CN106907021A - Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method - Google Patents

Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method Download PDF

Info

Publication number
CN106907021A
CN106907021A CN201710258610.5A CN201710258610A CN106907021A CN 106907021 A CN106907021 A CN 106907021A CN 201710258610 A CN201710258610 A CN 201710258610A CN 106907021 A CN106907021 A CN 106907021A
Authority
CN
China
Prior art keywords
big vast
hole
steel
bridge pier
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710258610.5A
Other languages
Chinese (zh)
Inventor
高朋飞
殷芳满
马国强
陈瑞
韩国光
刘阳春
杨翎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Jiangnan Blasting Engineering Co Ltd
Original Assignee
Anhui Jiangnan Blasting Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Jiangnan Blasting Engineering Co Ltd filed Critical Anhui Jiangnan Blasting Engineering Co Ltd
Priority to CN201710258610.5A priority Critical patent/CN106907021A/en
Publication of CN106907021A publication Critical patent/CN106907021A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

Enter big vast lock Bridge Pier shaping Cutting Blasting Demolition method the invention discloses a kind of steel and concrete structure, comprise the following steps:(1) basic structure and original state into big vast lock are recognized;(2) burst region division is carried out to entering Hong Zha, laying cuts line, clearly cuts part and member-retaining portion;(3) laid above line row's shock relieve vent along cutting on part entering cutting for big vast lock Bridge Pier, the pre- ceasma of a row, the spaced loading in pre- ceasma are made a call to above shock relieve vent;(4) row is made a call to above pre- ceasma and weakens blast hole, weakening spaced loading in blast hole;(5) the main blast hole of a row, the spaced loading in main blast hole are made a call to above decrease blast hole;(6) after properly protecting, using disposable detonation mode demolition blasting.The characteristics of present invention has saving blasting cost, lifting economic benefit, raising shotfiring safety, it is adaptable to Hydraulic and Hydro-Power Engineering, architectural engineering, the demolition blasting of all kinds of steel and concrete structure bridge piers in science of bridge building field.

