CN106948458A - A kind of drainage management construction method - Google Patents

A kind of drainage management construction method Download PDF

Info

Publication number
CN106948458A
CN106948458A CN201710357442.5A CN201710357442A CN106948458A CN 106948458 A CN106948458 A CN 106948458A CN 201710357442 A CN201710357442 A CN 201710357442A CN 106948458 A CN106948458 A CN 106948458A
Authority
CN
China
Prior art keywords
pipeline
hydraulic pressure
pressure sensor
construction method
drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710357442.5A
Other languages
Chinese (zh)
Inventor
李贵兴
张生统
高扬
任义亮
铁福春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Engineering Bureau 4 Co Ltd
Original Assignee
Sinohydro Engineering Bureau 4 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Engineering Bureau 4 Co Ltd filed Critical Sinohydro Engineering Bureau 4 Co Ltd
Priority to CN201710357442.5A priority Critical patent/CN106948458A/en
Publication of CN106948458A publication Critical patent/CN106948458A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F2201/00Details, devices or methods not otherwise provided for
    • E03F2201/20Measuring flow in sewer systems

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Testing Resistance To Weather, Investigating Materials By Mechanical Methods (AREA)

Abstract

A kind of drainage management construction method, belongs to construction engineering technical field, the construction applied to drainage pipeline.The present invention provides a kind of drainage management construction method, including channel excavation, basement process, pipe laying, Pipe installing, check well construction, seven steps of closed-water test and trench backfill, pressure sensor is installed in the inwall both sides of pipeline, the position connected between pipeline is using O-ring seal as pad, so and humidity sensor is installed in cushion rubber periphery, the hydraulic pressure value and water leakage situation in pipeline can be monitored by pressure sensor and humidity sensor, and produced problem in construction can in time be notified to safeguard unit, improve construction quality, shorten construction period, it is easy to utilize.

Description

A kind of drainage management construction method
Technical field
The invention belongs to construction engineering technical field, a kind of drainage management construction method is concretely related to.
Background technology
Urban underground water drainage pipe road is intricate, with the frequent draining use and aging of drainage pipeline, drainage pipeline Leakage problems often occur.Either valuable water resource waste, or the various economic losses caused after drainage pipeline seepage, So that drainage pipeline leakage problems must cause enough attention.
Because drainage pipeline is arranged on below wall or terrace so that drainage pipeline seepage is difficult to be found, and occurs It is difficult to check breakthrough after seepage.
For this reason, it is necessary to invent a kind of new drainage management construction method.
The content of the invention
, can it is an object of the invention to overcome above-mentioned deficiency of the prior art there is provided a kind of drainage management construction method To monitor the hydraulic pressure value and water leakage situation in pipeline in time by pressure sensor and humidity sensor.
To achieve the above object, the present invention uses following technical scheme:
A kind of drainage management construction method, its feature is:Comprise the following steps:
The first step, channel excavation:Line setting is carried out according to pipeline rout and depth, channel excavation is then carried out;
Second step, basement process:Soft soil horizon below pipeline foundation is cut out, then backfilling material and tamped as pipe Road basis;
3rd step, pipe laying:Pipeline is numbered, the barrel of pipe mouth of pipe of pipeline is cleared up, is then steadily put into pipeline In the groove dug;
4th step, Pipe installing:The first hydraulic pressure pressure sensor and the second hydraulic pressure pressure are respectively mounted at inner-walls of duct two ends Force snesor, is then linked in sequence to pipeline, and the position connected between pipeline uses O-ring seal as pad, before installation Water-soaked O-ring seal is first used, humidity sensor then is installed in cushion rubber periphery, finally pipeline is fixed;
5th step:Well construction is checked, is cut the earth according to the depth of inspection shaft, then constructs reinforcing bar in well base working face Net, then lays 200~220mm mixed mud bed courses;
Well room is built by laying bricks or stones, and inspection shaft sintering brick masonry simultaneously installs cat ladder, then inside and outside waterproof is done to well room, in well indoor and outdoor Wall is with 1:2 waterproof cement mortars are wiped one's face 20~25mm;
6th step:Closed-water test, the water filling into the inspection shaft of water flowing section again after well room design strength reaches 75~80%, Untill monitoring the measurement result of hydraulic pressure pressure sensor and humidity sensor, no drainage simultaneously;
7th step, trench backfill:The groove for placing pipeline is backfilled, backfill should be from ttom of pipe upwards manually successively Layering is symmetrically backfilled and tamped.
Further, the backfill material in described step two is concrete, as thickness of earth covering≤6m of pipeline, is used 120 ° of concrete, as the thickness of earth covering > 6m of pipeline, pipeline foundation are used as using 180 ° of concrete as pipeline foundation bed course Bed course.
Further, the cushion rubber material in described step four is the synthetic rubber with acid and alkali resistance and corrosion in water.
Further, in described step five bar-mat reinforcement a diameter of 10mm, spacing be 200 × 200mm.
Further, in described step six carry out closed-water test when, after pipeline water flowing, the first hydraulic pressure pressure sensor and Second hydraulic pressure pressure sensor is measured respectively obtains the first hydraulic pressure value and the second hydraulic pressure value, and the second hydraulic pressure pressure sensor is by second Hydraulic pressure value is wirelessly sent to the first hydraulic pressure pressure sensor, if the difference of the first hydraulic pressure value and the second hydraulic pressure value is big In 0.03MPa, pipeline there may be splintering problem, and now the first hydraulic pressure pressure sensor wirelessly sends out measurement result Give ECC engineering control center.
The present invention has the advantages that compared with prior art:
A kind of drainage management construction method that the present invention is provided, can be supervised by hydraulic pressure pressure sensor and humidity sensor The water leakage situation of junction between hydraulic pressure value and pipeline in keyholed back plate road, and can be by the quality problems occurred in building construction process Notify to safeguard unit in time, be effectively improved efficiency of construction and quality, shorten construction period, it is easy to utilize.
The other features and advantages of the invention will be illustrated in the following description.
Embodiment
Here is the embodiment of a specific drainage management construction method, and technical solution of the present invention is made in conjunction with the embodiments Further describe.
Embodiment 1
Embodiments in accordance with the present invention, propose a kind of construction method of drainage pipeline, comprise the following steps:
The first step, channel excavation:Pipeline rout and pipeline depth in arrangement and method for construction carry out line setting, Ran Houkai Digging groove.
Second step, basement process:Soft soil horizon below pipeline foundation is cut out, then backfilling material and tamped as pipe Road basis, the backfill material of selection is concrete, and as thickness of earth covering≤6m of pipeline, pipeline foundation is used as using 120 ° of concrete Bed course, as the thickness of earth covering > 6m of pipeline, pipeline foundation bed course is used as using 180 ° of concrete.
3rd step, pipe laying:Pipeline is transported into job site, pipeline is numbered, while by pipeline internal cleaning It is clean and carry out mouth of pipe closure;The first hydraulic pressure pressure sensor is respectively mounted at the inwall two ends of pipeline and the second hydraulic pressure pressure is passed Sensor, is then transported to each working face by pipeline with flat car, pipeline is steadily put into the groove dug.
4th step, Pipe installing:Pipeline is linked in sequence according to numbering, should be away from interface in counterpart between pipeline Glacing flatness is measured at the 200mm of center, as the DN < 100 of the pipeline, it is allowed to which deviation is 1mm, when DN >=100 of the pipeline When, it is allowed to deviation is 2mm.
The position connected between pipeline water-soaked O-ring seal, as pad, is first used, then before installing using O-ring seal Humidity sensor is installed in cushion rubber periphery, finally pipeline is fixed from the firm pipeline of two checkposts with clean stone or rubble.
5th step, checks well construction:Cut the earth according to the depth of inspection shaft, then construct a diameter of in well base working face 10mm, spacing is 200 × 200mm bar-mat reinforcement, is finally used as well basic unit in working face laying 200mm mixed muds bed course.
Brick masonry is sintered to the well room of inspection shaft and cat ladder is installed, inside and outside waterproof then is done to well room, in well indoor and outdoor Wall is with 1:2 waterproof cement mortars are wiped one's face 20mm.
6th step, closed-water test:Well room is conserved, again to the inspection shaft of water flowing section after well room design strength reaches 75% Interior water filling, while monitoring the measurement result of pressure sensor and humidity sensor, it is to avoid there is drainage.
7th step, trench backfill:The groove for placing pipeline is backfilled, backfill should be from ttom of pipe upwards manually successively Layering is symmetrically backfilled and tamped.
In the present embodiment, the pipeline is ductile iron pipe, the thick insulating rubber plastics of outside winding 30mm.
In the present embodiment, the material of cushion rubber is the synthetic rubber with acid and alkali resistance, corrosion in water in step 4.
In the present embodiment, the well lid of inspection shaft is molded composite heavy type well lid for macromolecule.
In the present embodiment, the inspection shaft provided pipe mouth of pipe is built sealing by laying bricks or stones using low-intensity mortar and wiped one's face.
In the present embodiment, when carrying out closed-water test, after pipeline water flowing, the first hydraulic pressure pressure sensor measurement obtains the first water Pressure value, the second hydraulic pressure pressure sensor measurement obtains the second hydraulic pressure value, and the second hydraulic pressure pressure sensor passes through the second hydraulic pressure value The first hydraulic pressure pressure sensor is wirelessly transmitted to, if the difference of the first hydraulic pressure value and the second hydraulic pressure value is more than 0.03MPa, Imply that pipeline there may be splintering problem, then measurement result is wirelessly sent to work by the first hydraulic pressure pressure sensor Process control center, wherein, the measurement result at least number information including pipeline, the first hydraulic pressure value, the second hydraulic pressure value.
Wherein, number information is sent to engineering maintenance personnel by ECC engineering control center by wireless network, and passes through signaling It is required that the first hydraulic pressure pressure sensor sends alarm sound, the engineering maintenance personnel at convenient scene quickly position the pipe gone wrong Road.
In addition, after pipeline water flowing, humidity sensor measurement obtains humidity value, if humidity value is more than preset value, humidity Measurement result is wirelessly sent to ECC engineering control center by sensor, wherein, measurement result at least includes the pipe of connection The identification information and humidity value in road.Preset value is sent to humidity sensor by ECC engineering control center by wireless network.
Number information is sent to engineering maintenance personnel by ECC engineering control center by wireless network, and wet by signaling request Degree sensor sends alarm sound, facilitates field engineering attendant quickly to position the pipeline gone wrong.
Embodiment 2
Embodiments in accordance with the present invention, propose a kind of construction method of drainage pipeline, comprise the following steps:
The first step, channel excavation:Line setting is carried out according to pipeline rout and depth, earth excavation is then carried out.
