CN107090971A - A kind of method and apparatus for quick and precisely installing flue arch top template - Google Patents

A kind of method and apparatus for quick and precisely installing flue arch top template Download PDF

Info

Publication number
CN107090971A
CN107090971A CN201710445726.XA CN201710445726A CN107090971A CN 107090971 A CN107090971 A CN 107090971A CN 201710445726 A CN201710445726 A CN 201710445726A CN 107090971 A CN107090971 A CN 107090971A
Authority
CN
China
Prior art keywords
vault
flue
tyre shoe
arch
wood
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710445726.XA
Other languages
Chinese (zh)
Inventor
陈磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201710445726.XA priority Critical patent/CN107090971A/en
Publication of CN107090971A publication Critical patent/CN107090971A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/04Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for structures of spherical, spheroid or similar shape, or for cupola structures of circular or polygonal horizontal or vertical section; Inflatable forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a kind of method for quick and precisely installing flue arch top template, including:Step 1: making circular arc vault tyre shoe using reinforcing bar setting-out according to flue drawing;Vault, middle section spot welding arch tire joint steel pipe in vault tyre shoe vertical reinforcement, make vault tyre shoe connect into a monolithic stability component;Vault tyre shoe is vertical upright after making, 56 one group;Step 2: welding cutting back reinforcing bar in vault tyre shoe both sides, reinforcing bar is propped up as the vault shuttering supporting lumps of wood, in order to place the vault shuttering supporting lumps of wood;Step 3: setting up flue arch backform plate bracing frame, the horizontal spacing of vertical rod is consistent with vault tyre shoe spacing;Vertically and horizontally horizon bar step pitch 1000mm 1200mm;Bridging is laterally set;Spiral jacking is installed on vertical rod top, for adjusting the steps such as vault absolute altitude.The present invention can be installed quickly to supporting square timber, be conducive to the dismounting of vault template, be easy to recycling.

Description

A kind of method and apparatus for quick and precisely installing flue arch top template
Technical field
It is more particularly to a kind of that flue arch top template is quick and precisely installed the present invention relates to industrial coke oven flue construction field Method and apparatus.
Background technology
In industrial coke oven flue civil engineering, what its circular arch topmast mould was set up can be quick and precisely subsequent construction Thin time, the pouring quality of vault concrete is also built by laying bricks or stones and carried with being smoothed out of installing of waste gas bend pipe for the flue lining in later stage For ensureing.
The content of the invention
Can quick and precisely it be installed it is an object of the invention to overcome the deficiencies of the prior art and provide one kind, fast quick-detach, again The method and apparatus of the flue circular arch top template used again.
The purpose of the present invention is achieved through the following technical solutions:It is a kind of that flue arch top template is quick and precisely installed Method, it comprises the following steps:
Step 1: making circular arc vault tyre shoe using reinforcing bar setting-out according to flue drawing;In vault tyre shoe vertical reinforcement Vault, middle section spot welding arch tire joint steel pipe, vault tyre shoe is connected into a monolithic stability component;After vault tyre shoe is made It is vertical upright, 5-6 one group;
Step 2: welding cutting back reinforcing bar in vault tyre shoe both sides, reinforcing bar is propped up as the vault shuttering supporting lumps of wood, in order to Place the vault shuttering supporting lumps of wood;
Step 3: setting up flue arch backform plate bracing frame, the horizontal spacing of vertical rod is consistent with vault tyre shoe spacing;Vertically and horizontally level Bar step pitch 1000mm-1200mm;;Bridging is laterally set;Spiral jacking is installed on vertical rod top, and (vertical rod connects with spiral jacking screw thread Connect), for adjusting vault absolute altitude;
Step 4: the vault tyre shoe that will be connected is placed on vault support frame, the horizontal dowel in arch tyre shoe bottom is put into In spiral jacking upper recess;
Step 5: being propped up what the vault shuttering supporting lumps of wood was placed on that vault tyre shoe outer is welded on reinforcing bar;
To be many with wooden peg along vault tyre shoe bottom to vault Step 6: being laid with multi-layer sheet to the vault shuttering supporting lumps of wood Laminate stickfast on the vault shuttering supporting lumps of wood, forms complete vault camber template;
Step 7: the vault formwork elevation measuring that level measurement has been installed is set up, according to spiral shell of the measurement situation to support frame top Rotation jacking is adjusted, and vault is raised and lowered, absolute altitude is reached engine request;
Step 8: casting concrete after the completion of vault formwork erection, (i.e. a kind of quick to falsework after the completion of maintenance The accurate device for installing flue arch top template) removed.
It is preferred that, the reinforcing bar of vault tyre shoe is the reinforcing bars of φ 25;The spacing of vault tyre shoe is 600mm;Vault tyre shoe Symmetrically and evenly weld the long cutting back reinforcing bars of φ 25 of 5-6 60mm-80mm in both sides.Use the reinforcement fabrication vault tyre shoes of φ 25, making side Just, it is with low cost, it is reusable, reduce working measure cost.
It is preferred that, the specification of the vault shuttering supporting lumps of wood and the vault shuttering supporting lumps of wood is 100x50mm, length For 3-6m;Flue arch backform plate bracing frame sets up all round victory support using Φ 48*3.5 steel pipes, and the horizontal spacing 600mm of vertical rod × 600mm, it is consistent with vault tyre shoe spacing.
It is preferred that, set up flue arch backform plate bracing frame and set bar of sweeping the floor away from ground 200mm.
It is preferred that, 6 meters of flue arch backform plate bracing frame lateral separation setting bridging.
A kind of device for quick and precisely installing flue arch top template, it includes the flue side wall shuttering supporting lumps of wood, vault tire Piece, the vault shuttering supporting lumps of wood, spiral jacking, flue vault and side wall formwork-support and the vault shuttering supporting lumps of wood prop up steel Muscle;
Vault tyre shoe is set on flue vault and side wall formwork-support;
Flue vault and side wall formwork-support include flue arch backform plate bracing frame and flue side wall formwork-support;
Vault tyre shoe both sides set the welding long cutting back reinforcing bars of φ 25 of 5-6 60mm-80mm, and the vault shuttering supporting lumps of wood is placed On cutting back reinforcing bar;
Flue arch backform plate bracing frame includes vertical rod, vertically and horizontally horizon bar and bridging, vertically and horizontally horizon bar step pitch 1000mm-1200mm;Bridging is laterally set;Spiral jacking is installed on vertical rod top, for adjusting vault absolute altitude;
The flue side wall shuttering supporting lumps of wood is arranged on flue vault and side wall formwork-support side.
It is preferred that, it is provided with jacking upper recess on described spiral jacking.
It is preferred that, vault tyre shoe 5-6 is one group, and the distance between vault tyre shoe is 600mm.
It is preferred that, it is attached between vault tyre shoe by encircleing tire joint steel pipe.
It is preferred that, vault tyre shoe be made up of the reinforcing bars of φ 25 (vault tyre shoe include vertical reinforcement, oblique reinforcing bar and Circular arc reinforcing bar), vault, middle section spot welding arch tire joint steel pipe in vault tyre shoe vertical reinforcement;The vault shuttering supporting lumps of wood Specification with the vault shuttering supporting lumps of wood is 100x50mm, and length is 3-6m;Flue arch backform plate bracing frame uses Φ 48*3.5 Steel pipe sets up all round victory support, vertical rod horizontal spacing 600mm × 600mm, consistent with vault tyre shoe spacing;Set up flue arch top template Support frame sets bar of sweeping the floor away from ground 200mm;6 meters of flue arch backform plate bracing frame lateral separation setting bridging.
The beneficial effects of the invention are as follows:
1st, using fastener for connection vault tyre shoe, tyre shoe group stability is good, and rigidity is high, is not susceptible to deformation;
2nd, vault tyre shoe assembling mode flexibly, can assemble vault tyre shoe group number according to site machinery, artificial situation's adjustment, with Lifting or manual type, which are installed, places;
3rd, vault is installed fast, and continuous productive process can be effectively organized according to engineering construction progress, duration, improves construction effect Rate;