Description

Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method
Technical field
The present invention relates to Blasting Demolition Technology field, more particularly to a kind of steel and concrete structure enters big vast lock Bridge Pier shaping cutting Blasting demolishing method.
Background technology
Have both the intake gate drained off floodwater with navigation function, it is past with the growth and the change of national regulation of use time Toward there are problems that sluicing, not smooth, gate branch hinge burn into opening and closing device is outmoded and standard deviation is low, to improve flood control antidetonation and logical Row ability, it is necessary to carry out partial demolition and reinforce reconstruction.
Conventional steel and concrete structure method for dismounting has demolition blasting method, mechanical removal method and manual demolition method etc. at present, wherein, Demolition blasting method with its short time limit, economize on resources and be safe the features such as, show applicability higher.Cutting Blasting method Using blasting technique, it is capable of achieving to building, the control of structures implosion rupture seam propagation direction, then realizes to building, structures Shaping cutting.
It is all kinds of build, in the demolishing process of structures, it will usually run into and certain steel and concrete structure removed into a part, while retaining Another part, has reached the purpose of saving fund.Actually build, during the demolition blasting of structures, because theory lacks and advises Model disunity, majority construction is all, by engineering experience, the demolition blasting theoretical system of system not to be formed then, to engineering cost Rationally control can not be realized.Meanwhile, enter big vast lock Bridge Pier shaping Cutting Blasting in steel and concrete structure in existing demolition blasting achievement and tear open Research blank in terms of except method.
Therefore a kind of steel and concrete structure of offer is needed badly to enter big vast lock Bridge Pier shaping Cutting Blasting Demolition method to solve above-mentioned asking Topic.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of steel and concrete structure to be entered big vast lock Bridge Pier shaping Cutting Blasting and tears open It is simple to operate except method, feasibility, high safety.
In order to solve the above technical problems, one aspect of the present invention is:A kind of steel and concrete structure is provided and enters Hong Zha Bridge Pier is molded Cutting Blasting Demolition method, comprises the following steps:
(1) basic structure and original state into big vast lock are recognized;
(2) burst region division is carried out to entering Hong Zha, laying cuts line, clearly cuts part and member-retaining portion;
(3) laid above line row's shock relieve vent along cutting on part entering cutting for big vast lock Bridge Pier, above shock relieve vent Make a call to the pre- ceasma of a row, the spaced loading in pre- ceasma;
(4) the main blast hole of a row, the spaced loading in main blast hole are made a call to above pre- ceasma;
(5) after properly protecting, using disposable detonation mode demolition blasting.
In a preferred embodiment of the present invention, square shaped enters big vast lock burst region, pre- ceasma and main blast hole it Between make a call to again a row weaken blast hole, weaken blast hole in spaced loading.
In a preferred embodiment of the present invention, in step (1), measure that lock is long, lock according to big vast brake structure design drawing is entered It is wide high with lock, specify the physical dimension of headstock gear, maintenance bridge and access bridge, Site Detection bridge floor material.
In a preferred embodiment of the present invention, in step (2), the foundation that the burst region is divided is into the design of big vast lock Elevation and basic structure feature, to enhance the capacity of preventing floods, the traffic capacity and are continuing with the time limit, to it is built enter big vast brake structure enter Row demolition blasting part-structure is reinforced when rebuilding, and big vast brake structure years already spent, structural failure and top layer corrosion feelings are entered according to original Condition, original structure existing concrete intensity, original structure arrangement of reinforcement arrangement, owner require, intend rebuilding reinforcement scheme into big vast brake structure, intend Rebuild the design height into big vast brake structure, demolition blasting construction needs etc. and divide burst region.What different burst regions was used Blasting method is otherwise varied, for example, original enters part where big vast lock bracket, it is not necessary to set and weaken blast hole;Original enters big vast brake structure Headstock gear framed bent part, is cut broken using machinery.
Further, the aperture of shock relieve vent is 38mm, and pitch-row is 20cm, is beaten to perforation, is 120cm per side opening depth.
Further, at the 10cm of shock relieve vent top, aperture is 38mm to presplitting hole position, and pitch-row is 30cm, and hole depth is 110cm。
Further, weaken blast hole to be located at the 15cm of pre- ceasma top, aperture is 38mm, and pitch-row is 50cm, and hole depth is 110cm。
Further, main blast hole is located at and weakens at the 30cm -100cm of blast hole top, and aperture is 38mm, and pitch-row is 50cm, hole depth is 110cm.
Further, the mode of spaced loading is away between bottom hole 10cm depth part coupling chargings, the center section in hole Every powder charge, the section of blocking up of cave entrance reservation 10cm depth is 4-5 times of hole center section aperture away from bottom hole 10cm depth parts.
Further, in step (5), detonation mode is using same section of other detonator once blasting, each hole unit consumption control In 0.5-1.2kg/m3Between, pre- ceasma with primacord load, be bundled into using three primacords it is a branch of, in load hole, as pre- Ceasma pack.
The beneficial effects of the invention are as follows:
(1) the method for the invention it is simple and reliable, shaping good cutting effect, by recognize into big vast this structure type of sluice foundation with Original state, can preferably select blasting method and divide burst region, and rational burst region is divided and blasting parameter selection Ensure that good shaping cutting effect;
(2) the method for the invention cost is relatively low, high financial profit, quick-fried by Reasonable Arrangement shock relieve vent, pre- ceasma and master Hole, and by the way of spaced loading, detonator consumption is reduced, then reduce cost;
(3) the method for the invention construction system is strong, reliability is high, technical maturity, workable, while ensure that Presplitting effect;
(4) the method for the invention can be entered for Hydraulic and Hydro-Power Engineering, architectural engineering, all kinds of steel and concrete structures in science of bridge building field The demolition blasting of big vast lock Bridge Pier provides reliable method support.
Brief description of the drawings
Fig. 1 is the flow that steel and concrete structure of the present invention enters the preferred embodiment of big vast lock Bridge Pier shaping Cutting Blasting Demolition method one Figure;
Fig. 2 is that single lock body burst region divides schematic diagram;
Fig. 3 is A, B area cloth hole schematic diagram;
Tu4Shi C areas cloth hole schematic diagram;
Fig. 5 is the cross-sectional view for weakening spaced loading in blast hole, main blast hole;
The mark of each part is as follows in accompanying drawing:1st, line is cut, 2, member-retaining portion, 3, cut part, 4, shock relieve vent, 5, presplitting Hole, 6, weaken blast hole, 7, main blast hole, 8, line of cut, 9, pilot hole, 10, explosive, 11, section of blocking up, 12, primacord.
Specific embodiment
Presently preferred embodiments of the present invention is described in detail below in conjunction with the accompanying drawings, so that advantages and features of the invention energy It is easier to be readily appreciated by one skilled in the art, apparent is clearly defined so as to be made to protection scope of the present invention.
Fig. 1 is referred to, a kind of steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, comprises the following steps:
(1) basic structure and original state into big vast lock are recognized;
(2) burst region division is carried out to entering Hong Zha, laying cuts line 1, clearly cuts part 3 and member-retaining portion 2;
(3) one row's shock relieve vent 4 of the top of line 1 laying is cut on the edge on part 3 that cuts for entering big vast lock Bridge Pier, in shock relieve vent 4 The pre- ceasma 5 of a row, the spaced loading in pre- ceasma 5 are made a call in top;
(4) make a call to a row in the top of pre- ceasma 5 and weaken blast hole 6, weaken spaced loading in blast hole 6;
(5) the main blast hole 7 of a row, the spaced loading in main blast hole 7 are made a call in the top of decrease blast hole 6;
(6) after properly protecting, using disposable detonation mode demolition blasting.
The steel and concrete structure is specifically described with reference to an embodiment enter big vast lock Bridge Pier shaping Cutting Blasting Demolition method:
1) certain enter Hong Zha have both flood control and traffic be used.Lock is long:Enter big vast lock 36 across single span 10m long, bridge pier 1.2m wide enter Big vast lock overall length 403m;Lock is wide:Enter big vast lock beam overall 17.5m, access bridge 6.455m wide, headstock gear lock chamber part 11.04m wide, open and close Machine column is located between maintenance bridge and access bridge, and maintenance bridge location is in west of a city lake side.Lock is high:(bridge base plate is high to enter big vast lock 13.5m high Journey 22.9, headstock gear cope level 36.4), base plate to bridge floor 7.6m, bridge floor to headstock gear top 5.9m high.Physical dimension:Open Frame is closed for double pillar construction, basal area is 70cm × 110cm, it is that two reinforced concrete beams are put down with bridge floor to open and close board On row accumbency column, bridge floor is single arched by 5 20cm thickness, sheet arch rib composition 60cm high, and bridge floor is armored concrete Mat formation, there is one expansion joint concrete road surface every 11.2m.To improve flood control antidetonation and the traffic capacity, it is necessary to carry out part Remove to reinforce and rebuild.
2) combine Fig. 2, enter the Bridge Pier of big vast lock access bridge position bottom comprising member-retaining portion 2 with cut part 3, wherein digging Except part 3 can be divided into 4 blast areas.A areas:Elevation 27.00-30.50, width 6.455m is a 100cm × 645.5cm Rectangular region;B areas:Elevation 30.90-31.90, is the region of 100cm × 264.5cm;C areas:Bracket position, be One inverted trapezoidal structure, elevation is in 26.40-31.90, upper width 5700cm, lower width 3000cm;D areas:It is headstock gear Framed bent.
3) Fig. 3 is referred to, the blasting method to A areas, B areas is:Shock relieve vent 4 is laid along the top of line 1 is cut, and aperture is 38mm, pitch-row is 20cm, is beaten to perforation, is 120cm per side opening depth;Pre- ceasma 5 is beaten at the top 10cm of shock relieve vent 4, aperture is 38mm, pitch-row is 30cm, and hole depth is 110cm, is bundled into three primacords 12 a branch of, loads the hole, as the pack of pre- ceasma 5; A row is made a call at the top 15cm of pre- ceasma 5 and weakens blast hole 6, aperture is 38mm, and pitch-row is 50cm, and hole depth is 110cm, between Every powder charge;Make a call to the main blast hole 7 of a row at 30cm above hole weakening, aperture is 38mm, and hole depth is 110cm, and pitch-row is 50cm, Using decked charge fashion, but improve explosive specific charge.From cut line 1 be upwardly into pre- ceasma 5 between for 15cm thickness protective layer, Peeled off using pneumatic pick.
4) Fig. 4 is referred to, the blasting method to C areas is:Shock relieve vent 4 is laid along the top of line 1 is cut, aperture is 38mm, hole Away from being 20cm, beat to perforation, be 120cm per side opening depth;Pre- ceasma 5 is beaten at the top 10cm of shock relieve vent 4, aperture is 38mm, hole Away from being 30cm, hole depth is 110cm, same to A, B area of charging means;Main blast hole 7, the pitch-row of main blast hole 7 are laid in the top of pre- ceasma 5 It is 100cm, aperture is 38mm, and hole depth is 110cm, explosive specific charge powder charge is diagonally gradually reduced from maintenance bridge turning; Pilot hole 9 is provided between the shock relieve vent of corner of C areas, pilot hole 9 uses emptying aperture, not powder charge.
Kong Jun in above-mentioned burst region is drilled using YT24 airleg rock drills, and other applicable rigs include Hand-held shallow bore hole rig, voluntarily medium-length hole rig, medium-length hole rig.
5) D areas:Cut using machinery upwards from elevation 31.90 broken.
6) Fig. 5 is referred to, the mode of spaced loading is that coupling charging is dress away from bottom hole 10cm depth part coupling chargings It is full, fill tight explosive 10, to reduce ultra-deep, the center section spaced loading in hole, the section 11 of blocking up of cave entrance reservation 10cm depth, away from Bottom hole 10cm depth parts are 4-5 times of hole center section aperture.More than each hole according to different parts, unit consumption control 0.6- 1.2kg/m3Between, pre- ceasma 5 is loaded with primacord 12, the not powder charge of shock relieve vent 4, it is considered to have that primacord 12 is loaded and old bridge is mixed The carbonization of soil is coagulated, dose drops to 0.5kg/m3.All powder charge holes use spaced loading method.
7) ensure that the successful pretreating process of presplitting is:Rule along 10cm on line 1 is cut, at online top 5cm simultaneously Standardized bar parallel lines;Electricity consumption saw cut, depth of cut is advisable with exposed steel bar;Reject mixed in the middle of twice line of cut 8 with pneumatic pick Solidifying soil;With oxyacetylene metal-cutting, the vertical reinforcement for exposing is cut off;Shock relieve vent 4, pre- ceasma 5 must be smoothed out, and up-down error is not more than 3cm, left and right Error is not more than 5cm;Vertical reinforcement will thoroughly cut, and not stay residuum;Concrete pneumatic pick between shock relieve vent 4 and pre- ceasma 5 Peel off, reject concrete structure, expose the reinforcing bar of reserved 15cm as the connecting material of the perpendicular muscle of subsequent reinforcement engineering.
8) after properly protecting, using disposable detonation mode demolition blasting.Detonation mode is using same section of other detonator Once detonation, the detonation mode can reach preferably cutting effect.
The method of the invention is simple and reliable, shaping good cutting effect, by recognize into big vast this structure type of sluice foundation with it is first Beginning state, can preferably select blasting method and divide burst region, and rational burst region is divided protects with blasting parameter selection Good shaping cutting effect is demonstrate,proved;Low cost, high financial profit, by Reasonable Arrangement shock relieve vent, pre- ceasma and main blast hole, and By the way of spaced loading, detonator consumption is reduced, then reduce cost;Construction system is strong, reliability is high, technique into It is ripe, workable, while ensure that presplitting effect;Can be Hydraulic and Hydro-Power Engineering, architectural engineering, all kinds of steel in science of bridge building field The demolition blasting that mixed structure enters big vast lock Bridge Pier provides reliable method support.
Embodiments of the invention are the foregoing is only, the scope of the claims of the invention is not thereby limited, it is every to utilize this hair Equivalent structure or equivalent flow conversion that bright specification and accompanying drawing content are made, or directly or indirectly it is used in other related skills Art field, is included within the scope of the present invention.

Claims (10)

1. a kind of steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, comprises the following steps:
(1) basic structure and original state into big vast lock are recognized;
(2) burst region division is carried out to entering Hong Zha, laying cuts line, clearly cuts part and member-retaining portion;
(3) laid above line row's shock relieve vent along cutting on part entering cutting for big vast lock Bridge Pier, one is made a call to above shock relieve vent Pre- ceasma is arranged, the spaced loading in pre- ceasma;
(4) the main blast hole of a row, the spaced loading in main blast hole are made a call to above pre- ceasma;
(5) after properly protecting, using disposable detonation mode demolition blasting.
2. steel and concrete structure according to claim 1 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, it is characterised in that Square shaped enters big vast lock burst region, a row is made a call between pre- ceasma and main blast hole again and weakens blast hole, is weakening blast hole Interior spaced loading.
3. steel and concrete structure according to claim 1 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, it is characterised in that In step (1), measure that lock is long, lock is wide high with lock according to big vast brake structure design drawing is entered, specify headstock gear, overhaul bridge and access bridge Physical dimension, Site Detection bridge floor material.
4. steel and concrete structure according to claim 1 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, it is characterised in that In step (2), the foundation that burst region is divided enters big vast lock design altitude, original and enters big vast brake structure years already spent, structure including original Damage and required with top layer corrosion condition, original structure existing concrete intensity, original structure arrangement of reinforcement arrangement, owner, intend rebuilding into Hong Zha The reinforcement scheme of structure, plan rebuild design height, the demolition blasting construction needs into big vast brake structure.
5. steel and concrete structure according to claim 1 and 2 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, and its feature exists In the aperture of shock relieve vent is 38mm, and pitch-row is 20cm, is beaten to perforation, is 120cm per side opening depth.
6. steel and concrete structure according to claim 1 and 2 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, and its feature exists In at the 10cm of shock relieve vent top, aperture is 38mm to presplitting hole position, and pitch-row is 30cm, and hole depth is 110cm.
7. steel and concrete structure according to claim 2 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, it is characterised in that Weaken blast hole to be located at the 15cm of pre- ceasma top, aperture is 38mm, and pitch-row is 50cm, and hole depth is 110cm.
8. steel and concrete structure according to claim 1 and 2 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, and its feature exists In main blast hole is located at and weakens at the 30cm -100cm of blast hole top, and aperture is 38mm, and pitch-row is 50cm, and hole depth is 110cm.
9. steel and concrete structure according to claim 1 and 2 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, and its feature exists In the mode of spaced loading is away from bottom hole 10cm depth part coupling chargings, the center section spaced loading in hole, cave entrance reservation The section of blocking up of 10cm depth, is 4-5 times of hole center section aperture away from bottom hole 10cm depth parts.
10. steel and concrete structure according to claim 1 and 2 enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method, its feature It is that in step (5), detonation mode is that each hole unit consumption control is in 0.5-1.2kg/ using same section of other detonator once blasting m3Between, pre- ceasma with primacord load, be bundled into using three primacords it is a branch of, in load hole, as pre- ceasma pack.
CN201710258610.5A 2017-04-19 2017-04-19 Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method Pending CN106907021A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710258610.5A CN106907021A (en) 2017-04-19 2017-04-19 Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710258610.5A CN106907021A (en) 2017-04-19 2017-04-19 Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method

Publications (1)

Publication Number Publication Date
CN106907021A true CN106907021A (en) 2017-06-30

Family

ID=59211068

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710258610.5A Pending CN106907021A (en) 2017-04-19 2017-04-19 Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method

Country Status (1)

Country Link
CN (1) CN106907021A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108708305A (en) * 2018-05-28 2018-10-26 广西路桥工程集团有限公司 A kind of construction method of low pier bridging toughening
CN112923820A (en) * 2021-02-09 2021-06-08 江西荣达爆破新技术开发有限公司 Perforation charge explosion method suitable for blasting demolition of middle upright column
CN113137898A (en) * 2021-03-25 2021-07-20 中国能源建设集团广西水电工程局有限公司 Cofferdam blasting demolition method based on combination of variable linear density charging and digital electronic detonator

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100766099B1 (en) * 2007-06-25 2007-10-17 조금원 Blasting a method of base rock
CN101832744A (en) * 2010-05-25 2010-09-15 江南水利水电工程公司 Blasting demolishing method
CN102937024A (en) * 2012-11-13 2013-02-20 金诚信矿业管理股份有限公司 Digging and building method for water-proof gate chamber
CN103940307A (en) * 2014-04-21 2014-07-23 杨世梁 Blasting method
CN104089551A (en) * 2014-04-11 2014-10-08 中国水利水电第十一工程局有限公司 Old sluice directional incline, collapse, demolition and blasting construction method
CN104215137A (en) * 2014-09-28 2014-12-17 武汉大学 Method for blasting and excavating dam foundation and rock foundation
CN104634198A (en) * 2014-12-13 2015-05-20 中铁十九局集团第二工程有限公司 Controlled blasting construction method in mountain excavation close to expressway side
CN104654941A (en) * 2015-03-02 2015-05-27 武汉大学 Dam foundation rapid excavation blasting forming method based on mixed loading truck
CN105823387A (en) * 2016-02-25 2016-08-03 中铁十八局集团有限公司 Rapid construction method for deep hole blasting of vertical shaft frozen bedrock

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100766099B1 (en) * 2007-06-25 2007-10-17 조금원 Blasting a method of base rock
CN101832744A (en) * 2010-05-25 2010-09-15 江南水利水电工程公司 Blasting demolishing method
CN102937024A (en) * 2012-11-13 2013-02-20 金诚信矿业管理股份有限公司 Digging and building method for water-proof gate chamber
CN104089551A (en) * 2014-04-11 2014-10-08 中国水利水电第十一工程局有限公司 Old sluice directional incline, collapse, demolition and blasting construction method
CN103940307A (en) * 2014-04-21 2014-07-23 杨世梁 Blasting method
CN104215137A (en) * 2014-09-28 2014-12-17 武汉大学 Method for blasting and excavating dam foundation and rock foundation
CN104634198A (en) * 2014-12-13 2015-05-20 中铁十九局集团第二工程有限公司 Controlled blasting construction method in mountain excavation close to expressway side
CN104654941A (en) * 2015-03-02 2015-05-27 武汉大学 Dam foundation rapid excavation blasting forming method based on mixed loading truck
CN105823387A (en) * 2016-02-25 2016-08-03 中铁十八局集团有限公司 Rapid construction method for deep hole blasting of vertical shaft frozen bedrock

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108708305A (en) * 2018-05-28 2018-10-26 广西路桥工程集团有限公司 A kind of construction method of low pier bridging toughening
CN108708305B (en) * 2018-05-28 2020-05-01 广西路桥工程集团有限公司 Construction method for dismantling low-pier bridge
CN112923820A (en) * 2021-02-09 2021-06-08 江西荣达爆破新技术开发有限公司 Perforation charge explosion method suitable for blasting demolition of middle upright column
CN113137898A (en) * 2021-03-25 2021-07-20 中国能源建设集团广西水电工程局有限公司 Cofferdam blasting demolition method based on combination of variable linear density charging and digital electronic detonator
CN113137898B (en) * 2021-03-25 2022-10-21 中国能源建设集团广西水电工程局有限公司 Cofferdam blasting demolition method based on combination of variable-linear-density charging and digital electronic detonator

Similar Documents

Publication Publication Date Title
CN101858222B (en) Method for controlling deformation in zero-distance tunneling of new tunnel under existing subway construction
CN104652279B (en) Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN205654349U (en) Device based on interconnection removes shield zone cataract or glaucoma impenetrability foreign matter
CN107288653A (en) A kind of the benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three and construction method
CN104653187B (en) Water-rich sand layer geology large cross-section tunnel excavation method
CN101148882A (en) Stable excavating method for cracked weak rock road cutting high slope
CN106907021A (en) Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method
CN110439571A (en) Flat pilot tunnel leads to the adit construction method and transverse passage-way of main tunnel
CN102535474A (en) Construction method for deep-foundation pit excavation
CN206319886U (en) Tunnel lining structure
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
CN110242305A (en) A kind of inclined shaft applies the construction technique in main hole into single side heading method
CN105350526B (en) Method for setting up steel platform
CN107939415A (en) Stay the micro- two step constructions method of Core Soil in the soft plastic clay tunnel of Shallow-buried Large-span
CN105155556B (en) A kind of open-pit slope separate unit rank wedge-shaped indentation flattens domatic construction method
CN107489433A (en) A kind of tunnel CRD engineering methods anti-leakage structure and Antiseep method
CN104141500B (en) One hardens sand and gravel stratum cavern con struction method
CN108166771A (en) Steel reinforced concrete pool structural reform makes construction method
CN108951431A (en) Bridge concrete earth cofferdam and bridge pier building technology
CN107327306A (en) Tunnel excavation construction method is superimposed under the conditions of the shallow embedding of city
CN207111103U (en) A kind of benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three
CN106545019A (en) For the support-replacing system and construction method of stage differential style Underground Construction
CN108756901A (en) Former times lattice reach special formation Shallow Tunnel Construction method
CN108708284A (en) A kind of steel trestle construction method for resisting flood discharge bed scour

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170630

RJ01 Rejection of invention patent application after publication