall top is modified after the completion of diaphram wall and binds crown beam reinforcing bar, using combination steel
Template formwork erection, commodity concrete placings.Concrete support described in this station construction method and step S1 include cast-in-situ bored pile, rotary churning pile,
Casing bitten pile, reinforced concrete pile and lattice column;
Further, the cast-in-situ bored pile places steel using rotary drilling rig or impact drilled as holes, crawler crane or truck crane
Muscle cage, conduit underwater grouting concrete pile;The rotary churning pile uses rotary churning pile machine drill hole. while being promoted after drilling to completion
Jet groutinl is carried out to design height;Described sleeve pipe interlocking pile is drilled using all casing drill, is drilled into and is set by scheme drilling sequences
Count depth;The reinforced concrete pile places steel reinforcement cage, conduit underwater grouting concrete pile using crawler crane or truck crane;The lattice column
It is drilled using rotary drilling rig, lattice column, conduit underwater grouting concrete pile is placed using crawler crane or truck crane after pore-forming.
Main structure described in this station construction method and step S2 is according to bed course, bottom plate, side wall, middle plate, side wall, top plate, anti-
Water is taken according to sequence from top to bottom using full hall scaffold+bulk combined steel formwork formwork erection, point of pumping commodity concrete placings
Section parallel line production method successively carries out.
Further, the main structure piecewise-parallel continuous productive process method the specific steps are,
After bottom plate performs waterproof, assembling reinforcement, installed plug template simultaneously pours concrete;
After side wall performs waterproof, assembling reinforcement according to design, poured using pumping concrete is carried out after bulk combined steel formwork formwork erection;
Middle plate, top plate set up full hall scaffold, are laid with template after bottom plate and middle plate pour completion and reach design strength
After partly wire-tiing, pumping concrete placings are carried out;
After the completion of the binding of pillar reinforcing bar, using shaping combined steel shuttering, completes after reinforcing, carry out pumping concrete placings.
Single section described in this station construction method is since both ends, to intermediate two-way parallel excavation.
A kind of station construction method of the present invention, sectional level substantially increase construction efficiency to capable construction process;
Stage excavation cooperates foundation pit, main structure alternately operating mode, ensure that Work sectors foundation pit digs the stabilization in face and main structure
Property;With excavate, with go along with sb. to guard him, with build, with remove, with the section construction of backfill, reduce the influence to public transport.
Detailed description of the invention
Station construction method of the present invention is described further with reference to the accompanying drawing:
Fig. 1 is total construction process line frame graph of this station construction method;
Fig. 2 is the specific process schematic diagram of this station construction method;
Fig. 3 is the main structure piecewise-parallel continuous productive process process line frame graph of this station construction method.
Specific embodiment
As shown in Figure 1, 2, this station construction method include the layering excavation of foundation pit operation alternately of parallel sectional, point
Layer main body constructs operation and backfill operation, wherein single section construction operation, along construction method, specifically includes following step using open cut
Suddenly,
S1 --- layering excavation of foundation pit operation: (1) perform diaphram wall, interim column pile foundation, dewatering well;(2) it opens
It digs to 1m under first of support center line, then first of concrete support is installed;(3) precipitation is excavated in second support
0.5m under heart line installs second concrete support, applies prestressing force;(4) precipitation is excavated under third road support center line
0.5m simultaneously installs third road concrete support;Precipitation is excavated to final excavation face;
S2 --- stratified body constructs operation: (1) performing under bottom plate and part side wall waterproof layer;Pour station bottom plate, low
Beam, part side wall and column concrete;Remove the support of third road;(2) two layers of underground part interior wall, middle plate are poured;Remove second
Road support;(3) basement one interior wall, column, top beam are poured;Waterproof roofing layer is performed, capping beam of constructing;Remove first
Support, interim column and steel binder;
S3 --- backfill operation: (1) remove temporary structure above ground-connecting-wall;(2) bottom surface is backfilled to resume traffic.
Diaphram wall described in this station construction method and step S1 cooperates hydraulic grooving machine grooving, crawler crane using impact drill
Steel reinforcement cage is put, double duct underwater grouting concrete is at wall;Wall top is modified after the completion of diaphram wall and binds crown beam reinforcing bar, using combination steel
Template formwork erection, commodity concrete placings.Concrete support described in this station construction method and step S1 include cast-in-situ bored pile, rotary churning pile,
Casing bitten pile, reinforced concrete pile and lattice column;
Further, the cast-in-situ bored pile places steel using rotary drilling rig or impact drilled as holes, crawler crane or truck crane
Muscle cage, conduit underwater grouting concrete pile;The rotary churning pile uses rotary churning pile machine drill hole. while being promoted after drilling to completion
Jet groutinl is carried out to design height;Described sleeve pipe interlocking pile is drilled using all casing drill, is drilled into and is set by scheme drilling sequences
Count depth;The reinforced concrete pile places steel reinforcement cage, conduit underwater grouting concrete pile using crawler crane or truck crane;The lattice column
It is drilled using rotary drilling rig, lattice column, conduit underwater grouting concrete pile is placed using crawler crane or truck crane after pore-forming.
As shown in figure 3, main structure described in this station construction method and step S2 is according to bed course, bottom plate, side wall, middle plate, side
Wall, top plate, waterproof are taken according to sequence from top to bottom using full hall scaffold+bulk combined steel formwork formwork erection, pump commodity
The piecewise-parallel continuous productive process method of concrete placings successively carries out.
Further, the main structure piecewise-parallel continuous productive process method the specific steps are,
After bottom plate performs waterproof, assembling reinforcement, installed plug template simultaneously pours concrete;
After side wall performs waterproof, assembling reinforcement according to design, poured using pumping concrete is carried out after bulk combined steel formwork formwork erection;
Middle plate, top plate set up full hall scaffold, are laid with template after bottom plate and middle plate pour completion and reach design strength
After partly wire-tiing, pumping concrete placings are carried out;
After the completion of the binding of pillar reinforcing bar, using shaping combined steel shuttering, completes after reinforcing, carry out pumping concrete placings.
Single section described in this station construction method is since both ends, to intermediate two-way parallel excavation.
This station construction method, sectional level substantially increase construction efficiency to capable construction process;Stage excavation
Cooperate foundation pit, main structure alternately operating mode, ensure that Work sectors foundation pit digs the stability in face and main structure;With opening
Dig, with go along with sb. to guard him, with build, with remove, with the section construction of backfill, reduce the influence to public transport.
Above embodiment, which is intended to illustrate the present invention, to be realized or use for professional and technical personnel in the field, to above-mentioned
Embodiment, which is modified, will be readily apparent to those skilled in the art, therefore the present invention includes but is not limited to
Above embodiment, it is any to meet the claims or specification description, meet with principles disclosed herein and novelty,
The method of inventive features, technique, product, fall within the scope of protection of the present invention.
Claims (6)
1. a kind of station construction method, it is characterized in that: including the operation of layering excavation of foundation pit, the layering of parallel sectional alternately
Subject construction operation and backfill operation, wherein single section construction operation, along construction method, specifically includes following step using open cut
Suddenly,
S1 --- layering excavation of foundation pit operation: (1) perform diaphram wall, interim column pile foundation, dewatering well;(2) it is excavated to
1m under first of support center line, then installs first of concrete support;(3) precipitation is excavated to second support center line
Lower 0.5m installs second concrete support, applies prestressing force;(4) precipitation, be excavated to third road support center line under 0.5m simultaneously
Third road concrete support is installed;Precipitation is excavated to final excavation face;
S2 --- stratified body constructs operation: (1) performing under bottom plate and part side wall waterproof layer;Pour station bottom plate, low beam, portion
Divide side wall and column concrete;Remove the support of third road;(2) two layers of underground part interior wall, middle plate are poured;Remove second branch
Support;(3) basement one interior wall, column, top beam are poured;Waterproof roofing layer is performed, capping beam of constructing;It removes first of support, face
Shi Lizhu and steel binder;
S3 --- backfill operation: (1) remove temporary structure above ground-connecting-wall;(2) bottom surface is backfilled to resume traffic.
