CN106836251A - A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method - Google Patents

A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method Download PDF

Info

Publication number
CN106836251A
CN106836251A CN201710101731.9A CN201710101731A CN106836251A CN 106836251 A CN106836251 A CN 106836251A CN 201710101731 A CN201710101731 A CN 201710101731A CN 106836251 A CN106836251 A CN 106836251A
Authority
CN
China
Prior art keywords
pipe well
steel sleeve
circular groove
base plate
borehole wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710101731.9A
Other languages
Chinese (zh)
Inventor
谢攀贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710101731.9A priority Critical patent/CN106836251A/en
Publication of CN106836251A publication Critical patent/CN106836251A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Abstract

The invention discloses a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, including pipe well, steel sleeve, steel sleeve and pipe well flax silk the mud mode that adds water are connected, coarse sand recharge layer is respectively equipped with inside it from bottom to top and high grade fast hardening concrete pours layer, the top of steel sleeve is less than base plate and is welded with steel deck-plate, and its top sets slightly expanded concrete sealing layer and flushed with plate top surface, and steel sleeve outside is welded with three sealing Ji rings;Closed with the cement mortar mixed with waterproofing agent at pipe well upper pipes well head, it is artificial picking out with pipe well center superposition and the circular groove at the top for being less than pipe well, circular groove bottom to the water-proof concrete consistent with base plate of one-piece casting between plate top surface that outside is provided with one.Invention additionally discloses a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, it is using multiple seepage control measure and preferred with material by process improving, make constructing operation easier, construction quality is more easy to ensure, and is prevented effectively from the generation of Seepage.

Description

A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method
Technical field
The invention belongs to technical field of buildings, more particularly to a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its Construction method.
Background technology
Generally, need to carry out tube well dewatering during basement construction, after the completion of basement bottom board concrete placings still Tube well dewatering need to be carried out, after main body construction reaches design requirement, precipitation can be stopped and pipe well closure is carried out.Current art one As use the box out on base plate, then fill fast hardening concrete to base plate bottom surface in pipe well, then with slightly expanded concrete the bottom of by Plate filling-in.The form of construction work carries out waterproof mainly by concrete, once fast hardening concrete is by groundwater infiltration in well, it is easy to make It is destroyed at pipe well into base plate leakage, and base plate waterproofing, it is impossible to form overall waterproof layer, influences waterproof quality.
The content of the invention
The present invention provides a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method, can using the present invention Effectively solve the problems, such as that underground water seepage occurs in pipe well.
The technical solution adopted for the present invention to solve the technical problems is:
A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, including pipe well, steel sleeve, base plate and bottom cushion, institute The diameter for stating steel sleeve is slightly less than the diameter of pipe well, and steel sleeve lower end is located at pipe well upper end inner side, steel sleeve lower end outside fiber crops The silk mud that adds water is connected with pipe well upper end, with the cement mortar closing mixed with waterproofing agent at pipe well upper pipes well head;Under the pipe well It is coarse sand recharge layer to hold, and the top of coarse sand recharge layer is high grade fast hardening concrete pouring layer, and high grade fast hardening concrete is poured The upper end of layer flushes with steel sleeve;The top of the steel sleeve is less than base plate, and steel deck-plate, steel are welded with the mouth of pipe of steel sleeve upper end Slightly expanded concrete sealing layer is poured above cover plate, slightly expanded concrete sealing layer is flushed with plate top surface, outside steel sleeve Side is located between steel deck-plate and pipe well top and is welded with three sealing Ji rings.The pipe well top is less than bottom cushion absolute altitude, pipe The upper pipes well head outside of well is provided with the center superposition of an artificial diameter the picked out circular groove bigger than pipe well, circular groove and pipe well, circle The bottom of groove less than pipe well top, in circular groove and circular groove top surface is to using the anti-water coagulation consistent with base plate between plate top surface Native one-piece casting.
Further, circular groove diameter 600mm bigger than the diameter of pipe well, circular groove bottom surface is away from bottom cushion bottom surface 400mm.
Further, the steel sleeve lower end and the lap of splice of pipe well upper end are 1000mm.
Further, the position of three sealing Jis ring is located at plate upper surface 150mm, apart from base plate respectively At lower surface 150mm and at circular groove bottom land 150mm.
Further, the thickness of sealing Ji ring is 6mm, and width is 150mm, and the thickness of the steel deck-plate is 6mm.
Further, the distance from top pipe well top surface 2000mm of the coarse sand recharge layer, high grade fast hardening concrete is poured Layer upper surface is away from plate top surface 100mm.
The present invention also provides a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, and its technical scheme is such as Under:
A kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, the construction method comprises the following steps:
When step one, earth excavation to bottom cushion absolute altitude, a diameter is manually picked out than pipe well diameter along pipe well periphery Big circular groove, pipe well and circular groove center superposition, block pipe well at circular groove bottom up 100mm;
Step 2, past pipe well are inserted into the diameter steel sleeve more smaller than pipe well internal diameter, and base top is higher by the top of steel sleeve Face 500mm, lower end and the pipe well of steel sleeve are overlapped, and the lap of splice is 1000mm;On the outside of steel sleeve wind flax silk add water mud with Pipe well upper end is connected, and pipe well upper pipes outer wellhead is closed with the cement mortar mixed with waterproofing agent, in steel sleeve outside top and pipe well Three sealing Ji rings are welded between top;
Step 3, using the water-proof concrete consistent with base plate by circular groove and base plate one-piece casting;
When step 4, shut-in well, steel sleeve is cut off at 100mm under plate top surface, apart from below pipe well top surface 2000mm Pipe well section uses coarse sand recharge, is then poured onto below plate top surface at 100mm with high grade fast hardening concrete again, is welded with steel deck-plate, Weld seam is full, is finally poured to plate top surface with slightly expanded concrete and flushed.
Further, the diameter of the circular groove in the step one 600mm bigger than the diameter of pipe well, depth is 400mm.
Further, in the step 2 three positions of sealing Ji ring be located at plate upper surface 150mm respectively, At base plate lower surface 150mm and at circular groove bottom land 150mm.
Further, three thickness of sealing Ji ring are 6mm in the step 2, and width is 150mm, in the step 4 The thickness of steel deck-plate is 6mm.
The present invention can effectively solve the problem that groundwater infiltration, construction quality easily occurs in traditional pipe well closure waterproof construction The problem that cannot ensure of requirement, compared with traditional pipe well closure waterproof construction, the present invention uses multiple seepage control measure, and passes through Process improving is preferred with material, makes constructing operation easier, and construction material is common construction material, construction cost Further declined, with very strong practicality, construction quality is more easy to be guaranteed and be prevented effectively from the generation of Seepage.
Brief description of the drawings
The invention will be further described with reference to the accompanying drawings and detailed description:
Fig. 1 is a kind of pre-buried deformation joint anti-seepage structure schematic diagram of the new pipe well borehole wall;
Fig. 2 is a kind of pre-buried deformation joint anti-seepage structure construction method schematic diagram of the new pipe well borehole wall;
In figure:1. steel sleeve 2. mixed with the flax silk of cement mortar 3. of waterproofing agent add water the coarse sand recharge of 4. steel deck-plate of mud 5. layer 6. high grade fast hardening concrete pours the pipe well of 8. 9. bottom cushion of sealing Ji ring of layer 7. slightly expanded concrete sealing layer 10. The circular groove of 11. water-proof concrete, 12. base plate 13..
Specific embodiment
In order to preferably explain the present invention, come in the present invention is furture elucidated with specific embodiment below in conjunction with the accompanying drawings Hold, but present disclosure is not limited only to following examples.