4th, vault tyre shoe both sides welded reinforcement cutting back can quickly be installed to supporting square timber, had as reinforcing bar is propped up Beneficial to the dismounting of vault template, it is easy to recycling;
5th, nail sets vault template on supporting square timber, and formwork erection speed is fast, good forming effect;
6th, steel pipe scaffolding top, which is installed, uses spiral jacking, flexibly can quickly adjust vault absolute altitude, lift operating efficiency, improve Vault installs precision.
Brief description of the drawings
Fig. 1 is vault tyre shoe structural representation of the present invention;
Fig. 2 is present invention arch tire top tyre shoe fastener for connection schematic diagram;
Fig. 3 is that supporting square timber schematic diagram is placed on vault tyre shoe of the present invention;
Fig. 4 is to lay template schematic diagram on vault tyre shoe of the present invention;
Fig. 5 is that vault formwork erection of the present invention completes schematic diagram;
In figure, 1- split bolts, the 2- flue side wall shuttering supporting lumps of wood, 3- flue side wall templates, 4- vault arc formworks, 5- vault tyre shoes, the 6- vault shuttering supporting lumps of wood, 7- spiral jackings, the 8- vault shuttering supporting lumps of wood props up reinforcing bar, and 9- arch tires connect Connect steel pipe, 10- jacking upper recess.
Embodiment
Technical scheme is described in further detail below in conjunction with the accompanying drawings, but protection scope of the present invention is not limited to It is as described below.
As shown in Fig. 1~Fig. 5, a kind of method for quick and precisely installing flue arch top template, it comprises the following steps:
S1, according to flue drawing using the reinforcing bar setting-outs of φ 25 make circular arc vault tyre shoe 5 (reinforcement centering).Vault tyre shoe 5 make rear vertical upright, general 5-6 one group, spacing 600mm.In the vault of the vertical reinforcement of vault tyre shoe 5, middle section point Weldering arch tire joint steel pipe 9, makes vault tyre shoe 5 connect into a monolithic stability component, sees Fig. 1.
S2, the long reinforcing bar cutting backs of φ 25 of 5-6 60mm-80mm are symmetrically and evenly welded in the both sides of vault tyre shoe 5, be used as vault The shuttering supporting lumps of wood props up reinforcing bar 8, and in order to place the vault shuttering supporting lumps of wood 6, the specification of the lumps of wood is generally 100x50mm.
S3, set up flue arch topmast support, Φ 48*3.5 steel pipes set up all round victory support, the horizontal spacing 600mm of vertical rod × 600mm, it is consistent with the spacing of vault tyre shoe 5.Vertically and horizontally horizon bar step pitch 1000mm -1200mm.Set and sweep the floor together away from ground 200mm Bar.6 meters of lateral separation setting bridging.Spiral jacking 7 is installed on vertical rod top, for adjusting vault absolute altitude.
S4, the vault tyre shoe 5 that will be connected are placed on vault support frame, and the horizontal dowel in arch tyre shoe bottom is put into spiral In the upper recess of jacking 7, Fig. 2 is seen.
S5, by the vault shuttering supporting lumps of wood 6, specification is 100x50mm, and length is 3-6m, is placed on the outer of vault tyre shoe 5 What is be welded props up on reinforcing bar, sees Fig. 3.
S6, laid to supporting square timber with multi-layer sheet, along the bottom of vault tyre shoe 5 to vault wooden peg by multi-layer sheet in support side Stickfast on wood, forms complete vault arc formwork 4, sees Fig. 4, Fig. 5.
The vault formwork elevation measuring that S7, erection level measurement have been installed, according to spiral top of the measurement situation to support frame top Support 7 is adjusted, and vault is raised and lowered, and absolute altitude is reached engine request.
Casting concrete after the completion of S8, vault formwork erection, after the completion of maintenance, to falsework (i.e. it is a kind of quick and precisely The device of flue arch top template is installed) removed.
A kind of device for quick and precisely installing flue arch top template, it includes the flue side wall shuttering supporting lumps of wood 2, vault tire Piece 5, the vault shuttering supporting lumps of wood 6, spiral jacking 7, flue vault and side wall formwork-support and vault shuttering supporting lumps of wood support Put reinforcing bar 8;
Vault tyre shoe 5 is set on flue vault and side wall formwork-support;
Flue vault and side wall formwork-support include flue arch backform plate bracing frame and flue side wall formwork-support;
The both sides of vault tyre shoe 5 set the welding long cutting back reinforcing bars of φ 25 of 5-6 60mm-80mm, and the vault shuttering supporting lumps of wood 6 is put Put on cutting back reinforcing bar;
Flue arch backform plate bracing frame includes vertical rod, vertically and horizontally horizon bar and bridging, vertically and horizontally horizon bar step pitch 1000mm-1200mm;Bridging is laterally set;Spiral jacking 7 is installed on vertical rod top, for adjusting vault absolute altitude;
The flue side wall shuttering supporting lumps of wood 2 is arranged on flue vault and side wall formwork-support side, by right when using Draw bolt 1 that flue side wall template 3 is fixed with flue vault and side wall formwork-support, the flue side wall shuttering supporting lumps of wood 2 are arranged between flue side wall template 3 and flue vault and side wall formwork-support.
Preferably, it is provided with jacking upper recess 10 on described spiral jacking 7.
Preferably, 5 quantity of vault tyre shoe 5-6 is one group, and the distance between vault tyre shoe 5 is 600mm.
Preferably, it is attached between vault tyre shoe 5 by encircleing tire joint steel pipe 9.
Preferably, vault tyre shoe 5 is made up that (vault tyre shoe 5 includes vertical reinforcement, oblique reinforcing bar and circular arc of the reinforcing bars of φ 25 Shape reinforcing bar), vault, middle section spot welding arch tire joint steel pipe 9 in the vertical reinforcement of vault tyre shoe 5;The He of the vault shuttering supporting lumps of wood 6 The specification of the vault shuttering supporting lumps of wood 6 is 100x50mm, and length is 3-6m;Flue arch backform plate bracing frame uses Φ 48*3.5 steel Pipe sets up all round victory support, vertical rod horizontal spacing 600mm × 600mm, consistent with the spacing of vault tyre shoe 5;Set up flue arch top template Support frame sets bar of sweeping the floor away from ground 200mm;6 meters of flue arch backform plate bracing frame lateral separation setting bridging.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, it is noted that all Any modifications, equivalent substitutions and improvements made within the spirit and principles in the present invention etc., should be included in the guarantor of the present invention Within the scope of shield.