Second step, basement process:Soft soil horizon below pipeline foundation is cut out, then backfilling material and tamped as pipe Road basis, the backfill material of selection is concrete, and as thickness of earth covering≤6m of pipeline, pipeline foundation is used as using 120 ° of concrete Bed course, as the thickness of earth covering > 6m of pipeline, pipeline foundation bed course is used as using 180 ° of concrete.
3rd step, pipe laying:Pipeline is transported into job site, pipeline is numbered, while by pipeline internal cleaning It is clean and carry out mouth of pipe closure;The first hydraulic pressure pressure sensor is respectively mounted at the inwall two ends of pipeline and the second hydraulic pressure pressure is passed Sensor, is then transported to each working face by pipeline with flat car, pipeline is steadily put into the groove dug.
4th step, Pipe installing:Pipeline is linked in sequence according to numbering, should be away from interface in counterpart between pipeline Glacing flatness is measured at the 200mm of center, as the DN < 100 of the pipeline, it is allowed to which deviation is 1mm, when DN >=100 of the pipeline When, it is allowed to deviation is 2mm.
The position connected between pipeline water-soaked O-ring seal, as pad, is first used, then before installing using O-ring seal Humidity sensor is installed in cushion rubber periphery, finally pipeline is fixed from the firm pipeline of two checkposts with clean stone or rubble.
5th step, checks well construction, is cut the earth according to the depth of inspection shaft, then construct a diameter of in well base working face 10mm, spacing is 200 × 200mm bar-mat reinforcement, then lays 220mm mixed muds bed course and is used as well basic unit.
Brick masonry is sintered to the well room of inspection shaft and cat ladder is installed, inside and outside waterproof then is done to well room, in well indoor and outdoor Wall is with 1:2 waterproof cement mortars are wiped one's face 25mm.
6th step, carries out closed-water test, well room is conserved, again to the inspection of water flowing section after well room design strength reaches 80% Water filling in well is looked into, while monitoring the measurement result of hydraulic pressure pressure sensor and humidity sensor, it is to avoid there is drainage.
7th step:Trench backfill, is backfilled to the groove for placing pipeline, and backfill should be from ttom of pipe upwards manually successively Layering is symmetrically backfilled and tamped.
In the present embodiment, the pipeline is ductile iron pipe, the thick insulating rubber plastics of outside winding 30mm.
In the present embodiment, the material of cushion rubber is the synthetic rubber with acid and alkali resistance, corrosion in water in step 4.
In the present embodiment, the well lid of inspection shaft is molded composite heavy type well lid for macromolecule.
In the present embodiment, the inspection shaft provided pipe mouth of pipe is built sealing by laying bricks or stones using low-intensity mortar and wiped one's face.
In the present embodiment, when carrying out closed-water test, after pipeline water flowing, the first hydraulic pressure pressure sensor measurement obtains the first water Pressure value, the second hydraulic pressure pressure sensor measurement obtains the second hydraulic pressure value, and the second hydraulic pressure pressure sensor passes through the second hydraulic pressure value The first hydraulic pressure pressure sensor is wirelessly transmitted to, if the difference of the first hydraulic pressure value and the second hydraulic pressure value is more than 0.03MPa, Imply that pipeline there may be splintering problem, then measurement result is wirelessly sent to work by the first hydraulic pressure pressure sensor Process control center, wherein, the measurement result at least number information including pipeline, the first hydraulic pressure value, the second hydraulic pressure value.
Wherein, number information is sent to engineering maintenance personnel by ECC engineering control center by wireless network, and passes through signaling It is required that the first hydraulic pressure pressure sensor sends alarm sound, the engineering maintenance personnel at convenient scene quickly position the pipe gone wrong Road.
In addition, after pipeline water flowing, humidity sensor measurement obtains humidity value, if humidity value is more than preset value, humidity Measurement result is wirelessly sent to ECC engineering control center by sensor, wherein, measurement result at least includes the pipe of connection The identification information and humidity value in road.Preset value is sent to humidity sensor by ECC engineering control center by wireless network.
Number information is sent to engineering maintenance personnel by ECC engineering control center by wireless network, and wet by signaling request Degree sensor sends alarm sound, facilitates field engineering attendant quickly to position the pipeline gone wrong.
The foregoing is intended to be a preferred embodiment of the present invention, but protection scope of the present invention is not limited thereto, Any one skilled in the art the invention discloses technical scope in, the change or replacement that can be readily occurred in, It should all be included within the scope of the present invention.

Claims (5)

1. a kind of drainage management construction method, it is characterised in that:Comprise the following steps:
The first step:Line setting is carried out according to pipeline rout, groove is then excavated;
Second step:Soft soil horizon below pipeline foundation is cut out, backfilling material and tamp be used as pipeline foundation;
3rd step:Pipeline is numbered, the barrel of pipe mouth of pipe of pipeline is cleared up, is then steadily put into pipeline in the groove dug;
4th step:The first hydraulic pressure pressure sensor and the second hydraulic pressure pressure sensor are respectively mounted at inner-walls of duct two ends, then Pipeline is linked in sequence, the position connected between pipeline, as pad, humidity is installed in cushion rubber periphery using O-ring seal Inductor, finally fixes pipeline;
5th step:Well construction is checked, inspection shaft is excavated, then bar-mat reinforcement is constructed in inspection shaft well base working face, and lay 200~ 220mm mixed mud bed courses;Inspection well chamber sinters brick masonry and installs cat ladder, and does inside and outside waterproof to well room, in well room Outer wall is with 1:2 waterproof cement mortars are wiped one's face 20~25mm;
6th step:Closed-water test is carried out, the water filling into the inspection shaft of water flowing section, prison after well room design strength reaches 75~80% Control the measurement result of hydraulic pressure pressure sensor and humidity sensor;
7th step:The groove for placing pipeline is backfilled, backfill is manually layered symmetrical backfill simultaneously successively upwards from ttom of pipe Compacting.
2. a kind of drainage management construction method according to claim 1, it is characterised in that:Backfill in described step two Expect for concrete, as thickness of earth covering≤6m of pipeline, using 120 ° of concrete as pipeline foundation bed course, when the earthing of pipeline During thickness G T.GT.GT 6m, pipeline foundation bed course is used as using 180 ° of concrete.
3. a kind of construction method of drainage pipeline according to claim 1, it is characterised in that:Glue in described step four The material of circle is synthetic rubber, and water-soaked cushion rubber is first used before installing.
4. a kind of construction method of drainage pipeline according to claim 1, it is characterised in that:Steel in described step five A diameter of 10mm of muscle net, spacing is 200 × 200mm.
5. a kind of drainage management construction method according to claim 1, it is characterised in that:Closed in described step six During water test, after pipeline water flowing, the first hydraulic pressure pressure sensor and the second hydraulic pressure pressure sensor measure obtain the first water respectively Second hydraulic pressure value is wirelessly sent to the first hydraulic pressure pressure by pressure value and the second hydraulic pressure value, the second hydraulic pressure pressure sensor Sensor, if the difference of the first hydraulic pressure value and the second hydraulic pressure value is more than 0.03MPa, there is splintering problem in pipeline, now first Measurement result is wirelessly sent to ECC engineering control center by hydraulic pressure pressure sensor.
CN201710357442.5A 2017-05-19 2017-05-19 A kind of drainage management construction method Pending CN106948458A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710357442.5A CN106948458A (en) 2017-05-19 2017-05-19 A kind of drainage management construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710357442.5A CN106948458A (en) 2017-05-19 2017-05-19 A kind of drainage management construction method

Publications (1)

Publication Number Publication Date
CN106948458A true CN106948458A (en) 2017-07-14

Family

ID=59479841

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710357442.5A Pending CN106948458A (en) 2017-05-19 2017-05-19 A kind of drainage management construction method

Country Status (1)

Country Link
CN (1) CN106948458A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589885A (en) * 2018-04-24 2018-09-28 青岛新华友建工集团股份有限公司 Finished product sewage network construction under complex geological condition
CN108978838A (en) * 2018-08-10 2018-12-11 湖南省建筑设计院有限公司 Concrete expires packet drainage pipeline tubine construction method
CN110273424A (en) * 2018-03-13 2019-09-24 中冶建筑研究总院(上海)有限公司 A kind of construction method of yard piping
CN110424518A (en) * 2019-08-01 2019-11-08 中化明达(福建)地质勘测有限公司 A kind of construction method of geotechnical engineering drainpipe

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007004485A1 (en) * 2006-08-02 2008-05-08 Schneider, Elmar Drive unit for a hinged television inspection unit for sewer inspection comprises a pressure chamber produced between two driving units using inflatable rubber bladders
CN101565964A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for mounting outdoor embedded high-density polyethylene double-wall corrugated drain pipe
CN101936032A (en) * 2010-08-27 2011-01-05 常熟市浩通市政工程有限公司 Method for mounting and constructing polyethylene double-wall corrugated water discharge pipe
CN102392485A (en) * 2011-11-14 2012-03-28 四川泰鑫实业发展有限责任公司 Manufacturing method of plastic concrete inspection well
CN105113607A (en) * 2015-08-28 2015-12-02 济南城建集团有限公司 Rainwater pipeline structure and construction method thereof
CN105465613A (en) * 2015-11-19 2016-04-06 中建七局第二建筑有限公司 Urban subsurface drainage pipeline leakage locating system and construction method thereof
CN106284516A (en) * 2016-08-29 2017-01-04 中国水利水电第十三工程局有限公司 Water supply line suppress construction technology
CN106402492A (en) * 2016-10-26 2017-02-15 朱育盼 Method and device for pipeline laying

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007004485A1 (en) * 2006-08-02 2008-05-08 Schneider, Elmar Drive unit for a hinged television inspection unit for sewer inspection comprises a pressure chamber produced between two driving units using inflatable rubber bladders
CN101565964A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for mounting outdoor embedded high-density polyethylene double-wall corrugated drain pipe
CN101936032A (en) * 2010-08-27 2011-01-05 常熟市浩通市政工程有限公司 Method for mounting and constructing polyethylene double-wall corrugated water discharge pipe
CN102392485A (en) * 2011-11-14 2012-03-28 四川泰鑫实业发展有限责任公司 Manufacturing method of plastic concrete inspection well
CN105113607A (en) * 2015-08-28 2015-12-02 济南城建集团有限公司 Rainwater pipeline structure and construction method thereof
CN105465613A (en) * 2015-11-19 2016-04-06 中建七局第二建筑有限公司 Urban subsurface drainage pipeline leakage locating system and construction method thereof
CN106284516A (en) * 2016-08-29 2017-01-04 中国水利水电第十三工程局有限公司 Water supply line suppress construction technology
CN106402492A (en) * 2016-10-26 2017-02-15 朱育盼 Method and device for pipeline laying

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王云江等: "《透过案例学市政工程计量与计价》", 31 March 2015, 中国建材工业出版 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110273424A (en) * 2018-03-13 2019-09-24 中冶建筑研究总院(上海)有限公司 A kind of construction method of yard piping
CN108589885A (en) * 2018-04-24 2018-09-28 青岛新华友建工集团股份有限公司 Finished product sewage network construction under complex geological condition
CN108978838A (en) * 2018-08-10 2018-12-11 湖南省建筑设计院有限公司 Concrete expires packet drainage pipeline tubine construction method
CN110424518A (en) * 2019-08-01 2019-11-08 中化明达(福建)地质勘测有限公司 A kind of construction method of geotechnical engineering drainpipe

Similar Documents

Publication Publication Date Title
CN106948458A (en) A kind of drainage management construction method
CN110185844B (en) Shallow-earthing large-diameter pipe jacking construction method
CN109826239B (en) Basement outer wall post-pouring strip structure and construction method thereof
CN111305877B (en) Construction method for strong rockburst section tunnel in high-altitude area
CN110552370A (en) Reverse construction method based annular lining wall integral single-side formwork construction method
CN106759474A (en) The construction method of flexible spigot-and-socket common pipe trench
CN104153371A (en) Grouting-to-stop-water construction method of underwater rubble bed
CN111927548A (en) Method for plugging abandoned coal mine well mouth
CN112144559A (en) Well construction method in high water-rich loess sandy gravel stratum transformer tube well
CN101691840B (en) Water level observation well and construction method thereof
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN113152425B (en) Combined freezing and reinforcing method for non-drainage excavation of large foundation pit
CN212837843U (en) IV-class and V-class surrounding rock tunnel concrete lining anti-cracking structure
CN105064411B (en) Method for building post-pouring expansion reinforcing band of wallboard of underground structure
CN106498981A (en) A kind of brick type municipal administration comprehensive pipeline passage and its construction method
CN208122041U (en) A kind of IPS Cast-in-place concrete shear wall structure of self-heat preservation system system
CN100523394C (en) Construction method for concrete shaft wall module masonry
CN102296618A (en) Sleeve with anchor rod penetrating through diaphragm wall
CN111335445B (en) Construction method of concrete catch basin by using steel pipe as inner mold
CN109183800B (en) Construction process of preliminary grouting system
CN211312560U (en) Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures
CN214117025U (en) Wear floor riser waterproof construction
CN210013227U (en) Drainage device capable of effectively reducing anti-floating design water level of basement
CN102392460B (en) A kind of basement external waterproof structure and construction method thereof
CN113374055A (en) Construction method of buried reinforced HDPE (high-density polyethylene) spiral corrugated pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170714