CN205530280U - Novel prefabricated two walls unification foundation ditch enclosure system - Google Patents
Novel prefabricated two walls unification foundation ditch enclosure system Download PDFInfo
- Publication number
- CN205530280U CN205530280U CN201620101393.XU CN201620101393U CN205530280U CN 205530280 U CN205530280 U CN 205530280U CN 201620101393 U CN201620101393 U CN 201620101393U CN 205530280 U CN205530280 U CN 205530280U
- Authority
- CN
- China
- Prior art keywords
- water
- foundation pit
- new type
- wall
- prefabricated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本实用新型涉及一种新型预制两墙合一基坑围护体系,该新型预制两墙合一基坑围护体系由围护结构和支撑体系组成。所述围护结构由新型止水离心桩组成,所述新型止水离心桩采用导槽相对接、桩顶设置混凝土压顶梁的方式连接;所述支撑体系采用隔段浇筑建筑顶板;所述支撑体系通过预埋的钢筋接驳器与新型止水离心桩连接。与现有管廊类基坑围护体系相比,本实用新型具有施工周期短、无污染、低噪音、围护结构稳定性强、工程造价低、对周围环境影响小等优点。
The utility model relates to a novel prefabricated two-wall-in-one foundation pit enclosure system. The novel prefabricated two-wall-in-one foundation pit enclosure system consists of an enclosure structure and a support system. The enclosure structure is composed of new-type water-stop centrifugal piles, which are connected by means of butt-connecting guide grooves and setting concrete top beams on top of the piles; The system is connected with a new type of water-stop centrifugal pile through a pre-embedded steel connector. Compared with the existing foundation pit enclosure system of pipe gallery, the utility model has the advantages of short construction period, no pollution, low noise, strong enclosure structure stability, low engineering cost, and small impact on the surrounding environment.
Description
技术领域technical field
本实用新型涉及一种新型预制两墙合一基坑围护体系,主要应用于管廊类市政建筑的地基基坑围护及防止土方位移等领域。The utility model relates to a novel prefabricated two-wall-in-one foundation pit enclosure system, which is mainly used in the fields of foundation pit enclosure and prevention of earth displacement of municipal buildings such as pipe corridors.
背景技术Background technique
现代化城市土地资源极为匮乏,市政基础设施建设受到土地资源、市政规划、城市景观以及环境保护等越来越严格的限制,把各种缆线、管道综合放置迫在眉睫。地下市政综合管廊,又名共同沟,即在地下设置专供各种公共事业摆放缆线、管道的沟道。地下综合管廊是目前世界上比较先进的基础设施管网布置形式,是城市建设和城市发展的趋势和潮流,是充分利用地下空间的有效手段。目前,城市综合管廊基坑围护施工存在着经济性差、施工效率低、环境影响大等缺点。针对上述缺点,本实用新型涉及一种经济性良好、施工效率高、环境影响小的新型预制两墙合一基坑围护体系及其逆作法,该围护结构与建筑结构外墙两墙合一,支撑体系与顶板合一,经济性良好;围护结构为预制,施工效率高;新型止水离心桩挤土性小,环境影响小。Land resources in modern cities are extremely scarce, and the construction of municipal infrastructure is increasingly restricted by land resources, municipal planning, urban landscape and environmental protection. It is imminent to comprehensively place various cables and pipelines. The underground municipal comprehensive pipe corridor, also known as the common ditch, is to set up underground trenches for various public utilities to place cables and pipes. Underground comprehensive pipe gallery is a relatively advanced form of infrastructure pipe network layout in the world at present, it is the trend and trend of urban construction and urban development, and it is an effective means to make full use of underground space. At present, there are disadvantages such as poor economy, low construction efficiency, and large environmental impact in the construction of urban comprehensive pipe gallery foundation pit enclosure. In view of the above disadvantages, the utility model relates to a new type of prefabricated two-wall-in-one foundation pit enclosure system with good economy, high construction efficiency and little environmental impact and its reverse construction method. First, the support system and the roof are integrated, which is economical; the enclosure structure is prefabricated, and the construction efficiency is high; the new type of water-stop centrifugal pile has low soil extrusion and low environmental impact.
实用新型内容Utility model content
本实用新型的目的就是提供一种承载能力大,隔水效果好,施工便捷,效率高,围护结构与建筑外墙两墙合一,支撑体系与建筑顶板合一,成本造价低的基坑围护体系及其施工方法。The purpose of this utility model is to provide a foundation pit with large bearing capacity, good water-proof effect, convenient construction, high efficiency, combination of enclosure structure and building exterior wall, support system and building roof, and low cost Enclosure system and its construction method.
本实用新型的目的可以通过以下技术方案来实现:The purpose of this utility model can be achieved through the following technical solutions:
一种新型预制两墙合一基坑围护体系,该新型预制两墙合一基坑围护体系由围护结构和支撑体系组成,所述围护结构由新型止水离心桩组成,所述新型止水离心桩采用导槽相对接、桩顶设置混凝土压顶梁的方式连接,所述支撑体系采用隔段浇筑建筑顶板,所述支撑体系通过预埋的钢筋接驳器与新型止水离心桩连接。A new type of prefabricated two-wall-in-one foundation pit enclosure system. The novel prefabricated two-wall-in-one foundation pit enclosure system consists of an enclosure structure and a support system. The enclosure structure is composed of a new type of water-stop centrifugal pile. The new water-stop centrifugal piles are connected by connecting guide grooves and setting concrete top beams on the top of the piles. The support system adopts the construction roof slab poured in intervals. connect.
所述的新型止水离心桩为预制桩。The novel water-stop centrifugal pile is a prefabricated pile.
所述的新型止水离心桩导槽采用注浆保证围护体系止水。The guide groove of the novel water-stop centrifugal pile adopts grouting to ensure the water-stop of the enclosure system.
所述的围护结构兼作建筑外墙、建筑顶板兼作支撑体系,即新型止水离心桩兼作建筑外墙、建筑顶板兼作支撑体系。The enclosure structure doubles as a building exterior wall, and the building roof doubles as a support system, that is, the new water-stop centrifugal pile doubles as a building exterior wall, and the building roof doubles as a support system.
所述的新型止水离心桩在建筑底板及建筑顶板位置预埋钢筋接驳器。The new type of water-stop centrifugal pile pre-embeds steel bar connectors at the positions of the building floor and the building roof.
与现有管廊类基坑围护体系及施工方法相比,本实用新型有如下优点:Compared with the existing pipe gallery type foundation pit enclosure system and construction method, the utility model has the following advantages:
1、围护与建筑结构两墙合一,支撑体系与顶板合一,围护结构与建筑结构完美结合,经济效益好。1. The two walls of the enclosure and the building structure are integrated into one, the support system and the roof are integrated into one, the enclosure structure and the building structure are perfectly combined, and the economic benefits are good.
2、新型止水离心桩为预制桩,施工效率高,无需多余养护时间施工工期短;新型止水离心桩挤土性小,环境影响小。2. The new type of water-stop centrifugal pile is a prefabricated pile, which has high construction efficiency and a short construction period without redundant maintenance time; the new type of water-stop centrifugal pile has low soil extrusion and low environmental impact.
附图说明Description of drawings
图1为基坑围护示意图Figure 1 is a schematic diagram of foundation pit enclosure
1新型止水离心桩 2建筑顶板 3内衬墙 4建筑底板 5钢筋接驳器6混凝土压顶梁1 New type water-stop centrifugal pile 2 Building roof 3 Lined wall 4 Building floor 5 Rebar connector 6 Concrete pressure beam
图2为围护结构连接的形式Figure 2 is the form of enclosure structure connection
6混凝土压顶梁 7导槽6 Concrete pressure beam 7 Guide groove
图3为边桩机Figure 3 is the side pile machine
8边桩机 9静压装置8 Side pile driver 9 Static pressure device
具体实施方式detailed description
下面结合附图和具体实施例对本实用新型进行详细说明。本实施例以本实用新型技术方案为前提进行实施,给出了详细的实施方式和具体的操作过程,但本实用新型的保护范围不限于下述的实施例。The utility model will be described in detail below in conjunction with the accompanying drawings and specific embodiments. This embodiment is carried out on the premise of the technical solution of the utility model, and the detailed implementation and specific operation process are given, but the protection scope of the utility model is not limited to the following examples.
实施例Example
如图1所示,一种新型预制两墙合一基坑围护体系及其逆作法,该新型基坑围护体系由围护结构结合支撑体系组成。所述围护结构由新型止水离心桩1组成,该新型止水离心桩1采用导槽7相对接、桩顶设置混凝土压顶梁6的方式连接,如图2所示;所述支撑体系采用隔段浇筑建筑顶板2来保证基坑的稳定性;所述建筑顶板2通过预埋件钢筋接驳器5与新型止水离心桩1连接。As shown in Figure 1, a new type of prefabricated two-wall-in-one foundation pit enclosure system and its reverse method, the new foundation pit enclosure system consists of an enclosure structure combined with a support system. The enclosure structure is composed of a new type of water-stop centrifugal pile 1, the new type of water-stop centrifugal pile 1 is connected by a guide groove 7, and a concrete top beam 6 is arranged on the top of the pile, as shown in Figure 2; the support system adopts The building roof 2 is poured at intervals to ensure the stability of the foundation pit; the building roof 2 is connected to the new water-stop centrifugal pile 1 through the embedded steel bar connector 5 .
本实用新型所涉及的一种新型预制两墙合一基坑围护体系及其逆作法,采用边桩机8施工,其具体步骤为:A new type of prefabricated two-wall-in-one foundation pit enclosure system and its reverse method involved in the utility model are constructed by using a side pile machine 8, and the specific steps are as follows:
1)平整施工场地,根据施工图放出实样;1) Level up the construction site and release actual samples according to the construction drawings;
2)新型止水离心桩1进场验收后,堆放至便于施工的位置;2) After the new type of water-stop centrifugal pile 1 enters the site for acceptance, it is stacked to a position convenient for construction;
3)遥控控制边桩机8移动到施工放样位置,启动动力组件,边桩机吊臂将步骤2)中新型止水离心桩1吊至边桩机静压装置9;3) Remotely control the side pile machine 8 to move to the construction stakeout position, start the power assembly, and the side pile machine boom lifts the new water-stop centrifugal pile 1 in step 2) to the side pile machine static pressure device 9;
4)遥控控制启动边桩机静压装置9,将新型止水离心桩1压至设计标高;4) Start the static pressure device 9 of the side pile machine by remote control, and press the new water-stop centrifugal pile 1 to the design elevation;
5)遥控控制边桩机8移位,旋转边桩机吊臂,将步骤2)中新型止水离心桩1吊至边桩机静压装置9,将该桩导槽7与已施工桩体导槽7相对接,遥控控制启动边桩机静压装置9,将该桩压至设计标高;5) Remotely control the displacement of the side pile machine 8, rotate the boom of the side pile machine, hoist the new water-stop centrifugal pile 1 in step 2) to the static pressure device 9 of the side pile machine, and align the pile guide groove 7 with the constructed pile body The guide groove 7 is docked, and the static pressure device 9 of the side pile machine is activated by remote control to press the pile to the design elevation;
6)重复步骤5直至完成整个基坑围护结构新型止水离心桩1施工;6) Repeat step 5 until the construction of the new water-stop centrifugal pile 1 of the entire foundation pit enclosure structure is completed;
7)进行新型止水离心桩1桩顶混凝土压顶梁6施工;7) Carry out the construction of the new type water-stop centrifugal pile 1 pile top concrete pressure beam 6;
8)混凝土压顶梁6达到要求强度后,基坑开挖至预埋钢筋接驳器5完全暴露,隔段进行建筑顶板2施工,隔段长度根据设计计算确定;8) After the concrete capping beam 6 reaches the required strength, the foundation pit is excavated until the pre-embedded steel bar connector 5 is completely exposed, and the construction of the building roof 2 is carried out in intervals, and the length of the intervals is determined according to design calculations;
9)待建筑顶板2强度满足要求后,开挖至坑底预埋钢筋接驳器5完全暴露;9) After the strength of the building roof 2 meets the requirements, excavate until the pre-buried steel bar connector 5 at the bottom of the pit is completely exposed;
10)进行建筑底板4钢筋绑扎及混凝土浇筑施工;10) Carry out the construction of building floor 4 steel bar binding and concrete pouring;
11)向上进行内衬墙3及剩余隔段处建筑顶板2施工;11) Carry out the construction of the building roof 2 at the lining wall 3 and the remaining partitions upward;
12)全部施工完成后,回填至地坪标高。12) After all the construction is completed, backfill to the floor elevation.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620101393.XU CN205530280U (en) | 2016-02-01 | 2016-02-01 | Novel prefabricated two walls unification foundation ditch enclosure system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620101393.XU CN205530280U (en) | 2016-02-01 | 2016-02-01 | Novel prefabricated two walls unification foundation ditch enclosure system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205530280U true CN205530280U (en) | 2016-08-31 |
Family
ID=56775057
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201620101393.XU Expired - Fee Related CN205530280U (en) | 2016-02-01 | 2016-02-01 | Novel prefabricated two walls unification foundation ditch enclosure system |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205530280U (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106284412A (en) * | 2016-09-29 | 2017-01-04 | 陕西建筑产业投资集团有限公司 | A kind of prefabricated pipe gallery and construction method |
| CN106368211A (en) * | 2016-09-20 | 2017-02-01 | 俞晓东 | Rectangular concrete piles used for constructing side wall of pipe gallery |
| CN106480875A (en) * | 2016-09-21 | 2017-03-08 | 俞晓东 | For building the rectangular concrete pile of piping lane side wall |
| CN106836287A (en) * | 2017-03-28 | 2017-06-13 | 新疆维泰开发建设(集团)股份有限公司 | A kind of construction method of pipe gallery |
| CN107023015A (en) * | 2016-02-01 | 2017-08-08 | 上海城地建设股份有限公司 | A kind of new prefabricated two walls unification foundation pit system and its contrary sequence method |
| CN108797637A (en) * | 2017-04-26 | 2018-11-13 | 杭州南联土木工程科技有限公司 | Prefabricated board combined cast-in-situ concrete considers the underground pipe gallery construction method of structure and ground |
| CN116556412A (en) * | 2023-01-03 | 2023-08-08 | 中交(广州)建设有限公司 | Connection structure and connection method of new and old comprehensive pipe rack by using hidden excavation method |
-
2016
- 2016-02-01 CN CN201620101393.XU patent/CN205530280U/en not_active Expired - Fee Related
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107023015A (en) * | 2016-02-01 | 2017-08-08 | 上海城地建设股份有限公司 | A kind of new prefabricated two walls unification foundation pit system and its contrary sequence method |
| CN106368211A (en) * | 2016-09-20 | 2017-02-01 | 俞晓东 | Rectangular concrete piles used for constructing side wall of pipe gallery |
| CN106368211B (en) * | 2016-09-20 | 2018-10-23 | 俞晓东 | Rectangular concrete pile for building piping lane side wall |
| CN106480875A (en) * | 2016-09-21 | 2017-03-08 | 俞晓东 | For building the rectangular concrete pile of piping lane side wall |
| CN106284412A (en) * | 2016-09-29 | 2017-01-04 | 陕西建筑产业投资集团有限公司 | A kind of prefabricated pipe gallery and construction method |
| CN106284412B (en) * | 2016-09-29 | 2017-05-31 | 陕西建筑产业投资集团有限公司 | A kind of prefabricated pipe gallery and construction method |
| CN106836287A (en) * | 2017-03-28 | 2017-06-13 | 新疆维泰开发建设(集团)股份有限公司 | A kind of construction method of pipe gallery |
| CN106836287B (en) * | 2017-03-28 | 2019-03-22 | 新疆维泰开发建设(集团)股份有限公司 | A kind of construction method of pipe gallery |
| CN108797637A (en) * | 2017-04-26 | 2018-11-13 | 杭州南联土木工程科技有限公司 | Prefabricated board combined cast-in-situ concrete considers the underground pipe gallery construction method of structure and ground |
| CN116556412A (en) * | 2023-01-03 | 2023-08-08 | 中交(广州)建设有限公司 | Connection structure and connection method of new and old comprehensive pipe rack by using hidden excavation method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103981898B (en) | A kind of inverse underground engineering construction method done of overall open cut node | |
| CN104264688B (en) | Manually digging hole non-uniform pile support construction process | |
| CN103397660B (en) | Construction method of underground construction | |
| CN101886479B (en) | Underground storey-adding process of frame structural building by one-by-one independent foundation underpinning method | |
| CN101418569B (en) | Optimized composite arch wall with combination of prefabricated arch, support and main structure | |
| CN102127974A (en) | Design and construction method of additional cellar under existing building | |
| CN109914472B (en) | Soft soil area assembled comprehensive pipe gallery and construction method thereof | |
| CN102704957A (en) | Shed-frame method for shallowly burying large-sized underground structure construction | |
| CN112524338A (en) | Pipe jacking construction system for bidirectional jacking and construction process thereof | |
| CN110004991A (en) | Underground structure anti-floating system and construction method based on raised type tangs plate | |
| CN107701203A (en) | Pile foundation underpinning system and its construction method based on double-deck permanent lining, secondary lining structure | |
| CN110985042B (en) | Urban comprehensive pipe gallery and underground shallow-buried underground tunnel combined supporting system and process | |
| CN105756087A (en) | Assembling-type anchoring structure for adjacent plates of prefabricated comprehensive pipe rack | |
| CN101532386B (en) | Method and device for underpinning antifriction separator for shallow underground space construction | |
| CN104005414A (en) | Method for constructing large-diameter reinforced concrete cast-in-place pile supporting stand column | |
| CN110565686A (en) | Construction method for penetrating river channel under pipe gallery | |
| CN109594574A (en) | Large-scale push pipe open caisson reversed construction method based on the confined space | |
| CN105672351A (en) | Construction method of buckling type prefabricated ribbed reinforced concrete comprehensive pipe gallery structure | |
| CN211172070U (en) | Assembled type suspended wall retaining wall structure of reinforced concrete member | |
| CN205036388U (en) | Block of four encircles knot hunch construction structures that PBA secretly dug subway station | |
| CN100473791C (en) | Installing method for rail beam structure of magnetic suspension tunnel shoreside section | |
| CN206448293U (en) | A kind of reverse construction ground prop structure | |
| CN206158753U (en) | Shield constructs well end bassoon canopy system of consolidating based on major structure | |
| CN105065040A (en) | Top-plate-prefabricated underground space underground excavation building method | |
| CN205399401U (en) | Novel underground continuous wall of wallboard formula |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CP01 | Change in the name or title of a patent holder |
Address after: 201806, B, Lane 518, Lane 1, Heng Yong Road, Shanghai, Jiading District 502-1 Co-patentee after: SHANGHAI CHENGDI ROCK-SOIL DESIGN Co.,Ltd. Patentee after: Shanghai chengdixiangjiang Data Technology Co.,Ltd. Address before: 201806, B, Lane 518, Lane 1, Heng Yong Road, Shanghai, Jiading District 502-1 Co-patentee before: SHANGHAI CHENGDI ROCK-SOIL DESIGN Co.,Ltd. Patentee before: SHANGHAI CHENGDI CONSTRUCTION Co.,Ltd. |
|
| CP01 | Change in the name or title of a patent holder | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20231220 Address after: Room J815, 3rd Floor, No. 5358 Huyi Road, Jiading District, Shanghai, June 2018 Patentee after: Zhongji Engineering (Shanghai) Geotechnical Co.,Ltd. Address before: 502-1, area B, No.1, Lane 518, Hengyong Road, Jiading District, Shanghai, 201806 Patentee before: Shanghai chengdixiangjiang Data Technology Co.,Ltd. Patentee before: SHANGHAI CHENGDI ROCK-SOIL DESIGN Co.,Ltd. |
|
| TR01 | Transfer of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160831 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |