CN106758649A - A kind of field concrete road surface, process for constructing and concrete - Google Patents

A kind of field concrete road surface, process for constructing and concrete Download PDF

Info

Publication number
CN106758649A
CN106758649A CN201611108915.XA CN201611108915A CN106758649A CN 106758649 A CN106758649 A CN 106758649A CN 201611108915 A CN201611108915 A CN 201611108915A CN 106758649 A CN106758649 A CN 106758649A
Authority
CN
China
Prior art keywords
concrete
road surface
field
gravel
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611108915.XA
Other languages
Chinese (zh)
Other versions
CN106758649B (en
Inventor
饶松旺
陈艳华
申琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Geological Remote Sensing And Geographic Information Service Center
Fujian Land Development And Consolidation Center
Original Assignee
Fujian Land Development And Consolidation Center
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Land Development And Consolidation Center filed Critical Fujian Land Development And Consolidation Center
Priority to CN201611108915.XA priority Critical patent/CN106758649B/en
Publication of CN106758649A publication Critical patent/CN106758649A/en
Application granted granted Critical
Publication of CN106758649B publication Critical patent/CN106758649B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/18Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders
    • E01C7/26Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders mixed with other materials, e.g. cement, rubber, leather, fibre
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • C04B28/04Portland cements
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/0075Uses not provided for elsewhere in C04B2111/00 for road construction

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Road Paving Structures (AREA)

Abstract

A kind of field concrete road surface, process for constructing and concrete, wherein method comprises the following steps, preparation of construction, ready-mixed concrete, spread concrete, rolls;The preparation of construction includes step, removes soft base soil, flattening foot layer, and measurement control stake is set in basic unit, and the stirring slow setting soil includes step, by the 330kg of 32.5 cement 270, the 0.51m of middle sand 0.433, the 0.92m of gravel 0.763, the 0.08m of flyash 0.063It is stirred, 160 200s is stirred per tray concrete;The spread concrete includes step, infiltrates basic unit, uses land leveller spread concrete;The step that rolls includes vibration first pressing 12 times, does not open the multiple pressure 12 times of shaking, then carries out final pressure using rubber-tyred roller.Foregoing invention solves the problems, such as that field concrete road surface is built.

Description

A kind of field concrete road surface, process for constructing and concrete
Technical field
The present invention relates to field of pavement repair, more particularly to a kind of process for constructing of field concrete road surface, road and mixed Solidifying soil.
Background technology
Our province Land Consolidation Project was launched since 2005 in the whole province, had passed by so far 11 year, designed before Clay bound macadam is basic after having used several years to be damaged.
Field road clay bound macadam is primarily present the following aspects problem:
(1) ability to resist splash erosion is poor, and anti-natural calamity ability is poor,
(2) after agricultural machinery walking, road surface breakage is serious.
(3) construction quality is difficult to supervise, and construction party is easily used inferior materials and turned out substandard goods.
(4) can not be used on the soft base in field.
The content of the invention
For this reason, it may be necessary to provide a kind of new field concrete road surface process for constructing, solve the above problems
To achieve the above object, inventor provide
A kind of field concrete road surface process for constructing, comprises the following steps, preparation of construction, ready-mixed concrete, pave coagulation Soil, roll;
The preparation of construction includes step, removes soft base soil, flattening foot layer, and measurement control is set every 10m in basic unit Stake processed,
The ready-mixed concrete includes step, by 32.5 cement 270-330kg, middle sand 0.43-0.51m3, gravel 0.76- 0.92m3, flyash 0.06-0.08m3It is stirred, 160-200s is stirred per tray concrete;
The spread concrete includes step, infiltrates basic unit, uses land leveller spread concrete, and pave coefficient 1.2, and compacting is thick Degree 30cm;
It is described roll step include vibration first pressing 1-2 all over, do not open multiple pressure 1-2 times of shaking, then end is carried out using rubber-tyred roller Pressure.
Preferably, preparation of construction also includes step, changes and fills out the soft base in field, is rockfilled slag or gravel 35-45cm in dry land section, fills out Preceding rolling settlement control is in 9-11cm;In paddy field, section is rockfilled slag or gravel 60-80cm, fills out preceding rolling settlement control in 18- 22cm。
Specifically, roll step and roll section, spreading speed 1.5-2m/min with 30m as one.
Specifically, the coefficient 1.1-1.3 that paves of spread concrete, compacted depth 27-33cm.
Preferably, it is every after grinding coagulation soil intensity reaches more than the 70% of design strength also including seam construction procedure Transverse contraction joint is sawed every 10m, width 1cm, deep 6cm is stitched, using the pitch horseshoe fat cementation of fissures.
Preferably, also including step, after rolling end, health material, and moistening of sprinkling water are covered, is regularly sprinkled water after 4-6 days Health, until terminating during health.
A kind of concrete, with 32.5 cement 300kg to count, also including middle sand 0.43-0.51m3, gravel 0.76-0.92m3、 Flyash 0.06-0.08m3
Preferably, with 32.5 cement 300kg to count, also including middle sand 0.47m3, gravel 0.84m3, flyash 0.07m3
A kind of concrete road surface, the cement 300kg included with it is to count, including middle sand 0.43-0.51m3, gravel 0.76- 0.92m3, flyash 0.06-0.08m3
Preferably, the cement 300kg for being included with it to count, also including middle sand 0.47m3, gravel 0.84m3, flyash 0.07m3
It is different from prior art, above-mentioned technical proposal 1, can gathers materials on the spot.2nd, construction speed is fast.3rd, intensity is high.4th, anti-rain Water scouring capability is strong, and road surface freezing tolerance, anti-natural calamity ability are strong.5th, after agricultural machinery walking, road surface is without breakage.6th, construct Quality is easily supervised.7th, construction environment pollution is reduced.8th, can be used on soft base.9th, Land Consolidation Project field road, production road Road surface can use.10th, than every cubic metre of conventional concrete road surface saving more than cement 50KG.
Whether ocean surface field pavement engineering, or mountain ridge field produces pavement engineering, not as ordinary cement coagulation during construction Soil surface needs a set of large-scale equipment, it is possible to use the paver of surfacing, vibrated roller and rubber-tyred roller.
It is more durable than clay bound macadam ability to resist splash erosion, resistance to compression, wear-resisting and use after rolling compacted concrete pavement is formed Property etc. aspect greatly enhance, effect is significant improve.
Rolling compacted concrete pavement realizes that speed of application is fast compared with Common Concrete Pavement, while Load materials are saved, often Cubic meter of concrete saves more than cement 50KG.
Rolling compacted concrete pavement can gather materials on the spot compared with Common Concrete Pavement, save gather materials cost of transportation, remote mountain Area can use.
Environmental pollution is reduced, II grades of dry discharge fly ash can be not less than using quality in work progress.
Brief description of the drawings
Fig. 1 is the field concrete road surface process for constructing flow chart described in the specific embodiment of the invention;
Specific embodiment
To describe technology contents, structural feature, the objects and the effects of technical scheme in detail, below in conjunction with specific reality Apply example and coordinate accompanying drawing to be explained in detail.
Fig. 1 is referred to, is a kind of field concrete road surface process for constructing of the invention, as illustrated, method includes following step Suddenly, preparation of construction S100, ready-mixed concrete S102, spread concrete S104, roll S106;
The preparation of construction includes step, removes soft base soil, flattening foot layer, to ensure that surface evenness is every in basic unit Measurement control stake is set every 10m or so, measurement control stake is mainly used in controlling elevation.
The ready-mixed concrete includes step, by sand in 32.5R portland cements 270-330kg, 0.25-0.5 millimeter 0.43-0.51m3, 20-40 millimeters of gravel 0.76-0.92m3, flyash 0.06-0.08m3It is stirred, the stirring per tray concrete 160-200s;Choosing intensity can preferably adapt to the build demand of field concrete road surface for the portland cement of 32.5R, by force Du Yuegao basic units road surface external force resistance damage capability is bigger, and corresponding manufacturing cost is also higher, from the portland cement of 32.5R The use demand and cost control demand of field concrete road surface can preferably be adapted to.The middle sand of above-mentioned component and making for gravel With, by increasing capacitance it is possible to increase the shear behavior of concrete, the concrete road surface on the ridge of field is difficult to slide, in the case where moisture penetrates into Also ensure that performance.Flyash, is catching is got off from the flue gas after coal combustion fine ash, and flyash is coal-burning power plant's discharge Primary solids waste.The main oxides of the general flyash of China are constituted:SiO2、Al2O3、FeO、Fe2O3、CaO、TiO2 Deng.Addition flyash be advantageous in that can improve the workability of concrete batching system, water-retaining property, reduce hydration heat of concrete, Improve concrete durability;Specifically, effect of the flyash in concrete has the following aspects:(1) workability is improved, Reduce and separate;(2) Binder Materials, filler aggregate space are provided;(3) using flyash and the secondary response of cement, the later stage is increased Intensity, reduces cement consumption and reduces heat of hydration temperature rise;(4) environmental pollution is reduced, its danger to water, air and soil is reduced Evil;(5) closely knit smooth rolling compacted concrete pavement is provided.
For the mixing quality and supply that ensure grinding coagulation soil mixture are timely, in the particular embodiment, construction uses 1 Platform BH300 type forced stirring equipments, using 1 zl50 loading machine feeding, are produced using automatic blending, can be supplied per hour The grinding coagulation soil mix of 50-80t.Grinding coagulation soil is few because of its water consumption, and the mixing time will be grown compared with normal concrete.Roll The concrete mixing time is about 1.5 times of normal concrete.Determine that the control time mixed and stirred is every disk by trial mix during construction 180s or so.The workability of grinding coagulation soil mix, cohesiveness and plasticity can be improved after the extension mixing time.
Specifically, the transport of grinding coagulation soil preferably uses dump truck, in order to moisture evaporation causes in reducing transportation Denseness loss, wagon box planted agent keep moistening, transportation range should be advisable with the accessible distances of 30min, while taking necessary Covering methods.General construction is about 2km equipped with 5 12t dump trucks transports, transportation range.
The spread concrete includes step, infiltrates basic unit, uses land leveller spread concrete, and paving for spread concrete is Number 1.1-1.3, compacted depth 27-33cm.In some preferred embodiments, pave coefficient 1.2, compacted depth 30cm;Infiltration Basic unit is prevented from the moisture during basic unit absorbs concrete, improves the quality of concrete, and grinding coagulation soil design thickness is 30cm, Paving thickness is up to 36cm after considering coefficient of loose laying, and level land is used in the paving thickness of general paver, therefore construction Machine is paved.Coefficient of loose laying is the ratio of paving thickness and compacted depth, and it is the important parameter for controlling construction quality, formally Should be determined by trying paving before construction.Coefficient of loose laying when this paves is 1.2.Rolling compacted concrete pavement designs compacted depth 30cm, too thin holding can't stand that agricultural machinery is walked, and resistance to compression, shear resistance are poor, too thick and uneconomical, high expensive of building the road.
It is described roll step include vibration first pressing 1-2 all over, do not open multiple pressure 1-2 times of shaking, then end is carried out using rubber-tyred roller Pressure.Specifically in some embodiments, roll step and roll section, spreading speed 1.5-2m/min with 30m as one.
The key of rolling compacted concrete pavement is exactly to roll work, and the quality for rolling work directly determines the quality on road surface.
Influence the factor of consolidation effect to be mainly and roll work segment length, roll order, rolling speed, number of rolling and ring Border condition etc..
(1) segment length is rolled:With the evaporation of moisture, concrete consistence is increasing, and compressibility worse and worse, is rolled not Compactness can be caused not enough in time, influence grinding coagulation soil intensity.On the other hand, since the time interval to shaping mixing and stirring get over Long, the loss of strength of maturing is bigger.Therefore, it is guarantee pavement strength, it is necessary to make the road surface after paving as early as possible It is compacted.Wish that shortening rolls work segment length.But roll too short, necessarily cause road roller frequently to commutate, increase is rolled and connect Head, so as to influence the uniformity and surface evenness of compacting.According to the yield of stirring field 100t/h, 1.5-2m/min's paves Speed, and the solid density 7t that must pave that reaches long mixes and stirs the actual conditions of material per linear meter(lin.m.).This is constructed the length that paves every time 30m rolls section for one, and, in 30min, rolling operation time control is within 1.5 hours for the time control that paves.(2) roll secondary Sequence:Roll requirement and reach the closely knit and shaping surface of full thickness, should be carried out using vibrated roller.Roller compaction processes typically have first pressing (quiet Pressure), several sub- operations such as multiple pressure and final pressure.First pressing Main Function is to improve dense surface degree, will not be produced in vibroroller cmpacting The damaged surfaces phenomenons such as passage occur, for vibrating compacting provides basis.Can using multiple pressure with vibrated roller do not open to shake and carry out, Roll 2 times.Multiple pressure is to make road surface through thickness closely knit, reaches regulation packing, and need to open to shake is carried out, and muller overlaps to be preferably takes turns wide 1/ 3~1/2, impression is eliminated with profit, improve flatness.Compressed times and road roller performance, Roller Compacted Concrete Dam mix proportion, road surface thickness And to roll lap relevant, generally 5 times, suitable vibration frequency and amplitude are selected in roller compaction process, be first low frequency, it is high afterwards Frequently.Final pressure is a kind of indispensable roller compaction processes, and preferably using rubber-tyred roller, kneading action can disappear when rubber-tyred roller is rolled Can be formed with except steel wheel impression and fine cracks, and when rolling beneficial to the surface macro texture for improving pavement skid resistance condition, one As roll 2 times, rubber-tyred roller is the rolling apparatus for using of most having ready conditions in final pressure operation.This construction first pressing, multiple pressure are used Ca25 road rollers are carried out, and final pressure is produced rubber-tyred roller and carried out using Dezhou of large-tonnage.Compressed times reach regulation pressure by detection Solidity is controlled (generally 3~6 times), and the rolling speed of first pressing, multiple pressure and final pressure is 1.0~l.5km/h.(3) note Item:Vibrated roller should hoist from lower against spreading direction and be rolled, and each position rolling layer should be identical, must not leak Pressure, road width both sides should suitably increase number of rolling.Must at the uniform velocity be kept straight on when rolling, must not speed change or parking, meet special circumstances must When must stop, move backward, must first failure of oscillation.In construction section termination 4~5m scopes, road roller should be appropriate horizontal from low to high along road surface horizontal wall inscription To rolling, in case there is slumping crack or loose in junction.
Preferably, preparation of construction also includes step, changes and fills out the soft base in field, is rockfilled slag or gravel 35-45cm in dry land section, fills out Preceding rolling settlement control is in 9-11cm;In paddy field, section is rockfilled slag or gravel 60-80cm, fills out preceding rolling settlement control in 18- 22cm.Change and fill out the soft base in field and enable to basic unit more solid.Preferably solve the problems, such as that field road is built.
Preferably, in the embodiment shown in fig. 1, seam construction procedure is also included after rolling, treats that grinding coagulation soil is strong Degree reach design strength more than 70% after saw transverse contraction joint every 10m, seam width 1cm, deep 6cm is special using expansion joint joint filling The pitch horseshoe fat cementation of fissures, asphalt flame-retardant matizhi is that to use asphalt be base-material, using chemical adhesive, film forming agent, thickening The bitumastic of agent fiber stabilizer, emery dust and a small amount of fine aggregate composition, fills the coarse aggregate skeleton gap of gap grading Constitute the asphalt of one.With high content coarse aggregate, high content miberal powder, larger asphalt content, low content median diameter The compositing characteristic of particle.
Preferably, also including step S108, after rolling end, health material, and moistening of sprinkling water are covered, timing after 4-6 days Watering health, until terminating during health.
Health is the grinding coagulation soil of the necessary operation that cement concrete strength is formed, especially ultra-dry stiff, due to this Body moisture is few, if carrying out health well not in time, it will cause moisture loss, has a strong impact on the intensity hair of grinding coagulation soil Exhibition, therefore, kept the skin wet during health, it is the important measures for ensureing cement aquation.Grinding coagulation earth forming Fang Houli Later stage health can be carried out, after rolling end, health material, and moistening of sprinkling water is covered immediately, in our be preferable to carry out In example, start after 4-6 days every certain hour watering health.Until the conditioned time for specifying, generally 14 days.
By such scheme, field road concreting can be well solved the problems, such as, being capable of material-saving, materials Simplicity, the concrete road surface for pouring out has service life very high.
A kind of concrete, with 32.5 cement 300kg to count, also including middle sand 0.43-0.51m3, gravel 0.76-0.92m3、 Flyash 0.06-0.08m3
Preferably, with 32.5 cement 300kg to count, also including middle sand 0.47m3, gravel 0.84m3, flyash 0.07m3
A kind of concrete road surface, the cement 300kg included with it is to count, including middle sand 0.43-0.51m3, gravel 0.76- 0.92m3, flyash 0.06-0.08m3
Preferably, the cement 300kg for being included with it to count, also including middle sand 0.47m3, gravel 0.84m3, flyash 0.07m3
It should be noted that herein, such as first and second or the like relational terms are used merely to a reality Body or operation make a distinction with another entity or operation, and not necessarily require or imply these entities or deposited between operating In any this actual relation or order.And, term " including ", "comprising" or its any other variant be intended to Nonexcludability is included, so that process, method, article or terminal device including a series of key elements not only include those Key element, but also other key elements including being not expressly set out, or also include being this process, method, article or end The intrinsic key element of end equipment.In the absence of more restrictions, limited by sentence " including ... " or " including ... " Key element, it is not excluded that also there is other key element in the process including the key element, method, article or terminal device.This Outward, herein, " it is more than ", " being less than ", " exceeding " etc. are interpreted as not including this number;" more than ", " below ", " within " etc. understand It is to include this number.
It should be understood by those skilled in the art that, the various embodiments described above can be provided as method, device or computer program producing Product.These embodiments can be using the embodiment in terms of complete hardware embodiment, complete software embodiment or combination software and hardware Form.All or part of step in the method that the various embodiments described above are related to can be instructed by program correlation hardware come Complete, described program can be stored in the storage medium that computer equipment can read, for performing the various embodiments described above side All or part of step described in method.The computer equipment, including but not limited to:Personal computer, server, general-purpose computations Machine, special-purpose computer, the network equipment, embedded device, programmable device, intelligent mobile terminal, intelligent home device, Wearable Smart machine, vehicle intelligent equipment etc.;Described storage medium, including but not limited to:RAM, ROM, magnetic disc, tape, CD, sudden strain of a muscle Deposit, USB flash disk, mobile hard disk, storage card, memory stick, webserver storage, network cloud storage etc..
The various embodiments described above are with reference to the method according to embodiment, equipment (system) and computer program product Flow chart and/or block diagram are described.It should be understood that every during flow chart and/or block diagram can be realized by computer program instructions The combination of flow and/or square frame in one flow and/or square frame and flow chart and/or block diagram.These computers can be provided Programmed instruction is to the processor of computer equipment producing a machine so that by the finger of the computing device of computer equipment Order is produced for realizing what is specified in one flow of flow chart or multiple one square frame of flow and/or block diagram or multiple square frames The device of function.
These computer program instructions may be alternatively stored in the computer that computer equipment can be guided to work in a specific way and set In standby readable memory so that instruction of the storage in the computer equipment readable memory is produced and include the manufacture of command device Product, the command device is realized in one flow of flow chart or multiple one square frame of flow and/or block diagram or multiple square frame middle fingers Fixed function.
These computer program instructions can be also loaded on computer equipment so that performed on a computing device a series of Operating procedure is to produce computer implemented treatment, so that the instruction for performing on a computing device is provided for realizing in flow The step of function of being specified in one flow of figure or multiple one square frame of flow and/or block diagram or multiple square frames.
Although being described to the various embodiments described above, those skilled in the art once know basic wound The property made concept, then can make other change and modification to these embodiments, so embodiments of the invention are the foregoing is only, Not thereby scope of patent protection of the invention, the equivalent structure that every utilization description of the invention and accompanying drawing content are made are limited Or equivalent flow conversion, or other related technical fields are directly or indirectly used in, similarly it is included in patent of the invention Within protection domain.

Claims (10)

1. a kind of field concrete road surface process for constructing, it is characterised in that comprise the following steps, preparation of construction, ready-mixed concrete, Spread concrete, roll;
The preparation of construction includes step, removes soft base soil, flattening foot layer, and measurement control stake is set in basic unit,
The stirring slow setting soil includes step, by cement 270-330kg, middle sand 0.43-0.51m3, gravel 0.76-0.92m3, powder Coal ash 0.06-0.08m3It is stirred, 160-200s is stirred per tray concrete;
The spread concrete includes step, infiltrates basic unit, uses land leveller spread concrete;
It is described roll step include vibration first pressing 1-2 all over, do not open multiple pressure 1-2 times of shaking, then final pressure is carried out using rubber-tyred roller.
2. field concrete road surface according to claim 1 process for constructing, it is characterised in that preparation of construction also includes step Suddenly, change and fill out the soft base in field, rockfilled slag or gravel 35-45cm in dry land section, fill out preceding rolling settlement control in 9-11cm;In paddy field Section is rockfilled slag or gravel 60-80cm, fills out preceding rolling settlement control in 18-22cm.
3. field concrete road surface according to claim 1 process for constructing, it is characterised in that paving for spread concrete be Number 1.1-1.3, compacted depth 27-33cm.
4. field concrete road surface according to claim 1 process for constructing, it is characterised in that roll step with 30m be one It is individual to roll section, spreading speed 1.5-2m/min.
5. the field concrete road surface process for constructing according to claim any one of 1-4, it is characterised in that also including seam Construction procedure, transverse contraction joint is sawed after grinding coagulation soil intensity reaches more than the 70% of design strength every 10m, stitches width 1cm, deep 6cm, using the pitch horseshoe fat cementation of fissures.
6. field concrete road surface according to claim 5 process for constructing, it is characterised in that also including step, roll knot Shu Hou, covers health material, and moistening of sprinkling water, health of regularly being sprinkled water after 4-6 days, until terminating during health.
7. a kind of concrete, it is characterised in that with 32.5 cement 300kg to count, also including middle sand 0.43-0.51m3, gravel 0.76-0.92m3, flyash 0.06-0.08m3
8. a kind of concrete according to claim 7, it is characterised in that with 32.5 cement 300kg to count, also including middle sand 0.47m3, gravel 0.84m3, flyash 0.07m3
9. a kind of concrete road surface, it is characterised in that the cement 300kg included with it is to count, including middle sand 0.43-0.51m3, gravel Stone 0.76-0.92m3, flyash 0.06-0.08m3
10. concrete road surface according to claim 9, it is characterised in that the cement 300kg included with it is also wrapped to count Include middle sand 0.47m3, gravel 0.84m3, flyash 0.07m3
CN201611108915.XA 2016-12-06 2016-12-06 A kind of field concrete road surface, process for constructing and concrete Expired - Fee Related CN106758649B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611108915.XA CN106758649B (en) 2016-12-06 2016-12-06 A kind of field concrete road surface, process for constructing and concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611108915.XA CN106758649B (en) 2016-12-06 2016-12-06 A kind of field concrete road surface, process for constructing and concrete

Publications (2)

Publication Number Publication Date
CN106758649A true CN106758649A (en) 2017-05-31
CN106758649B CN106758649B (en) 2019-06-28

Family

ID=58879138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611108915.XA Expired - Fee Related CN106758649B (en) 2016-12-06 2016-12-06 A kind of field concrete road surface, process for constructing and concrete

Country Status (1)

Country Link
CN (1) CN106758649B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107805989A (en) * 2017-09-21 2018-03-16 中国电建集团华东勘测设计研究院有限公司 Temporary road rolling compacted concrete pavement reconstruction structure and its construction method
CN108677643A (en) * 2018-06-22 2018-10-19 杜宇 A kind of grinding coagulation soil composite pavement and preparation method thereof for not cracking, being not required to setting expansion or contraction joints

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100999889A (en) * 2006-12-30 2007-07-18 易志坚 Road surface structure of rolling flexiable fibre cement concrete and construction method thereof
CN101082199A (en) * 2007-07-05 2007-12-05 吴永芳 Road surface structure and construction method therefor
KR100924765B1 (en) * 2009-07-22 2009-11-05 (주) 지오시스 Road pavement composition of enhanced retentiveness and drainage, and constructing method using the composition
CN104446207A (en) * 2014-12-01 2015-03-25 中国电建集团贵阳勘测设计研究院有限公司 Fly ash concrete and mix proportion design method thereof
CN105776996A (en) * 2016-02-16 2016-07-20 河海大学 Ecological concrete with low manufacturing cost and preparing method of ecological concrete

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100999889A (en) * 2006-12-30 2007-07-18 易志坚 Road surface structure of rolling flexiable fibre cement concrete and construction method thereof
CN101082199A (en) * 2007-07-05 2007-12-05 吴永芳 Road surface structure and construction method therefor
KR100924765B1 (en) * 2009-07-22 2009-11-05 (주) 지오시스 Road pavement composition of enhanced retentiveness and drainage, and constructing method using the composition
CN104446207A (en) * 2014-12-01 2015-03-25 中国电建集团贵阳勘测设计研究院有限公司 Fly ash concrete and mix proportion design method thereof
CN105776996A (en) * 2016-02-16 2016-07-20 河海大学 Ecological concrete with low manufacturing cost and preparing method of ecological concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107805989A (en) * 2017-09-21 2018-03-16 中国电建集团华东勘测设计研究院有限公司 Temporary road rolling compacted concrete pavement reconstruction structure and its construction method
CN108677643A (en) * 2018-06-22 2018-10-19 杜宇 A kind of grinding coagulation soil composite pavement and preparation method thereof for not cracking, being not required to setting expansion or contraction joints

Also Published As

Publication number Publication date
CN106758649B (en) 2019-06-28

Similar Documents

Publication Publication Date Title
CN107059573B (en) Construction method for solidifying soil body as road water stabilization layer
JP6841964B2 (en) Construction method of combined dam
CN108842557B (en) Temporary road pavement structure and road building method
CN107746223A (en) A kind of RCCD and its construction method
CN104556887B (en) Cement stabilized base course material, prepare, apply and the preparation method of roadbase
CN103882788B (en) Based on the method for constructing roadway of the modification roller compacted concrete surface layer of enzyme soil cured substrate layer
CN100999890A (en) Road surface structure of felexiable fibre emulsifying asphalt stable material as base and construction method thereof
CN109914178A (en) A kind of biological enzyme curing materials integration paved roads construction method
CN106192907A (en) Set up the construction method of 150m~the 300m level high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN101619557A (en) Pavement base course material prepared from brick mixed building rubbish regenerated aggregate and preparation method thereof
CN106587835A (en) Cold-mixed cement-emulsified asphalt concrete and pavement method thereof
CN112681079A (en) Soil body solidification and concrete cap surface gathering construction method applied to temporary road foundation
CN106758649B (en) A kind of field concrete road surface, process for constructing and concrete
CN207244376U (en) A kind of creepage concrete compression-resistance pavement structure
CN108570897A (en) A kind of paving method of pavement of road base
CN106677003A (en) Pervious concrete structure and preparation method thereof
CN113668309A (en) Road construction method
CN113755176A (en) In-situ hardened soil road and soil curing material and preparation and construction method thereof
CN103422407A (en) Construction process using cement diatomite to stabilize desert sand mixture to build Niger desert road
CN112500039A (en) Construction method of steel slag permeable pavement brick
CN204940039U (en) Plant stone Bridge Surface Paving by Cement structure for one kind
CN104878672A (en) Stone-planted cement concrete bridge deck paving structure and method
CN107032706B (en) It is a kind of to use drift-sand for the sub-surface forming method of raw material
CN213115347U (en) Dampproof ground
CN111535323A (en) Full-section quasi-tertiary matching long-age roller compacted concrete construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Rao Songwang

Inventor after: Chen Yanhua

Inventor after: Shen Qi

Inventor after: Huang Dehua

Inventor after: Xu Zichang

Inventor after: Rao Qiuying

Inventor after: Rao Bin

Inventor before: Rao Songwang

Inventor before: Chen Yanhua

Inventor before: Shen Qi

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20180730

Address after: 350001 Kimcheon Road, Gulou District, Fuzhou, Fujian 38

Applicant after: Fujian land development and Consolidation Center

Applicant after: Fujian geological remote sensing and Geographic Information Service Center

Address before: 350001 Kimcheon Road, Gulou District, Fuzhou, Fujian 38

Applicant before: Fujian land development and Consolidation Center

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190628

CF01 Termination of patent right due to non-payment of annual fee