CN104652279B - Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge - Google Patents

Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge Download PDF

Info

Publication number
CN104652279B
CN104652279B CN201310602973.8A CN201310602973A CN104652279B CN 104652279 B CN104652279 B CN 104652279B CN 201310602973 A CN201310602973 A CN 201310602973A CN 104652279 B CN104652279 B CN 104652279B
Authority
CN
China
Prior art keywords
box culvert
jacking
subway
counterweight
frame bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310602973.8A
Other languages
Chinese (zh)
Other versions
CN104652279A (en
Inventor
刘运亮
李玲
白海卫
李宏
尹骁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction Design and Development Group Co Ltd
Original Assignee
Beijing Urban Construction Design and Development Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction Design and Development Group Co Ltd filed Critical Beijing Urban Construction Design and Development Group Co Ltd
Priority to CN201310602973.8A priority Critical patent/CN104652279B/en
Publication of CN104652279A publication Critical patent/CN104652279A/en
Application granted granted Critical
Publication of CN104652279B publication Critical patent/CN104652279B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention discloses and on a kind of newly-built frame bridge, wear existing structure of the subway box culvert jacking construction method, including: plan to build the side excavation jacking working pit of frame bridge position above existing structure of the subway;Prefabricated box culvert in jacking working pit, box culvert inner bottom part is set up counterweight, balance weight and box culvert weight sum and is fallen soil body weight equal to excavation;Jacking box culvert;After box culvert advancing puts in place, limit is removed counterweight limit and is performed accessory structure, removes counterweight and is equal in weight with the accessory structure performed, and completes frame bridge construction.The present invention is a kind of construction method using the box culvert advancing mode setting up counterweight to deform to control structure of the subway to float above existing structure of the subway during newly-built frame bridge, during utilizing box culvert advancing, use the form increasing counterweight, make up excavation by the weight of counterweight Yu box culvert and fall the weight of the soil body, the lower section soil body is made not unload, control structure of the subway deflection, reduce the impact that existing subway line operation is produced by construction to greatest extent, it is ensured that metro safety operation.

Description

Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge
Technical field
The present invention relates to utilize box culvert jacking construction when one builds frame bridge above operated subway circuit, come Control the construction method of structure of the subway floating deformation, belong to underground engineering field.
Background technology
Along with extensive development and the development construction of urban operating mechanism of urban track traffic, current urban road And the engineering worn on Box-shaped Drainage Culvert etc. and operated subway crossing elimination gets more and more, in these engineerings, absolutely Great majority use box culvert open-cut method easily, but inevitably produce surrounding soil during construction and disturb Dynamic, make the lower section soil body produce resilience, and then operating line malformation can be driven, train fortune can be affected Line speed, even jeopardizes the operation safety of train.
Specifically, at present, above existing subway line, build box culvert many employings open-cut grouting and reinforcing Measure, although this Technical comparing is ripe, construction is simple, has wide adaptability in underground engineering, but For track traffic, there is certain problem in it:
First, along with the web development of rail line, passenger flow is great to be increased, Train Interval pole Tool shortens, and especially at the route of heavy traffic or higher to Operational requirements, builds during open-cut Train speed limit or stoppage in transit that box culvert may cause will produce large effect to track traffic.
Second, open-cut can cause the unloading of the lower section soil body at excavation of foundation pit, and then can make the lower section soil body Deformation of floating occurs, and this deformation is the most uncontrollable, and the track structure of track traffic need to keep higher Ride comfort, with safety and the requirement of comfortableness of satisfied driving.
As can be seen here, work out a kind of can reduction to greatest extent to construct to existing subway line Influence to operation Reasonable construction method is current urgent problem.
Summary of the invention
It is an object of the invention to provide and on a kind of newly-built frame bridge, wear existing structure of the subway box culvert jacking construction Method, the method, during utilizing box culvert advancing, uses the form increasing counterweight, with counterweight and box culvert Weight makes up excavation and falls the weight of the soil body so that the soil body does not occur unloading effect below, thus controls subway The floating deflection of structure, reduces construction impact produced on the operation of existing subway line to greatest extent, The safety and the stationarity that make train operation are guaranteed.
To achieve these goals, present invention employs techniques below scheme:
Existing structure of the subway box culvert jacking construction method is worn, it is characterised in that its bag on a kind of newly-built frame bridge Include following steps: step one: above existing structure of the subway, plan to build the side of frame bridge position, excavate jacking Working pit;Step 2: prefabricated box culvert in this jacking working pit, is additionally arranged at the bottom of counterweight in this box culvert, should The weight of counterweight is equal to, with the weight sum of this box culvert, the soil body weight that excavation falls, to make up excavation jacking work The weight of the soil body is lost during hole;Step 3: this box culvert of jacking, wherein: in the process of this box culvert of jacking In, gradually dig the soil body in jacking direction, in order to complete box culvert advancing operation;Step 4: when this box culvert top After entering position, remove this counterweight, while performing accessory structure, this counterweight of dismounting with perform this is attached Belong to construction weight equal, make this accessory structure substitute this counterweight, it is ensured that the existing structure of the subway periphery soil body keeps Stress equilibrium, completes the construction of newly-built frame bridge above existing structure of the subway.
Described counterweight is steel ingot or concrete slab.
Along described box culvert by end face install steel plate, bar-mat reinforcement can be set between this steel plate and described box culvert, will This bar-mat reinforcement is banded on the reinforcing bar of described concrete slab.
Before performing described step 3, calculate maximum top power and jacking institute that box culvert described in jacking is allowed State the top journey of box culvert.
If described box culvert size is relatively big, the most described box culvert segmentation is prefabricated and merogenesis jacking.
The invention have the advantage that
The present invention is the box culvert using during newly-built frame bridge above existing structure of the subway and setting up counterweight Jacking mode controls a kind of construction method of structure of the subway floating deformation, compared with traditional open-cut, The inventive method, during utilizing box culvert advancing, uses the form increasing counterweight, with the weight of counterweight Yu box culvert Amount makes up excavation and falls the weight of the soil body so that the lower section soil body does not occur unloading effect, thus controls structure of the subway Deflection, reduce construction impact produced on the operation of existing subway line to greatest extent so that train Safety and the stationarity run are guaranteed.Rephrasing the statement, the present invention is a kind of box culvert jacking construction method, But they are different from traditional box culvert jacking construction method, the present invention is at the base of traditional box culvert jacking construction method Add counterweight on plinth, make up, by the weight of counterweight Yu box culvert, the soil body weight that excavation falls, serve suppression The effect of lower section soil body floating deformation, takes full advantage of the principle of stress equilibrium.
Compared with traditional open-cut, train operation will not be caused any shadow in work progress by the present invention Ringing, train is without speed limit or stoppage in transit.
The composite can be widely applied to road or other urban operating mechanism is built and worn operated subway circuit on box culvert In construction, it is effective to ensure that the safety of existing subway line, reduces what existing subway line was runed by construction Impact, is particularly suited for runing busier or higher to track malformation requirement location, can produce Raw preferable economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is the implementing procedure figure of the present invention.
Fig. 2 is box culvert advancing schematic diagram.
Fig. 3 is as viewed from the side of Fig. 2, and the accessory structure after frame bridge has been constructed illustrates figure.
Detailed description of the invention
Include as it is shown in figure 1, wear existing structure of the subway box culvert jacking construction method on the newly-built frame bridge of the present invention Following steps:
Step one: plan to build the side of frame bridge position above existing structure of the subway, excavates jacking working pit;
Step 2: prefabricated box culvert in this jacking working pit, is additionally arranged at the bottom of counterweight in this box culvert, this counterweight The soil body weight fallen equal to excavation of the weight sum of weight and this box culvert (refer to excavate in whole work progress The soil body gross weight fallen), to lose the weight of the soil body during making up excavation jacking working pit;
Step 3: this box culvert of jacking, wherein: during this box culvert of jacking, gradually dig jacking direction The soil body of (referring to the direction of jacking box culvert), i.e. excavation front, the limit jacking limit soil body, forbids to backbreak, in order to complete Become box culvert advancing operation;
Step 4: after this box culvert advancing puts in place, while remove this counterweight, while perform accessory structure, dismounting This counterweight is equal in weight with this accessory structure performed, and makes this accessory structure substitute this counterweight, existing to ensure The structure of the subway periphery soil body keeps stress equilibrium, thus completes newly-built frame bridge above existing structure of the subway Construction.
In reality is implemented, counterweight is chosen as steel ingot or concrete slab, depending on concrete condition according to calculating decision.
In jack-in process, protective measure can be taked, such as, by end face, steel plate is installed along box culvert, should Bar-mat reinforcement is set between steel plate and box culvert, this bar-mat reinforcement is banded on the reinforcing bar of concrete slab, to prevent top Box culvert is damaged during entering.
In reality is implemented, performing before step 3, should calculate maximum top power that jacking box culvert allowed with And the top journey of jacking box culvert, control top power and top journey with strict in jack-in process.
If box culvert size is relatively big, then box culvert sectional is prefabricated and merogenesis jacking.
It is preferred that the slide plate of beneficially jacking can be built in jacking working pit, prefabricated box culvert on this slide plate.
In the present invention, the maximum top that the excavation of jacking working pit, the making of box culvert, jacking box culvert are allowed Power and the top calculating of journey, the making of slide plate, the performing and traditional box culvert jacking construction method of accessory structure The technology such as the such as jacking involved by are technology known in the art, are not described in detail.
The present invention is the box culvert using during newly-built frame bridge above existing structure of the subway and setting up counterweight Jacking mode controls a kind of construction method of structure of the subway floating deformation, compared with traditional open-cut, The inventive method, during utilizing box culvert advancing, uses the form increasing counterweight, with the weight of counterweight Yu box culvert Amount makes up excavation and falls the weight of the soil body so that the lower section soil body does not occur unloading effect, thus controls structure of the subway Deflection, reduce construction impact produced on the operation of existing subway line to greatest extent so that train Safety and the stationarity run are guaranteed.
Rephrasing the statement, the present invention is a kind of box culvert jacking construction method, but itself and traditional box culvert jacking construction Method is different, present invention is different in that it increases on the basis of traditional box culvert jacking construction method Counterweight, makes up, by the weight of counterweight Yu box culvert, the soil body weight that excavation falls, thus serves below suppression The effect of soil body floating deformation, this is to wear in existing structure of the subway construction work never to make on newly-built frame bridge Used.
Compared with traditional open-cut, train operation will not be caused any shadow in work progress by the present invention Ringing, train is without speed limit or stoppage in transit.
With an example, the present invention will be described below.
Intend at the newly-built frame bridge in an existing structure of the subway (subway tunnel 10 as shown in Figure 2) top, Cause the unloading of the underground tunnel upper soil body to make soil body generation resilience to prevent from constructing, make tunnel 10 With the soil body about, deformation of floating occurring, building of frame bridge uses box culvert jacking construction method of the present invention, keeps away Exempt from train operation is impacted.
Design top board thickness 0.8m of this frame bridge, base plate thickness 1.0m, side wall, middle wall thickness 0.8m, frame bridge Clear height 6.09~6.56m, height overall 7.89~8.36m, along alignment direction overall length 25.4m, bridge top is laid Pavement structure.
The detailed process using the inventive method to carry out frame bridge construction building is:
Before construction, take traffic to lead measures such as changing according to practical situation, be beneficial to being smoothed out of construction;
Above existing structure of the subway, plan to build the side, position of frame bridge, excavate jacking working pit 20, in reality In enforcement, jacking working pit 20 can use 1:1 to put slope excavation, can arrange gutter and sump in hole;
The slide plate (such as armored concrete slide plate) 30 being beneficial to jacking is built in this jacking working pit 20, Back beam 60 after prefabricated box culvert (i.e. frame bridge base structure) 40 on this slide plate 30, and build, at this back Banketing in beam 60 rear, forms back 70 (such as armored concrete back), and back bankets gradient form can root (after jacking completes, back needs to remove) is made the appropriate adjustments according to field condition;
Being additionally arranged at the bottom of counterweight in this box culvert 40, this counterweight elects steel ingot 50 as, and steel ingot 50 is at box culvert 40 The most successively putting on inner bottom plating, gross thickness is 0.5m, and its weight and box culvert 40 weight sum are equal to opening The soil body gross weight dug up, to lose the weight of the soil body during making up excavation jacking working pit, makes the soil body unload Carrying capacity is minimum, makes the soil body around structure of the subway lie substantially in virgin state of stress, makes uplift of soil deform It is down to minimum, fundamentally reduces the probability of deformation of floating;
Use this box culvert 40 of relay well method jacking, during this box culvert 40 of jacking, gradually dig jacking The soil body in front, i.e. limit excavation front soil body limit jacking, every time excavation drilling depth must not exceed setpoint distance (as Cannot be greater than 0.4m), need if desired ground is processed, before jacking, it is considered to various frictional force are (no Consider frontal drag), calculating the maximum top power that box culvert allowed is 82858KN, pushes up journey about 49m;
After this box culvert 40 jacking puts in place, removing this steel ingot 50, while performing accessory structure, removing Steel ingot 50 weight equal to the weight of accessory structure performed so that this accessory structure substitutes this steel ingot 50, Ensure that the existing structure of the subway periphery soil body keeps stress equilibrium, such as, perform the waterproof construction at structural joint and case Contain the pavement structure (bridge floor railing 81 as shown in Figure 3 etc.) above 40, thus complete existing The construction operation of newly-built frame bridge above iron construction.
In reality is implemented, during jacking, the two sides that box culvert 40 is pushed up can be provided with cold gluing emulsion waterproof layer, Additionally, 1:3 machine oil Pulvis Talci also can be coated with, to reduce jacking frictional force.
In reality is implemented, slide plate 30 surface requirements is smooth, and, during for preventing box culvert 40 jacking Pricking head, slide plate 30 end face can be provided with and face upward slope accordingly, and slide plate 30 bottom front can be provided with fore slope, the gradient It is 1 ‰~5 ‰.
Reality implement in, except arranging slide plate 30, also can relative set crushed stone concrete bed course, reinforcing bar mix Solidifying soil base plate, lubricating layer (smearing machine oil, Pulvis Talci on it), plastic bottom board sealing coat etc., these all may be used Need and respective design according to practical situation, belong to techniques well known.
In reality is implemented, can set up corresponding appurtenant work according to practical situation in work progress, these are attached Belonging to the accessory structure building related in engineering is all technology known in the art, is exemplified below.Such as, The armored concrete basil 41 can be set in box culvert (frame bridge base structure) 40 front ends, to prevent side soil Body caves in, when box culvert 40 jacking rear cutout in place is removed.The most such as, can be in jacking construction, in box culvert 40 side The basil and bottom front arrange steel side edge angle and steel shear blade angle, to ensure to cut soil and the entering smoothly of jacking OK, remove after box culvert 40 jacking is in place.The most such as, after frame bridge construction, can be to its both sides one The soil body in the range of Ding processes, and can perform transition slab at bridge head 82 accordingly, with improve driving safety and Comfortableness.The most such as, after frame bridge has been constructed, if the built position of frame bridge is in river course, then need The structures such as the original river course barricade etc. removed before constructing recovers, the river course barricade of recovery see in Fig. 3 Part shown in label 90.
The composite can be widely applied to road or other urban operating mechanism is built and worn operated subway circuit on box culvert In construction, it is effective to ensure that the safety of existing subway line, reduces what existing subway line was runed by construction Impact, is particularly suited for runing busier or higher to track malformation requirement location, can produce Raw preferable economic benefit and social benefit.
The above is presently preferred embodiments of the present invention and the know-why used thereof, for the skill of this area For art personnel, without departing from the spirit and scope of the present invention, any based on the technology of the present invention side Equivalent transformation on the basis of case, simple replacement etc. obviously change, belong to scope it In.

Claims (4)

1. wear existing structure of the subway box culvert jacking construction method on a newly-built frame bridge, it is characterised in that It comprises the steps:
Step one: plan to build the side of frame bridge position above existing structure of the subway, excavates jacking working pit;
Step 2: prefabricated box culvert in this jacking working pit, is additionally arranged at the bottom of counterweight in this box culvert, this counterweight The soil body weight fallen equal to excavation of the weight sum of weight and this box culvert, to make up excavation jacking working pit mistake Journey is lost the weight of the soil body;
Step 3: this box culvert of jacking, wherein: during this box culvert of jacking, gradually dig jacking direction The soil body, in order to complete box culvert advancing operation;
Step 4: after this box culvert advancing puts in place, removes this counterweight, while performing accessory structure, tears open This counterweight removed is equal in weight with this accessory structure performed, and makes this accessory structure substitute this counterweight, it is ensured that both There is the structure of the subway periphery soil body to keep stress equilibrium, complete executing of above existing structure of the subway newly-built frame bridge Work.
Existing structure of the subway box culvert jacking construction method is worn on newly-built frame bridge the most as claimed in claim 1, It is characterized in that:
Described counterweight is steel ingot or concrete slab.
Existing structure of the subway box culvert jacking construction method is worn on newly-built frame bridge the most as claimed in claim 1, It is characterized in that:
Before performing described step 3, calculate maximum top power and jacking institute that box culvert described in jacking is allowed State the top journey of box culvert.
Existing structure of the subway box culvert jacking construction method is worn on newly-built frame bridge the most as claimed in claim 1, It is characterized in that:
If described box culvert size is relatively big, the most described box culvert segmentation is prefabricated and merogenesis jacking.
CN201310602973.8A 2013-11-25 2013-11-25 Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge Active CN104652279B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310602973.8A CN104652279B (en) 2013-11-25 2013-11-25 Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310602973.8A CN104652279B (en) 2013-11-25 2013-11-25 Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge

Publications (2)

Publication Number Publication Date
CN104652279A CN104652279A (en) 2015-05-27
CN104652279B true CN104652279B (en) 2016-08-17

Family

ID=53243875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310602973.8A Active CN104652279B (en) 2013-11-25 2013-11-25 Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge

Country Status (1)

Country Link
CN (1) CN104652279B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109797717A (en) * 2019-01-21 2019-05-24 北京通成达水务建设有限公司 The construction method for having subway tunnel is worn on a kind of river

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064216B (en) * 2015-07-29 2016-08-24 中铁六局集团天津铁路建设有限公司 Prevent existing line from traversing method occurring during a kind of jacking extra-long frame bridge
CN105809246B (en) * 2016-02-25 2018-02-02 东南大学 A kind of structure of the subway Deformation Forecasting Method based on the fusion of BP time serieses
CN105672356B (en) * 2016-03-25 2017-06-06 中船第九设计研究院工程有限公司 A kind of municipal pipeline group's Underground Construction method of spanning over subway tunnel
CN105804758B (en) * 2016-04-22 2018-02-16 中国电建集团铁路建设有限公司 Across constructing metro tunnel method on the rectangular top pipe of the shallow small spacing of earthing big cross section
CN106120566B (en) * 2016-08-16 2017-10-20 中铁六局集团天津铁路建设有限公司 The jacking new frame bridge construction method in the case of extreme angles close on existing frame bridge
CN107419741B (en) * 2017-07-04 2023-04-18 中铁上海设计院集团有限公司 Slideway structure for preventing jacking box body from deviating and construction method thereof
CN107447673B (en) * 2017-09-13 2018-10-12 中铁六局集团天津铁路建设有限公司 Method for adjusting frame bridge upper box jacking height difference
CN107675628B (en) * 2017-10-12 2018-12-28 中铁六局集团有限公司 It is worn on urban road frame bridge and wears railway in operation jacking construction method under operated subway
CN108166397B (en) * 2017-12-31 2019-08-09 中铁十九局集团第二工程有限公司 Railway Frame Bridge construction method
CN109914474A (en) * 2019-03-24 2019-06-21 北京工业大学 A kind of pipe gallery U-type groove, which is excavated, presses push construction method
CN110306449B (en) * 2019-05-31 2021-08-27 武汉市武昌市政建设(集团)有限公司 Method for connecting new box culvert and existing road box culvert
CN111305074B (en) * 2020-03-23 2021-05-14 中铁七局集团郑州工程有限公司 Construction method for integrally dropping jacking box bridge with upward floating exceeding standard
CN112647958A (en) * 2020-12-28 2021-04-13 中铁广州工程局集团有限公司 Construction method of box culvert
CN114910028A (en) * 2022-01-13 2022-08-16 中铁二十四局集团有限公司 Measurement and calculation method for box culvert jacking attitude
CN114561882B (en) * 2022-03-29 2023-09-15 北京市市政二建设工程有限责任公司 Frame box culvert jacking structure of underpass railway and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101343861A (en) * 2008-08-22 2009-01-14 中铁六局集团有限公司 Construction method for replacing old frame bridge by new frame bridge in existing railway lines
JP2009185564A (en) * 2008-02-08 2009-08-20 Ihi Corp Sending-off method of bridge
CN102031757A (en) * 2011-01-06 2011-04-27 李家稳 Method for constructing bottom plate guide layer of jacked-in frame bridge
CN201924288U (en) * 2011-01-06 2011-08-10 李家稳 Guide device for bottom plate of jacked frame bridge
CN103362073A (en) * 2013-08-08 2013-10-23 中铁六局集团天津铁路建设有限公司 Method for pushing frame bridge

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009185564A (en) * 2008-02-08 2009-08-20 Ihi Corp Sending-off method of bridge
CN101343861A (en) * 2008-08-22 2009-01-14 中铁六局集团有限公司 Construction method for replacing old frame bridge by new frame bridge in existing railway lines
CN102031757A (en) * 2011-01-06 2011-04-27 李家稳 Method for constructing bottom plate guide layer of jacked-in frame bridge
CN201924288U (en) * 2011-01-06 2011-08-10 李家稳 Guide device for bottom plate of jacked frame bridge
CN103362073A (en) * 2013-08-08 2013-10-23 中铁六局集团天津铁路建设有限公司 Method for pushing frame bridge

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
软土地基箱涵顶进扎头的原因及预防措施;杨秀玲;《铁道运营技术》;20091031(第4期);第40-42页 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109797717A (en) * 2019-01-21 2019-05-24 北京通成达水务建设有限公司 The construction method for having subway tunnel is worn on a kind of river

Also Published As

Publication number Publication date
CN104652279A (en) 2015-05-27

Similar Documents

Publication Publication Date Title
CN104652279B (en) Existing structure of the subway box culvert jacking construction method is worn on a kind of newly-built frame bridge
CN101831873B (en) Temporary bridge covered excavation method for constructing box culvert below traffic ground line of operating track
CN101858222B (en) Method for controlling deformation in zero-distance tunneling of new tunnel under existing subway construction
CN105003272B (en) Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways
CN105064397B (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN104018405B (en) The double-deck road structure that a kind of " stake-anchor-framework " is compound
CN105041349A (en) Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN105672347A (en) Structure of prefabricated pile-plate brackets for underpinning existing pile foundations through shield tunneling and construction method
CN103874803A (en) Method for building structures, particularly passages under operating railways or the like.
CN1837506A (en) Construction method for excavating box-shape structure over an operating tunnel
CN106640091A (en) Shallow-buried tunnel section construction method
CN104563158A (en) Construction method for implementing transfer between platform floor of existing subway station and platform floor of new subway station
CN109371763A (en) A kind of phreatic high is low to fill out shallow cut subgrade in swelling soil zone construction method
CN105350589A (en) Underpinning construction method for pile foundation crossing existing protective building structure
CN107326928A (en) A kind of part is related to the construction method in the deeper subsurface garage of basement
CN107938680A (en) A kind of excavation of foundation pit safe construction method
CN106759486A (en) A kind of underground structure being made up of stake and wall and its construction method
CN106498976A (en) A kind of inter-city passenger rail underpass of freeways open-cut group pushes up support and change method
CN111501451B (en) Construction method for jacking municipal frame bridge
CN100535392C (en) Bridge type shield construction method for box type bridge
CN104975877A (en) Portal external road surface water blocking and discharging system with tunnel portal in downslope direction and manufacturing method for same
CN106907021A (en) Steel and concrete structure enters big vast lock Bridge Pier shaping Cutting Blasting Demolition method
CN111636894A (en) Open cut tunnel structure of high and steep slope tunnel portal and method for preventing avalanche falling of rocks
CN106758886B (en) A kind of method of the existing bridges and culverts structure of novel dismounting
CN109797717A (en) The construction method for having subway tunnel is worn on a kind of river

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant