CN106638648A - Deviation rectifying method of open caisson - Google Patents

Deviation rectifying method of open caisson Download PDF

Info

Publication number
CN106638648A
CN106638648A CN201611189590.2A CN201611189590A CN106638648A CN 106638648 A CN106638648 A CN 106638648A CN 201611189590 A CN201611189590 A CN 201611189590A CN 106638648 A CN106638648 A CN 106638648A
Authority
CN
China
Prior art keywords
mud
open caisson
mudhole
construction
forced landing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611189590.2A
Other languages
Chinese (zh)
Other versions
CN106638648B (en
Inventor
叶香竹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU TANGYUAN BIOLOGICAL POWER Co.,Ltd.
Original Assignee
叶香竹
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 叶香竹 filed Critical 叶香竹
Priority to CN201611189590.2A priority Critical patent/CN106638648B/en
Priority to CN201810855115.7A priority patent/CN109024648B/en
Publication of CN106638648A publication Critical patent/CN106638648A/en
Application granted granted Critical
Publication of CN106638648B publication Critical patent/CN106638648B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons

Abstract

The invention discloses a deviation rectifying method of an open caisson. The deviation rectifying method is characterized in that mud discharging holes are formed at the periphery of the open caisson, the diameter of each of the mud discharging hole is 0.15-0.3m, the interval among the mud discharging holes in a main forced landing direction is 0.8m, the interval among the mud discharging holes in a side forced landing direction is 0.8-1.3m, the closer the mud discharging holes in the side forced landing direction to a main forced landing shaft, the smaller the interval is, the adjacent intervals of the mud discharging holes in the side forced landing direction decreases in sequence along the side forced landing shaft, and the decreasing range is 50-100mm; interval construction is adopted when mud absorbing is conducted, that is, the mud discharging holes are arranged according to a sequence, construction is firstly conducted on the mud discharging holes in an odd number sequence, and then construction is conducted on the mud discharging holes in an even number sequence; arrangement is conducted on mud absorbing construction according to the condition of the deviation rectifying amount, the deviation rectifying amount of each time is less than or equal to 5cm, when target deviation rectifying amount is big, a multi-wheel mud absorbing construction technology is adopted, and the intermittence of the construction time of mud absorbing between adjacent wheels is no less than 30min. According to the deviation rectifying method of the open caisson, the operation technology is reliable, and the deviation rectifying effect is good.

Description

The method for correcting error of open caisson
Technical field
The present invention relates to a kind of method for correcting error of open caisson, it is adaptable to municipal field.
Background technology
Open caisson construction is improper to cause inclination of open caisson accident, and during the correction for inclining open caisson, subsoil extraction is traditional Method for correcting error.But currently used soil digging technique needs first to excavate operation well or operation slot mostly, then in operation well or Soil digging is carried out to open caisson edge with various methods in person's operation slot, back work amount is larger and rectifying effect is not obvious.Particularly In the case where level of ground water is higher, construction can become difficult because of operation well or operation slot internal water accumulation.Can be using suction mud Mode carries out stress removal to inclination of open caisson position so as to reach rectifying effect, mudding is inhaled in this process and closes whether measure has Effect property is to concern correction success or failure.
The content of the invention
The present invention is to provide a kind of method for correcting error of open caisson, solves the problems, such as that open caisson deviation rectification effect is bad.
Mudhole, a diameter of 0.15~0.3m of mudhole, main forced landing direction mudhole are arranged around open caisson in the present invention Spacing is 0.8m, and side forced landing direction mud extraction pitch of holes is 0.8~1.3m, side force-land direction mudhole from main forced landing shaft more close to spacing Less, sides adjacent forced landing direction mud extraction pitch of holes is reduced successively along side forced landing shaft, and reduction amplitude is 50~100mm.
Mud extraction hole depth is closely related with rectifying effect, has carried out lot of experiments situation for this, table 1 be mud extraction hole depth with Settlement relationship, result of the test shows that sedimentation gradually increases as mud extraction hole depth increases, and increases to certain amplitude sedimentation and tends to flat Surely.
According to many experimental results, mixed economy factor, mud extraction hole depth determines according to soil property situation, when open caisson bottom is During clay, mud extraction hole depth is 2m below open caisson bottom;When open caisson bottom is silt, mud extraction hole depth is below open caisson bottom 1.5m;When open caisson bottom is muck soil, mud extraction hole depth is 1m below open caisson bottom;When open caisson bottom is sand, go out Mud hole depth is 0.5m below open caisson bottom.
The mud extraction hole depth of table 1 and settlement relationship
Using interval construction when inhaling mud, i.e., in order mudhole carried out into layout, the mudhole of odd number order of first constructing, The mudhole of even number order of constructing again.
Inhale mud construction arranged according to correction amount situation, each correction amount be less than or equal to 5cm, when target correction amount compared with When big, mud construction technologies are inhaled using wheel more, adjacent wheels inhale the mud construction intermittent time no less than 30min, it is to avoid sediment failure.
The drilling rod of construction mudhole carries air intake duct, dredging tube and gas tube, and rubber bulb is installed in drilling rod bottom.Bar drill to be drilled To mudhole bottom, then 0.6m is lifted, the rubber bulb of drilling rod bottom is inflated, air pressure is 0.3~0.4MPa.Rubber bulb rises The effect of closing mudhole, then clay is clogged on rubber bulb further seal, clay refilling thickness is 0.3~0.4m. Then the air compressor machine being connected with drilling rod air intake duct is started, the space below rubber bulb forms negative pressure, treats that negative pressure reaches 75~85MPa When close air compressor machine, starting the siphon suction dredge being connected with dredging tube carries out suction operation.
Because the factors such as native bore deformation cause vacuum to decay in work progress, the excessive vacuum decay of drilling rod hoisting depth Can be excessive.Due to the pressure change size of closed gas it is related to volume of air, if drilling rod hoisting depth is too small to cause true Reciprocal of duty cycle amplitude of variation is excessive, it is difficult to maintain expected vacuum.Because here drilling rod hoisting depth determines according to test, table 2 is brill Bar hoisting depth and the relation of vacuum, determine that drilling rod hoisting depth is 0.6m according to table 1.
Table 2 is the relation of drilling rod hoisting depth and vacuum
Drilling rod hoisting depth/m Maintain vacuum/MPa
0.4 63
0.4 61
0.4 60
0.5 72
0.5 70
0.5 73
0.6 78
0.6 80
0.6 81
0.7 75
0.7 74
0.7 73
0.8 65
0.8 64
0.8 67
Duct can be backfilled with sand after correction purpose is reached, and continue the sedimentation situation for observing open caisson, the sedimentation of 7 days back open caissons In unsteady phenomena, i.e. settling amount more than 0.05mm/d, the grouting and reinforcing soil body is carried out.
Operating procedure reliability of the present invention, rectifying effect is good.
Description of the drawings
The correction schematic diagram of Fig. 1 open caissons.
1st, open caisson, 2, mudhole.
Specific embodiment
The present embodiment is described in detail below in conjunction with accompanying drawing.
The differential settlement of certain open caisson east and west reaches 110mm, and open caisson bottom is clay.
Mudhole is arranged around open caisson, a diameter of 0.2m of mudhole, main forced landing direction mud extraction pitch of holes is 0.8m, in figure Forced landing shaft based on A axles, side forced landing direction mud extraction pitch of holes is 0.8~1.3m, and a axles and b axles are side forced landing shaft in figure, side forced landing side To mudhole from main forced landing shaft more close to spacing it is less, sides adjacent forced landing direction mud extraction pitch of holes reduce successively along side forced landing shaft, subtract Few amplitude is 50~100mm.Mud extraction hole depth is 2m below open caisson bottom.
Using interval construction when inhaling mud, i.e., in order mudhole carried out into layout, the mudhole of odd number order of first constructing, The mudhole of even number order of constructing again.
Inhale mud construction to be arranged according to correction amount situation, mud construction technology is inhaled using three-wheel, first round correction amount is 40mm, the second wheel correction amount is 40mm, and third round correction amount is 30mm, and the adjacent wheels suction mud construction intermittent time is no less than 30min, Avoid sediment failure.
The drilling rod of construction mudhole carries air intake duct, dredging tube and gas tube, and rubber bulb is installed in drilling rod bottom.Bar drill to be drilled To mudhole bottom, then 0.6m is lifted, the rubber bulb of drilling rod bottom is inflated, air pressure is 0.35MPa.Rubber bulb has played envelope The effect of mudhole is closed, then clay is clogged on rubber bulb and further sealed, clay refilling thickness is 0.35m.Then start The air compressor machine being connected with drilling rod air intake duct, the space below rubber bulb forms negative pressure, and pneumatics is closed when negative pressure reaches 80MPa Machine, starting the siphon suction dredge being connected with dredging tube carries out suction operation.
The duct sand backfill after correction purpose is reached, continues the sedimentation situation for observing open caisson, the settling amount of 7 days back open caissons For 0.01mm/d, sedimentation is in stability state.

Claims (2)

1. a kind of method for correcting error of open caisson, is characterized in that arranging mudhole around open caisson, a diameter of 0.15~0.3m of mudhole, Main forced landing direction mud extraction pitch of holes is 0.8m, and side forced landing direction mud extraction pitch of holes is 0.8~1.3m, side force-land direction mudhole from The nearlyer spacing of main forced landing shaft is less, and sides adjacent forced landing direction mud extraction pitch of holes is reduced successively along side forced landing shaft, and the amplitude that reduces is 50 ~100mm;
Using interval construction when inhaling mud, i.e., in order mudhole carried out into layout, the mudhole of odd number order of first constructing, then apply The mudhole of work even number order;
Inhale mud construction arranged according to correction amount situation, each correction amount be less than or equal to 5cm, when target correction amount it is larger When, mud construction technology is inhaled using many wheels, the adjacent wheels suction mud construction intermittent time is no less than 30min, it is to avoid sediment failure;
The drilling rod of construction mudhole carries air intake duct, dredging tube and gas tube, and rubber bulb is installed in drilling rod bottom;Bar drill to be drilled is to going out Mud bottom hole portion, then 0.6m is lifted, the rubber bulb of drilling rod bottom is inflated, air pressure is 0.3~0.4MPa;Rubber bulb has played envelope The effect of mudhole is closed, then clay is clogged on rubber bulb and further sealed, clay refilling thickness is 0.3~0.4m;Then The air compressor machine that startup is connected with drilling rod air intake duct, the space below rubber bulb forms negative pressure, closes when negative pressure reaches 75~85MPa Air compressor machine is closed, starting the siphon suction dredge being connected with dredging tube carries out suction operation;
Duct can be backfilled with sand after correction purpose is reached, and continue the sedimentation situation for observing open caisson, and the sedimentation of 7 days back open caissons is in Unsteady phenomena, i.e. settling amount carry out the grouting and reinforcing soil body more than 0.05mm/d.
2. the method for correcting error of open caisson according to claim 1, is characterized in that mud extraction hole depth determines according to soil property situation, when When open caisson bottom is clay, mud extraction hole depth is 2m below open caisson bottom;When open caisson bottom is silt, mud extraction hole depth is heavy 1.5m below bottom;When open caisson bottom is muck soil, mud extraction hole depth is 1m below open caisson bottom;When open caisson bottom is During sand, mud extraction hole depth is 0.5m below open caisson bottom.
CN201611189590.2A 2016-12-13 2016-12-13 The method for correcting error of open caisson Active CN106638648B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201611189590.2A CN106638648B (en) 2016-12-13 2016-12-13 The method for correcting error of open caisson
CN201810855115.7A CN109024648B (en) 2016-12-13 2016-12-13 Deviation rectifying construction method for open caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611189590.2A CN106638648B (en) 2016-12-13 2016-12-13 The method for correcting error of open caisson

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201810855115.7A Division CN109024648B (en) 2016-12-13 2016-12-13 Deviation rectifying construction method for open caisson

Publications (2)

Publication Number Publication Date
CN106638648A true CN106638648A (en) 2017-05-10
CN106638648B CN106638648B (en) 2018-11-09

Family

ID=58833424

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201810855115.7A Active CN109024648B (en) 2016-12-13 2016-12-13 Deviation rectifying construction method for open caisson
CN201611189590.2A Active CN106638648B (en) 2016-12-13 2016-12-13 The method for correcting error of open caisson

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201810855115.7A Active CN109024648B (en) 2016-12-13 2016-12-13 Deviation rectifying construction method for open caisson

Country Status (1)

Country Link
CN (2) CN109024648B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61176719A (en) * 1985-01-29 1986-08-08 Sumitomo Metal Ind Ltd Method and apparatus for penetration of structure into bottom ground under water
CN1058069A (en) * 1991-06-26 1992-01-22 黄正轩 The method of correcting and then reinforcing inclined house
JP2000345572A (en) * 1999-06-09 2000-12-12 Hiroshi Saito Basement caisson construction method, lower frame member used therefor, internal panel member, external panel member, and separator
CN2654698Y (en) * 2003-06-30 2004-11-10 唐业清 Negative frictional force inclined correction precipitation well
CN102155021A (en) * 2011-05-10 2011-08-17 河北二十冶工程技术有限公司 Method for correcting open caisson in collapsible loess area
CN102995649A (en) * 2012-12-04 2013-03-27 中国一冶集团有限公司 Method for levelling inclination of open caisson in grading and layer-by-layer manner

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1271045A (en) * 2000-03-03 2000-10-25 天津建岩岩土工程有限公司 Inclined building correcting method
CN1654749A (en) * 2005-02-28 2005-08-17 广州大学 Lean correcting and foundation consolidating method for building by filling water
RU2348760C1 (en) * 2007-06-27 2009-03-10 Вячеслав Николаевич Кровяков Method of heeling compression of buildings constructed on water - saturated grounds
CN100567660C (en) * 2007-12-26 2009-12-09 南京工业大学 The sink well given force construction method of house deviation rectifying
CN103711154B (en) * 2013-12-17 2015-10-21 上海岩土工程勘察设计研究院有限公司 The rectifying of leaned building method of negative hole pressure boring soil digging
CN104763004B (en) * 2014-01-02 2016-10-05 百盛联合建设集团有限公司 Soil base building method for correcting error
CN105464154A (en) * 2015-12-14 2016-04-06 神翼航空器科技(天津)有限公司 Construction method of deep digging pipe

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61176719A (en) * 1985-01-29 1986-08-08 Sumitomo Metal Ind Ltd Method and apparatus for penetration of structure into bottom ground under water
CN1058069A (en) * 1991-06-26 1992-01-22 黄正轩 The method of correcting and then reinforcing inclined house
JP2000345572A (en) * 1999-06-09 2000-12-12 Hiroshi Saito Basement caisson construction method, lower frame member used therefor, internal panel member, external panel member, and separator
CN2654698Y (en) * 2003-06-30 2004-11-10 唐业清 Negative frictional force inclined correction precipitation well
CN102155021A (en) * 2011-05-10 2011-08-17 河北二十冶工程技术有限公司 Method for correcting open caisson in collapsible loess area
CN102995649A (en) * 2012-12-04 2013-03-27 中国一冶集团有限公司 Method for levelling inclination of open caisson in grading and layer-by-layer manner

Also Published As

Publication number Publication date
CN109024648B (en) 2020-08-28
CN106638648B (en) 2018-11-09
CN109024648A (en) 2018-12-18

Similar Documents

Publication Publication Date Title
CN106703871B (en) A kind of method of high pressure water injection prevention and treatment gas and coal dust
US11453991B2 (en) High strength grouting method for single pile rock-socketed foundation of weakly weathered bed rock for offshore wind power
CN102278142B (en) Vacuum lightweight well-point dewatering method
CN104775443B (en) A kind of well-points dewatering method and device
CN105863648A (en) Underground-excavation shallow-covering large-cross-section tunnel construction method
CN104047280B (en) Soft foundation sharp separation compacting method
CN201485896U (en) Non-pump differential pressure water supplying device for well
CN208121835U (en) Inclined building correcting and then reinforcing structure
CN106638648B (en) The method for correcting error of open caisson
CN210658408U (en) Foundation pit dewatering well and plugging structure thereof
CN109139057B (en) Coal mining roadway floor water absorption bottom heave treatment method
CN104727325B (en) A kind of method of construction of polder sea wall
CN106522201A (en) Swell-shrink type drainage device and sludge positive and negative pressure drainage method
CN109750684A (en) A kind of multi-purpose precipitation well construction and preparation method thereof
CN205823286U (en) In a kind of water, shield machine arrives and receives structure
CN203284787U (en) Composite pipe well precipitation system
CN204098050U (en) A kind of control artesian water precipitation system
CN105970910A (en) Well point plastic draining pipe film coating type vacuum preloading and dewatering preloading combined power consolidation method
CN105862714A (en) Soft foundation water cover type integrated well point plastic strip vacuum system
CN106013046A (en) Grading loading method for variable-stress path well point plastic drainage vacuum preloading seepage consolidation
CN108547320A (en) A kind of deep piping lane foundation pit method for digging of Collapsible Loess District
CN115637721B (en) Active control method for sinking of open caisson structure of bridge pier
CN205348149U (en) Well point dewatering of hydraulic engineering construction usefulness
CN112695767B (en) Water lowering structure and water lowering method for micro-expansive soil foundation pit soaked by underground water
CN218716630U (en) Well flushing device for in-situ leaching uranium mining mine process well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201222

Address after: 225700 industrial concentration area, Xinduo Town, Xinghua City, Taizhou City, Jiangsu Province

Patentee after: JIANGSU TANGYUAN BIOLOGICAL POWER Co.,Ltd.

Address before: Room 302, building 11, Jingshan group, Wenzhou City, Zhejiang Province 325000

Patentee before: Ye Xiangzhu