A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall as shown in Figure 1, including pipe well 10, steel sleeve 1, base plate 12 and bottom cushion 9, the diameter of the steel sleeve 1 is slightly less than the diameter of pipe well 10, and the lower end of steel sleeve 1 is located in the upper end of pipe well 10 Side, the lower end outside flax silk of steel sleeve 1 mud 3 that adds water is connected with the upper end of pipe well 10, with mixed with waterproof at the upper pipes well head of pipe well 10 The cement mortar 2 of agent is closed;The lower end of the pipe well 10 be coarse sand recharge layer 5, coarse sand recharge layer 5 top for high grade rapid hardening mix Solidifying soil pours layer 6, and the upper end that high grade fast hardening concrete pours layer 6 flushes with the top of steel sleeve 1;The top of the steel sleeve 1 Less than base plate 12, steel deck-plate 4 is welded with the upper end mouth of pipe of steel sleeve 1, the top of steel deck-plate 4 has poured slightly expanded concrete and sealed Layer 7, slightly expanded concrete sealing layer 7 is flushed with the top surface of base plate 12, and the outside of steel sleeve 1 is located at steel deck-plate 4 with the top of pipe well 10 Between be welded with three sealing Ji rings 8;The top of the pipe well 10 is less than the absolute altitude of bottom cushion 9, the upper pipes well head outside of pipe well 10 It is provided with the center superposition of an artificial diameter the picked out circular groove 13 bigger than pipe well 10, circular groove 13 and pipe well 10, the bottom of circular groove 13 Less than the top of pipe well 10, circular groove 13 is interior and the top surface of circular groove 13 is mixed between the top surface of base plate 12 using the waterproof consistent with base plate 12 Coagulate native 11 one-piece casting.The new pre-buried deformation joint anti-seepage structure design of the pipe well borehole wall is succinct, by setting various waterproof constructions, Can effectively prevent underground water from seepage occurring, material therefor is common construction material, construction costs can be made further to be reduced, There is larger economic benefit.
Circular groove 13 described in a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention may be configured as diameter and compare pipe well The 10 big 600mm of diameter, bottom surface is away from the bottom surface 400mm of bottom cushion 9.
The lower end of steel sleeve 1 described in a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention and the upper end of pipe well 10 The lap of splice may be configured as 1000mm.
Three positions of sealing Ji ring 8 can be set described in a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention It is located at respectively at the upper surface 150mm of base plate 12, at the lower surface 150mm of base plate 12 and apart from the bottom land 150mm of circular groove 13 Place.
The thickness of sealing Ji ring 8 may be configured as described in a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention 6mm, width may be configured as 150mm.
The distance from top pipe well of coarse sand recharge layer 5 described in a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention 10 top surfaces may be configured as 2000mm, and high grade fast hardening concrete pours the upper surface of layer 6 and may be configured as 100mm away from the top surface of base plate 12.
The thickness of steel deck-plate 4 may be configured as 6mm described in a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention.
Above-mentioned is that the new pre-buried deformation joint anti-seepage structure material therefor of the pipe well borehole wall is carried out preferably, to reach more preferably Waterproof effect.
As shown in Fig. 2 a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, the construction method includes Following steps:
When step one, earth excavation to 9 absolute altitude of bottom cushion, manually a diameter is picked out along the periphery of pipe well 10 more straight than pipe well The big circular groove 13 in footpath, pipe well 10 and the center superposition of circular groove 13, block pipe well 10 at the bottom of circular groove 13 up 100mm;
Step 2, past pipe well 10 are inserted into the diameter steel sleeve 1 more smaller than the internal diameter of pipe well 10, and the top of steel sleeve 1 is higher by Plate top surface 500mm, lower end and the pipe well 10 of steel sleeve 1 are overlapped, and the lap of splice is 1000mm;In the outside flax silk of steel sleeve 1 The mud 3 that adds water is connected with the upper end of pipe well 10, and the upper pipes outer wellhead of pipe well 10 is closed with the cement mortar 2 mixed with waterproofing agent, in steel sleeve 1 Three sealing Ji rings 8 are welded between outside top and the top of pipe well 10.
Step 3, using the water-proof concrete 11 consistent with base plate 12 by circular groove 13 and the one-piece casting of base plate 12.
When step 4, shut-in well, steel sleeve 1 is cut off at 100mm under the top surface of base plate 12, apart from the top surface 2000mm of pipe well 10 Following pipe well section uses coarse sand recharge, is then poured onto below plate top surface at 100mm with high grade fast hardening concrete again, is welded with thickness It is the steel deck-plate 4 of 6mm, weld seam is full, is finally poured to the top surface of base plate 12 with slightly expanded concrete and flushed.
A kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the invention described above, work progress operation letter Single, construction quality is easier to be guaranteed, and is that can effectively prevent basement bottom board waterproof construction from the construction technique of seepage occur, With very strong practicality, the features such as it has process is simple, cheap, excellent performance, in rich water deep basal pit basement tool There is very strong applicability.
Setting in step one described in a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention The diameter 600mm bigger than the diameter of pipe well 10 of circular groove 13 is put, depth is 400mm.
Three are stopped in step 2 described in a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention The position of water Ji ring 8 is settable be located at respectively at the upper surface 150mm of base plate 12, at the lower surface 150mm of base plate 12 and At the bottom land 150mm of circular groove 13.
Three are stopped in step 2 described in a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention The thickness of water Ji ring 8 may be configured as 6mm, and width may be configured as 150mm.
Steel deck-plate 4 in step 4 described in a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall of the present invention Thickness may be configured as 6mm.
Above-mentioned is that material therefor is carried out preferably in construction method to the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, More preferable waterproof effect can be reached.
Presently preferred embodiments of the present invention is these are only, but protection scope of the present invention is not limited thereto, it is any to be familiar with sheet Those skilled in the art the invention discloses technical scope in, the change or replacement that can be readily occurred in should all be covered Within protection scope of the present invention.Therefore, the protection domain that protection scope of the present invention should be defined by claim is defined.

Claims (10)

1. a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, including pipe well (10), steel sleeve (1), base plate (12) and bottom Plate bed course (9), it is characterised in that:The diameter of the steel sleeve (1) is slightly less than the diameter of pipe well (10), steel sleeve (1) lower end position In pipe well (10) upper end inner side, steel sleeve (1) lower end outside flax silk mud (3) that adds water is connected with pipe well (10) upper end, pipe well (10) closed with the cement mortar (2) mixed with waterproofing agent at upper pipes well head;The lower end of the pipe well (10) is coarse sand recharge layer (5), the top of coarse sand recharge layer (5) is high grade fast hardening concrete pouring layer (6), and high grade fast hardening concrete pours layer (6) Upper end flushed with steel sleeve (1);The top of the steel sleeve (1) is less than base plate (12), is welded at the mouth of pipe of steel sleeve (1) upper end There is steel deck-plate (4), slightly expanded concrete sealing layer (7), slightly expanded concrete sealing layer (7) have been poured above steel deck-plate (4) Flushed with base plate (12) top surface, steel sleeve (1) outside is located between steel deck-plate (4) and pipe well (10) top and is welded with three sealings Ji Huan (8);Pipe well (10) top is less than bottom cushion (9) absolute altitude, and the upper pipes well head outside of pipe well (10) is provided with a people The center superposition of the diameter that work the is picked out circular groove (13) bigger than pipe well (10), circular groove (13) and pipe well (10), the bottom of circular groove (13) Less than the top of pipe well (10), circular groove (13) is interior and circular groove (13) top surface is used and base plate (12) between base plate (12) top surface in portion Consistent water-proof concrete (11) one-piece casting.
2. a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall according to claim 1, it is characterised in that:The circular groove (13), than the big 600mm of diameter of pipe well (10), circular groove (13) bottom surface is away from bottom cushion (9) bottom surface 400mm for diameter.
3. a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall according to claim 1, it is characterised in that:The steel bushing Pipe (1) lower end is 1000mm with the lap of splice of pipe well (10) upper end.
4. a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall according to claim 1, it is characterised in that:Described three The position of sealing Ji ring (8) is located at base plate (12) upper surface 150mm, at base plate (12) lower surface 150mm respectively With at circular groove (13) bottom land 150mm.
5. a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall according to claim 1, it is characterised in that:The sealing The thickness of Ji Huan (8) is 6mm, and width is 150mm, and the thickness of the steel deck-plate (4) is 6mm.
6. a kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall according to claim 1, it is characterised in that:The coarse sand The top 2000mm of the distance from top pipe well (10) of recharge layer (5), high grade fast hardening concrete pours layer (6) upper surface away from base plate (12) top surface 100mm.
7. a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall, it is characterised in that:The construction method includes Following steps:
When step one, earth excavation to bottom cushion (9) absolute altitude, a diameter is manually picked out along pipe well (10) periphery more straight than pipe well The big circular groove in footpath (13), pipe well (10) and circular groove (13) center superposition, by pipe well (10) at circular groove (13) bottom up 100mm Block;
Step 2, past pipe well (10) are inserted into the diameter steel sleeve (1) more smaller than pipe well (10) internal diameter, the top of steel sleeve (1) Plate top surface 500mm is higher by, lower end and the pipe well (10) of steel sleeve (1) are overlapped, and the lap of splice is 1000mm;In steel sleeve (1) The flax silk mud (3) that adds water in outside is connected with pipe well (10) upper end, pipe well (10) cement of upper pipes outer wellhead mixed with waterproofing agent Slurry (2) closing, three sealing Jis ring (8) are welded between steel sleeve (1) outside top and pipe well (10) top;
Step 3, using the water-proof concrete (11) consistent with base plate (10) by circular groove (13) and base plate (12) one-piece casting;
When step 4, shut-in well, steel sleeve (1) is cut off at 100mm under base plate (12) top surface, apart from pipe well (10) top surface Below 2000mm pipe wells section uses coarse sand recharge, is then poured onto below plate top surface at 100mm with high grade fast hardening concrete again, plus Weldering thickness is the steel deck-plate (4) of 6mm, and weld seam is full, is finally poured to base plate (12) top surface with slightly expanded concrete and flushed.
8. a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall according to claim 8, its feature exists In:Than the big 600mm of diameter of pipe well (10), depth is 400mm to the diameter of the circular groove (13) in the step one.
9. a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall according to claim 8, its feature exists In:Three positions of sealing Ji ring (8) are located at base plate (12) upper surface 150mm, the bottom of apart from respectively in the step 2 At plate (12) lower surface 150mm and at circular groove (13) bottom land 150mm.
10. a kind of construction method of the new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall according to claim 8, its feature exists In:Three thickness of sealing Ji ring (8) are 6mm in the step 2, and width is 150mm, steel deck-plate (4) in the step 4 Thickness is 6mm.
CN201710101731.9A 2017-02-24 2017-02-24 A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method Pending CN106836251A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710101731.9A CN106836251A (en) 2017-02-24 2017-02-24 A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710101731.9A CN106836251A (en) 2017-02-24 2017-02-24 A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method

Publications (1)

Publication Number Publication Date
CN106836251A true CN106836251A (en) 2017-06-13

Family

ID=59133457

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710101731.9A Pending CN106836251A (en) 2017-02-24 2017-02-24 A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method

Country Status (1)

Country Link
CN (1) CN106836251A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111021425A (en) * 2019-12-05 2020-04-17 中冶天工集团天津有限公司 Seepage-proofing construction method for deformation joint of underground pipe gallery

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08109651A (en) * 1994-10-11 1996-04-30 Meisho Giken:Kk Cut-off method of deep well in building work
JP2006265964A (en) * 2005-03-24 2006-10-05 Shimizu Corp Drainage treatment method
CN202124865U (en) * 2011-06-22 2012-01-25 南通海洲建设集团有限公司 Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN103526766A (en) * 2013-10-12 2014-01-22 中建八局第三建设有限公司 Method for plugging relief well of deep foundation pit
CN204080836U (en) * 2014-09-10 2015-01-07 中国建筑第六工程局有限公司 The fast plugging device of dewatering well in a kind of building basement
CN105951859A (en) * 2016-05-31 2016-09-21 中国冶集团有限公司 Treatment method of plugging water stop construction for foundation pit dewatering well to penetrate through concrete base plate of basement

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08109651A (en) * 1994-10-11 1996-04-30 Meisho Giken:Kk Cut-off method of deep well in building work
JP2006265964A (en) * 2005-03-24 2006-10-05 Shimizu Corp Drainage treatment method
CN202124865U (en) * 2011-06-22 2012-01-25 南通海洲建设集团有限公司 Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN103526766A (en) * 2013-10-12 2014-01-22 中建八局第三建设有限公司 Method for plugging relief well of deep foundation pit
CN204080836U (en) * 2014-09-10 2015-01-07 中国建筑第六工程局有限公司 The fast plugging device of dewatering well in a kind of building basement
CN105951859A (en) * 2016-05-31 2016-09-21 中国冶集团有限公司 Treatment method of plugging water stop construction for foundation pit dewatering well to penetrate through concrete base plate of basement

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111021425A (en) * 2019-12-05 2020-04-17 中冶天工集团天津有限公司 Seepage-proofing construction method for deformation joint of underground pipe gallery
CN111021425B (en) * 2019-12-05 2021-11-16 中冶天工集团天津有限公司 Seepage-proofing construction method for deformation joint of underground pipe gallery

Similar Documents

Publication Publication Date Title
CN204343312U (en) A kind of plugging device of precipitation well in foundation pit
CN105178344B (en) The construction method of the built-in anti-float anchor rod plugging structure of sole plate precipitation of deep well
CN202124865U (en) Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN102797266B (en) Well sealing waterproof construction method for dewatering well
CN101614020B (en) Flexible bladder type anticorrosion device, anticorrosion pile and construction method using same
CN206706791U (en) Base pit dewatering well plugging structure
CN103924978B (en) The construction method of freeze-wellboring inner layer well wall
CN104947700B (en) A kind of shut-in well method of dewatering well
CN104988915B (en) A kind of prefabricated installation method of detachable steel casing and under water connection beam
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN209339169U (en) A kind of precipitation well in foundation pit plugging device
CN106522252A (en) Seepage-proofing blocking mechanism and method for deep foundation pit raft dewatering well
CN108755723A (en) A kind of removable dewatering well well mouth sealing device and slip casting plugging construction method
CN104818713A (en) Profile steel cement soil pile construction method adaptive to various stratums
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN202730786U (en) Well-sealing waterproof construction structure of dewatering well
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN207862925U (en) A kind of slip casting casing device
CN110344448A (en) A kind of blocking method of the deep hole perfusion grouting material of basement bottom board large-scale water leakage
CN214245694U (en) Pile forming system for large-diameter cast-in-situ bored pile in karst area
CN203768925U (en) Seal device for dewatering well in foundation pit
CN212129150U (en) Deep basal pit precipitation well block structure
CN212506349U (en) Water-logging well sealing device for water-lowering zone of ultra-deep foundation pit pipe well
CN106089245A (en) A kind of delay grouting method after single shield TBM wall
CN108360542A (en) Waterproof between piles curtain combination stake side sleeve valve barrel grouting water stop construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170613