CN106827193A CN201710253801.2A CN201710253801A CN106827193A CN 106827193 A CN106827193 A CN 106827193A CN 201710253801 A CN201710253801 A CN 201710253801A CN 106827193 A CN106827193 A CN 106827193A
Authority
CN
China
Prior art keywords
box culvert
mould
internal model
door pillar
support door
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710253801.2A
Other languages
Chinese (zh)
Other versions
CN106827193B (en
Inventor
徐延庆
李冀龙
牟惠跃
荣文婷
牛根根
王本亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongxin Road & Bridge Material Co Ltd
Original Assignee
Zhongxin Road & Bridge Material Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongxin Road & Bridge Material Co Ltd filed Critical Zhongxin Road & Bridge Material Co Ltd
Priority to CN201710253801.2A priority Critical patent/CN106827193B/en
Publication of CN106827193A publication Critical patent/CN106827193A/en
Application granted granted Critical
Publication of CN106827193B publication Critical patent/CN106827193B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/02Moulds with adjustable parts specially for modifying at will the dimensions or form of the moulded article
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/04Producing shaped prefabricated articles from the material by tamping or ramming
    • B28B1/045Producing shaped prefabricated articles from the material by tamping or ramming combined with vibrating or jolting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/093Producing shaped prefabricated articles from the material by vibrating or jolting by means directly acting on the material, e.g. by cores wholly or partly immersed in the material or elements acting on the upper surface of the material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/02Feeding the unshaped material to moulds or apparatus for producing shaped articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/04Discharging the shaped articles
    • B28B13/06Removing the shaped articles from moulds
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B17/00Details of, or accessories for, apparatus for shaping the material; Auxiliary measures taken in connection with such shaping
    • B28B17/0063Control arrangements
    • B28B17/0072Product control or inspection
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/12Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed to form prestressed circumferential reinforcements

Landscapes

  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Structural Engineering (AREA)
  • Moulds, Cores, Or Mandrels (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

Multiple box culvert makes mould, belongs to box and duct works technical field, and the present invention makes difficult to solve existing box culvert and multiple box culvert, long construction period, cost of manufacture problem high.First internal model plate supporting device, the second internal model plate supporting device and the 3rd internal model plate supporting device are successively set on box culvert base plate from left to right, two row sub-trusses are installed on the box culvert base plate of the first internal model plate supporting device and the 3rd internal model plate supporting device both sides, sub-truss is oppositely arranged and parallel, and every group of two upper ends of sub-truss being oppositely arranged are connected by connecting rod;Exterior sheathing is mounted on the inside of two row sub-trusses, the two ends of exterior sheathing are provided with end-blocking template.Multiple box culvert of the invention makes mould energy in-situ precast assembling, and recycling realizes that inner mold is supported automatically, after box culvert completes, inner mold automatic demoulding, and running to next station carries out box culvert making.

Description

Multiple box culvert makes mould and the method for producing box culvert using three hole box culvert moulds
Technical field
The present invention relates to a kind of box culvert mould and the preparation method of box culvert, and in particular to a kind of multiple box culvert make mould and The method that mould produces box culvert is made using multiple box culvert, belongs to box and duct works technical field.
Background technology
Pipe gallery, is exactly underground urban duct synthesis corridor, is made up of concrete box culvert.One is built in Urban Underground Individual tunnel space, by electric power, communication, the various utilities pipelines such as combustion gas, heat supply, plumbing are integrated in one, and are provided with special maintenance Mouth, hoisting port and monitoring system, implement unified planning, Uniting, unified construction and manage, and are the important of guarantee city operations Infrastructure and " lifeline ".The making pattern of the main body box culvert of current pipe gallery is mainly cast in situs formula, and scene is poured Formula concrete box culvert is built in manufacturing process, it is necessary to first gone out with a large amount of wooden or steel template splicings the outside of required box culvert with Interior shape, is commonly called as exterior sheathing and inner template, then fixes exterior sheathing and inner template by various supports and fixing device, makes Inner template and exterior sheathing form a firm structure, finally carry out concreting, cause cast in situs formula concrete box culvert Construction period is long, and the assembling of inner template and exterior sheathing is fixed difficult cumbersome, complete to be also needed to after box culvert makes to remove inner and outer template, Support and fixing device, and template after is easily damaged in demolishing process, it is impossible to it is continuing with, causes very big Waste, and also need to move to next box culvert making place after template and support and fixing device dismounting;Therefore need big The workmen of amount participates in construction, and construction cost is high, and efficiency is low, and construction safety has hidden danger, and quality is not readily available guarantee, especially It is that, when holes or multiple box culvert is made, the exposure of above drawback is obvious.Accordingly, it would be desirable to it is a kind of convenient and swift, tear easy to assembly open, The method that inner template automatic demoulding and moveable multiple box culvert are made mould and box culvert is produced using multiple box culvert mould.
The content of the invention
The method for making mould it is an object of the invention to provide multiple box culvert and box culvert being produced using multiple box culvert mould, with Solve existing box culvert and multiple box culvert makes difficult, long construction period, cost of manufacture problem high.
The multiple box culvert makes mould including in the first internal model plate supporting device, the second internal model plate supporting device, the 3rd Mould plate supporting device, sub-truss, exterior sheathing and end-blocking template;
The first internal model plate supporting device, the second internal model plate supporting device and the 3rd internal model plate supporting device are from left to right It is successively set on box culvert base plate, pacifies on the box culvert base plate of the first internal model plate supporting device and the 3rd internal model plate supporting device both sides Equipped with two row sub-trusses, sub-truss is oppositely arranged and parallel, and the upper end of every group of two sub-trusses being oppositely arranged passes through Connecting rod is connected;Exterior sheathing is mounted on the inside of two row sub-trusses, the two ends of exterior sheathing are provided with end-blocking template.
Preferably:First internal model plate supporting device includes first base, the first support door pillar, the first track girder, the first top Template back beam, the first supporting mechanism, first hydraulic cylinder, the first side template back beam, the first top template, the first side template, on first Cornea, first time cornea and second hydraulic cylinder,
Second internal model plate supporting device includes second base, the second support door pillar, the second track girder, the second backform backboard Beam, the second supporting mechanism, the 3rd hydraulic cylinder, the second side template back beam, the second top template, the second side template, cornea, on second Two times corneas and the 4th hydraulic cylinder,
3rd internal model plate supporting device includes the 3rd base, the 3rd support door pillar, the 3rd track girder, the 3rd backform backboard Beam, the 3rd supporting mechanism, the 5th hydraulic cylinder, the 3rd side template back beam, the 3rd top template, the 3rd side template, cornea, on the 3rd Three times corneas and the 6th hydraulic cylinder;
Described two first track girders be arranged in parallel, and the bottom of each the first track girder is provided with multiple rail wheels, rail wheel On rail;Two the first track girders are connected by multiple first bases, and first is provided with two neighboring first base Support door pillar, the first support door pillar is oppositely arranged and parallel, and every group of two first support door pillars being oppositely arranged are provided with two First top template back beam, the first top template is provided with two the first top template back beams;The outside of each the first support door pillar is equal Two the first side template back beams are provided with, the first side template is installed on the outside of two the first side template back beams;Each first side form The upper end of backboard beam is connected by the first supporting mechanism with the outer upper end of the first support door pillar, and lower end passes through the first liquid Cylinder pressure is connected with the outside lower end of the first support door pillar;The two ends of the first top template are respectively by cornea and two on two first Individual first side template is connected, and the lower end of each the first side template is mounted on first time cornea, the bottom of each first time cornea End is connected by second hydraulic cylinder with the first side template back beam lower end;
Described two second track girders be arranged in parallel, and the bottom of each the second track girder is provided with multiple rail wheels, rail wheel On rail;Two the second track girders are connected by multiple second bases, and second is provided with two neighboring second base Support door pillar, the second support door pillar is oppositely arranged and parallel, and every group of two second support door pillars being oppositely arranged are provided with two Second top template back beam, the second top template is provided with two the second top template back beams;The outside of each the second support door pillar is equal Two the second side template back beams are provided with, the second side template is installed on the outside of two the second side template back beams;Each second side form The upper end of backboard beam is connected by the second supporting mechanism with the outer upper end of the second support door pillar, and lower end passes through the 3rd liquid Cylinder pressure is connected with the outside lower end of the second support door pillar;The two ends of the second top template are respectively by cornea and two on two second Individual second side template is connected, and the lower end of each the second side template is mounted on second time cornea, the bottom of each second time cornea End is connected by the 4th hydraulic cylinder with the second side template back beam lower end;
Described two 3rd track girders be arranged in parallel, and the bottom of each the 3rd track girder is provided with multiple rail wheels, rail wheel On rail;Two the 3rd track girders are connected by multiple 3rd bases, and the 3rd is provided with two neighboring 3rd base Support door pillar, the 3rd support door pillar is respectively positioned on same axis, and each the 3rd support door pillar is provided with two the 3rd backform backboards Beam, the 3rd top template is provided with two the 3rd top template back beams;The upper end both sides of each the 3rd support door pillar pass through two respectively Individual 3rd supporting mechanism is connected with the upper end of two the 3rd side template back beams, the lower end both sides difference of each the 3rd support door pillar It is connected with the lower end of two the 3rd side template back beams by two the 5th hydraulic cylinders, two outside peaces of the 3rd side template back beam Equipped with the 3rd side template;The two ends of the 3rd top template are connected by cornea on two the 3rd with two the 3rd side templates respectively, The lower end of each the 3rd side template is mounted on the three times corneas, each the three times bottom of cornea by the 6th hydraulic cylinder with 3rd side template back beam lower end is connected.
Preferably:Two the first poles and two the second poles, first are equipped with the inside of each second support door pillar The two ends of bar are connected with the second support door pillar and the second top template back beam respectively;The two ends of the second pole support with second respectively Door pillar is connected with second base.
Preferably:First supporting mechanism is made up of two screw thread poles, sleeve pipe and two screw thread pole sockets, two screw thread poles The two ends of sleeve pipe are separately mounted to, the free end of each screw thread pole is connected with screw thread pole socket.
Preferably:Second supporting mechanism and the 3rd supporting mechanism are identical with the composition structure of the first supporting mechanism.
The method that mould produces multiple box culvert is made using multiple box culvert, it is characterised in that comprise the following steps,
Step one, box culvert foot mat concrete construction:The position of box culvert foot mat is determined using theodolite, and assembles box culvert Template required for foot mat, then carries out concreting, while ensureing box culvert foot mat using spirit level, laser leveling machine The flatness and slope requirement of concrete;
Step 2, the construction of box culvert underplate concrete:The position of box culvert base plate is determined using theodolite, and assembles box culvert base plate Required template, then carries out concreting, while ensureing box culvert underplate concrete using spirit level, laser leveling machine Flatness and slope requirement;
Step 3, mould preassembling:It is pre-splicing that construction speed according to box culvert underplate concrete carries out mould simultaneously in factory Dress, the internal model of box culvert, external mold, end mould are completed by the way of preassembling, and size can be adjusted according to actual requirement of engineering, During assembly, all of connection member all uses high strength exploitation to mould, and stitching portion ensures mould by alignment pin Tool precision;
Step 4, box culvert steel reinforcement cage is prefabricated:Using reinforced mesh welding machine in factory prefabricated mesh sheet, mesh sheet transport to construction Onsite application mesh sheet bender according to the bending of steel reinforcement cage design size, be assembled into suitable steel reinforcement cage;
Step 5, mould, the construction of precast reinforced cage position line:After the completion of concrete bottom cushion construction, using high-accuracy water The instruments such as quasi- instrument, theodolite, according to the position unwrapping wire of mould requirement;
Step 6, precast reinforced cage is in place:Live bending, the reinforcing bar cage hoisting being completed is in place, and in steel reinforcement cage It is lower that the thickness that concrete pad ensures protective layer is installed;
Step 7, internal model track installation:Installation level, the adjustable track support means of height, then attachment rail, Last track leveling, track support means use PVC sleeve pipes, reusable;
Step 8, internal model is installed:The pre-splicing mould for installing is assembled on track, the internal model for having assembled is received in the demoulding Contracting state, then internal model steel reinforcement cage is sailed into by hoist engine or hauling machine, using hydraulic jack by internal model jack-up, and be adjusted to State is poured, is split again after the completion of whole project after once assembling, whole internal model can be realized using driving or haulage gear It is quick mobile;
Step 9, external mold, end module dress:The pre-splicing external mold for installing is installed on truss, with the pre-splicing end mould for installing, Inside and outside mould is assembled integrally, formation can pour mould state, and overall precision is carried out to mould and detected and calibrate, and specified Position is installed by concrete strength inspection instrument;
Step 10, concreting:Concreting is carried out after mould calibration, internal vibration rod is utilized after the completion of pouring Coordinate wall-mounted vibrator to vibrate concrete, Curing Method is then determined for steam curing according to engineering project progress or Natural Health preservation;
Step 11, concrete strength inspection and form removal:Reality is carried out to concrete strength by concrete strength inspection instrument When detect, the intensity of overall box culvert carries out form removal after reaching requirement, and internal model overall shrinkage sails to next into demoulding states in parallel Station, external mold transports directly to next station with end mould according to modularization, is capable of achieving the quick assembling of mould, entirely constructs Journey, mould only need to it is pre-assembled once, until construction terminate, mould split into can transportation module, be put into warehouse after being maintained.
The present invention has the following effects that compared with existing product:The box culvert die assembly for realizing semi-automation and dismounting, subtract Lack substantial amounts of artificial, shortened the fabrication cycle of box culvert, integrated engineering efficiency of construction has been significantly improved, and mould is integrally customized, and is protected Demonstrate,proved the making precision and quality of box culvert, mould assembling once can Reusability, it is single after dismounting until box culvert production process completes Solely storage, the next engineering of preparation is continued with, die width, height, length, wall thickness dimension can modularization regulation, meet various Automation is realized in the application of engineering project, reinforced mesh welding, Bending Processing, the fabrication of reinforcing cage amount of a set of equipment equivalent to 200 outputs of experienced operator, high efficiency, high-quality, low cost, box culvert main body one-time-concreting shaping is secondary without carrying out Pour, product quality can more be guaranteed, interior external mold is once assembled, can at the construction field (site) realize quick mobile, assembling, Lifting Modules The turnaround speed of tool, accelerates the completion speed of engineering, and concrete strength inspection uses flush type detection means, can rapidly obtain mixed Solidifying soil strength information, reaches the intensity demoulding immediately, reduces because the time that detection is caused not in time wastes.
Brief description of the drawings
Fig. 1 is the structural representation that multiple box culvert of the present invention makes mould;
Fig. 2 is the A-A sectional views of Fig. 1;
Fig. 3 is the B-B sectional views of Fig. 2;
Fig. 4 is the first supporting mechanism structural representation.
In figure:The first internal models of 1- plate supporting device, the second internal models of 2- plate supporting device, the internal model plate supporting devices of 3- the 3rd, 4- sub-trusses, 5- exterior sheathings, 6- end-blockings template, 7- first bases, the supports of 8- first door pillar, the track girders of 9- first, 10- first Top template back beam, the supporting mechanisms of 11- first, 12- first hydraulic cylinders, the first side templates of 13- back beam, the 14, first top template, 15- Cornea, 18- second hydraulic cylinders, 19- second bases, the supports of 20- second door pillar, the rails of 21- second on first side template, 16- first Road beam, the second top templates of 22- back beam, the supporting mechanisms of 23- second, the hydraulic cylinders of 24- the 3rd, the second side templates of 25- back beam, 26- Cornea on two top templates, the side templates of 27- second, 28- second, second time cornea of 29-, the hydraulic cylinders of 30- the 4th, the bases of 31- the 3rd, The supports of 32- the 3rd door pillar, the track girders of 33- the 3rd, the top template back beams of 34- the 3rd, the supporting mechanisms of 35- the 3rd, the hydraulic pressure of 36- the 5th Cornea on cylinder, the side template back beams of 37- the 3rd, the top templates of 38- the 3rd, the side templates of 39- the 3rd, 40- the 3rd, the three times corneas of 41-, The hydraulic cylinders of 42- the 6th, 43- connecting rods, 44- box culverts base plate, the poles of 45- first, the poles of 46- second, 47- screw threads pole, 48- sets Pipe, 49- screw threads pole socket, 50- box culvert foot mats.
Specific embodiment
The preferred embodiment of the present invention is elaborated below according to accompanying drawing.
As shown in Figures 1 to 4, multiple box culvert of the present invention makes mould includes the first internal model plate supporting device 1, the Two internal model plate supporting devices 2, the 3rd internal model plate supporting device 3, sub-truss 4, exterior sheathing 5 and end-blocking template 6;
The first internal model plate supporting device 1, the second internal model plate supporting device 2 and the 3rd internal model plate supporting device 3 are from a left side It is successively set on box culvert base plate 44 to the right side, box culvert base plate 44 has box culvert foot mat 50, the He of the first internal model plate supporting device 1 Two row sub-trusses 4 are installed on the box culvert base plate 44 of the both sides of the 3rd internal model plate supporting device 3, sub-truss 4 be oppositely arranged and Parallel, every group of two upper ends of sub-truss 4 being oppositely arranged are connected by connecting rod 43;Pacify the inner side of two row sub-trusses 4 Equipped with exterior sheathing 5, the two ends of exterior sheathing 5 are provided with end-blocking template 6.First internal model plate supporting device 1, the second inner template support dress Put 2 and the 3rd internal model plate supporting device 3 assembling finish after can be moved on rail by hoist engine or hauling machine.
Preferably:First internal model plate supporting device 1 includes the support of first base 7, first door pillar 8, the first track girder 9, the One top template back beam 10, the first supporting mechanism 11, first hydraulic cylinder 12, the first side template back beam 13, the first top template 14, first Cornea 16, first time cornea 17 and second hydraulic cylinder 18 on side template 15, first;
Second internal model plate supporting device 2 includes the support of second base 19, second door pillar 20, the second track girder 21, the second top Template back beam 22, the second supporting mechanism 23, the 3rd hydraulic cylinder 24, the second side template back beam 25, the second top template 26, the second side form Cornea 28, second time hydraulic cylinder 30 of cornea 29 and the 4th on plate 27, second;
3rd internal model plate supporting device 3 includes the support of the 3rd base the 31, the 3rd door pillar 32, the 3rd track girder 33, the 3rd top Template back beam 34, the 3rd supporting mechanism 35, the 5th hydraulic cylinder 36, the 3rd side template back beam 37, the 3rd top template 38, the 3rd side form Cornea 40, the three times hydraulic cylinders 42 of cornea 41 and the 6th on plate the 39, the 3rd;
Described two first track girders 9 be arranged in parallel, and the bottom of each the first track girder 9 is provided with multiple rail wheels, track Wheel is located on rail;Two the first track girders 9 are connected by multiple first bases 7, are provided with two neighboring first base 7 First support door pillar 8, the first support door pillar 8 is oppositely arranged and parallel, is set on every group of two first support door pillars 8 being oppositely arranged There are two the first top template back beams 10, first top template 14 is installed in two the first top template back beams 10;Each first support The outside of door pillar 8 is equipped with two the first side template back beams 13, and the outside of two the first side template back beams 13 is provided with the first side Template 15;On outside of the upper end of each the first side template back beam 13 by the first supporting mechanism 11 and the first support door pillar 8 End is connected, and lower end is connected by first hydraulic cylinder 12 with the outside lower end of the first support door pillar 8;First top template 14 Two ends are connected by cornea 16 on two first with two the first side templates 15 respectively, and the lower end of each the first side template 15 is equal First time cornea 17 is installed, the bottom of each first time cornea 17 passes through the side template back beam 13 of second hydraulic cylinder 18 and first Lower end is connected;
Described two second track girders 21 be arranged in parallel, and the bottom of each the second track girder 21 is provided with multiple rail wheels, rail Road wheel is located on rail;Two the second track girders 21 are connected by multiple second bases 19, in two neighboring second base 19 Second support door pillar 20 is installed, the second support door pillar 20 is oppositely arranged and parallel, every group of two second supports being oppositely arranged Door pillar 20 is provided with two the second top template back beams 22, and the second top template 26 is provided with two the second top template back beams 22;Often The outside of individual second support door pillar 20 is equipped with two the second side template back beams 25, two outside peaces of the second side template back beam 25 Equipped with the second side template 27;The upper end of each the second side template back beam 25 is by the second supporting mechanism 23 and the second support door pillar 20 outer upper end is connected, and lower end is connected by the 3rd hydraulic cylinder 24 with the outside lower end of the second support door pillar 20;The The two ends of two top templates 26 are connected by cornea 28 on two second with two the second side templates 27 respectively, each second side form The lower end of plate 27 is mounted on second time cornea 29, and the bottom of each second time cornea 29 passes through the 4th hydraulic cylinder 30 and second The lower end of side template back beam 25 is connected;
Described two 3rd track girders 33 be arranged in parallel, and the bottom of each the 3rd track girder 33 is provided with multiple rail wheels, rail Road wheel is located on rail;Two the 3rd track girders 33 are connected by multiple 3rd bases 31, on two neighboring 3rd base 31 3rd support door pillar 32 is installed, the 3rd support door pillar 32 is respectively positioned on same axis, each the 3rd support door pillar 32 is provided with Two the 3rd top template back beams 34, the 3rd top template 38 is provided with two the 3rd top template back beams 34;Each the 3rd support door The upper end both sides of post 32 are connected by two the 3rd supporting mechanisms 35 with the upper end of two the 3rd side template back beams 37 respectively, often The lower end both sides of individual 3rd support door pillar 32 are respectively by under two the 5th hydraulic cylinders 36 and two the 3rd side template back beams 37 End is connected, and the outside of two the 3rd side template back beams 37 is provided with the 3rd side template 39;The two ends difference of the 3rd top template 38 It is connected with two the 3rd side templates 39 by cornea 40 on two the 3rd, the lower end of each the 3rd side template 39 is mounted on Three times corneas 41, each the three times bottom of cornea 41 are connected by the 6th hydraulic cylinder 42 with the lower end of the 3rd side template back beam 37 Connect.
Preferably:The inner side of each the second support door pillar 20 is equipped with two the first poles 45 and two the second poles 46, The two ends of the first pole 45 are connected with the second support top template back beam 22 of door pillar 20 and second respectively;The two ends of the second pole 46 It is connected with the second support door pillar 20 and second base 19 respectively.
Preferably:First supporting mechanism 11 is made up of two screw thread poles 47, sleeve pipe 48 and two screw thread pole sockets 49, two Screw thread pole 47 is separately mounted to the two ends of sleeve pipe 48, and the free end of each screw thread pole 47 is connected with screw thread pole socket 49.
Preferably:Second supporting mechanism 23 and the 3rd supporting mechanism 35 are identical with the composition structure of the first supporting mechanism 11; First supporting mechanism 11, the second supporting mechanism 23 and the 3rd supporting mechanism 35 can be replaced hydraulic cylinder support.
The method that mould produces multiple box culvert is made using multiple box culvert, it is characterised in that comprise the following steps,
Step one, box culvert foot mat concrete construction:The position of box culvert foot mat is determined using theodolite, and assembles box culvert Template required for foot mat, then carries out concreting, while ensureing box culvert foot mat using spirit level, laser leveling machine The flatness and slope requirement of concrete;
Step 2, the construction of box culvert underplate concrete:The position of box culvert base plate is determined using theodolite, and assembles box culvert base plate Required template, then carries out concreting, while ensureing box culvert underplate concrete using spirit level, laser leveling machine Flatness and slope requirement;
Step 3, mould preassembling:It is pre-splicing that construction speed according to box culvert underplate concrete carries out mould simultaneously in factory Dress, the internal model of box culvert, external mold, end mould are completed by the way of preassembling, and size can be adjusted according to actual requirement of engineering, During assembly, all of connection member all uses high strength exploitation to mould, and stitching portion ensures mould by alignment pin Tool precision;
Step 4, box culvert steel reinforcement cage is prefabricated:Using reinforced mesh welding machine in factory prefabricated mesh sheet, mesh sheet transport to construction Onsite application mesh sheet bender according to the bending of steel reinforcement cage design size, be assembled into suitable steel reinforcement cage;
Step 5, mould, the construction of precast reinforced cage position line:After the completion of concrete bottom cushion construction, using high-accuracy water The instruments such as quasi- instrument, theodolite, according to the position unwrapping wire of mould requirement;
Step 6, precast reinforced cage is in place:Live bending, the reinforcing bar cage hoisting being completed is in place, and in steel reinforcement cage It is lower that the thickness that concrete pad ensures protective layer is installed;
Step 7, internal model track installation:Installation level, the adjustable track support means of height, then attachment rail, Last track leveling, track support means use PVC sleeve pipes, reusable;
Step 8, internal model is installed:The pre-splicing mould for installing is assembled on track, the internal model for having assembled is received in the demoulding Contracting state, then internal model steel reinforcement cage is sailed into by hoist engine or hauling machine, using hydraulic jack by internal model jack-up, and be adjusted to State is poured, is split again after the completion of whole project after once assembling, whole internal model can be realized using driving or haulage gear It is quick mobile;
Step 9, external mold, end module dress:The pre-splicing external mold for installing is installed on truss, with the pre-splicing end mould for installing, Inside and outside mould is assembled integrally, formation can pour mould state, and overall precision is carried out to mould and detected and calibrate, and specified Position is installed by concrete strength inspection instrument;
Step 10, concreting:Concreting is carried out after mould calibration, internal vibration rod is utilized after the completion of pouring Coordinate wall-mounted vibrator to vibrate concrete, Curing Method is then determined for steam curing according to engineering project progress or Natural Health preservation;
Step 11, concrete strength inspection and form removal:Reality is carried out to concrete strength by concrete strength inspection instrument When detect, the intensity of overall box culvert carries out form removal after reaching requirement, and internal model overall shrinkage sails to next into demoulding states in parallel Station, external mold transports directly to next station with end mould according to modularization, is capable of achieving the quick assembling of mould, entirely constructs Journey, mould only need to it is pre-assembled once, until construction terminate, mould split into can transportation module, be put into warehouse after being maintained.
Present embodiment is the exemplary illustration to this patent, does not limit its protection domain, people in the art Member can also be changed to its part, as long as no the Spirit Essence beyond this patent, all in the protection domain of this patent.

Claims (6)

1. multiple box culvert makes mould, it is characterised in that:Including the first internal model plate supporting device (1), the second inner template support dress Put (2), the 3rd internal model plate supporting device (3), sub-truss (4), exterior sheathing (5) and end-blocking template (6);
The first internal model plate supporting device (1), the second internal model plate supporting device (2) and the 3rd internal model plate supporting device (3) from Left-to-right is successively set on box culvert base plate (44), the first internal model plate supporting device (1) and the 3rd internal model plate supporting device (3) two Two row sub-trusses (4) are installed, sub-truss (4) is oppositely arranged and parallel on the box culvert base plate (44) of side, every group sets relatively Two upper ends of sub-truss (4) put are connected by connecting rod (43);Exterior sheathing is mounted on the inside of two row sub-trusses (4) (5), the two ends of exterior sheathing (5) are provided with end-blocking template (6).
2. multiple box culvert according to claim 1 makes mould, it is characterised in that:First internal model plate supporting device (1) is wrapped Include first base (7), the first support door pillar (8), the first track girder (9), the first top template back beam (10), the first supporting mechanism (11), first hydraulic cylinder (12), the first side template back beam (13), the first top template (14), the first side template (15), angle on first Film (16), first time cornea (17) and second hydraulic cylinder (18),
Second internal model plate supporting device (2) includes second base (19), the second support door pillar (20), the second track girder (21), the Two top template back beams (22), the second supporting mechanism (23), the 3rd hydraulic cylinder (24), the second side template back beam (25), the second backform Plate (26), the second side template (27), cornea (28), second time cornea (29) and the 4th hydraulic cylinder (30) on second,
3rd internal model plate supporting device (3) includes the 3rd base (31), the 3rd support door pillar (32), the 3rd track girder (33), the Three top template back beams (34), the 3rd supporting mechanism (35), the 5th hydraulic cylinder (36), the 3rd side template back beam (37), the 3rd backform Plate (38), the 3rd side template (39), cornea (40), the three times corneas (41) and the 6th hydraulic cylinder (42) on the 3rd;
Described two first track girders (9) be arranged in parallel, and the bottom of each the first track girder (9) is provided with multiple rail wheels, track Wheel is located on rail;Two the first track girders (9) are connected by multiple first bases (7), on two neighboring first base (7) First support door pillar (8) is installed, the first support door pillar (8) is oppositely arranged and parallel, every group of two first for being oppositely arranged Support door pillar (8) is provided with two the first top template back beams (10), and the first backform is provided with two the first top template back beams (10) Plate (14);Two the first side template back beams (13), two the first side form backboards are equipped with the outside of each first support door pillar (8) First side template (15) is installed on the outside of beam (13);The upper end of each the first side template back beam (13) is by the first support machine Structure (11) is connected with the outer upper end of the first support door pillar (8), and lower end is by first hydraulic cylinder (12) and the first support door The outside lower end of post (8) is connected;The two ends of the first top template (14) respectively by cornea (16) on two first with two the One side template (15) is connected, and the lower end of each the first side template (15) is mounted on first time cornea (17), and each is under first The bottom of cornea (17) is connected by second hydraulic cylinder (18) with first side template back beam (13) lower end;
Described two second track girders (21) be arranged in parallel, and the bottom of each the second track girder (21) is provided with multiple rail wheels, rail Road wheel is located on rail;Two the second track girders (21) are connected by multiple second bases (19), two neighboring second base (19) the second support door pillar (20) is installed, the second support door pillar (20) is oppositely arranged and parallel, every group of two for being oppositely arranged on Individual second support door pillar (20) is provided with two the second top template back beams (22), is provided with two the second top template back beams (22) Second top template (26);It is equipped with two the second side template back beams (25) on the outside of each second support door pillar (20), two the The second side template (27) is installed on the outside of two side template back beams (25);The upper end of each the second side template back beam (25) passes through Second supporting mechanism (23) with second support door pillar (20) outer upper end be connected, lower end by the 3rd hydraulic cylinder (24) with The outside lower end of the second support door pillar (20) is connected;The two ends of the second top template (26) are respectively by cornea on two second (28) it is connected with two the second side templates (27), the lower end of each the second side template (27) is mounted on second time cornea (29), the bottom of each second time cornea (29) is connected by the 4th hydraulic cylinder (30) with second side template back beam (25) lower end Connect;
Described two 3rd track girders (33) be arranged in parallel, and the bottom of each the 3rd track girder (33) is provided with multiple rail wheels, rail Road wheel is located on rail;Two the 3rd track girders (33) are connected by multiple 3rd bases (31), two neighboring 3rd base (31) the 3rd support door pillar (32) is installed, the 3rd support door pillar (32) is respectively positioned on same axis on, each the 3rd support door Post (32) is provided with two the 3rd top template back beams (34), and the 3rd top template is provided with two the 3rd top template back beams (34) (38);The upper end both sides of each the 3rd support door pillar (32) are respectively by two the 3rd supporting mechanisms (35) and two the 3rd side forms The upper end of backboard beam (37) is connected, and the lower end both sides of each the 3rd support door pillar (32) pass through two the 5th hydraulic cylinders respectively (36) lower end with two the 3rd side template back beams (37) is connected, and is provided with the outside of two the 3rd side template back beams (37) Three side templates (39);The two ends of the 3rd top template (38) are respectively by cornea (40) on two the 3rd and two the 3rd side templates (39) it is connected, the lower end of each the 3rd side template (39) is mounted on the three times corneas (41), each the three times cornea (41) Bottom be connected with the 3rd side template back beam (37) lower end by the 6th hydraulic cylinder (42).
3. multiple box culvert according to claim 2 makes mould, it is characterised in that:Each second support door pillar (20) it is interior Side is equipped with two the first poles (45) and two the second poles (46), and the two ends of the first pole (45) support door with second respectively Post (20) is connected with the second top template back beam (22);The two ends of the second pole (46) respectively with the second support door pillar (20) and the Two bases (19) are connected.
4. multiple box culvert according to claim 2 makes mould, it is characterised in that:First supporting mechanism (11) is by two spiral shells Line pole (47), sleeve pipe (48) and two screw thread pole socket (49) compositions, two screw thread poles (47) are separately mounted to sleeve pipe (48) Two ends, the free end of each screw thread pole (47) is connected with screw thread pole socket (49).
5. multiple box culvert according to claim 4 makes mould, it is characterised in that:Second supporting mechanism (23) and the 3rd Support mechanism (35) is identical with the composition structure of the first supporting mechanism (11).
6. the method that mould produces multiple box culvert is made using multiple box culvert, it is characterised in that comprise the following steps,
Step one, box culvert foot mat concrete construction:The position of box culvert foot mat is determined using theodolite, and assembles box culvert heelpiece Template required for layer, then carries out concreting, while ensureing box culvert foot mat coagulation using spirit level, laser leveling machine The flatness and slope requirement of soil;
Step 2, the construction of box culvert underplate concrete:The position of box culvert base plate is determined using theodolite, and needed for assembling box culvert base plate The template wanted, then carries out concreting, while ensureing the smooth of box culvert underplate concrete using spirit level, laser leveling machine Degree and slope requirement;
Step 3, mould preassembling:Construction speed according to box culvert underplate concrete carries out mould preassembling, case simultaneously in factory The internal model of culvert, external mold, end mould are completed by the way of preassembling, and size can be adjusted according to actual requirement of engineering, mould During assembly, all of connection member all uses high strength exploitation, and stitching portion ensures mould essence by alignment pin Degree;
Step 4, box culvert steel reinforcement cage is prefabricated:Using reinforced mesh welding machine in factory prefabricated mesh sheet, mesh sheet transport is to job site Using mesh sheet bender according to the bending of steel reinforcement cage design size, be assembled into suitable steel reinforcement cage;
Step 5, mould, the construction of precast reinforced cage position line:After the completion of concrete bottom cushion construction, using high-precision level, The instruments such as theodolite, according to the position unwrapping wire of mould requirement;
Step 6, precast reinforced cage is in place:Live bending, the reinforcing bar cage hoisting being completed is in place, and pacify under steel reinforcement cage Dress concrete pad ensures the thickness of protective layer;
Step 7, internal model track installation:Installation level, the adjustable track support means of height, then attachment rail, finally Track leveling, track support means use PVC sleeve pipes, reusable;
Step 8, internal model is installed:The pre-splicing mould for installing is assembled on track, it is contraction-like that the internal model for having assembled is in the demoulding State, then internal model steel reinforcement cage is sailed into by hoist engine or hauling machine, using hydraulic jack by internal model jack-up, and be adjusted to pour State, is split again after once assembling after the completion of whole project, and whole internal model can be realized quickly using driving or haulage gear It is mobile;
Step 9, external mold, end module dress:The pre-splicing external mold for installing is installed on truss, with the pre-splicing end mould for installing, by External mold is assembled integrally, and formation can pour mould state, and carries out overall precision to mould and detect and calibrate, and in specified location Concrete strength inspection instrument is installed;
Step 10, concreting:Concreting is carried out after mould calibration, is coordinated using internal vibration rod after the completion of pouring Wall-mounted vibrator vibrates to concrete, then determines that Curing Method is steam curing or nature according to engineering project progress Health;
Step 11, concrete strength inspection and form removal:Concrete strength is examined in real time by concrete strength inspection instrument Survey, the intensity of overall box culvert carries out form removal after reaching requirement, and internal model overall shrinkage sails to next station into demoulding states in parallel, External mold transports directly to next station with end mould according to modularization, is capable of achieving the quick assembling of mould, whole work progress, mould Tool only need to it is pre-assembled once, until construction terminate, mould split into can transportation module, be put into warehouse after being maintained.
CN201710253801.2A 2017-04-18 2017-04-18 Multiple box culvert makes mold and the method using three hole box culvert molds production box culvert Active CN106827193B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710253801.2A CN106827193B (en) 2017-04-18 2017-04-18 Multiple box culvert makes mold and the method using three hole box culvert molds production box culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710253801.2A CN106827193B (en) 2017-04-18 2017-04-18 Multiple box culvert makes mold and the method using three hole box culvert molds production box culvert

Publications (2)

Publication Number Publication Date
CN106827193A true CN106827193A (en) 2017-06-13
CN106827193B CN106827193B (en) 2019-03-01

Family

ID=59146915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710253801.2A Active CN106827193B (en) 2017-04-18 2017-04-18 Multiple box culvert makes mold and the method using three hole box culvert molds production box culvert

Country Status (1)

Country Link
CN (1) CN106827193B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108472777A (en) * 2018-03-30 2018-08-31 深圳市君盈建筑科技有限公司 Migration formula steel bar meter method
CN109203221A (en) * 2018-09-14 2019-01-15 中铁四局集团第四工程有限公司 A kind of piping lane tube coupling method for prefabricating
WO2021051429A1 (en) * 2019-09-16 2021-03-25 长沙远大住宅工业集团股份有限公司 Die assembly for producing prefabricated parts and production method
CN113320001A (en) * 2021-06-01 2021-08-31 台州学院 Assembly turnover type beam making pedestal and use method thereof
CN114683375A (en) * 2022-03-31 2022-07-01 北京港创瑞博混凝土有限公司 Box culvert template and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101885206A (en) * 2010-07-02 2010-11-17 中铁四局集团第四工程有限公司 Hydraulic internal mold truss type walking track system of high speed railway prefabricating box girder
CN202428530U (en) * 2011-12-16 2012-09-12 北京联东投资(集团)有限公司 Segment hydraulic internal mold device capable of adjusting size
CN203765763U (en) * 2014-02-11 2014-08-13 中铁二十三局集团第八工程有限公司 Expressway prefabricated small box girder formwork set
CN105365042A (en) * 2015-09-25 2016-03-02 佛山路桥预制构件有限公司 Manufacturing method of small prefabricated box girder
CN205711786U (en) * 2016-03-18 2016-11-23 杭州江润科技有限公司 Big cross section porous overlength cast-in-place box culvert formwork system
CN206678146U (en) * 2017-04-18 2017-11-28 黑龙江省中信路桥材料有限公司 Multiple box culvert makes mould

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101885206A (en) * 2010-07-02 2010-11-17 中铁四局集团第四工程有限公司 Hydraulic internal mold truss type walking track system of high speed railway prefabricating box girder
CN202428530U (en) * 2011-12-16 2012-09-12 北京联东投资(集团)有限公司 Segment hydraulic internal mold device capable of adjusting size
CN203765763U (en) * 2014-02-11 2014-08-13 中铁二十三局集团第八工程有限公司 Expressway prefabricated small box girder formwork set
CN105365042A (en) * 2015-09-25 2016-03-02 佛山路桥预制构件有限公司 Manufacturing method of small prefabricated box girder
CN205711786U (en) * 2016-03-18 2016-11-23 杭州江润科技有限公司 Big cross section porous overlength cast-in-place box culvert formwork system
CN206678146U (en) * 2017-04-18 2017-11-28 黑龙江省中信路桥材料有限公司 Multiple box culvert makes mould

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108472777A (en) * 2018-03-30 2018-08-31 深圳市君盈建筑科技有限公司 Migration formula steel bar meter method
WO2019183948A1 (en) * 2018-03-30 2019-10-03 深圳市君盈建筑科技有限公司 Method for preparing movable steel bar
CN109203221A (en) * 2018-09-14 2019-01-15 中铁四局集团第四工程有限公司 A kind of piping lane tube coupling method for prefabricating
WO2021051429A1 (en) * 2019-09-16 2021-03-25 长沙远大住宅工业集团股份有限公司 Die assembly for producing prefabricated parts and production method
CN113320001A (en) * 2021-06-01 2021-08-31 台州学院 Assembly turnover type beam making pedestal and use method thereof
CN114683375A (en) * 2022-03-31 2022-07-01 北京港创瑞博混凝土有限公司 Box culvert template and construction method thereof
CN114683375B (en) * 2022-03-31 2023-08-08 北京港创瑞博混凝土有限公司 Box culvert template and construction method thereof

Also Published As

Publication number Publication date
CN106827193B (en) 2019-03-01

Similar Documents

Publication Publication Date Title
CN106827193B (en) Multiple box culvert makes mold and the method using three hole box culvert molds production box culvert
CN102943565B (en) Construction method of large-sized arc-shaped wall
CN112060307B (en) Segment box girder short line matching control and prefabricating construction method
CN106436578A (en) Constructing method and constructing device for cantilever sectional beam with specially-shaped cross section through short-line matching method
CN109487814A (en) Cast-in-place piping lane integrated moveable formwork jumbo construction method
CN108556121A (en) The Modularized vertical steel die and its operating method of prefabricated pipe gallery
CN104234079A (en) Subway station Y-shaped cast steel combining steel pipe post processing and construction method
CN107326930A (en) A kind of live rapidform machine of Urban Underground pipe gallery and its method of work
CN109736204A (en) A kind of precast of segmental beam by short line method construction technology
CN104727226A (en) Construction method for steel-concrete composite girder
KR100924701B1 (en) Construction method for Utility-pipe conduit
CN107460889A (en) Integral movable type rack template and its construction method in underground pipe gallery construction
CN103233424A (en) Hanging-basket-method support-free anti-collision wall construction method, construction hanging basket and template for construction
CN103374923A (en) Method for prefabricating and mounting underwater pier
CN109972655A (en) A kind of prefabricated piping lane machinery and Combined hydraulic type, which are integrally pacified, tears steel form and installation method open
CN105926672A (en) Mined metro station steel pipe column construction method
CN107653900A (en) A kind of preparation method of Prefabricated pipe gallery
CN203174510U (en) Movable assembly type hanging basket for bridge anti-collision guardrail construction and formwork for construction
CN107575023A (en) A kind of sliding formwork component and apply its caisson cutting edge layer slding form operation method
CN206678146U (en) Multiple box culvert makes mould
CN113021603A (en) Construction method for prefabricated assembled diamond type bent cap
CN109112903A (en) Solid concrete roabed trackless construction technology is cheated in a kind of phase library inner column formula inspection
CN105040731A (en) Assembled integral type reinforced concrete underground comprehensive pipe gallery and production mold thereof
CN108978699B (en) Land integral prefabricated bearing platform and production and installation method thereof
CN117027859A (en) Tunnel lining double-trolley combined device and integral pouring construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant