CN106760135A - A kind of furred ceiling hanger erection method - Google Patents

A kind of furred ceiling hanger erection method Download PDF

Info

Publication number
CN106760135A
CN106760135A CN201710102892.XA CN201710102892A CN106760135A CN 106760135 A CN106760135 A CN 106760135A CN 201710102892 A CN201710102892 A CN 201710102892A CN 106760135 A CN106760135 A CN 106760135A
Authority
CN
China
Prior art keywords
suspension rod
hanger erection
row
hanger
erection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710102892.XA
Other languages
Chinese (zh)
Inventor
赵家贵
刘祖国
唐世敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710102892.XA priority Critical patent/CN106760135A/en
Publication of CN106760135A publication Critical patent/CN106760135A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of furred ceiling hanger erection method, belong to furred ceiling suspension rod technical field.Step of the invention is:Step one:Make suspension rod special implement:Cutting 10mm Hexagonal jackets wide in side are welded on square steel tube, square wood strip end is then attached to;Step 2:Survey sets hanger erection datum line in length and breadth:Surveyed on ceiling and set hanger erection datum line in length and breadth, with line of ink marker mark hanger erection position, need to be qualified through checking;Step 3:The drilling of first row suspension rod, borehole cleaning;Step 4:First row suspension rod is installed:In the band expanding screw suspension rod insertion hanger erection specific purpose tool hole of first end, in the suspension rod insertion mounting hole that will be installed, expansion bolt nut on suspension rod is tightened by row, then unload hanger erection specific purpose tool.The method convenient and reliable operation, standardized construction, energy-conservation reduces hand labor intensity, has saved cost, improves hanger erection quality and effect, shortens the hanger erection construction period.

Description

A kind of furred ceiling hanger erection method
Technical field
The present invention relates to furred ceiling suspension rod technical field, more specifically to a kind of furred ceiling hanger erection method.
Background technology
At present, large area furred ceiling hanger erection method to ceiling furred ceiling installation effects higher such as Conference Hall, indoor aisle not Substantially, it is uneconomical, it is necessary to set up full hall scaffold or tool type scaffold, easily occur suspension rod anchoring loosely, loosen, there is shadow Ring construction safety, quality, progress hidden danger.
The content of the invention
1. the invention technical problem to be solved
For the shortcomings and deficiencies that prior art is present, the invention provides a kind of furred ceiling hanger erection method, operation side Just reliable, standardized construction, energy-conservation reduces hand labor intensity, has saved cost, improves hanger erection quality and effect, Shorten the hanger erection construction period.
2. technical scheme
To reach above-mentioned purpose, the technical scheme that the present invention is provided is:
A kind of furred ceiling hanger erection method of the invention, its step is:
Step one:Make suspension rod special implement:Cutting 10mm Hexagonal jackets wide in side are welded on square steel tube, weld seam Height 3mm, is then attached to square wood strip end;
Step 2:Survey sets hanger erection datum line in length and breadth:Surveyed on ceiling and set hanger erection datum line in length and breadth, use line of ink marker mark Know hanger erection position, need to be qualified through checking;
Step 3:The drilling of first row suspension rod, borehole cleaning:The suspension rod determined according to decoration drawing and scheme using electric boring machine Position and depth carry out first row suspension rod drilling, are by row purged totally dust in hole using compressed air after pore-forming;
Step 4:First row suspension rod is installed:In the band expanding screw suspension rod insertion hanger erection specific purpose tool hole of first end, In the suspension rod insertion mounting hole that will be installed, expansion bolt nut on suspension rod is tightened by row, then unload hanger erection specific purpose tool, Other each row's ceiling hanger erections are carried out by that analogy.
3. beneficial effect
The technical scheme provided using the present invention, compared with prior art, is had the advantages that:
Convenient and reliable operation of the present invention, standardized construction, energy-conservation reduces hand labor intensity, has saved cost, improves Hanger erection quality and effect, shorten the hanger erection construction period.
Specific embodiment
With reference to embodiment, the invention will be further described:
Embodiment 1
A kind of furred ceiling hanger erection method of the present embodiment, its step is:
Step one:Make suspension rod special implement:Cutting 10mm Hexagonal jackets wide in side are welded on square steel tube, weld seam Height 3mm, is then attached to square wood strip end;
Step 2:Survey sets hanger erection datum line in length and breadth:Surveyed on ceiling and set hanger erection datum line in length and breadth, use line of ink marker mark Know hanger erection position, need to be qualified through checking;
Step 3:The drilling of first row suspension rod, borehole cleaning:The suspension rod determined according to decoration drawing and scheme using electric boring machine Position and depth carry out first row suspension rod drilling, are by row purged totally dust in hole using compressed air after pore-forming;
Step 4:First row suspension rod is installed:In the band expanding screw suspension rod insertion hanger erection specific purpose tool hole of first end, In the suspension rod insertion mounting hole that will be installed, expansion bolt nut on suspension rod is tightened by row, then unload hanger erection specific purpose tool, Other each row's ceiling hanger erections are carried out by that analogy.
A kind of furred ceiling hanger erection method of the present embodiment, convenient and reliable operation, standardized construction, energy-conservation reduces people Work labour intensity, has saved cost, improves hanger erection quality and effect, shortens the hanger erection construction period.
Schematical above that the present invention and embodiments thereof are described, the description does not have restricted, actual side Method is not limited thereto.So, if one of ordinary skill in the art is enlightened by it, do not departing from the invention objective In the case of, frame mode and the embodiment similar to the technical scheme being designed without creative, all should belong to of the invention Protection domain.

Claims (1)

1. a kind of furred ceiling hanger erection method, it is characterised in that:Its step is:
Step one:Make suspension rod special implement:Cutting 10mm Hexagonal jackets wide in side are welded on square steel tube, weld bead height 3mm, is then attached to square wood strip end;
Step 2:Survey sets hanger erection datum line in length and breadth:Surveyed on ceiling and set hanger erection datum line in length and breadth, hung with line of ink marker mark Bar mounting arrangements position, need to be qualified through checking;
Step 3:The drilling of first row suspension rod, borehole cleaning:Arranged according to the suspension rod that decoration drawing and scheme determine using electric boring machine Position and depth carry out first row suspension rod drilling, are by row purged totally dust in hole using compressed air after pore-forming;
Step 4:First row suspension rod is installed:In the band expanding screw suspension rod insertion hanger erection specific purpose tool hole of first end, will fill In good suspension rod insertion mounting hole, expansion bolt nut on suspension rod is tightened by row, hanger erection specific purpose tool is then unloaded, with this Analogizing carries out other each row's ceiling hanger erections.
CN201710102892.XA 2017-02-24 2017-02-24 A kind of furred ceiling hanger erection method Pending CN106760135A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710102892.XA CN106760135A (en) 2017-02-24 2017-02-24 A kind of furred ceiling hanger erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710102892.XA CN106760135A (en) 2017-02-24 2017-02-24 A kind of furred ceiling hanger erection method

Publications (1)

Publication Number Publication Date
CN106760135A true CN106760135A (en) 2017-05-31

Family

ID=58960448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710102892.XA Pending CN106760135A (en) 2017-02-24 2017-02-24 A kind of furred ceiling hanger erection method

Country Status (1)

Country Link
CN (1) CN106760135A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202416664U (en) * 2011-11-28 2012-09-05 中国华冶科工集团有限公司 Tool for installing suspender in construction of suspended ceiling
CN102661031A (en) * 2012-05-18 2012-09-12 中建一局集团第三建筑有限公司 Simple and easy tool for mounting bracket hanging rod of roof and application method thereof
KR20140065799A (en) * 2012-11-22 2014-05-30 현대중공업 주식회사 Zig for mounting ceiling panel of cabin
CN205976389U (en) * 2016-08-17 2017-02-22 陕西建工集团有限公司 Hanger rod installation tool

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202416664U (en) * 2011-11-28 2012-09-05 中国华冶科工集团有限公司 Tool for installing suspender in construction of suspended ceiling
CN102661031A (en) * 2012-05-18 2012-09-12 中建一局集团第三建筑有限公司 Simple and easy tool for mounting bracket hanging rod of roof and application method thereof
KR20140065799A (en) * 2012-11-22 2014-05-30 현대중공업 주식회사 Zig for mounting ceiling panel of cabin
CN205976389U (en) * 2016-08-17 2017-02-22 陕西建工集团有限公司 Hanger rod installation tool

Similar Documents

Publication Publication Date Title
CN201292587Y (en) Combined stone curtain wall connecting piece for high-rise building
CN105507539A (en) Light external wall point-hang heat-insulation and decorative plate combined anchoring system and method for constructing same
CN110984446A (en) Efficient curtain wall installation method
CN104060704A (en) Mechanical repairing method and structure for hollowing of thermal insulation mortar of outer wall
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN105370315B (en) A kind of frost zone tunnel drainage construction technology
CN204295000U (en) A kind of ceiling suspended ceiling hangs muscle drilling equipment
CN205362751U (en) Processing frock suitable for coupling hole
CN106761846A (en) A kind of grid steel frame for tunnel just branch construction exempts to weld pin-connected panel supporting construction
CN106760135A (en) A kind of furred ceiling hanger erection method
CN104234361A (en) Assembling method of facade stones
CN207436424U (en) A kind of decoration panel cladding system
CN106836577B (en) A kind of method of building stone curtain wall dried hanging
CN106812233A (en) A kind of construction method of building abnormity wall decorative curtain wall
CN214462463U (en) Combined type wall connecting piece for erecting external scaffold of shear wall
CN212358610U (en) Mounting structure of top surface spherical net rack
CN204876448U (en) Two back ofs body of stone material are tied two expanding and are tied integration steel pendant
CN103628602A (en) Building curtain wall glass fiber reinforcement composite board mounting assembly and method
CN210059892U (en) Drilling auxiliary device of chassis girder
CN204876450U (en) Stone material back of body is tied two expanding of hook and is tied integration aluminum alloy pendant
CN206408784U (en) New and old wall joint connecting device
CN104907980A (en) Device and method for tightening ceiling rib expansion bolt
CN213308912U (en) Hollow brick wall fixing part
CN206632937U (en) A kind of top plate nut locking apparatus
CN105298144B (en) High-rise glass curtain wall interlayer fireproof partition construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531