CN105370315B - A kind of frost zone tunnel drainage construction technology - Google Patents

A kind of frost zone tunnel drainage construction technology Download PDF

Info

Publication number
CN105370315B
CN105370315B CN201510904655.6A CN201510904655A CN105370315B CN 105370315 B CN105370315 B CN 105370315B CN 201510904655 A CN201510904655 A CN 201510904655A CN 105370315 B CN105370315 B CN 105370315B
Authority
CN
China
Prior art keywords
concrete
splash guard
waterstop
construction
construction technology
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510904655.6A
Other languages
Chinese (zh)
Other versions
CN105370315A (en
Inventor
苏春生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201510904655.6A priority Critical patent/CN105370315B/en
Publication of CN105370315A publication Critical patent/CN105370315A/en
Application granted granted Critical
Publication of CN105370315B publication Critical patent/CN105370315B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of frost zone tunnel drainage construction technologies, include the following steps:(1)Surveying and locating;(2)Longitudinal drainage pipe, transverse drain, ring direction drainpipe are installed;(3)Modify the concrete surface of scar and preliminary bracing;(4)Splash guard is installed;(5)Blocking plate and waterstop are installed.Construction technology of the present invention is simple, and construction equipment is few, and the construction period is short, has directive function to the guarded drainage construction in frozen ground regions tunnel.

Description

A kind of frost zone tunnel drainage construction technology
Technical field
The invention belongs to highway construction technology fields, more particularly to refer to a kind of frost zone tunnel drainage construction work Skill.
Background technology
In recent years, although China achieves many achievements in terms of tunnel construction, progress is achieved on tunnel water handling, But there is also many problems to varying degrees for tunnel water handling, and great challenges are constituted to safe driving.Waterproof and Drainage Construction of Tunnel It is the key that ensure that tunnel is smoothly built up, it haves laid a good foundation for works waterproofing work;Carry out structure guarded drainage work Journey is the important prerequisite for ensureing tunnel normal operation.For this purpose, highway road owner pays much attention to, it is based on this, studies and develops Devise a kind of frost zone tunnel water proofing construction technology.
Invention content
It is an object of the invention to:A kind of frost zone tunnel drainage construction technology is provided, is frozen mainly for seasonality The guarded drainage construction of tunnel highway under soil area complex geological condition, and the working procedure is simple, construction equipment is few, the construction period It is short, there is directive function to the guarded drainage construction in extremely frigid zones tunnel.
What the present invention was achieved through the following technical solutions:A kind of frost zone tunnel drainage construction technology, including it is following Step:(1)Surveying and locating measures and releases tunnel center line, per 1 point of 5.0m, measures and releases longitudinal drainage pipe plan-position, often 1 point of 5m is used in combination spirit level to measure longitudinal drainage pipe tube bottom designed elevation, measures and releases short abutment wall sideline, per 1 point of 5m, is used in combination Spirit level measures short abutment wall top mark height, calculates short abutment wall top mark height according to trolley formwork, short abutment wall top mark height is in cable duct top 20cm;
(2)Longitudinal drainage pipe, transverse drain, ring direction drainpipe are installed, one per 10m of transverse drain is short pouring Transverse drain is supported by steel bracket when abutment wall, and transverse drain horizontal slope is 2%, and longitudinal row is determined according to transverse drain absolute altitude Longitudinal drainage pipe is fixed on the concrete band of wide 20cm by water pipe elevation, and longitudinal drainage pipe is laid along the full tunnel holing through in both sides corner, Transverse drain, longitudinal drainage pipe are connect with ring direction drainpipe by threeway, and junction uses non-woven wraps;
(3)The concrete surface for modifying scar and preliminary bracing, to concrete skin cut steel at preliminary bracing before installing splash guard Muscle head and anchor pole head are repaiied chisel to uneven position and are filled spray with mortar levelling;
(4)Splash guard is installed, both sides are symmetrically hung from top to bottom from vault when hanging up, and are bored with qi of chong channel ascending adversely by being tied up on waterproof material The spacing of band bores the deep 5-holes 10cm, has the wooden unit of thin wire to squeeze into hole on bolt in the early stage on supporting concrete, then steel wire with Bandage on splash guard is fixedly connected;
(5)Blocking plate and waterstop are installed.
Further, in order to preferably realize the present invention, the step(5)The installation method of middle waterstop is:5-1, root According to lining thickness, waterstop is placed among blocking plate, waterstop is located at lining cutting concrete center, every 70-90cm on blocking plate It is close to drill under waterstop;5-2, reinforcing bar card is penetrated by the one lateral other side of concrete to be built, the one of inside clamping waterstop Half, the other half of waterstop is contacted with blocking plate;5-3, blocking plate is removed after concrete setting, waterstop is stretched, is evened up, It is fastened on waterstop through bar bending.Construction joint is subjected to artificial chiseling processing before pouring concrete and is rinsed using high-pressure blast, then It carries out next plate two and serves as a contrast concrete placings.
Further, it in order to preferably realize the present invention, further limits, the step(2)Middle ring direction drainpipe construction Specific method be:Using detecting water by pilot hole geophysical prospecting, determines that face anteriorly descends moisture distribution situation, carry out pre-pouring grout envelope It is stifled.
Further, it in order to preferably realize the present invention, further limits, the step(2)Middle ring direction drainpipe construction Specific method be:Ring direction drainpipe uses spring drainpipe, leads to tunnel drainage ditch, encryption arrangement spring circle draining side by side Pipe, the effective reinforcing bar of circle draining are made circumferential snap ring and are fixed every 1m.
Further, it in order to preferably realize the present invention, further limits, the step(2)Middle ring direction drainpipe construction Specific method be:Scar is close to using drain bar, two pieces of suspension holdfasts of interval 50cm are set every 1m, and will using steel wire Drain bar is fixed.
Further, it in order to preferably realize the present invention, further limits, the step(2)Middle ring direction drainpipe construction Specific method be:Using installation splash guard processing.
Further, it in order to preferably realize the present invention, further limits, the step(4)The specific of splash guard is installed Step includes:Splash guard cuts out blanking, bond in hole or welding, seam inspection, be laid with rack in place, along the longitudinally disposed gas of vault Capsule is longitudinally laid with steel wire on rack, splash guard is laid on rack, rises supporting rack, airbag aeration, hangs and hold iron wire, phase Neighbour's cycle joint treatment falls supporting rack, deflation and takes out air bag, laying quality inspection.
Further, it in order to preferably realize the present invention, further limits, the specific method of the installation splash guard is: 4-1, it can be in close contact with preliminary bracing concrete under the extruding of perfusion concrete, the length of splash guard is than preliminary bracing concrete profile line length Spend big 5% -10%;4-2, using suitable Mobile workbench, from vault, both sides symmetrically hang splash guard from top to bottom, and qi of chong channel ascending adversely brill is pressed The spacing of waterproof material bandage bores the hole of deep 5-10m on supporting concrete in the early stage, has the wooden unit of finer wire to insert in the hole on bolt, so Steel wire and the bandage on splash guard are tightly fastened afterwards.
Compared with prior art, the present invention haing the following advantages and advantageous effect:
Construction technology of the present invention is simple, and construction equipment is few, and the construction period is short, to the guarded drainage in frozen ground regions tunnel Construction has directive function.
Description of the drawings
Fig. 1 is the construction flow chart of the present invention.
Specific implementation mode
The present invention is described in further detail with reference to embodiment, embodiments of the present invention are not limited thereto, Without departing from the idea case in the present invention described above, according to ordinary skill knowledge and customary means, various replace is made It changes and changes, should all be included within the scope of the invention.
Embodiment 1:
As shown in Figure 1, a kind of frost zone tunnel drainage construction technology, and the technique is primarily adapted for use in frost zone Vcehicular tunnel guarded drainage in tunnel is constructed under regional complex geological condition, which mainly includes the following steps that:
(1)Surveying and locating measures and releases tunnel center line, per 1 point of 5.0m, measures and releases longitudinal drainage pipe plan-position, Per 1 point of 5m, spirit level is used in combination to measure longitudinal drainage pipe tube bottom designed elevation, measures and release short abutment wall sideline, per 1 point of 5m, and Short abutment wall top mark height is measured with spirit level, short abutment wall top mark height is calculated according to trolley formwork, short abutment wall top mark height is in cable duct Push up 20cm;
(2)Longitudinal drainage pipe, transverse drain, ring direction drainpipe are installed, one per 10m of transverse drain is short pouring Transverse drain is supported by steel bracket when abutment wall, and transverse drain horizontal slope is 2%, and longitudinal row is determined according to transverse drain absolute altitude Longitudinal drainage pipe is fixed on the concrete band of wide 20cm by water pipe elevation, and longitudinal drainage pipe is laid along the full tunnel holing through in both sides corner, Transverse drain, longitudinal drainage pipe are connect with ring direction drainpipe by threeway, and junction uses non-woven wraps;
(3)The concrete surface for modifying scar and preliminary bracing, to concrete skin cut steel at preliminary bracing before installing splash guard Muscle head and anchor pole head are repaiied chisel to uneven position and are filled spray with mortar levelling;
(4)Splash guard is installed, splash guard should supporting in the early stage it is stable and be laid with after reporting management acceptance(check);
According to the material of plate when splash guard is hanged up, and ensure there is certain surplus capacity, hang up unsuitable tension, in squeezing for perfusion concrete Pressure can be closely connected with preliminary bracing concrete, the length of splash guard and the profile line length big 5% -10% of preliminary bracing concrete.
Splash guard is installed, using Mobile workbench, when installation, from vault, both sides are symmetrically hung from top to bottom, with qi of chong channel ascending adversely bore according to The spacing of bandage bores the hole of deep 5 ~ 10cm on supporting concrete in the early stage on waterproof material, and the wooden unit for fastening finer wire is squeezed into hole, Then the bandage on steel wire and splash guard is posted and is tied admittedly.Waterproof plate surface should smooth out, non-wrinkle, no disrepair phenomenon, and and hole Wall is closely connected, elastic appropriateness, and nothing tightens phenomenon.
The adjacent splash guard lap of splice is not less than 10cm, and the weld width of splash guard meets design specification requirement, when welding It is welded with special Hot welding.When splash guard breakage, repair welding is carried out using the same material more than damaged crack.Weld seam, benefit eye are answered It is closely knit full, must not there are bubble, gap.Repair welding is answered at solder skip, dry joint, if having at burned, burn-through, is welded using same splash guard Covering is handled by supervising engineer's instruction.
(5)Blocking plate and waterstop are installed.
Embodiment 2:
The present embodiment further limits on the basis of embodiment 1, the step(5)The installation method of middle waterstop is: 5-1, according to lining thickness, waterstop is placed among blocking plate, waterstop is located at lining cutting concrete center, is being kept off every 70-90cm It is close to drill under waterstop in head plate;5-2, reinforcing bar card is penetrated by the one lateral other side of concrete to be built, inside clamping sealing The half of band, the other half of waterstop are contacted with blocking plate;5-3, blocking plate is removed after concrete setting, waterstop is drawn Directly, it evens up, is fastened on waterstop through bar bending.Construction joint is subjected to artificial chiseling processing before pouring concrete and is rushed using high-pressure blast It washes, then carries out next plate two and serve as a contrast concrete placings.
Embodiment 3:
The present embodiment further limits on the basis of the above embodiments, the step(2)Middle ring direction drainpipe construction Specific method is:Using detecting water by pilot hole geophysical prospecting, determines that face anteriorly descends moisture distribution situation, carries out pre-pouring grout closure, The operating method seeps water mainly for water burst, gushing water section in tunnel, i.e., in tunnel when rainy season the water flush region of formation in a tubular form.
Embodiment 4:
The present embodiment further limits on the basis of the above embodiments, the step(2)Middle ring direction drainpipe construction Specific method is:Ring direction drainpipe uses spring drainpipe, leads to tunnel drainage ditch, encryption arrangement spring circle draining side by side Pipe, the effective reinforcing bar of circle draining are made circumferential snap ring and are fixed every 1m, and the operating method is mainly for water burst, gushing water in tunnel Section, i.e., the water flush region for formation of seeping water in a tubular form when rainy season in tunnel.
Embodiment 5:
The present embodiment further limits on the basis of the above embodiments, the step(2)Middle ring direction drainpipe construction Specific method is:Scar is close to using drain bar, two pieces of suspension holdfasts of interval 50cm are set every 1m, and will arrange using steel wire Water plate is fixed, the side by drain bar and splash guard combination processing which is taken mainly for location of dripping in tunnel Method.
Embodiment 6:
The present embodiment further limits on the basis of the above embodiments, the step(2)Middle ring direction drainpipe construction Specific method is:Using installation splash guard processing, the operating method mainly for the locations infiltration Shao Shui in tunnel, i.e., no matter rain Whether season, palisades drying is without underwater drop.
Embodiment 7:
The present embodiment further limits on the basis of the above embodiments, the step(4)The specific step of splash guard is installed Suddenly include:Splash guard cuts out blanking, bond in hole or welding, seam inspection, be laid with rack in place, along the longitudinally disposed gas of vault Capsule is longitudinally laid with steel wire on rack, splash guard is laid on rack, rises supporting rack, airbag aeration, hangs and hold iron wire, phase Neighbour's cycle joint treatment falls supporting rack, deflation and takes out air bag, laying quality inspection.
Embodiment 8:
The present embodiment further limits on the basis of the above embodiments, and the specific method of the installation splash guard is:4- 1, it can be in close contact with preliminary bracing concrete under the extruding of perfusion concrete, the length of splash guard is than preliminary bracing concrete profile line length Big 5% -10%;4-2, using suitable Mobile workbench, from vault, both sides symmetrically hang splash guard from top to bottom, and qi of chong channel ascending adversely is bored by anti- The spacing of water material bandage bores the hole of deep 5-10m on supporting concrete in the early stage, has the wooden unit of finer wire to insert in the hole on bolt, then Steel wire and the bandage on splash guard are tightly fastened.
The above is only presently preferred embodiments of the present invention, not does limitation in any form to the present invention, it is every according to According to the technical spirit of the present invention to any simple modification, equivalent variations made by above example, the protection of the present invention is each fallen within Within the scope of.

Claims (8)

1. a kind of frost zone tunnel drainage construction technology, which is characterized in that include the following steps,(1)Surveying and locating measures Tunnel center line is released, per 1 point of 5.0m, measures and releases longitudinal drainage pipe plan-position, per 1 point of 5m, spirit level is used in combination to measure Longitudinal drainage pipe tube bottom designed elevation measures and releases short abutment wall sideline, per 1 point of 5m, spirit level is used in combination to measure short abutment wall top mark Height calculates short abutment wall top mark height according to trolley formwork, and short abutment wall top mark height is in cable duct top 20cm;
(2)Longitudinal drainage pipe, transverse drain, ring direction drainpipe are installed, transverse drain together, is pouring short abutment wall per 10m When transverse drain supported by steel bracket, transverse drain horizontal slope be 2%, longitudinal drainage pipe is determined according to transverse drain absolute altitude Longitudinal drainage pipe is fixed on the concrete band of wide 20cm by elevation, and longitudinal drainage pipe is laid along the full tunnel holing through in both sides corner, laterally Drainpipe, longitudinal drainage pipe are connect with ring direction drainpipe by threeway, and junction uses non-woven wraps;
(3)The concrete surface for modifying scar and preliminary bracing, to concrete skin cut steel bar end at preliminary bracing before installing splash guard Chisel is repaiied to uneven position and is filled spray with mortar levelling with anchor pole head;
(4)Splash guard is installed, both sides are symmetrically hung from top to bottom from vault when hanging up, and are bored by bandage on waterproof material with qi of chong channel ascending adversely Spacing bores the deep 5-holes 10cm, has the wooden unit of thin wire to squeeze into hole on bolt, then steel wire and waterproof in the early stage on supporting concrete Bandage on plate is fixedly connected;
(5)Blocking plate and waterstop are installed.
2. a kind of frost zone tunnel drainage construction technology according to claim 1, it is characterised in that:The step (5)The installation method of middle waterstop is:5-1, according to lining thickness, waterstop is placed among blocking plate, waterstop be located at lining Concrete center is built, is close to drill under waterstop on blocking plate every 70-90cm;5-2, by reinforcing bar card by concrete side to be built It is penetrated to the other side, the half of inside clamping waterstop, the other half of waterstop is contacted with blocking plate;5-3, concrete setting is waited for After remove blocking plate, waterstop is stretched, is evened up, is fastened on waterstop through bar bending, by construction joint into pedestrian before pouring concrete Work dabbing handles and high-pressure blast is used to rinse, and then carries out next plate two and serves as a contrast concrete placings.
3. a kind of frost zone tunnel drainage construction technology according to claim 2, it is characterised in that:The step (2)The specific method of middle ring direction drainpipe construction is:Using detecting water by pilot hole geophysical prospecting, determine that face anteriorly descends moisture distribution Situation carries out pre-pouring grout closure.
4. a kind of frost zone tunnel drainage construction technology according to claim 2, it is characterised in that:The step (2)The specific method of middle ring direction drainpipe construction is:Ring direction drainpipe uses spring drainpipe, leads to tunnel drainage ditch side by side, Encryption arrangement spring ring direction drainpipe, the effective reinforcing bar of circle draining are made circumferential snap ring and are fixed every 1m.
5. a kind of frost zone tunnel drainage construction technology according to claim 2, it is characterised in that:
The step(2)The specific method of middle ring direction drainpipe construction is:Scar is close to using drain bar, is arranged every 1m and is spaced Two pieces of suspension holdfasts of 50cm, and fixed drain bar using steel wire.
6. a kind of frost zone tunnel drainage construction technology according to claim 2, it is characterised in that:The step (2)The specific method of middle ring direction drainpipe construction is:Using installation splash guard processing.
7. according to a kind of frost zone tunnel drainage construction technology of claim 3 to 6 any one of them, it is characterised in that: The step(4)Installation splash guard specific steps include:Splash guard cuts out blanking, bonds in hole or welding, seam inspection, spreads If rack is in place, is longitudinally laid with steel wire along the longitudinally disposed air bag of vault, on rack, splash guard is laid on rack, is risen Supporting rack, airbag aeration hang and hold iron wire, adjacent circulation joint treatment, fall supporting rack, deflation and take out air bag, laying quality It checks.
8. according to a kind of frost zone tunnel drainage construction technology of claim 3 to 6 any one of them, it is characterised in that: It is described installation splash guard specific method be:4-1, it can be in close contact with preliminary bracing concrete under the extruding of perfusion concrete, waterproof The length of plate is bigger by 5% -10% than preliminary bracing concrete profile line length;4-2, using suitable Mobile workbench, from top to bottom from vault Both sides symmetrically hang splash guard, and the hole for boring deep 5-10cm on supporting concrete in the early stage by the spacing of waterproof material bandage is bored in qi of chong channel ascending adversely, will Bolt has the wooden unit of finer wire to insert in the hole, and then steel wire and the bandage on splash guard are tightly fastened.
CN201510904655.6A 2015-12-09 2015-12-09 A kind of frost zone tunnel drainage construction technology Active CN105370315B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510904655.6A CN105370315B (en) 2015-12-09 2015-12-09 A kind of frost zone tunnel drainage construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510904655.6A CN105370315B (en) 2015-12-09 2015-12-09 A kind of frost zone tunnel drainage construction technology

Publications (2)

Publication Number Publication Date
CN105370315A CN105370315A (en) 2016-03-02
CN105370315B true CN105370315B (en) 2018-09-28

Family

ID=55372872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510904655.6A Active CN105370315B (en) 2015-12-09 2015-12-09 A kind of frost zone tunnel drainage construction technology

Country Status (1)

Country Link
CN (1) CN105370315B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106014478A (en) * 2016-05-30 2016-10-12 爱佩仪中测(成都)精密仪器有限公司 Cooling circulation system used for single-arm three-dimensional measurement scribing instrument
CN106385837A (en) * 2016-08-29 2017-02-15 山东胜伟园林科技有限公司 Drainage construction process for improvement of saline-alkali land
CN108222979B (en) * 2017-12-29 2019-11-22 中铁二局第一工程有限公司 Rich water karst waterproof and Drainage Construction of Tunnel method
CN108999635A (en) * 2018-08-14 2018-12-14 湖南科技大学 A kind of pilot drainage arrangement and construction method for the weak cementing roadway surrounding rock of rich water
CN113464202A (en) * 2021-07-22 2021-10-01 陕西聚博德新材料科技有限公司 Mounting process of tunnel drainage plate

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102678174A (en) * 2012-05-28 2012-09-19 中交第一公路勘察设计研究院有限公司 Tunnel drainage system passing through permafrost region and non-frozen ground region and arrangement method thereof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102678174A (en) * 2012-05-28 2012-09-19 中交第一公路勘察设计研究院有限公司 Tunnel drainage system passing through permafrost region and non-frozen ground region and arrangement method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
冻土隧道防排水浅探;罗定伦;《西部探矿工程》;20110831(第8期);第192-193,196页 *
浅谈季节性冻土隧道进口段防排水施工;黄鑫;《民营科技》;20120131(第1期);第271页 *

Also Published As

Publication number Publication date
CN105370315A (en) 2016-03-02

Similar Documents

Publication Publication Date Title
CN105370315B (en) A kind of frost zone tunnel drainage construction technology
CN104806272B (en) Tunnel shunting combined type guarded drainage integrated system and construction method and using method
CN204572015U (en) A kind of tunnel shunting combined type waterproof and water drainage system
CN110617083A (en) Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness
CN101906768B (en) Panel construction method of concrete faced rock-fill dam
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN102619522A (en) Construction method for subway contact passage
CN109931077B (en) Support system for tunnel repair and construction method thereof
CN106120801A (en) In water-rich sand layer, pipeline crosses the construction method at foundation ditch
CN102400470B (en) Multi-platform deep foundation construction method for slope high-rise building
CN107327308A (en) A kind of Railway Tunnel waterproof method
CN104912088A (en) Slope protection structure and construction method thereof
CN110863498A (en) Deep foundation pit combined supporting construction method next to subway station
CN106120872A (en) A kind of tower crane foundation is combined the construction method of antiseep with basement bottom board
CN108301440A (en) With waterproof, the underground pipe gallery construction method of drain function
CN110145364A (en) A kind of construction method of tunnel water handling structure
CN107100649A (en) A kind of construction technology for inclined shaft concreting
CN103758045B (en) Box girder wet joint formwork construction method under space limitation condition
CN113153379B (en) Tunnel waterproof and drainage system and construction process
CN102927364B (en) Reinforced concrete pipe installation method and clamp special for reinforced concrete pipe
CN108118689B (en) Prefabricated underground diaphragm wall capable of being partially recycled, lifting appliance and construction method
CN109989407A (en) Railway increases two wires platform way of escape foundation pile pipe curtain supporting construction newly
CN106948350B (en) The rapid constructing method of deep basal pit accessory structure
CN210216467U (en) Seepage-proofing structure without anchoring groove and anchoring platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant