CN107063017A - It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise - Google Patents

It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise Download PDF

Info

Publication number
CN107063017A
CN107063017A CN201611211317.5A CN201611211317A CN107063017A CN 107063017 A CN107063017 A CN 107063017A CN 201611211317 A CN201611211317 A CN 201611211317A CN 107063017 A CN107063017 A CN 107063017A
Authority
CN
China
Prior art keywords
eye
mud
noise
tunnel
powder charge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611211317.5A
Other languages
Chinese (zh)
Inventor
张馨
陈历珊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201611211317.5A priority Critical patent/CN107063017A/en
Publication of CN107063017A publication Critical patent/CN107063017A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • F42D1/08Tamping methods; Methods for loading boreholes with explosives; Apparatus therefor

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise, drilling is positioned by quick-fried layout drawing is bored.It is clean that with high-pressure blast eye is swept before powder charge, rock emulsion explosive and non-electrical second-delay detonator are selected respectively, powder charge is carried out to powder charge eye by buffer blasting parameter designing table, periphery hole spaced loading, remaining borehole continuous charging, powder charge on earth, and should be blocked in place with stemming, and empty eye is filled using plastic bag mud.Detonator is connected on request in place, equipment, personnel are removed beyond safe distance, detonated after confirming safety.The present invention can not only strengthen the quick-fried power in eyeground, improve explosion drilling depth, especially strengthen to blasting impact wave reflection, refraction and absorb, accelerate shock wave → decay → stress wave → decay → seismic wave, greatly reduce blasting vibration and noise, Explosive Vibrating Velocity is greatly reduced and disturbed residents in below 5cm/s after testing, achieves good techno-economic effect.

