CN106882325B - A kind of split type rudder paddle diversion pipe hanging method - Google Patents

A kind of split type rudder paddle diversion pipe hanging method Download PDF

Info

Publication number
CN106882325B
CN106882325B CN201710133920.4A CN201710133920A CN106882325B CN 106882325 B CN106882325 B CN 106882325B CN 201710133920 A CN201710133920 A CN 201710133920A CN 106882325 B CN106882325 B CN 106882325B
Authority
CN
China
Prior art keywords
bracket
diversion pipe
rudder paddle
split type
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710133920.4A
Other languages
Chinese (zh)
Other versions
CN106882325A (en
Inventor
孙德
孙德一
高文斌
卢宇明
陈国强
黄昌妙
郑孟
陈健恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG XINCHUAN HEAVY INDUSTRY Co Ltd
Original Assignee
GUANGDONG XINCHUAN HEAVY INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG XINCHUAN HEAVY INDUSTRY Co Ltd filed Critical GUANGDONG XINCHUAN HEAVY INDUSTRY Co Ltd
Priority to CN201710133920.4A priority Critical patent/CN106882325B/en
Publication of CN106882325A publication Critical patent/CN106882325A/en
Application granted granted Critical
Publication of CN106882325B publication Critical patent/CN106882325B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance

Abstract

The present invention relates to shipbuilding technical fields, specifically disclose split type rudder paddle diversion pipe hanging method, comprising: preparation tooling bracket → diversion pipe is fixed on bracket → ship plank freeze ship hanging code → on diversion pipe and bracket integral hoisting to the tank trolley on building berth ground → be moved to tugboat enclose downhole → chain block will in diversion pipe and bracket integral hoisting to rudder paddle shaft hole → installation positioning.Before present invention lifting, the center centering as far as possible of rudder paddle water conservancy diversion tube portion and equipment is fulfiled ahead of schedule, after reducing diversion pipe chain block pull-up, adjust the workload of axis hole centering;Easy to operate, efficient, safe, the workload of 4 hours originally is lifted, present 2 hours can be completed.

Description

A kind of split type rudder paddle diversion pipe hanging method
Technical field
The present invention relates to shipbuilding technical fields, and in particular to a kind of split type rudder paddle diversion pipe hanging method.
Background technique
During shipbuilding industry, since tugboat rudder paddle draft-tube diameter is bigger than normal compared with well diameter is enclosed, water conservancy diversion tube portion can not be from Deck is enclosed well aperture and is hung in, therefore diversion pipe must be hung to rudder paddle by loop wheel machine and enclose downhole and be installed.And water conservancy diversion tube shape is special It very, is security consideration, the 90 ° of angles that should first fall steadily are put in ground.Then 6 are freezed in tugboat outside plate (enclosing well position all around) Hanging code, with chain block gradually by its pull-up, then slowly adjustment water conservancy diversion tube hub face encloses well center (both sides gap after centering Only 5mm or so), little by little rudder paddle is pulled to and is enclosed inside well, positioning is completed;However under art methods, need using multiple Chain block co-locates diversion pipe, should adjust the hand of corresponding region according to the drift condition of diversion pipe in actual mechanical process Cucurbit is drawn, entire position fixing process spends the artificial and time more.
Summary of the invention
In view of this, it is necessary to for above-mentioned problem, provide a kind of simple, convenient, efficient split type rudder paddle Diversion pipe hanging method.
To achieve the above object, the present invention takes technical solution below:
The split type rudder paddle diversion pipe hanging method of the present invention, comprising the following steps:
Step 1): production rudder paddle diversion pipe ceiling mount bracket;
Step 2): diversion pipe is fixed on bracket;
Step 3): it freezes more ship hanging codes in ship plank;
Step 4): tank trolley is placed on building berth ground;
Step 5): above diversion pipe and bracket integral hoisting to tank trolley;
Step 6): diversion pipe and bracket are moved integrally to tugboat using tank trolley and enclose downhole;
Step 7): using chain block connection ship hanging code and bracket hanging code, diversion pipe and bracket are integrally pulled up to rudder In paddle shaft hole;
Step 8): being fixed on corresponding position for diversion pipe, unloads bottom bracket, completes diversion pipe positioning;
The height of the bracket+tank trolley height+diversion pipe height be less than tugboat enclose well to ground height.
Further, the bracket includes bracket base and bracket hanging code;Multiple bracket hanging codes are set on bracket base.
Further, it is additionally provided with multiple support tubes on the bracket, is connected with top plate on the support tube top end face;Institute It states support tube to be fixedly installed on the first backing plate, first backing plate is connect with the second backing plate on bracket by band nut bolt It is fixed on bracket base;Position of centre of gravity of the top plate for support support diversion pipe.
Further, reinforcement cross bar is connected between the support tube.
Further, the top board undersurface is welded with reinforcer.
Further, support pier is also welded on the bracket.
Further, reinforcing rib is also welded on the bracket base.
It further, is that diversion pipe and bracket are moved integrally to tugboat to the underface for enclosing well in step 6).
Further, the effective rope of water conservancy diversion described in step 2) is bundled on bracket fixed.
The invention has the benefit that
1, it before lifting by crane, fulfils the center centering as far as possible of rudder paddle water conservancy diversion tube portion and equipment ahead of schedule, reduces diversion pipe hand After drawing cucurbit pull-up, the workload of axis hole centering is adjusted;
2, lifting is easy to operate, efficient, safe, and the workload of 4 hours, present 2 hours can be completed originally;
3, the tooling bracket disposably made repeats and is applied to subsequent tugboat ship type.
Detailed description of the invention
Fig. 1 is tooling carrier structure main view of the invention;
Fig. 2 is the side view of Fig. 1;
Fig. 3 is the top view that tube portion set-up mode is supported in Fig. 1;
Fig. 4 is the structural schematic diagram that reinforcer is arranged on tray top panel medial surface;
Fig. 5 is the top view of Fig. 1;
Fig. 6 is the status diagram after diversion pipe is placed on bracket;
Fig. 7 is the schematic top plan view that diversion pipe uses state after rope binding in Fig. 6;
Fig. 8 is that diversion pipe and bracket are integrally placed in the status diagram after tank trolley;
Fig. 9 is the schematic diagram that ship hanging code is arranged on ship plank;
Figure 10 is that diversion pipe and bracket move integrally to tugboat the status diagram enclosed immediately below well;
Figure 11 is the status diagram that diversion pipe and bracket integrally use chain block to lift.
Detailed description of the invention: 1, bracket;101, bracket base;102, support tube;103, reinforce cross bar;104, support pier;105, First backing plate;106, the second backing plate;107, bracket hanging code;108, band nut bolt;109, top plate;110, longitudinal reinforcer; 111, lateral reinforcer;112, reinforcing rib;2, diversion pipe;3, rope;4, ship hanging code;5, tank trolley;6, tugboat encloses well;7, Chain block;8, rudder paddle shaft hole.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with the embodiment of the present invention, to this hair Bright technical solution work further clearly and completely describes.It should be noted that described embodiment is only the present invention one Section Example, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not doing Every other embodiment obtained under the premise of creative work out, shall fall within the protection scope of the present invention.
It is to be appreciated that term " on ", "lower", "front", "rear", "left", "right", "horizontal", "top", "inner" etc. indicate Orientation or positional relationship be based on the orientation or positional relationship shown in the drawings, be merely for convenience of description the present invention and simplification retouch It states, rather than the device or element of indication or suggestion meaning must have a particular orientation, be constructed and operated in a specific orientation, Therefore it is not considered as limiting the invention.
Term " first ", " second ", " third " are used for description purposes only, and are not understood to indicate or imply relatively important Property or implicitly indicate the quantity of indicated technical characteristic.Define as a result, " first ", " second ", " third " feature can To explicitly or implicitly include one or more of the features.
Embodiment
The split type rudder paddle diversion pipe hanging method of the present invention, comprising the following steps:
Step 1): production rudder paddle diversion pipe ceiling mount bracket 1.
As shown in Figure 1, the bracket 1 is the bracket that channel steel is welded, including bracket base 101 and bracket hanging code 107; Multiple bracket hanging codes 107 are set on bracket base 101.The bracket hanging code 107 is welded in the upper surface of bracket 1 by proximal edge On.Bracket hanging code 107 is installed for slinging diversion pipe 2, bracket hanging code 107 at least two, and position is arranged should Guarantee horizontal steady when bracket 1 is lifted.1 upper surface of bracket is symmetrically disposed on before and after bracket hanging code 107 in the present embodiment.
As depicted in figs. 1 and 2, multiple support tubes 102,102 top of support tube are also provided on the bracket 1 Top plate 109 is connected on face;The support tube 102 is fixedly installed on the first backing plate 105, first backing plate 105 and bracket 1 On the second backing plate 106 pass through band nut bolt 108 be connected and fixed on bracket base 101.Support tube 102 is used to support diversion pipe 2 center of gravity.
As shown in figure 3, the support tube 102 in the present embodiment is set as 4, it is horizontal that reinforcement is welded between adjacent supports pipe 102 Bar 103, to improve the support strength of support tube 102.As shown in figure 4, preferably, 109 bottom surface of the top plate be welded with it is vertical To reinforcer 110 and lateral reinforcer 111.
As shown in figure 5, being also welded with reinforcing rib on bracket base 101 because support 2 center stress of diversion pipe is larger 112, shown reinforcing rib 112 is respectively arranged at the left and right sides and upside of bracket base 101.
As shown in fig. 6, being also welded with support on the left and right sides of the bracket 1 to be further supported to diversion pipe 2 Pier 104.
Step 2): diversion pipe 2 is fixed on the bracket 1 of acceptance(check);As shown in fig. 7, using rope 3 by diversion pipe 2 It is bundled on the bracket 1 of acceptance(check).The intensity of the bracket 1 is greater than the weight of its born rudder paddle diversion pipe 2.
Step 3): as shown in figure 9, freezing 4 ship hanging codes 4 in ship plank;On the corresponding bracket 1 of 4 ship hanging codes 4 Four bracket hanging codes 107.
Step 4): 4 tank trolleies 5 are placed on building berth ground;
Step 5): as shown in figure 8, by above diversion pipe 2 and 1 integral hoisting of bracket to tank trolley 5;
Step 6): as shown in Figure 10, diversion pipe 2 and bracket 1 is moved integrally to tugboat using tank trolley 5 and enclosed under well 6 Side;Position is adjusted, so that diversion pipe 2 and 1 entirety of bracket are placed exactly in the underface that tugboat encloses well 6.
Step 7): it as shown in figure 11, is connected one to one four groups of ship hanging codes 4 and bracket hanging code using chain block 7 107, diversion pipe 2 and 1 entirety of bracket are pulled up in rudder paddle shaft hole 8;
Step 8): being fixed on corresponding position for diversion pipe 2, unloads bottom bracket 1, completes diversion pipe 2 and positions.
The height of the height of bracket 1 of the invention+tank trolley 5 height+diversion pipe 2 is less than tugboat and encloses well 6 to ground Height.Hoisting method of the invention can be applied to the lifting of 32m/33m tugboat series rudder for ship paddle diversion pipe.
Hanging method of the invention before lifting, fulfils the center centering as far as possible of rudder paddle water conservancy diversion tube portion and equipment ahead of schedule, After reducing diversion pipe chain block pull-up, the workload of axis hole centering is adjusted;Lift easy to operate, efficient, safe, script 4 A hour workload, present 2 hours can be completed.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously Limitations on the scope of the patent of the present invention therefore cannot be interpreted as.It should be pointed out that for those of ordinary skill in the art For, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to guarantor of the invention Protect range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (7)

1. a kind of split type rudder paddle diversion pipe hanging method, which comprises the following steps:
Step 1): production rudder paddle diversion pipe ceiling mount bracket;
Step 2): diversion pipe is fixed on the bracket of acceptance(check);
Step 3): it freezes more ship hanging codes in ship plank;
Step 4): tank trolley is placed on building berth ground;
Step 5): above diversion pipe and bracket integral hoisting to tank trolley;
Step 6): diversion pipe and bracket are moved integrally to tugboat using tank trolley and enclose downhole;
Step 7): using chain block connection ship hanging code and bracket hanging code, diversion pipe and bracket are integrally pulled up to rudder paddle shaft In hole;
Step 8): being fixed on corresponding position for diversion pipe, unloads bottom bracket, completes diversion pipe positioning;
The height of the bracket+tank trolley height+diversion pipe height be less than tugboat enclose well to ground height;
The bracket includes bracket base and bracket hanging code;Multiple bracket hanging codes are set on bracket base;
It is additionally provided with multiple support tubes on the bracket, is connected with top plate on the support tube top end face;The support tube is fixed It is set on the first backing plate, the second backing plate on first backing plate and bracket is connected and fixed on bracket bottom by band nut bolt Seat;Position of centre of gravity of the top plate for support support diversion pipe.
2. split type rudder paddle diversion pipe hanging method according to claim 1, which is characterized in that connected between the support tube There is reinforcement cross bar.
3. split type rudder paddle diversion pipe hanging method according to claim 1, which is characterized in that the top board undersurface welding There is reinforcer.
4. the split type rudder paddle diversion pipe hanging method according to claim 2-3 any one, which is characterized in that the support Support pier is also welded on frame.
5. split type rudder paddle diversion pipe hanging method according to claim 1 to 3, which is characterized in that the support Reinforcing rib is also welded on frame pedestal.
6. split type rudder paddle diversion pipe hanging method according to claim 1, which is characterized in that be by water conservancy diversion in step 6) Pipe and bracket move integrally to tugboat the underface for enclosing well.
7. split type rudder paddle diversion pipe hanging method according to claim 1, which is characterized in that led described in step 2) Flow tube is bundled on bracket fixed with rope.
CN201710133920.4A 2017-03-08 2017-03-08 A kind of split type rudder paddle diversion pipe hanging method Expired - Fee Related CN106882325B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710133920.4A CN106882325B (en) 2017-03-08 2017-03-08 A kind of split type rudder paddle diversion pipe hanging method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710133920.4A CN106882325B (en) 2017-03-08 2017-03-08 A kind of split type rudder paddle diversion pipe hanging method

Publications (2)

Publication Number Publication Date
CN106882325A CN106882325A (en) 2017-06-23
CN106882325B true CN106882325B (en) 2019-04-26

Family

ID=59180445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710133920.4A Expired - Fee Related CN106882325B (en) 2017-03-08 2017-03-08 A kind of split type rudder paddle diversion pipe hanging method

Country Status (1)

Country Link
CN (1) CN106882325B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110053711A (en) * 2019-04-30 2019-07-26 广船国际有限公司 Embedded hanging code component and the ship comprising it

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107878674A (en) * 2017-10-19 2018-04-06 中船黄埔文冲船舶有限公司 A kind of split type side propeller enters cabin method
CN108298016B (en) * 2017-12-29 2019-07-12 南通中远船务工程有限公司 Crude oil rejects shipowner's propeller bracket sliding lifting installation method
CN108298017B (en) * 2018-01-03 2019-09-27 广东凯力船艇股份有限公司 A kind of well formula vibration damping installation method of steering gear
CN113320659B (en) * 2021-06-25 2022-07-01 广船国际有限公司 Method for assembling flange and barrel of double-angle steering oar of ship
CN113715989B (en) * 2021-08-31 2022-12-13 广船国际有限公司 Steering oar device jacking bracket and steering oar device installation method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101475045A (en) * 2008-11-14 2009-07-08 大连船舶重工集团有限公司 Hoisting method for rudder blade during shipbuilding process
CN103129701A (en) * 2011-11-22 2013-06-05 上海船厂船舶有限公司 Positioning method of stream guidance cover on segmentation
CN104443260A (en) * 2014-11-18 2015-03-25 中船黄埔文冲船舶有限公司 Installing device and method for underwater part of full-revolving propeller
CN204353702U (en) * 2014-12-26 2015-05-27 浙江国际海运职业技术学院 A kind of frock moulding bed of ship honeycomb duct

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101475045A (en) * 2008-11-14 2009-07-08 大连船舶重工集团有限公司 Hoisting method for rudder blade during shipbuilding process
CN103129701A (en) * 2011-11-22 2013-06-05 上海船厂船舶有限公司 Positioning method of stream guidance cover on segmentation
CN104443260A (en) * 2014-11-18 2015-03-25 中船黄埔文冲船舶有限公司 Installing device and method for underwater part of full-revolving propeller
CN204353702U (en) * 2014-12-26 2015-05-27 浙江国际海运职业技术学院 A kind of frock moulding bed of ship honeycomb duct

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110053711A (en) * 2019-04-30 2019-07-26 广船国际有限公司 Embedded hanging code component and the ship comprising it

Also Published As

Publication number Publication date
CN106882325A (en) 2017-06-23

Similar Documents

Publication Publication Date Title
CN106882325B (en) A kind of split type rudder paddle diversion pipe hanging method
CN106882698B (en) A kind of integral type rudder oar hanging method
CN104443260B (en) A kind of all-direction propeller underwater portion erecting device and method
CN106741603B (en) The flow container fast and accurately localization method when liquefaction vessel is built
CN107161282B (en) A kind of propeller shrouding mounting device
CN108455451B (en) A kind of 600 tons of gantry cranes hold the method for hanging installation superelevation flare tower
CN106218811A (en) A kind of ship stern tube shaft wears axle method
CN104242152A (en) Lifting device for lifting overhead ground wire on straight concrete pole
CN103939299A (en) Split type installation process for offshore wind turbine
CN209050366U (en) The connecting rod bearing shell mounting tool of marine diesel
CN104891325B (en) A kind of whole ship handling launching method of use hull bracket
CN207566717U (en) A kind of I-shaped floor steel beam lifting structure
CN108860450A (en) A kind of propeller for vessels blade assemble method
CN201703776U (en) Inverted lifting device of storage tank
CN106143808B (en) Assembled crane for container ship and assembling mode thereof
CN110053720A (en) Immersed tube combination transport installs equipment and transportation installation method
CN107653857A (en) A kind of offshore platform installation method
CN202247682U (en) Bridge crane for installing curtain board
KR20160134729A (en) Method for manufacturing crane and system for mounting superstructure of crane
CN204689351U (en) A kind of H profile steel structural elements suspender
CN108999428A (en) A kind of method for dismounting of submerged tunnel steel closure door
KR101429551B1 (en) Installation module of trolley hoist for vessel or marine structure and the operating method of it
CN211589918U (en) Container guide rail anti-top installation device
CN208577339U (en) A kind of prefabricated pipe gallery lifting balancing stand
CN208897265U (en) A kind of novel rudder paddle mounting tool

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Sun Deyi

Inventor after: Gao Wenbin

Inventor after: Lu Yuming

Inventor after: Chen Guoqiang

Inventor after: Huang Changmiao

Inventor after: Zheng Meng

Inventor after: Chen Jianheng

Inventor before: Gao Wenbin

Inventor before: Sun Deyi

Inventor before: Lu Yuming

Inventor before: Chen Guoqiang

Inventor before: Huang Changmiao

Inventor before: Zheng Meng

Inventor before: Chen Jianheng

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190426

Termination date: 20210308

CF01 Termination of patent right due to non-payment of annual fee