CN1271045A - Inclined building correcting method - Google Patents

Inclined building correcting method Download PDF

Info

Publication number
CN1271045A
CN1271045A CN 00103377 CN00103377A CN1271045A CN 1271045 A CN1271045 A CN 1271045A CN 00103377 CN00103377 CN 00103377 CN 00103377 A CN00103377 A CN 00103377A CN 1271045 A CN1271045 A CN 1271045A
Authority
CN
China
Prior art keywords
soil
inclined building
mud
correcting method
building correcting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 00103377
Other languages
Chinese (zh)
Inventor
林威
杨怀玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN JIANYAN ROCK AND SOIL ENGINEERING Co Ltd
Original Assignee
TIANJIN JIANYAN ROCK AND SOIL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN JIANYAN ROCK AND SOIL ENGINEERING Co Ltd filed Critical TIANJIN JIANYAN ROCK AND SOIL ENGINEERING Co Ltd
Priority to CN 00103377 priority Critical patent/CN1271045A/en
Publication of CN1271045A publication Critical patent/CN1271045A/en
Pending legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The inclined building correcting process includes successive steps of drilling holes into soil to be dug out and inserting PVC pipes, injecting water with a high-pressure pump, through the PVC pipes and to make soil become slurry, which sweels to flow out, measuring the amount and specific weight of out going slurry and calculating the volume of removed soil, and finally filling the holes with expanding and densifying stuffing after the required correcting soil volume is reached. The present invention has obvious correcting effect, fast construction speed and low cost.

Description

Inclined building correcting method
The invention belongs to construction techniques, particularly a kind of inclined building correcting method.
The present invention in the past, the structure normal inclination correction method that adopts in back that tilts is: (1) is soil digging method directly, draws near the soil the foundation bed, easily makes to occur stress in the structure base and concentrate, the rectification effect is not satisfactory; (2) directly take the side local method: the shortcoming of existence the digging property that is back to incline is poor, easily to tilting in the other direction; (3) stress fetches earth and separates division, and with above-mentioned all to exist construction noise big, the construction plant is destroyed serious, and the drawback that floor space is big does not still have the appearance of the desirable inclined building correcting method of science up to now.
It is little that purpose of the present invention aims to provide a kind of construction noise, easy and simple to handle, and effect is remarkable, need not destroy place on every side and influence the inclined building correcting method that structure use.
The objective of the invention is to realize with following technical scheme:
A kind of inclined building correcting method is characterized in that: its inclination correction method is followed successively by:
(1) to the soil layer boring of need soil digging, dark pvc pipe is drawn in test;
(2) with the high pressure clarified water pump water under high pressure is injected in the soil layer of bottom in the pvc pipe, soil is made mud;
(3) mud expands and is extruded ground surface;
(4) mud amount that flows out of metering and mud balance calculate the earth volume of drawing out and reach expected rectification target;
(5) behind the inclined building correcting, fill out the real pvc pipe of envelope hole with the compacted material that expands.
The prescription and the volume ratio of the above-mentioned compacted material of expansion are: quicklime: flyash: 425 #Portland cement=6.5: 2.5: 1.
The compacted material external packets of above-mentioned expansion is wrapped with waterproofing membrane.
Characteristics of the present invention: fetch earth easily, rectification is accurate, and the construction plant is destroyed little, and noise is little, does not influence the normal use of structure in the construction.
Below in conjunction with embodiment in detail the present invention is described in detail: the following 5 meters dark soil of layer that fetch earth are example.
Inclined building correcting method is followed successively by:
(1) holes 5 meters dark pvc pipes of test to the soil layer of need soil digging;
(2) with 2-6MPa high-pressure plunger clarified water pump, with nozzle before the water under high pressure pipeline water under high pressure is injected in the pvc pipe in the soil layer of bottom, soil is made mud, the mud expansion is recycled extrudes ground surface;
(3) mud amount and the mud balance of metering outflow calculate the earth volume of drawing out, and reach rectification target;
(4) use quicklime after the rectification, flyash and 425 #The compacted material of the expansion of Portland cement proportioning is filled out sealing of hole.When filling out envelope, meet that water is filled out and unreal, then its external packets is wrapped with the plastic sheeting of waterproof for the compacted material that prevents to expand.
It is remarkable that the present invention has the rectification effect, quick construction, convenience, invest little, cost low significantly Advantage.

Claims (3)

1, a kind of inclined building correcting method is characterized in that: its inclination correction method is followed successively by:
(1) to the soil layer boring of need soil digging, dark pvc pipe is drawn in test;
(2) with the high pressure clarified water pump water under high pressure is injected in the soil layer of bottom in the pvc pipe, soil is made mud;
(3) mud expands and is extruded ground surface;
(4) mud amount that flows out of metering and mud balance calculate the earth volume of drawing out and reach expected rectification target;
(5) behind the inclined building correcting, fill out the real pvc pipe of envelope hole with the compacted material that expands.
2, inclined building correcting method according to claim 1 is characterized in that, the prescription and the volume ratio of the above-mentioned compacted material of expansion are: quicklime: flyash: 425 #Portland cement=6.5: 2.5: 1.
3, inclined building correcting method according to claim 1 is characterized in that, the compacted material external packets of above-mentioned expansion is wrapped with waterproofing membrane.
CN 00103377 2000-03-03 2000-03-03 Inclined building correcting method Pending CN1271045A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 00103377 CN1271045A (en) 2000-03-03 2000-03-03 Inclined building correcting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 00103377 CN1271045A (en) 2000-03-03 2000-03-03 Inclined building correcting method

Publications (1)

Publication Number Publication Date
CN1271045A true CN1271045A (en) 2000-10-25

Family

ID=4576936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 00103377 Pending CN1271045A (en) 2000-03-03 2000-03-03 Inclined building correcting method

Country Status (1)

Country Link
CN (1) CN1271045A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864779A (en) * 2010-06-29 2010-10-20 天津建岩岩土工程有限公司 Building deep soil excavating rectification method
CN101691765B (en) * 2009-09-21 2011-01-26 唐业清 Double-ash well pole stress relief coordination and rectification method for complex foundation
CN102839825A (en) * 2012-09-25 2012-12-26 天津建岩岩土工程有限公司 Reverse rectifying method for building
CN102979113A (en) * 2012-12-15 2013-03-20 陈向东 House rectification method
CN103290865A (en) * 2013-05-11 2013-09-11 叶长青 Building inclination rectifying method
CN103321261A (en) * 2013-07-18 2013-09-25 张继红 Construction method for directional expansion-rise deviation rectification
CN104763004A (en) * 2014-01-02 2015-07-08 百盛联合建设集团有限公司 Soil foundation building rectifying method
CN105256849A (en) * 2015-10-23 2016-01-20 宁波市岩土工程有限公司 Deviation rectifying method for inclined building on cement mixing pile composite foundation
CN105401606A (en) * 2015-12-14 2016-03-16 神翼航空器科技(天津)有限公司 Deep drawing pipe type inclination correcting method and deep drawing device
CN105464154A (en) * 2015-12-14 2016-04-06 神翼航空器科技(天津)有限公司 Construction method of deep digging pipe
CN105569099A (en) * 2014-10-13 2016-05-11 湖南征驰工程技术咨询有限公司 Method for correcting building inclination caused by pile inclination
CN106088175A (en) * 2016-06-12 2016-11-09 岩土科技股份有限公司 Rectifying of leaned building device and method
CN107313602A (en) * 2016-04-26 2017-11-03 湖北建科结构加固有限责任公司 Building substrate is that sand changes the jetting forced falling rectifying deviation method filled out
CN109024648A (en) * 2016-12-13 2018-12-18 叶香竹 The deviation rectification construction method of open caisson

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101691765B (en) * 2009-09-21 2011-01-26 唐业清 Double-ash well pole stress relief coordination and rectification method for complex foundation
CN101864779A (en) * 2010-06-29 2010-10-20 天津建岩岩土工程有限公司 Building deep soil excavating rectification method
CN102839825A (en) * 2012-09-25 2012-12-26 天津建岩岩土工程有限公司 Reverse rectifying method for building
CN102979113A (en) * 2012-12-15 2013-03-20 陈向东 House rectification method
CN103290865A (en) * 2013-05-11 2013-09-11 叶长青 Building inclination rectifying method
CN103321261A (en) * 2013-07-18 2013-09-25 张继红 Construction method for directional expansion-rise deviation rectification
CN104763004A (en) * 2014-01-02 2015-07-08 百盛联合建设集团有限公司 Soil foundation building rectifying method
CN104763004B (en) * 2014-01-02 2016-10-05 百盛联合建设集团有限公司 Soil base building method for correcting error
CN105569099A (en) * 2014-10-13 2016-05-11 湖南征驰工程技术咨询有限公司 Method for correcting building inclination caused by pile inclination
CN105256849A (en) * 2015-10-23 2016-01-20 宁波市岩土工程有限公司 Deviation rectifying method for inclined building on cement mixing pile composite foundation
CN105401606A (en) * 2015-12-14 2016-03-16 神翼航空器科技(天津)有限公司 Deep drawing pipe type inclination correcting method and deep drawing device
CN105464154A (en) * 2015-12-14 2016-04-06 神翼航空器科技(天津)有限公司 Construction method of deep digging pipe
CN107313602A (en) * 2016-04-26 2017-11-03 湖北建科结构加固有限责任公司 Building substrate is that sand changes the jetting forced falling rectifying deviation method filled out
CN106088175A (en) * 2016-06-12 2016-11-09 岩土科技股份有限公司 Rectifying of leaned building device and method
CN109024648A (en) * 2016-12-13 2018-12-18 叶香竹 The deviation rectification construction method of open caisson

Similar Documents

Publication Publication Date Title
CN109629566B (en) Vacuum drainage anchor rod and construction method thereof
CN1271045A (en) Inclined building correcting method
CN105961120B (en) One kind being suitable for arid biogeographic zone ecological restoration of mine side slope vegetation quick recovery method
CN101806059B (en) Drilling, grouting and sand-throwing process of ground surface of mined-out region under highway
CN101144274B (en) Method for carrying vacuum prepressing consolidation by using plastic draining plate with box
CN102691296A (en) Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN107044128A (en) Supporting and dewatering construction method in Deep Excavation
CN105155563A (en) Reinforcing and treating method for water burst of soft-flow muddy stratum of foundation pit
CN112761174B (en) Grouting plugging method suitable for large karst cave under high-flow-rate flowing water condition
CN107447613A (en) A kind of deep super embankment on soft soil and construction method
CN107299650B (en) A kind of remote open caisson casting method for correcting error
CN109424054A (en) The technique constructed in construction to storm sewer
CN203488191U (en) Grouting system for tunnel water plugging construction
CN110820720A (en) Water-blocking and drainage-resisting anti-floating construction structure and method
CN201317935Y (en) Paramos frozen soil region culvert frost heaving thaw collapse preventing device
CN114278300B (en) Method for repairing coal mining damaged water-proof soil layer through vacuum preloading of thin sand layer coverage area
CN108194104A (en) A kind of interval rock pillar reinforcement means of city shallow embedding small-clear-distance tunnel
CN104499491B (en) Draining is compound from boring tire string data suspension roof support structure and construction method
KR20060100315A (en) Upstream part retaining wall type fill dam
CN205993248U (en) A kind of system for improving soil groundwater flow speed and heat exchange property
CN207794115U (en) A kind of recyclable water sealing structure of foundation pit freezing supporting
CN211143046U (en) Water-blocking and draining anti-floating construction structure
CN208634542U (en) One kind subtracting swollen drainpipe
CN110563396A (en) Steel sheet pile cofferdam lead hole backfill material, preparation method and backfill method
CN2465022Y (en) Permeation-proof underground high-pressure water pipe made of double-layer concrete and steel sheet

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Tianjin construction rock and Soil Engineering Co

Document name: Notification before expiration of term

C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Tianjin Jianyan Rock and Soil Engineering Co., Ltd.

Document name: Deemed as a notice of withdrawal

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication