CN106759450A - A kind of full cable outlet integral type GIS foundation arrangement - Google Patents

A kind of full cable outlet integral type GIS foundation arrangement Download PDF

Info

Publication number
CN106759450A
CN106759450A CN201611012080.8A CN201611012080A CN106759450A CN 106759450 A CN106759450 A CN 106759450A CN 201611012080 A CN201611012080 A CN 201611012080A CN 106759450 A CN106759450 A CN 106759450A
Authority
CN
China
Prior art keywords
gis
raft
foundation
ditch body
outlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611012080.8A
Other languages
Chinese (zh)
Inventor
沈青松
张振华
吴亮
黄达余
杨卫星
周志超
钱锋
盛晓红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Energy Source In China Construction Group Zhejiang Province Power Design Institute Co Ltd
Original Assignee
Energy Source In China Construction Group Zhejiang Province Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Energy Source In China Construction Group Zhejiang Province Power Design Institute Co Ltd filed Critical Energy Source In China Construction Group Zhejiang Province Power Design Institute Co Ltd
Priority to CN201611012080.8A priority Critical patent/CN106759450A/en
Publication of CN106759450A publication Critical patent/CN106759450A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/02Flat foundations without substantial excavation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of full cable outlet integral type GIS foundation arrangement, it is that GIS raft foundations are merged with outlet cable ditch body, described outlet cable ditch body is directly arranged in GIS outlets lower section, GIS raft foundations are zigzag, and the GIS raft foundations integrated poured construction together with outlet cable ditch body is formed;The top surface absolute altitude of the GIS raft foundations is in 0.20m and is embedded in underground, the 0.8m of GIS raft foundations thickness 0.6;Integral type raft foundation is adapted to subsoil and pile foundation raft foundation, and being made on GIS raft foundations has GIS foundation buttress;Width B1=1.5m, B2=0.5m of the outlet cable ditch body, depth H=2.0m, the outlet cable ditch body are open design or are arranged to tunnel structure;It has can reach easy construction, safeguard that smooth, operation safety etc. is required, it is easy to the features such as popularization and application.

Description

A kind of full cable outlet integral type GIS foundation arrangement
Technical field
The present invention relates to full cable outlet integral type GIS foundation arrangement in a kind of transformer station, it is adaptable to power transformation Stand, current conversion station, power plant etc. need to arrange the engineering of GIS device, belong to project of transmitting and converting electricity design field.
Background technology
As State Grid Corporation of China " amphitypy one is changed " transformer substation construction is advanced, intensive miniaturization GIS equipment is adopted extensively With requirement more and more higher of the city to environment, to avoid overhead transmission line inconvenience, is increased increasingly using substation with cable outlets It is many.
Existing civil Engineering Design connects ditch (well) with GIS outlets often through pipe laying, and GIS device basis is divided with duct (well) is gone out From design, usual GIS foundation uses pile foundation, and ditch (well) often uses subsoil, in coastal soft clay area, separation design Differential settlement between the two will be caused, the safe operation of transformer station will be threatened.Existing conventional GIS foundation separate layout structure is shown in Shown in Fig. 1.
The content of the invention
It is an object of the invention to overcome the shortcomings of that prior art is present, and one kind is provided and is reached easy construction, safeguarded suitable Freely, run safety etc. to require, it is easy to the full cable outlet integral type GIS foundation arrangement of popularization and application.
The purpose of the present invention is completed by following technical solution, a kind of full cable outlet integral type GIS foundation cloth Structure is put, it is that GIS raft foundations are merged with outlet cable ditch body, described outlet cable ditch body is directly arranged in GIS outlets lower section, GIS raft foundations be zigzag, the GIS raft foundations together with outlet cable ditch body it is integrated poured construction and Into.
As preferred:The top surface absolute altitude of the GIS raft foundations is in -0.20m and is embedded in underground, GIS raft foundation thickness 0.6-0.8m;Integral type raft foundation is adapted to subsoil and pile foundation raft foundation, and being made on GIS raft foundations has GIS foundation Buttress;Width B1=1.5m, B2=0.5m of the outlet cable ditch body, depth H=2.0m, the outlet cable ditch body is unlimited Structure is arranged to tunnel structure.
The present invention makes civil engineering and electrically installation, cable using integral type basis, the earth excavation backfill on reduction basis Lay more convenient, can arbitrarily change outlet direction, solve the uncertainty of distant view outlet direction, it is to avoid soft clay area basis Differential settlement;It can reduce the land seizure area of power distribution equipment, save land resource, by State Grid Corporation of China's " amphitypy One changes " transformer substation construction propulsion is deeply.
The present invention has can reach easy construction, safeguard that smooth, operation safety etc. is required, it is easy to the features such as popularization and application.
Brief description of the drawings
Fig. 1 is existing conventional GIS foundation separate layout structural representation.
Fig. 2 is integral type GIS foundation arrangement schematic diagram of the present invention.
Fig. 3 is the A-A cross section structure diagrams of Fig. 2.
Specific embodiment
Below in conjunction with accompanying drawing, the present invention will be described in detail:Fig. 2, shown in 3, a kind of full cable of the present invention goes out Line integral type GIS foundation arrangement, it be by GIS raft foundations 1 and outlet cable ditch body it is 2-in-1 and together with, described goes out Line cable slot body 2 is directly arranged in the lower section of GIS outlets 3, and described GIS raft foundations 1 are made into zigzag, the GIS raft plate bases The integrated poured construction together with outlet cable ditch body 2 of plinth 1 is formed.
Shown in figure, the GIS raft foundations 1 top surface absolute altitude is in -0.20m and is embedded in underground, GIS raft foundations 1 are thick Degree 0.6-0.8m;Integral type raft foundation is adapted to subsoil and pile foundation raft foundation, and being made on GIS raft foundations 1 has GIS bases Plinth buttress 4;Width B1=1.5m, B2=0.5m of the outlet cable ditch body 2, depth H=2.0m, the outlet cable ditch body 2 is Open design is arranged to tunnel structure.
The method have the benefit that:
1)GIS foundation unites two into one with duct (well) is gone out, using integral type basis, integral type cast basis, make civil engineering and Electrically installation, cable laying are more convenient, can arbitrarily change outlet direction, solve the uncertainty of distant view outlet direction, one Body formula basis can also avoid soft clay area foundation uneven settlement.
2)GIS foundation with go out duct(Well)Unite two into one, using integral type basis, reduce the earth excavation backfill on basis, The land seizure area of power distribution equipment is reduced, State owned land resource has been saved, by State Grid Corporation of China " amphitypy one is changed " transformer station Build propulsion deeply.
Apply specific case in the present invention to be set forth principle of the invention and implementation method, above example Explanation be only intended to help and understand the method for the present invention and core concept;The contents of the section should not be construed as to limit of the invention System.

Claims (2)

1. a kind of full cable outlet integral type GIS foundation arrangement, it is to merge GIS raft foundations with outlet cable ditch body Together, it is characterised in that described outlet cable ditch body is directly arranged in GIS outlets lower section, GIS raft foundations are zigzag, The GIS raft foundations integrated poured construction together with outlet cable ditch body is formed.
2. full cable outlet integral type GIS foundation arrangement according to claim 1, it is characterised in that the GIS rafts Plate basis top surface absolute altitude is in -0.20m and is embedded in underground, GIS raft foundation thickness 0.6-0.8m;Integral type raft foundation is adapted to Subsoil and pile foundation raft foundation, being made on GIS raft foundations has GIS foundation buttress;The width of the outlet cable ditch body B1=1.5m, B2=0.5m, depth H=2.0m, the outlet cable ditch body are open design or are arranged to tunnel structure.
CN201611012080.8A 2016-11-17 2016-11-17 A kind of full cable outlet integral type GIS foundation arrangement Pending CN106759450A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611012080.8A CN106759450A (en) 2016-11-17 2016-11-17 A kind of full cable outlet integral type GIS foundation arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611012080.8A CN106759450A (en) 2016-11-17 2016-11-17 A kind of full cable outlet integral type GIS foundation arrangement

Publications (1)

Publication Number Publication Date
CN106759450A true CN106759450A (en) 2017-05-31

Family

ID=58968602

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611012080.8A Pending CN106759450A (en) 2016-11-17 2016-11-17 A kind of full cable outlet integral type GIS foundation arrangement

Country Status (1)

Country Link
CN (1) CN106759450A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115387169A (en) * 2022-08-15 2022-11-25 中国能源建设集团广东省电力设计研究院有限公司 Road foundation suitable for transformer substation in soft soil area

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DK110291A (en) * 1989-01-05 1991-07-03 Goeran Karlsson PREPARED BUILDING FOUNDATION ELEMENT AND PROCEDURE AND MEANS OF MANUFACTURING THE ELEMENT
CN103015454A (en) * 2012-12-28 2013-04-03 浙江省电力设计院 Combined raft foundation of outdoor framework and GIS equipment in transformer substation
JP2013112926A (en) * 2011-11-24 2013-06-10 Takenaka Komuten Co Ltd Foundation structure for photovoltaic generation device, and construction method for the same
CN203684263U (en) * 2013-12-17 2014-07-02 浙江省电力设计院 General foundation for GIS equipment at transformer station
CN206204984U (en) * 2016-11-17 2017-05-31 中国能源建设集团浙江省电力设计院有限公司 Full cable outlet integral type GIS foundation arrangement

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DK110291A (en) * 1989-01-05 1991-07-03 Goeran Karlsson PREPARED BUILDING FOUNDATION ELEMENT AND PROCEDURE AND MEANS OF MANUFACTURING THE ELEMENT
JP2013112926A (en) * 2011-11-24 2013-06-10 Takenaka Komuten Co Ltd Foundation structure for photovoltaic generation device, and construction method for the same
CN103015454A (en) * 2012-12-28 2013-04-03 浙江省电力设计院 Combined raft foundation of outdoor framework and GIS equipment in transformer substation
CN203684263U (en) * 2013-12-17 2014-07-02 浙江省电力设计院 General foundation for GIS equipment at transformer station
CN206204984U (en) * 2016-11-17 2017-05-31 中国能源建设集团浙江省电力设计院有限公司 Full cable outlet integral type GIS foundation arrangement

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115387169A (en) * 2022-08-15 2022-11-25 中国能源建设集团广东省电力设计研究院有限公司 Road foundation suitable for transformer substation in soft soil area

Similar Documents

Publication Publication Date Title
CN106202766B (en) Soil body vertical deformation calculation method caused by the suction/discharge type shield method tunnel construction of ground
CN205530280U (en) Novel prefabricated two walls unification foundation ditch enclosure system
CN103981898A (en) Integral open-excavation node top-down underground engineering construction method
Egan et al. Overview of the 500MW EirGrid East-West Interconnector, considering System Design and execution-phase issues
CN103132539A (en) Construction method of underground continuous wall connector cutting
CN104420480A (en) Collapsible loess area integrated pipe network layout method and structure
CN206204984U (en) Full cable outlet integral type GIS foundation arrangement
CN202595756U (en) Piled raft foundation structure of narrow-base power transmission tower
CN106759450A (en) A kind of full cable outlet integral type GIS foundation arrangement
CN203625883U (en) Steel sheet support pile with pipes for foundation pit construction
CN101440894B (en) Method and structure for arranging plant pipe network
CN203260979U (en) Cable trench and cover plate thereof
CN202881967U (en) Transmission tower plate type three-cable base structure
CN105155488A (en) Arrangement mode and structure of small ecological flow unit of hydropower station underground powerhouse
CN102163829B (en) Fully-sealed buried cable branch box
CN101552384B (en) Method for laying direct current grounding pole
CN103595001A (en) Composite reinforced HDPE cable sheath tube
CN210724048U (en) MPP cable sleeve convenient to connect
CN211351260U (en) Three-layer three-dimensional cable channel for indoor transformer substation
CN203660480U (en) Prefabricated culvert cable channel
CN204691255U (en) Diaphragm wall
CN105006795A (en) Method for laying benzene hydrogenation engineering direct-buried cable
CN104047273A (en) Energy dissipation anti-flushing wall for hydropower station and construction method thereof
CN113202084A (en) Embedded type sleeve milling joint method for underground diaphragm wall
CN206673539U (en) A kind of cable laying piping lane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531

RJ01 Rejection of invention patent application after publication