Description

It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise
Technical field
The empty eye mud vibration damping Controlled blasting technique in tunnel with noise is shaken the present invention relates to a kind of effective reduction, specifically Say, be the construction technology that empty eye is set in blasting body and plastic bag mud is clogged.
Background technology
Big Black Hills tunnel abuts residential block, because blast working noise and vibrations are larger, is hindered work by neighbouring resident for a long time, Repeatedly night blast working is forbidden in dispatch for Environmental Protection Agency, and progress is very slow.
The content of the invention
The problem of purpose of the present invention is that solution blast working noise is big, vibrations are big, disturbs residents serious, proposes that one kind has The vibration damping Controlled blasting technique of effect reduction concussion of blasting and noise, using many emptying eyes, the empty eye of periphery interorbital space and powder charge eye Residue length is by design dress Φ 35mm × 500mm or Φ 35mm × 1000mm plastic bag mud, and the ophthalmically acceptable stemming closure of powder charge should Method construction technology is simple, practical, economical, efficient.
The technical scheme is that:The empty eye mud vibration damping control in tunnel of a kind of effective reduction concussion of blasting and noise is quick-fried Broken technology.It is characterized in that:Carried out according to the following steps:
1. drilling is positioned by brill quick-fried layout drawing, self-spraying paint sign is determined according to buffer blasting parameter designing table Technical parameter carries out perforating from Φ 38mm " one " fonts drill bit.
2. eye is swept before powder charge with high-pressure blast totally, is emulsified respectively from specification Φ 32mm × 200mm × 200g 2# rocks Explosive and non-electrical second-delay detonator, by buffer blasting parameter designing table to powder charge eye carry out powder charge, periphery hole spaced loading, remaining Borehole continuous charging, powder charge on earth, and should be blocked in place with stemming, empty eye using Φ 35mm × 500mm or Φ 35mm × 1000mm plastic bags mud is filled.
3. detonator is connected on request in place, equipment, personnel are removed beyond safe distance, risen after confirming safety It is quick-fried.
During above-mentioned perforating, determine eye and want standard, borehole is straight, and angle is right, in addition to snubber and bottom eye, other eyes want base Originally fall at grade.
Above-mentioned mud specification of plastic bag is the ㎜ of the ㎜ or ㎜ of Φ 35 of ㎜ of Φ 35 × 500 × 1000, polybag must producer have made to order, Ensure quality.
Above-mentioned packed mud is put into sky at the moment, to handle with care, be put if necessary with relatively thin Φ 38mm pvc pipe sets, it is ensured that Crust is not broken, and mud can not be spread out.
Appeal stemming makes of yellow clay, watering moistening, soft appropriateness, is conducive to loading, blocks heel.
Above-mentioned powder charge uses second-delay detonator, is 1.2~1.4 seconds per adjacent two intersegmental extension times.
The tunnel of table 1 sky eye mud vibration damping controlled blasting top bar blasting parameter design table
The tunnel of table 2 sky eye mud vibration damping controlled blasting initial condition and expected blasting effect table
The sky eye mud vibration damping controlled blasting of the tunnel of table 3 is got out of a predicament or an embarrassing situation unilateral buffer blasting parameter designing table
The sky eye mud vibration damping controlled blasting of the tunnel of table 4 is got out of a predicament or an embarrassing situation unilateral buffer blasting initial condition and Expected Results table
The present invention has the advantage that and good effect:
1. the quick-fried power in eyeground can not only be strengthened by filling empty eye and stemming closure powder charge eye using packed mud, improved explosion and entered Chi, especially strengthens to blasting impact wave reflection, refraction and absorbs, accelerate shock wave → decay → stress wave → decay → earthquake Ripple, greatly reduces blasting vibration, noise, and Explosive Vibrating Velocity is greatly reduced and disturbed residents in 5cm/s after testing.2. residence nearby is solved The people hinder work problem, realize night work continuous construction in 24 hours, improve construction speed, achieve good Technological Economy effect Really.
Brief description of the drawings
Fig. 1 is that the empty eye mud vibration damping Controlled blasting technique in tunnel bores quick-fried layout drawing
Embodiment
A kind of empty eye mud vibration damping Controlled blasting technique in tunnel of effective reduction concussion of blasting and noise.Specific implementation process It is as follows:1. excavation face crag is purged, drilling is accurately positioned by quick-fried layout drawing is bored, self-spraying paint sign, according to explosion ginseng In number design table, the technical parameter such as inclination angle, eye depth, eye distance applies brill from Φ 38mm " one " font drill bit, digs out 40mm blastholes. 2. sweep that eye is clean before powder charge using high-pressure blast, respectively the 2# rock emulsion explosives from specification Φ 32mm × 200mm × 200g and Non-electrical second-delay detonator, carries out powder charge, periphery hole spaced loading, remaining borehole connects by buffer blasting parameter designing table to powder charge eye Continuous powder charge, powder charge on earth, and should be blocked in place with stemming.3. empty eye using Φ 35mm × 500mm or Φ 35mm × 1000mm plastic bags mud is filled, and should be handled with care during filling, be put if necessary using Φ 38mmPVC pipe sleeves, prevent polybag Breakage, mud is spread out.4. detonator is connected on request in place, equipment, personnel are removed beyond safe distance, confirms that safety is laggard Row detonation.

Claims (5)

1. a kind of reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise, it is characterised in that:According to following step It is rapid to carry out:S1 is positioned by quick-fried layout drawing is bored to drilling, and the technical parameter determined according to buffer blasting parameter designing table is selected Φ 38mm " one " fonts drill bit carries out perforating;Eye is swept with high-pressure blast totally, before S2 powder charges respectively from specification Φ 32mm × 200mm × 200g 2# rock emulsion explosives and non-electrical second-delay detonator, powder charge is carried out by buffer blasting parameter designing table to powder charge eye, Periphery hole spaced loading, remaining borehole continuous charging, powder charge on earth, and should be blocked in place with stemming, and empty eye uses Φ 35mm × 500mm or Φ 35mm × 1000mm plastic bags mud filling;S3 connects detonator in place on request, equipment, personnel Remove beyond safe distance, detonated after confirming safety.
2. a kind of reduction vibrations according to claim 1 and the empty eye mud vibration damping controlled blasting method in tunnel of noise, its It is characterised by:Mud specification of plastic bag is Φ 35mm × 500mm or Φ 35mm × 1000mm, and polybag is tailor-made part.
3. a kind of reduction vibrations according to claim 1 and the empty eye mud vibration damping controlled blasting method in tunnel of noise, its It is characterised by:Packed mud is put into sky at the moment, to handle with care, be put if necessary with thin Φ 38mmPVC pipe sleeves, it is ensured that crust is not Broken, mud can not be spread out.
4. a kind of reduction vibrations according to claim 1 and the empty eye mud vibration damping controlled blasting method in tunnel of noise, its It is characterised by:Stemming is made from yellow clay, watering moistening, soft appropriateness, is conducive to loading, is blocked heel.
5. a kind of reduction vibrations according to claim 1 and the empty eye mud vibration damping controlled blasting method in tunnel of noise, its It is characterised by:Powder charge uses second-delay detonator, is 1.2~1.4 seconds per adjacent two intersegmental extension times.
CN201611211317.5A 2016-12-24 2016-12-24 It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise Pending CN107063017A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611211317.5A CN107063017A (en) 2016-12-24 2016-12-24 It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611211317.5A CN107063017A (en) 2016-12-24 2016-12-24 It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise

Publications (1)

Publication Number Publication Date
CN107063017A true CN107063017A (en) 2017-08-18

Family

ID=59623800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611211317.5A Pending CN107063017A (en) 2016-12-24 2016-12-24 It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise

Country Status (1)

Country Link
CN (1) CN107063017A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109341450A (en) * 2018-10-30 2019-02-15 中电建南方建设投资有限公司 A kind of Tunnel Blasting structure and Tunnel Blasting construction method
CN111023927A (en) * 2019-12-02 2020-04-17 中国铁建重工集团股份有限公司 Soft rock single-step deep hole undercutting vibration-reduction flat-bottom light explosion structure in tunnel
CN114322686A (en) * 2021-12-31 2022-04-12 北京住总集团有限责任公司 Detonating network structure and control method for safety blasting of underground excavation tunnel
CN115183643A (en) * 2022-06-21 2022-10-14 贵州省公路工程集团有限公司 Safe construction method for controlling blasting noise and shock wave of tunnel close to residential area

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102095338A (en) * 2010-12-14 2011-06-15 中国建筑第八工程局有限公司 Tunneling electron detonator blasting construction method
CN102809329A (en) * 2012-08-17 2012-12-05 重庆市爆破工程建设有限责任公司 Stone shallow hole blasting control method applied in town
CN103017622A (en) * 2012-12-18 2013-04-03 山西大同大学 Water-resisting returnable multi-stage buffer fractured self-deformation self-latching shot hole stopper
CN103175451A (en) * 2013-03-13 2013-06-26 中国建筑土木建设有限公司 Construction method of tunnel shock relieve hole controlling blasting
CN103983147A (en) * 2014-04-18 2014-08-13 同济大学 Permafrost region road tunnel peripheral hole blasting construction method
CN105588479A (en) * 2016-02-25 2016-05-18 中铁十八局集团有限公司 Three-times elementary error vibration reduction major blasting method using rock flour spaced loading in blasting holes

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102095338A (en) * 2010-12-14 2011-06-15 中国建筑第八工程局有限公司 Tunneling electron detonator blasting construction method
CN102809329A (en) * 2012-08-17 2012-12-05 重庆市爆破工程建设有限责任公司 Stone shallow hole blasting control method applied in town
CN103017622A (en) * 2012-12-18 2013-04-03 山西大同大学 Water-resisting returnable multi-stage buffer fractured self-deformation self-latching shot hole stopper
CN103175451A (en) * 2013-03-13 2013-06-26 中国建筑土木建设有限公司 Construction method of tunnel shock relieve hole controlling blasting
CN103983147A (en) * 2014-04-18 2014-08-13 同济大学 Permafrost region road tunnel peripheral hole blasting construction method
CN105588479A (en) * 2016-02-25 2016-05-18 中铁十八局集团有限公司 Three-times elementary error vibration reduction major blasting method using rock flour spaced loading in blasting holes

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109341450A (en) * 2018-10-30 2019-02-15 中电建南方建设投资有限公司 A kind of Tunnel Blasting structure and Tunnel Blasting construction method
CN109341450B (en) * 2018-10-30 2022-06-21 中电建南方建设投资有限公司 Tunnel blasting structure and tunnel blasting construction method
CN111023927A (en) * 2019-12-02 2020-04-17 中国铁建重工集团股份有限公司 Soft rock single-step deep hole undercutting vibration-reduction flat-bottom light explosion structure in tunnel
CN111023927B (en) * 2019-12-02 2022-04-05 中铁十八局集团有限公司 Soft rock single-step deep hole undercutting vibration-reduction flat-bottom light explosion structure in tunnel
CN114322686A (en) * 2021-12-31 2022-04-12 北京住总集团有限责任公司 Detonating network structure and control method for safety blasting of underground excavation tunnel
CN115183643A (en) * 2022-06-21 2022-10-14 贵州省公路工程集团有限公司 Safe construction method for controlling blasting noise and shock wave of tunnel close to residential area
CN115183643B (en) * 2022-06-21 2023-11-10 贵州省公路工程集团有限公司 Safe construction method for controlling blasting noise and shock waves of tunnels in close vicinity of residential areas

Similar Documents

Publication Publication Date Title
CN107063017A (en) It is a kind of to reduce the empty eye mud vibration damping controlled blasting method in the tunnel of vibrations and noise
CN104989405B (en) Mining steeply dipping coal seam bump orients prevention and controls
CN103453809B (en) Water-mist dust settling method implemented during blast excavation for large-scale underground project
CN104634198B (en) Close on controlled blasting construction method in the massif excavation of highway limit
CN105874299A (en) Explosive tube having air gap and method of blasting bedrock using same
CN106014414B (en) A kind of explosion stoping method of block stoping level pillar
CN103670412B (en) A kind of Mined-out Area control of high-dipping ore block exploitation and Depressurized mining method
CN103983147A (en) Permafrost region road tunnel peripheral hole blasting construction method
CN102733808B (en) Closed pit open-pit mine ore recovery method
CN107328327A (en) The soft or hard blast hole loading structure and its method for being mingled with beded rock mass Long-hole Bench Blasting
CN110595308B (en) Method for treating goaf by ultra-deep hole blasting of strip mine
CN102808621B (en) Method for blasting heavy-inclined thick ore bodies
CN107339920B (en) The method of superdeep holes presplit blasting
CN109870084B (en) VCR mining method hole-sweeping-free blasting charge structure and construction method thereof
CN107060773A (en) A kind of underground chamber drilling and blasting method damping excavation method of static(al) explosion presplitting shock insulation
CN106545344B (en) A kind of Karst area tunnel wall-hanging country rock face blast excavation method
CN105649626B (en) The slotting formula scarps filling mining method of the very thin arteries and veins orebody mining of high-dipping
CN102269544A (en) One-end-closed cumulative blasting slotted pipe device
CN110924398B (en) High-strength rock slope widening excavation construction method under condition of traffic protection
CN109974545B (en) Medium-length hole blasting suspended roof processing method in sublevel caving method
US3611933A (en) Nuclear cavity configuration control
CN209857781U (en) Mine blasting big gun hole structure
CN105823388A (en) Blasting network structure used for slight dynamite
CN109594986A (en) A kind of foam type creates medium-length hole back production explosion collocation structure and its construction method
CN219197326U (en) Rock mass suspended ceiling medium-length hole bottom pulling structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818