Claims (10)

1. a kind of method for quick and precisely installing flue arch top template, it is characterised in that:It comprises the following steps:
Step 1: making circular arc vault tyre shoe using reinforcing bar setting-out according to flue drawing;In the arch of vault tyre shoe vertical reinforcement Top, middle section spot welding arch tire joint steel pipe, make vault tyre shoe connect into a monolithic stability component;Vault tyre shoe is vertical after making Uprightly, 5-6 one group;
Step 2: welding cutting back reinforcing bar in vault tyre shoe both sides, reinforcing bar is propped up as the vault shuttering supporting lumps of wood, in order to place The vault shuttering supporting lumps of wood;
Step 3: setting up flue arch backform plate bracing frame, the horizontal spacing of vertical rod is consistent with vault tyre shoe spacing;Vertically and horizontally horizon bar is walked Away from 1000mm-1200mm;;Bridging is laterally set;Spiral jacking is installed on vertical rod top, for adjusting vault absolute altitude;
Step 4: the vault tyre shoe that will be connected is placed on vault support frame, the horizontal dowel in arch tyre shoe bottom is put into spiral In jacking upper recess;
Step 5: being propped up what the vault shuttering supporting lumps of wood was placed on that vault tyre shoe outer is welded on reinforcing bar;
Step 6: laid with multi-layer sheet to the vault shuttering supporting lumps of wood, along vault tyre shoe bottom to vault wooden peg by multi-layer sheet The stickfast on the vault shuttering supporting lumps of wood, forms complete vault camber template;
Step 7: the vault formwork elevation measuring that level measurement has been installed is set up, according to spiral top of the measurement situation to support frame top Support is adjusted, and vault is raised and lowered, and absolute altitude is reached engine request;
Step 8: casting concrete after the completion of vault formwork erection, after the completion of maintenance, is removed to falsework.
2. a kind of method for quick and precisely installing flue arch top template according to claim 1, it is characterised in that:Vault tire The reinforcing bar of piece is the reinforcing bars of φ 25;The spacing of vault tyre shoe is 600mm;Symmetrically and evenly weld 5-6 60mm- in vault tyre shoe both sides The long cutting back reinforcing bars of φ 25 of 80mm.
3. a kind of method for quick and precisely installing flue arch top template according to claim 2, it is characterised in that:Vault mould The specification of plate supporting square timber and the vault shuttering supporting lumps of wood is 100x50mm, and length is 3-6m;Flue arch backform plate bracing frame is adopted Set up all round victory support with Φ 48*3.5 steel pipes, vertical rod horizontal spacing 600mm × 600mm is consistent with vault tyre shoe spacing.
4. a kind of method for quick and precisely installing flue arch top template according to claim 1 or 2 or 3, it is characterised in that: Set up flue arch backform plate bracing frame and set bar of sweeping the floor away from ground 200mm.
5. a kind of method for quick and precisely installing flue arch top template according to claim 4, it is characterised in that:Flue arch 6 meters of backform plate bracing frame lateral separation setting bridging.
6. a kind of device for quick and precisely installing flue arch top template, it is characterised in that:It includes flue side wall shuttering supporting side Wood, vault tyre shoe, the vault shuttering supporting lumps of wood, spiral jacking, flue vault and side wall formwork-support and vault shuttering supporting The lumps of wood props up reinforcing bar;
Vault tyre shoe is set on flue vault and side wall formwork-support;
Flue vault and side wall formwork-support include flue arch backform plate bracing frame and flue side wall formwork-support;
Vault tyre shoe both sides set the welding long cutting back reinforcing bars of φ 25 of 5-6 60mm-80mm, and the vault shuttering supporting lumps of wood is placed on short Cut on reinforcing bar;
Flue arch backform plate bracing frame includes vertical rod, vertically and horizontally horizon bar and bridging, vertically and horizontally horizon bar step pitch 1000mm- 1200mm;Bridging is laterally set;Spiral jacking is installed on vertical rod top, for adjusting vault absolute altitude;
The flue side wall shuttering supporting lumps of wood is arranged on flue vault and side wall formwork-support side.
7. a kind of device for quick and precisely installing flue arch top template according to claim 6, it is characterised in that:Described Jacking upper recess is provided with spiral jacking.
8. a kind of device for quick and precisely installing flue arch top template according to claim 6 or 7, it is characterised in that:Arch It is one group to push up tyre shoe 5-6, and the distance between vault tyre shoe is 600mm.
9. a kind of device for quick and precisely installing flue arch top template according to claim 8, it is characterised in that:Vault tire It is attached between piece by encircleing tire joint steel pipe.
10. a kind of device for quick and precisely installing flue arch top template according to claim 9, it is characterised in that:Vault Tyre shoe is made up of the reinforcing bars of φ 25;The specification of the vault shuttering supporting lumps of wood and the vault shuttering supporting lumps of wood is 100x50mm, and length is 3-6m;Flue arch backform plate bracing frame sets up all round victory support using Φ 48*3.5 steel pipes, the horizontal spacing 600mm × 600mm of vertical rod, It is consistent with vault tyre shoe spacing;Set up flue arch backform plate bracing frame and set bar of sweeping the floor away from ground 200mm;Flue arch backform plate bracing frame 6 meters of lateral separation setting bridging.
CN201710445726.XA 2017-06-14 2017-06-14 A kind of method and apparatus for quick and precisely installing flue arch top template Pending CN107090971A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710445726.XA CN107090971A (en) 2017-06-14 2017-06-14 A kind of method and apparatus for quick and precisely installing flue arch top template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710445726.XA CN107090971A (en) 2017-06-14 2017-06-14 A kind of method and apparatus for quick and precisely installing flue arch top template

Publications (1)

Publication Number Publication Date
CN107090971A true CN107090971A (en) 2017-08-25

Family

ID=59640270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710445726.XA Pending CN107090971A (en) 2017-06-14 2017-06-14 A kind of method and apparatus for quick and precisely installing flue arch top template

Country Status (1)

Country Link
CN (1) CN107090971A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108468556A (en) * 2018-05-29 2018-08-31 中铁十四局集团第二工程有限公司 A kind of variable section is by multiple formwork-support
CN110205141A (en) * 2019-05-31 2019-09-06 中国五冶集团有限公司 Tire bone stand manufacturing method is encircleed in capacity coke oven flue vault concreting
CN110579108A (en) * 2019-09-02 2019-12-17 新兴铸管股份有限公司 Method for building supporting roof of steelmaking mixer
CN113431192A (en) * 2021-08-11 2021-09-24 中建八局第四建设有限公司 Arc-curved surface end part and construction method thereof, and vault channel and construction method thereof
CN114874791A (en) * 2022-05-30 2022-08-09 中化二建集团有限公司 Coke oven flue upside-down mounting construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101870872A (en) * 2010-07-22 2010-10-27 中国一冶集团有限公司 Method for building vault lining of flue
CN103059883A (en) * 2011-10-24 2013-04-24 五冶集团上海有限公司 Arch stuffing supporting technology by bricking arch apex for division of flue in coke oven
CN203947752U (en) * 2014-07-23 2014-11-19 中国五冶集团有限公司 The servicing unit of building by laying bricks or stones for coke oven flue vault
CN105838392A (en) * 2016-03-30 2016-08-10 中国冶集团有限公司 BIM-technology-based construction method for 90-DEG mouth-to-mouth vaulting mould used for flues of coke oven
CN106147800A (en) * 2015-04-14 2016-11-23 五冶集团上海有限公司 A kind of coke oven flue lining construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101870872A (en) * 2010-07-22 2010-10-27 中国一冶集团有限公司 Method for building vault lining of flue
CN103059883A (en) * 2011-10-24 2013-04-24 五冶集团上海有限公司 Arch stuffing supporting technology by bricking arch apex for division of flue in coke oven
CN203947752U (en) * 2014-07-23 2014-11-19 中国五冶集团有限公司 The servicing unit of building by laying bricks or stones for coke oven flue vault
CN106147800A (en) * 2015-04-14 2016-11-23 五冶集团上海有限公司 A kind of coke oven flue lining construction method
CN105838392A (en) * 2016-03-30 2016-08-10 中国冶集团有限公司 BIM-technology-based construction method for 90-DEG mouth-to-mouth vaulting mould used for flues of coke oven

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
方海滨: "浅谈焦炉机焦两侧烟道弯管及烟道顶板模板加固方法", 《科技风》, 31 January 2012 (2012-01-31), pages 73 *
殷雁洪: "闭合拱架通道桥拱形模板施工方法", 《交通世界(建筑.机械)》, no. 15, 31 August 2009 (2009-08-31), pages 156 - 159 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108468556A (en) * 2018-05-29 2018-08-31 中铁十四局集团第二工程有限公司 A kind of variable section is by multiple formwork-support
CN110205141A (en) * 2019-05-31 2019-09-06 中国五冶集团有限公司 Tire bone stand manufacturing method is encircleed in capacity coke oven flue vault concreting
CN110579108A (en) * 2019-09-02 2019-12-17 新兴铸管股份有限公司 Method for building supporting roof of steelmaking mixer
CN113431192A (en) * 2021-08-11 2021-09-24 中建八局第四建设有限公司 Arc-curved surface end part and construction method thereof, and vault channel and construction method thereof
CN114874791A (en) * 2022-05-30 2022-08-09 中化二建集团有限公司 Coke oven flue upside-down mounting construction method

Similar Documents

Publication Publication Date Title
CN107090971A (en) A kind of method and apparatus for quick and precisely installing flue arch top template
CN101886466B (en) Construction method for support structure of coal tower template for tamping type coke oven
CN105863253B (en) Integral formwork support is asynchronous to pour staircase wall column formwork system and construction method
CN103669865A (en) Stair construction method through shaped supports
CN107989447A (en) A kind of large-scale earthing concrete tank dome steel support structure and installation method
CN103790423B (en) Large-sized concrete silo construction method
CN103556823A (en) Construction method with silo sliding formwork operating platform as top cover plate formwork supporting system
CN105586833A (en) Construction method for integrally forming large cast-in-place thin-wall high pier through stiff skeleton reinforcement cage
CN104962296A (en) Coke oven basis flue fast construction method free of top die erecting
CN111576856A (en) Aluminum alloy template assembling system and assembling method
CN103590420A (en) Top-formwork-erection-free construction method of coke oven base smoke dividing flue
CN110158951B (en) Construction method of all-wood template with frame structure
CN109778911B (en) Underground pipe gallery composite plastic formwork assembling and disassembling construction method
CN206829603U (en) A kind of device for quick and precisely installing flue arch top template
CN211228607U (en) Integrally formed construction structure of outer wall and bottom plate of cast-in-place concrete structure of structure
CN101586810B (en) Secondary mounting method for construction elbow of flue opening
CN205975637U (en) A template reinforcing apparatus for concrete placement in circular well
CN206016230U (en) It is based on assembled wall-connecting piece exterior wall scaffold system
CN102605988B (en) Synchronous construction method for chimney lining external concrete
CN108951643B (en) Super high-rise deep foundation pit basement core tube large-span large-area support changing construction method
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN104131635A (en) Method and platform for constructing peripheral shear wall of prefabricated staircase
CN112942809A (en) Combined template assembling method capable of realizing mechanical construction
CN205875706U (en) Asynchronous stairwell wall post formwork system that pours of whole formwork
CN105178594B (en) A kind of hollow column template and its construction method for exempting from scaffold construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170825

RJ01 Rejection of invention patent application after publication