2. station construction method according to claim 1, it is characterized in that: diaphram wall described in S1 is cooperated using impact drill
Hydraulic grooving machine grooving, crawler belt hang steel reinforcement cage, and double duct underwater grouting concrete is at wall;Wall top is modified after the completion of diaphram wall to tie up
Crown beam reinforcing bar is pricked, using combined steel formwork formwork erection, commodity concrete placings.
3. station construction method according to claim 1, it is characterized in that: concrete support described in S1 includes drill-pouring
Stake, rotary churning pile, casing bitten pile, reinforced concrete pile and lattice column;
The cast-in-situ bored pile places steel reinforcement cage using rotary drilling rig or impact drilled as holes, crawler crane or truck crane, and conduit is underwater
Concrete pile is perfused;
The rotary churning pile uses rotary churning pile machine drill hole, carries out jet groutinl after drilling to completion while being promoted to designing height
Degree;
Described sleeve pipe interlocking pile is drilled using all casing drill, by scheme drilling sequences drilling to completion;
The reinforced concrete pile places steel reinforcement cage, conduit underwater grouting concrete pile using crawler crane or truck crane;
The lattice column is drilled using rotary drilling rig, places lattice column using crawler crane or truck crane after pore-forming, and conduit fills under water
Infuse concrete pile.
4. station construction method according to claim 1, it is characterized in that: main structure described in s2 is according to bed course, bottom plate, side
Wall, middle plate, side wall, top plate, waterproof are taken vertical using full hall scaffold+bulk combined steel formwork according to sequence from top to bottom
The piecewise-parallel continuous productive process method of mould, pumping commodity concrete placings successively carries out.
5. station construction method according to claim 4, it is characterized in that: main structure piecewise-parallel continuous productive process side
Method the specific steps are,
After bottom plate performs waterproof, assembling reinforcement, installed plug template simultaneously pours concrete;
After side wall performs waterproof, assembling reinforcement according to design, poured using pumping concrete is carried out after bulk combined steel formwork formwork erection;
Middle plate, top plate set up full hall scaffold after bottom plate and middle plate pour completion and reach design strength, are laid with template half and prick
After reinforcing bar, pumping concrete placings are carried out;
After the completion of the binding of pillar reinforcing bar, using shaping combined steel shuttering, completes after reinforcing, carry out pumping concrete placings.
6. station construction method according to any one of claims 1 to 5, it is characterized in that: the single section from both ends to
Intermediate two-way parallel excavation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910595962.9A CN110306593A (en) | 2019-07-03 | 2019-07-03 | A kind of station construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910595962.9A CN110306593A (en) | 2019-07-03 | 2019-07-03 | A kind of station construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110306593A true CN110306593A (en) | 2019-10-08 |
Family
ID=68079614
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910595962.9A Pending CN110306593A (en) | 2019-07-03 | 2019-07-03 | A kind of station construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110306593A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112177008A (en) * | 2020-09-07 | 2021-01-05 | 中国一冶集团有限公司 | Construction method for deep foundation pit excavation |
CN112609698A (en) * | 2020-11-18 | 2021-04-06 | 中铁二局集团有限公司 | Construction method of frame support foundation pit |
CN113153384A (en) * | 2021-03-24 | 2021-07-23 | 中交路桥建设有限公司 | Construction method for deep-buried subway station under rock geology |
CN113153383A (en) * | 2021-03-24 | 2021-07-23 | 中交路桥建设有限公司 | Construction method for deep-buried large-section subway station |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103590425A (en) * | 2013-11-28 | 2014-02-19 | 中铁二十局集团第五工程有限公司 | Peaty soft soil stratum subway station construction technology |
CN108914966A (en) * | 2018-08-15 | 2018-11-30 | 北京市政建设集团有限责任公司 | A kind of open-cut station main structure and its construction method |
-
2019
- 2019-07-03 CN CN201910595962.9A patent/CN110306593A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103590425A (en) * | 2013-11-28 | 2014-02-19 | 中铁二十局集团第五工程有限公司 | Peaty soft soil stratum subway station construction technology |
CN108914966A (en) * | 2018-08-15 | 2018-11-30 | 北京市政建设集团有限责任公司 | A kind of open-cut station main structure and its construction method |
Non-Patent Citations (3)
Title |
---|
俞英娜等: "《土木工程概论 双色》", 31 May 2017, 上海交通大学出版社 * |
王中华等: "《实用建筑工程施工手册》", 31 May 2015, 湖南科学技术出版社 * |
长沙市轨道交通集团有限公司: "《明挖顺作法地铁车站施工工艺》", 14 June 2019 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112177008A (en) * | 2020-09-07 | 2021-01-05 | 中国一冶集团有限公司 | Construction method for deep foundation pit excavation |
CN112609698A (en) * | 2020-11-18 | 2021-04-06 | 中铁二局集团有限公司 | Construction method of frame support foundation pit |
CN113153384A (en) * | 2021-03-24 | 2021-07-23 | 中交路桥建设有限公司 | Construction method for deep-buried subway station under rock geology |
CN113153383A (en) * | 2021-03-24 | 2021-07-23 | 中交路桥建设有限公司 | Construction method for deep-buried large-section subway station |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101440708B (en) | PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method | |
CN1307348C (en) | Construction method for underground structure through half reverse course of action of inverting connection | |
CN110306593A (en) | A kind of station construction method | |
CN102536273B (en) | 26-meter large-span space one-step forming construction method | |
CN101725149B (en) | Construction method of long open-cut tunnel | |
CN103741714A (en) | Construction method for full cover-excavation reverse method of underground engineering | |
CN101761068A (en) | Box-raft pressure-bearing type foundation underpinning and construction reinforcing method for tunnel across pile foundation of bridge above river | |
CN108868778B (en) | Non-excavation construction method for large underground structure | |
CN110469341B (en) | Subway underground excavation station assembling and pouring combined integrated structure and construction method | |
CN102995659B (en) | Method for constructing from central area to periphery of ultra-large type underground engineering | |
CN103874803A (en) | Method for building structures, particularly passages under operating railways or the like. | |
CN104727302A (en) | Cast-in-place construction process for inter-pile board wall between slide-resistant piles | |
CN108677924B (en) | Double-row miniature steel pipe pile grouting wall-forming partition structure and method | |
KR20180118009A (en) | Duplex tunnel construction method | |
CN108035379B (en) | Comprehensive pipe gallery and construction method thereof | |
KR20190079588A (en) | Construction Method of Duplex Tunnel | |
CN110700860B (en) | Construction method of soil-stone boundary tunnel crossing loess valley | |
CN106930321B (en) | The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole | |
CN110284432B (en) | Construction method for filling bridge abutment in high-fill area after first construction | |
CN106759486A (en) | A kind of underground structure being made up of stake and wall and its construction method | |
CN110486062A (en) | A kind of method of mechanical tunneling multilayer multispan underground engineering in weak soil | |
WO2018133740A1 (en) | Underground building and construction method for same | |
KR102021496B1 (en) | Retaining wall construction method and retaining wall structure by the method | |
CN205036380U (en) | Block of four encircles PBA and secretly digs subway station major structure | |
CN110792440B (en) | Construction method of water-rich loess tunnel penetrating through loess towards valley |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |