CN106759337A - 整体推进式截桩施工方法 - Google Patents
整体推进式截桩施工方法 Download PDFInfo
- Publication number
- CN106759337A CN106759337A CN201611204245.1A CN201611204245A CN106759337A CN 106759337 A CN106759337 A CN 106759337A CN 201611204245 A CN201611204245 A CN 201611204245A CN 106759337 A CN106759337 A CN 106759337A
- Authority
- CN
- China
- Prior art keywords
- stake
- cut
- pile
- earth
- excavator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
本发明主要应用于建筑施工领域,特别涉及一种整体推进式截桩施工方法,其特征在于采取以下步骤:1)采用大型机械开挖至桩顶以上500mm位置;2)采用小型挖掘机清除剩余500mm土方;3)小型挖掘机采用倒退开挖法清理桩间土;4)人工挖土;5)当挖至桩部位时,清理桩身周围的土方;6)制作厚度为5mm的铁板放置在桩外周;7)截桩人员进入,依据弹好的标高控制线在设计桩顶标高位置截桩;8)挖土机配合将截断的桩头清理出基坑集中堆放,或自卸汽车运走。本发明采用整体推进式截桩施工方法,三个工序先后介入后同步进行,桩头截断后在铁板的保护和人工的牵引下定向放倒,桩头不会砸到持力层,不会对桩间土造成扰动。
Description
技术领域
本发明涉及一种整体推进式截桩施工方法,主要应用于建筑施工领域。
背景技术
目前,在CFG桩身截桩施工中,为了加快进度和节约成本,挖土机开挖桩间土预留人工开挖的厚度普遍不足100mm,甚至普遍存在开挖至基础持力层或超挖现象,违反验收规范和施工工艺要求,人工开挖后截桩时不采取任何保护措施,直接放倒桩头,破坏持力层,然后汽车吊吊离桩头至自卸汽车运离。
现阶段截桩施工的传统施工方法是先机械开挖桩间土,再人工开挖至基础持力层,再截桩,截桩时必须用汽车吊紧桩头,防止桩头倾倒,扰动基础持力层,此种方法机械挖土、人工挖土、截桩都作为关键工作占用工期,并且吊车和自卸汽车要随时配合截桩施工,耗费大量的机械费,达不到保护基础持力层和节约成本的目的。
发明内容
本发明要解决的技术问题是:提供一种大大缩短施工工期,同时又节省机械费用的整体推进式截桩施工方法。
本发明所述的整体推进式截桩施工方法,其特征在于采取以下步骤:
1)场区设立标高控制点,定位桩的位置,采用大型机械开挖至桩顶以上500mm位置;
2)采用小型挖掘机清除剩余500mm土方;
3)小型挖掘机采用倒退开挖法清理桩间土,不得对桩身造成损坏,并预留300mm人工清槽,然后在桩身上弹标高控制线;
4)当机械开挖达到3米以上留出足够安全距离时人工挖土介入,人工挖土的人数能够保持与机械开挖的进度保持一致;
5)当挖至桩部位时,清理桩身周围的土方;
6)制作厚度为5mm的铁板放置在桩外周,保护基底持力层;
7)截桩人员进入,依据弹好的标高控制线在设计桩顶标高位置截桩,截桩采用手持切割机,然后用风镐嵌入将桩截断,截桩时将桩头位置绑牢,向未开挖土方方向定向放倒,铁板保护桩间土不受扰动;
8)挖土机配合将截断的桩头清理出基坑集中堆放,或自卸汽车运走。
所述的机械开挖、人工挖土、截桩同步进行,整体推进。
本发明的有益效果是:
采用整体推进式截桩施工方法,三个工序先后介入后同步进行,桩头截断后在铁板的保护和人工的牵引下定向放倒,桩头不会砸到持力层,不会对桩间土造成扰动;传统工艺耗费机械挖土、人工挖土、截桩三个工序的工期,而整体推进式截桩三个工序同步进行最大限度的节约了工期,同时充分利用挖土机的优势,直接将桩头从基坑内运离。
附图说明
图1是本发明整体推进式截桩施工方法的平面示意图。
图2是本发明整体推进式截桩施工方法的立面示意图。
图中:1、铁板;2、桩;3、基底持力层;4、人工清槽;5、桩间土。
具体实施方式
下面结合附图对本发明做进一步描述:
如图1~图2所示,本发明所述的整体推进式截桩施工方法,采取以下步骤:
1)场区设立标高控制点,定位桩2的位置,采用大型机械开挖至桩顶以上500mm位置;
2)采用小型挖掘机清除剩余500mm土方;
3)小型挖掘机采用倒退开挖法清理桩间土5,不得对桩身造成损坏,并预留300mm人工清槽4,然后在桩身上弹标高控制线;
4)当机械开挖达到3米以上留出足够安全距离时人工挖土介入,人工挖土的人数能够保持与机械开挖的进度保持一致;
5)当挖至桩部位时,清理桩身周围的土方;
6)制作厚度为5mm的铁板1放置在桩外周,保护基底持力层3;
7)截桩人员进入,依据弹好的标高控制线在设计桩顶标高位置截桩,截桩采用手持切割机,然后用风镐嵌入将桩截断,截桩时将桩头位置绑牢,向未开挖土方方向定向放倒,铁板1保护桩间土5不受扰动;
8)挖土机配合将截断的桩头清理出基坑集中堆放,或自卸汽车运走。
所述的机械开挖、人工挖土、截桩同步进行,整体推进。
Claims (2)
1.一种整体推进式截桩施工方法,其特征在于采取以下步骤:
1)场区设立标高控制点,定位桩的位置,采用大型机械开挖至桩顶以上500mm位置;
2)采用小型挖掘机清除剩余500mm土方;
3)小型挖掘机采用倒退开挖法清理桩间土(5),不得对桩身造成损坏,并预留300mm人工清槽(4),然后在桩身上弹标高控制线;
4)当机械开挖达到3米以上留出足够安全距离时人工挖土介入,人工挖土的人数能够保持与机械开挖的进度保持一致;
5)当挖至桩部位时,清理桩身周围的土方;
6)制作厚度为5mm的铁板(1)放置在桩(2)外周,保护基底持力层(3);
7)截桩人员进入,依据弹好的标高控制线在设计桩顶标高位置截桩,截桩采用手持切割机,然后用风镐嵌入将桩截断,截桩时将桩头位置绑牢,向未开挖土方方向定向放倒,铁板(1)保护桩间土不受扰动;
8)挖土机配合将截断的桩头清理出基坑集中堆放,或自卸汽车运走。
2.根据权利要求书1所述的整体推进式截桩施工方法,其特征在于:机械开挖、人工挖土、截桩同步进行,整体推进。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611204245.1A CN106759337A (zh) | 2016-12-23 | 2016-12-23 | 整体推进式截桩施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611204245.1A CN106759337A (zh) | 2016-12-23 | 2016-12-23 | 整体推进式截桩施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106759337A true CN106759337A (zh) | 2017-05-31 |
Family
ID=58897735
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611204245.1A Pending CN106759337A (zh) | 2016-12-23 | 2016-12-23 | 整体推进式截桩施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106759337A (zh) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203129145U (zh) * | 2013-01-29 | 2013-08-14 | 中铁十五局集团有限公司 | 一种截桩机 |
CN103615009A (zh) * | 2013-11-26 | 2014-03-05 | 中冶天工集团有限公司 | Cfg桩复合地基的桩间土挖除方法 |
CN204370424U (zh) * | 2014-12-31 | 2015-06-03 | 韩世伟 | 一种水泥搅拌桩桩头截取机 |
-
2016
- 2016-12-23 CN CN201611204245.1A patent/CN106759337A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203129145U (zh) * | 2013-01-29 | 2013-08-14 | 中铁十五局集团有限公司 | 一种截桩机 |
CN103615009A (zh) * | 2013-11-26 | 2014-03-05 | 中冶天工集团有限公司 | Cfg桩复合地基的桩间土挖除方法 |
CN204370424U (zh) * | 2014-12-31 | 2015-06-03 | 韩世伟 | 一种水泥搅拌桩桩头截取机 |
Non-Patent Citations (2)
Title |
---|
LIYULIANGWENKU: "截桩方案", 《百度文库HTTPS://WENKU.BAIDU.COM/VIEW/FD3989C4D5BBFD0A78567303.HTML?FROM=SEARCH》 * |
曹海彬: "桩间土方开挖及截桩头施工方案", 《百度文库HTTPS://WENKU.BAIDU.COM/VIEW/864116C6A1C7AA00B52ACB4D.HTML?FROM=SEARCH,第6-7》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102182472B (zh) | 隧道塌方空腔的回填修复方法 | |
CN102505695B (zh) | 一种立体车库深基坑施工方法 | |
CN107938656A (zh) | 复杂复建基坑工程桩基施工方法 | |
CN102094425A (zh) | 采用浅埋深拉森钢板桩作为防护围堰的基坑施工方法 | |
CN104847364B (zh) | 一种盾构连续切削桩基础穿越居民楼群施工方法 | |
CN103452561A (zh) | 一种地铁暗挖车站多层横向通道竖向进洞施工方法、以及东、西两侧施工方法 | |
CN102535474A (zh) | 一种深基坑挖土的施工方法 | |
CN108457282A (zh) | 深水硬岩无封底钢板桩围堰施工方法 | |
CN102505704A (zh) | 软弱地质竖井中大型沉井施工方法 | |
CN106522235A (zh) | 狭小场地深基坑开挖支护施工方法 | |
CN113832958B (zh) | 一种机械配合人工开挖的抗滑桩施工方法 | |
CN112281857A (zh) | 深基坑开挖施工方法 | |
CN104480929A (zh) | 一种将咬合桩应用于永久地下室外墙的桩墙合一施工方法 | |
CN102235010B (zh) | 沉井因膨胀土悬挂停沉的处理方法 | |
CN111750172A (zh) | 一种顶管施工工艺 | |
CN102235007A (zh) | 上钉下桩组合的深基支护方法 | |
CN106759337A (zh) | 整体推进式截桩施工方法 | |
CN109577337A (zh) | 排水管线的深基坑施工方法 | |
CN107503354A (zh) | 一种塔吊基础围护支撑加固及开挖方法 | |
CN110438857A (zh) | 一种山岭重丘区钢筋笼石笋桩及其施工工艺 | |
CN201495571U (zh) | 逆作法地下暗挖工程专用提土设备 | |
CN108590662A (zh) | 高陡边坡地铁车站隧道通风竖井的施工方法 | |
CN108661065A (zh) | 一种适用于砂土地基开挖的预制沉箱及开挖方法 | |
CN105804003B (zh) | 一种宽肩台式防波堤及其运输安装方法 | |
CN113684838A (zh) | 一种嵌岩超深地下连续墙成槽施工的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170531 |
|