CN106682877A - Method of project management - Google Patents
Method of project management Download PDFInfo
- Publication number
- CN106682877A CN106682877A CN201611242901.7A CN201611242901A CN106682877A CN 106682877 A CN106682877 A CN 106682877A CN 201611242901 A CN201611242901 A CN 201611242901A CN 106682877 A CN106682877 A CN 106682877A
- Authority
- CN
- China
- Prior art keywords
- project
- data
- information
- item
- server
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Engineering & Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Operations Research (AREA)
- Economics (AREA)
- Marketing (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The embodiment of the invention relates to a method of project management. The method of project management includes the steps: receiving the information of a new project by means of a server, wherein the information of a new project includes a project ID; according to the project ID, acquiring the development plan information; according to the development time data and the development content data, generating the project development schedule data; according to the project ID, acquiring the design plan information which includes the design time data and the design content data; according to the design plan information and the project development schedule data, generating the project design schedule data; performing contrastive analysis on the project development schedule data and the project design schedule data, and generating the project development plan data; performing time node dividing on the project development plan data, and according to the divided time node, performing analysis processing on the project development plan data, and generating the progress node data; and according to the progress node data, generating the project management display data, and sending the project management display data to a user terminal.
Description
Technical field
The present invention relates to project supervision technical field, more particularly to a kind of method of project management.
Background technology
As society develops rapidly, engineering construction project is also more and more, and an engineering construction project includes multiple individual events
Engineering, any one individual works include multiple construction units again.Project management is carried out to engineering project can be limited in limited resources
The management personnel of ancillary works project carry out overall control to project under fixed condition, for example:Control cost, item controlled progress,
Prediction profit, realizes or the demand more than project settings and expectation.
However as the development of society, engineering project tends to complication, variation, involved in project monitor and control or project supervision
And project management, field management, cost management, Benefit management etc., traditional project supervision method can not again meet day
The different project management of crescent is required.
The content of the invention
The purpose of the present invention is the defect for prior art, there is provided a kind of method of project management, can formulate accurately,
The management of optimization shows form, using the teaching of the invention it is possible to provide in time, accurately, easily carries out data processing, improves the efficiency of project management,
The burden of project manager's manual handle data is reduced, human resourcess are saved.
In view of this, a kind of method of project management is embodiments provided, including:
Server receives new projects information;The new projects information includes item id;
Development plan information is obtained according to the item id;The development plan information includes development time data and exploitation
Content-data;
Project development project table data are generated according to the development time data and exploitation content-data;
Planned design information is obtained according to the item id;The planned design information includes design time data and design
Content-data;
According to the planned design information and the project development planning table data genaration Project design planning chart data;
The project development planning table data and the Project design planning chart data are analyzed, project is generated
Development plan data;
Timing node cutting is carried out to the project development planning data, project is opened according to the timing node that cutting is obtained
Sending out planning data carries out dissection process, generates progress node data;
Project management video data is generated according to the progress node data, and is sent to user terminal, to by institute
State user terminal and the project management video data is shown as into project management display form.
Preferably, methods described also includes:
The engineering progress data of the user terminal receiving user's input, and it is sent to the server;The engineering is entered
Degrees of data includes item id;
The server is carried out the engineering progress data and the progress node data according to the item id
Match somebody with somebody;
When the project progress number with and the progress node data mismatch when, generate progress early warning and report, and send
To the user terminal.
It is further preferred that it is described when the engineering progress data with and the progress node data mismatch when, give birth to
Into progress early warning report, and after showing, methods described also includes:
The user terminal receives the project adjustment information of the user input;The project adjustment information includes project
ID;
The project development planning data is adjusted according to the project adjustment information.
Preferably, before the server receives new projects information, methods described also includes:
The user terminal receives the new projects information of the user input, and is sent to the server;It is described new
New-added item mesh information includes item id.
Preferably, methods described also includes:
The user terminal receives the project of the user input and suspends information, and is sent to the server;The item
Mesh suspends information includes item id and time out information;
The project development planning data is kept in project and suspends number by the server according to the time out information
According in storehouse.
It is further preferred that methods described also includes:
The user terminal receives the project restarting information of the user input, and is sent to the server;The item
Mesh suspends information includes item id and reboot time information;
The server deletes described according to the reboot time information and item id in the project suspends data base
Project suspends information.
It is further preferred that being suspended in the project according to the reboot time information and item id in the server
After the project time-out information is deleted in data base, methods described also includes:
The server updates the project according to the item id, time out information and reboot time information
Development plan data;
Progress node data is regenerated according to the project development planning data.
Preferably, methods described also includes:
The user terminal receives the deletion of items information of the user input, and is sent to the server;The item
Mesh deletes information includes the item id;
The server deletes corresponding project development planning data and/or progress node data according to the item id.
Preferably, methods described also includes:
The user terminal receives the project of the user input and completes information, and is sent to the server;The item
Mesh completes information including the item id;
The server obtains corresponding project management video data according to the item id;
Project acceptance inspection video data is generated according to the project management video data, and is sent to user terminal.
A kind of method of project management provided in an embodiment of the present invention, can formulate accurate, optimization management and show form,
Can provide it is timely, accurate, easily carry out data processing, improve the efficiency of project management, reduce project manager
The burden of manual handle data, saves human resourcess.
Description of the drawings
Fig. 1 is a kind of method flow diagram of project management provided in an embodiment of the present invention.
Specific embodiment
Below by drawings and Examples, technical scheme is described in further detail.
A kind of method of project management that the present embodiment is provided, in can apply to various project managements, its covering
Approve and initiate a project, progress control, the project acceptance inspection, project suspend, project recover etc. each stage.
Fig. 1 is a kind of method flow diagram of project management provided in an embodiment of the present invention, as shown in figure 1, including:
Step 110, server receives new projects information.
Specifically, the new projects information of user terminal receiving user's input, and it is sent to server;New projects information
Include item id.
Wherein, each project has an item id, and disparity items makes a distinction according to item id, and all of operation is all
Carried out based on item id.Wherein, item id can be that system is automatically generated, or user input.
New projects information, information of as setting up the project, except item id, new projects information can also include the personnel of project
Distribution information, such as can include project house steward, project leader, product owner, exploitation director, designer and exploitation
Personnel etc..
User, can be project leader, or project manager.One project can have multiple project leaders,
Same project leader can also simultaneously be responsible for multiple projects.
Additionally, having signed contract if when project starts, then this can be added in new projects information
Purpose associates contract information.Association contract information refers to the contract information involved by the project, it may be possible to a contract, it is also possible to
It is multiple contracts, it is also possible to be to be related to multiple projects in a contract.Association is added to close in new projects information
Same information, is easy for calling inquiry during project management.The information such as project income, time requirement can such as be obtained.Association contract
The input of information can be the method be somebody's turn to do by Selection and call in the server realizing, also support what user directly inputted certainly
Mode.
In practical operation, also have in many cases, at the beginning of project starts project verification contract is not also formed, therefore can be with
After approving and initiate a project, the association contract information of project is added.
Step 120, according to item id development plan information is obtained.
Specifically, exploration project ID and development plan information are one-to-one.Development plan information is related by project
Developer setting, the development plan information of all items is stored within project development list of schedules, development plan letter
Breath can be previously stored with professional template base, and development plan information can include development time data and exploitation content-data, open
Sending out content-data can include budget forecast data, quality control data.Wherein, development time data can include project development
Time started and terminate the time;Budget forecast data refers to that prediction project wants input.
Step 130, according to development time data and exploitation content-data project development project table data are generated.
Specifically, server according to item id obtain in project development list of schedules it is corresponding send out plan information it
Afterwards, project development planning table data are automatically generated according to the development time data and exploitation content-data sent out in plan information,
Project development planning table data include development time data and exploitation content-data.
Step 140, according to item id planned design information is obtained.
Specifically, exploration project ID and planned design information are one-to-one.Planned design information is related by project
Designer setting, the planned design information of all items is stored within Project design list of schedules, planned design letter
Breath is set in advance, and planned design information can include design time data and design content data, and design content data can
With including budget forecast data, quality control data.Wherein, design time data can include project development time started and
The termination time;Budget forecast data refers to that prediction project wants input.
Step 150, according to planned design information and project development planning table data genaration Project design planning chart data.
Wherein, Project design planning chart data are design time data, Budgetary Forecast number in planned design information
Project development planning table data are carried out optimization processing according to, quality control data.
Step 160, project development planning table data and Project design planning chart data are analyzed, and generate project
Development plan data.
Wherein, project development planning data be to project development planning table data and Project design planning chart data the two
The optimization processing of data, so as to get project development planning data more rationalize.
Step 170, to project development planning data timing node cutting is carried out, and the timing node obtained according to cutting is to item
Mesh development plan data carry out dissection process, generate progress node data.
Specifically, according to timing node to project development planning data in every content carry out cutting, obtain progress section
Point data, progress node data can include Budgetary Forecast registration list data and management work order data.Wherein, management work order number
According to project, Quality Inspection Point, quality control requirement, the task instruction for above showing project supervision etc. information.
Step 180, according to progress node data project management video data is generated, and is sent to user terminal, to logical
Cross user terminal and project management video data is shown as into project management display form.
Wherein, the transmission can be event triggering, such as the project management of user terminal receiving user's input is obtained and referred to
Order, and server is sent to, project management obtains instruction includes item id;Server obtains project management and shows according to item id
Registration evidence, and user terminal is sent to, project management video data is shown as project management and shows form, user by user terminal
Can be checked on the subscriber terminal.
The transmission can also be what is set based on the generation of project management video data, when the server is according to entering
Degree node data is generated after project management video data, and server is by project management video data and is sent to user terminal,
Project management video data is shown as project management and shows form by user terminal, and user can on the subscriber terminal check project
Management shows form.
In project launch, project leader can show that form carries out supervising to project by project management,
Specifically may include steps of:
First, the engineering progress data of user terminal receiving user's input, and it is sent to server;Engineering progress data bag
Include item id.
In a specific example, project management video data can be distributed project by server according to the time to be responsible for
On the mobile terminal device of people, such as the work order on the same day is distributed daily, the item that same day needs are completed is included in the work order on the same day
Mesh, qualifying point etc., additionally provide quality control supervision information input item, cost payout item, construction operation information input item
Deng enabling project leader to be manipulated by mobile terminal device and be input into corresponding information being fed back.The letter being input into
Breath can specifically include live cost payout data (dinner cost, transportation expenses, communication expense and the other fees that occurred including the same day), matter
Amount control supervision information (including the actual field data for each qualifying point), construction operation information (were applied including the same day
Work completes content, retains problem feedback information etc.).
Server generates engineering progress data, engineering progress data according to the corresponding information of input that project leader is input into
Including item id.Wherein, it can generate according to prefixed time interval to generate engineering progress data, such as according to engineering phase,
Often completing a stage generates the stage engineering progress data, or daily 18:00 generates same day engineering progress data, it is also possible to
It is each generation for having continuity according to engineering progress by the engineering progress data of stream day to the same day.Specifically can be according to user
It is actually needed and is configured.Certainly can be by server-side user manual request form, user engineering is received the number of degrees being entered
When according to request is generated, the final updating data by the end of current time are captured, generate engineering progress data.
Secondly, server is matched engineering progress data with progress node data according to item id.
Specifically, server obtains corresponding progress node data, and the project progress number that will be generated according to item id
According to being matched according to timing node with progress node data.
Finally, when project progress number with and progress node data mismatch when, generate progress early warning and report, and be sent to use
Family terminal.
In a specific example, if when project proceeds to a certain stage, the actual expenses of project exceed plan
When the expenditure that should occur during to the stage exceedes threshold value, early warning is produced.Project manager is after early warning is connected to
Project actual expenses situation can be just checked, over-expense reason is confirmed, and can accordingly adjust subsequent project expenditure, so that project is most
An artificial situation at the end of end disclosure satisfy that budgetary request.Or if nonadjustable reasonable expenditure, then need follow-up
Need to be noted that in budget program when having similar item again.
User terminal receive user reports the project adjustment information of input according to early warning;Project adjustment information includes project
ID;According to project adjustment information adjusted iterm development plan data.Early warning is now produced, project pipe director can be allowed to cause weight
Depending on again close examination is checked to have completed part to project, and the reasonability to budget is checked, when having similar item again from now on
Can more accurately make a plan.
When project needs to suspend for some reason, the project of user terminal receiving user's input suspends information, concurrently
Give server;Project suspends information includes item id and time out information;Server is according to time out information by project
Development plan data are kept in project and are suspended in data base.
When project needs to restart, the project restarting information of user terminal receiving user's input, and it is sent to server;
Mesh suspends information includes item id and reboot time information;Server suspends according to reboot time information and item id in project
Project is deleted in data base and suspends information.And server is according to item id, time out information and reboot time information, update
Corresponding project development planning data;New progress node data is regenerated according to project development planning data.
Need to carry out an acceptance inspection project after project is completed, specifically, the project of user terminal receiving user's input is complete
Into information, and it is sent to server;Project completes information including item id;Server obtains corresponding project according to item id
Management video data;Project acceptance inspection video data is generated according to project management video data, and is sent to user terminal, the user
Terminal can be the user terminal of the user terminal of project leader, or project acceptance inspection personnel, and user tests according to project
Receive video data to carry out an acceptance inspection project.
No matter in project is carried out, or before project is not opened, deletion of items is can be carried out, specifically, user's end
The deletion of items information of end receiving user's input, and it is sent to server;Deletion of items information includes item id;Server according to
Item id deletes corresponding all information, can include in the project development planning data or progress node data of the project
Plant or various.
A kind of method of project management provided in an embodiment of the present invention, can formulate accurate, optimization management and show form,
Can provide it is timely, accurate, easily carry out data processing, improve the efficiency of project management, reduce project manager
The burden of manual handle data, saves human resourcess.
Professional should further appreciate that, with reference to each example of the embodiments described herein description
Unit and algorithm steps, can with electronic hardware, computer software or the two be implemented in combination in, it is hard in order to clearly demonstrate
The interchangeability of part and software, according to function has generally described the composition and step of each example in the above description.
These functions are performed with hardware or software mode actually, depending on the application-specific and design constraint of technical scheme.
Professional and technical personnel can use different methods to realize described function to each specific application, but this realization
It is not considered that beyond the scope of this invention.
Can be with hardware, computing device with reference to the method for the embodiments described herein description or the step of algorithm
Software module, or the combination of the two is implementing.Software module can be placed in random access memory (RAM), internal memory, read only memory
(ROM), electrically programmable ROM, electrically erasable ROM, depositor, hard disk, moveable magnetic disc, CD-ROM or technical field
In any other form of storage medium well known to interior.
Above-described specific embodiment, has been carried out further to the purpose of the present invention, technical scheme and beneficial effect
Describe in detail, should be understood that the specific embodiment that the foregoing is only the present invention, be not intended to limit the present invention
Protection domain, all any modification, equivalent substitution and improvements within the spirit and principles in the present invention, done etc. all should include
Within protection scope of the present invention.
Claims (9)
1. a kind of method of project management, it is characterised in that methods described includes:
Server receives new projects information;The new projects information includes item id;
Development plan information is obtained according to the item id;The development plan information includes development time data and exploitation content
Data;
Project development project table data are generated according to the development time data and exploitation content-data;
Planned design information is obtained according to the item id;The planned design information includes design time data and design content
Data;
According to the planned design information and the project development planning table data genaration Project design planning chart data;
The project development planning table data and the Project design planning chart data are analyzed, project development is generated
Planning data;
Timing node cutting is carried out to the project development planning data, the timing node obtained according to cutting is to project development meter
Drawing data carries out dissection process, generates progress node data;
Project management video data is generated according to the progress node data, and is sent to user terminal, to by the use
The project management video data is shown as project management and shows form by family terminal.
2. the method for a kind of project management according to claim 1, it is characterised in that methods described also includes:
The engineering progress data of the user terminal receiving user's input, and it is sent to the server;The project progress number
According to including item id;
The server is matched the engineering progress data with the progress node data according to the item id;
When the project progress number with and the progress node data mismatch when, generate progress early warning and report, and be sent to institute
State user terminal.
3. the method for a kind of project management according to claim 2, it is characterised in that described when the project progress number
During according to mismatching with the progress node data, progress early warning report is generated, and after showing, methods described also includes:
The user terminal receives the project adjustment information of the user input;The project adjustment information includes item id;
The project development planning data is adjusted according to the project adjustment information.
4. the method for a kind of project management according to claim 1, it is characterised in that receive new new-added item in the server
Before mesh information, methods described also includes:
The user terminal receives the new projects information of the user input, and is sent to the server;The new new-added item
Mesh information includes item id.
5. the method for a kind of project management according to claim 1, it is characterised in that methods described also includes:
The user terminal receives the project of the user input and suspends information, and is sent to the server;The project is temporary
Stop information including item id and time out information;
The project development planning data is kept in project and suspends data base by the server according to the time out information
In.
6. the method for a kind of project management according to claim 5, it is characterised in that methods described also includes:
The user terminal receives the project restarting information of the user input, and is sent to the server;The project is temporary
Stop information including item id and reboot time information;
The server deletes the project according to the reboot time information and item id in the project suspends data base
Time-out information.
7. the method for a kind of project management according to claim 6, it is characterised in that in the server according to described heavy
Temporal information and item id are opened, after the project time-out information is deleted in project time-out data base, methods described is also
Including:
The server updates the project development according to the item id, time out information and reboot time information
Planning data;
Progress node data is regenerated according to the project development planning data.
8. the method for a kind of project management according to claim 1, it is characterised in that methods described also includes:
The user terminal receives the deletion of items information of the user input, and is sent to the server;The project is deleted
Except information includes the item id;
The server deletes corresponding project development planning data and/or progress node data according to the item id.
9. the method for a kind of project management according to claim 1, it is characterised in that methods described also includes:
The user terminal receives the project of the user input and completes information, and is sent to the server;The project is complete
Include the item id into information;
The server obtains corresponding project management video data according to the item id;
Project acceptance inspection video data is generated according to the project management video data, and is sent to user terminal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611242901.7A CN106682877A (en) | 2016-12-29 | 2016-12-29 | Method of project management |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611242901.7A CN106682877A (en) | 2016-12-29 | 2016-12-29 | Method of project management |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106682877A true CN106682877A (en) | 2017-05-17 |
Family
ID=58872350
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611242901.7A Pending CN106682877A (en) | 2016-12-29 | 2016-12-29 | Method of project management |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106682877A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109034744A (en) * | 2018-07-28 | 2018-12-18 | 万翼科技有限公司 | Feedback method, device and the computer readable storage medium of item nodes state |
CN109213816A (en) * | 2018-08-06 | 2019-01-15 | 国网福建省电力有限公司信息通信分公司 | A method of early warning analysis is carried out based on the electric network data obtained in real time |
CN109544097A (en) * | 2018-10-19 | 2019-03-29 | 中国平安人寿保险股份有限公司 | Monthly closing entry information processing method, electronic device and readable storage medium storing program for executing based on new product development |
CN109783488A (en) * | 2018-12-12 | 2019-05-21 | 平安科技(深圳)有限公司 | Project Management Information processing method, device, server and storage medium |
CN109949006A (en) * | 2019-03-13 | 2019-06-28 | 深圳市元征科技股份有限公司 | A kind of project management method, device and relevant device |
CN109978512A (en) * | 2019-04-10 | 2019-07-05 | 上海外高桥造船有限公司 | The control method of project management system, electronic equipment, storage medium |
CN110009308A (en) * | 2019-04-10 | 2019-07-12 | 上海外高桥造船有限公司 | Project management system |
CN110321467A (en) * | 2019-05-30 | 2019-10-11 | 广东民航机场建设有限公司 | Airport engineering project information methods of exhibiting, device, system, equipment and medium |
CN110610350A (en) * | 2019-08-30 | 2019-12-24 | 深圳市元征科技股份有限公司 | Project management method, device and equipment |
CN110705959A (en) * | 2019-09-12 | 2020-01-17 | 武汉儒松科技有限公司 | Project management method, device, equipment and medium based on risk big data |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040122724A1 (en) * | 2002-12-20 | 2004-06-24 | Hung-Shan Wei | System and method for generating priorities of manufacturing orders |
CN104636855A (en) * | 2013-11-06 | 2015-05-20 | Ips株式会社 | Project data management server and project data management program |
CN104751269A (en) * | 2014-11-13 | 2015-07-01 | 淳正兴 | Engineering maintenance scheduling management system |
CN106096905A (en) * | 2016-05-31 | 2016-11-09 | 北京诚公通信工程监理股份有限公司 | A kind of project management method and system |
-
2016
- 2016-12-29 CN CN201611242901.7A patent/CN106682877A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040122724A1 (en) * | 2002-12-20 | 2004-06-24 | Hung-Shan Wei | System and method for generating priorities of manufacturing orders |
CN104636855A (en) * | 2013-11-06 | 2015-05-20 | Ips株式会社 | Project data management server and project data management program |
CN104751269A (en) * | 2014-11-13 | 2015-07-01 | 淳正兴 | Engineering maintenance scheduling management system |
CN106096905A (en) * | 2016-05-31 | 2016-11-09 | 北京诚公通信工程监理股份有限公司 | A kind of project management method and system |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109034744A (en) * | 2018-07-28 | 2018-12-18 | 万翼科技有限公司 | Feedback method, device and the computer readable storage medium of item nodes state |
CN109213816A (en) * | 2018-08-06 | 2019-01-15 | 国网福建省电力有限公司信息通信分公司 | A method of early warning analysis is carried out based on the electric network data obtained in real time |
CN109544097A (en) * | 2018-10-19 | 2019-03-29 | 中国平安人寿保险股份有限公司 | Monthly closing entry information processing method, electronic device and readable storage medium storing program for executing based on new product development |
CN109544097B (en) * | 2018-10-19 | 2024-04-05 | 中国平安人寿保险股份有限公司 | Moon knot information processing method based on new product development, electronic device and readable storage medium |
CN109783488A (en) * | 2018-12-12 | 2019-05-21 | 平安科技(深圳)有限公司 | Project Management Information processing method, device, server and storage medium |
CN109783488B (en) * | 2018-12-12 | 2024-03-12 | 平安科技(深圳)有限公司 | Project management information processing method, device, server and storage medium |
CN109949006A (en) * | 2019-03-13 | 2019-06-28 | 深圳市元征科技股份有限公司 | A kind of project management method, device and relevant device |
CN109978512A (en) * | 2019-04-10 | 2019-07-05 | 上海外高桥造船有限公司 | The control method of project management system, electronic equipment, storage medium |
CN110009308A (en) * | 2019-04-10 | 2019-07-12 | 上海外高桥造船有限公司 | Project management system |
CN110321467A (en) * | 2019-05-30 | 2019-10-11 | 广东民航机场建设有限公司 | Airport engineering project information methods of exhibiting, device, system, equipment and medium |
CN110610350A (en) * | 2019-08-30 | 2019-12-24 | 深圳市元征科技股份有限公司 | Project management method, device and equipment |
CN110705959A (en) * | 2019-09-12 | 2020-01-17 | 武汉儒松科技有限公司 | Project management method, device, equipment and medium based on risk big data |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106682877A (en) | Method of project management | |
US10359997B2 (en) | Project modeling using iterative variable defect forecasts | |
CN106096905A (en) | A kind of project management method and system | |
US20150127579A1 (en) | Method and apparatus to present an integrated process modeler | |
US20150082281A1 (en) | System and Method for Providing Access to Data in a Plurality of Software Development Systems | |
US20130218626A1 (en) | Utilizing historic projects to estimate a new project schedule based on user provided high level parameters | |
CN108074072A (en) | A kind of financial transaction approval process management method | |
Gipson | An introduction to Sked | |
CN109961264A (en) | A kind of enterprise information management system and management method | |
CN105654243B (en) | A kind of project information automated programming system based on trajectory diagram | |
CN109325024A (en) | Label display method, apparatus, terminal device and the storage medium of project | |
Farid et al. | Visualization and scheduling of non-functional requirements for agile processes | |
CN105787633A (en) | System and method for processing concurrent examining and approving flow | |
Imanuel et al. | Development of Financial Planner Application Software Based on Waterfall Model | |
EP3109811A1 (en) | Certification management system | |
CN117291517A (en) | Method and device for constructing approval process | |
Hu | Information lifecycle modeling framework for construction project lifecycle management | |
DE102022210484A1 (en) | Smart multi-vehicle charging through learned experience | |
US10324594B2 (en) | Enterprise protocol management | |
CN109741157A (en) | A kind of processing method and system of budget overruns management | |
CN113240384A (en) | Salary statistical accounting method and device | |
Simonova | Identification of IT-service metrics for a business process when planning a transition to outsourcing | |
Kurz et al. | HITL-AB-BPM: Business Process Improvement with AB Testing and Human-in-the-Loop. | |
Li et al. | Implementation of agile development software based on project management | |
Karapantelakis | Estimating costs for adopting and using model-based testing in agile SCRUM teams |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170517 |