CN105464154A - Construction method of deep digging pipe - Google Patents

Construction method of deep digging pipe Download PDF

Info

Publication number
CN105464154A
CN105464154A CN201510943207.7A CN201510943207A CN105464154A CN 105464154 A CN105464154 A CN 105464154A CN 201510943207 A CN201510943207 A CN 201510943207A CN 105464154 A CN105464154 A CN 105464154A
Authority
CN
China
Prior art keywords
pipe
construction method
draw
deeply
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510943207.7A
Other languages
Chinese (zh)
Inventor
林威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wing Aircraft Technology (tianjin) Co Ltd
Original Assignee
Wing Aircraft Technology (tianjin) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wing Aircraft Technology (tianjin) Co Ltd filed Critical Wing Aircraft Technology (tianjin) Co Ltd
Priority to CN201510943207.7A priority Critical patent/CN105464154A/en
Publication of CN105464154A publication Critical patent/CN105464154A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material
    • E02F7/10Pipelines for conveying excavated materials

Abstract

The invention discloses a construction method of a deep digging pipe. The construction method comprises the following steps: (1) inserting a sleeve into a soil layer along a preset angle by utilizing a pushing device and enabling the sleeve to penetrate into a backfilled soil layer; (2) inserting the deep digging pipe into the sleeve by utilizing the pushing device until the deep digging pipe is inserted into a preset position; (3) digging out the soil in the deep digging pipe and then performing the soil digging operation. The construction method disclosed by the invention has the advantage of creatively changing a technique in which drilling is firstly performed and then the pipe is inserted; the sleeve directly penetrates into the backfilled soil layer under powerful jacking of an excavator, namely from the surface layer to the soft soil layer, the deep digging pipe can continuously deeply penetrate into the preset position along the preset angle under the jacking of the excavator by guidance and restriction effects of the sleeve on the deep digging pipe; the construction time of each deep digging pipe is shortened to be within one minute; the construction efficiency is greatly improved; the construction cost is lowered; moreover, the excavator is a general construction machinery, and the convenience of construction is also improved.

Description

Draw dark pipe construction method
Technical field
The present invention relates to technical field of building construction, particularly relate to one and draw dark pipe construction method.
Background technology
The inclination of building, mainly due to the differential settlement of ground.Differential settlement, normally due to building upper load skewness, causes the subsidiary stress of bearing stratum foundation soil uneven; Bearing stratum foundation soil thickness distribution is uneven, causes different parts soil body chrominance signal to be out of shape; Bearing stratum foundation soil substratum skewness, that causes soil body total compression to be out of shape is uneven; Essential bearing stratum is not selected on same soil layer; Building foundation side digs the reason such as foundation ditch and precipitation and causes.
When building run-off the straight exceeds the scope of permission, normal use can be had a strong impact on, even endanger life and the property safety of user.Therefore, when building run-off the straight, rectification should be carried out to it as early as possible.Application number be 00103377.8 patent of invention disclose a kind of building inclination rectification method, wherein the first step is exactly that then dark pvc pipe is drawn in test to needing the soil layer of soil digging to hole; Then carrying out soil digging operation by water under high pressure is auxiliary, but this drillable length is long, sometimes more than ten rice even twenty or thirty rice is reached, and to ensure that boring can ensure that follow-up pvc pipe inserts, this just increases boring difficulty greatly, causes the increase of construction cost and the prolongation of construction period.
Summary of the invention
The object of the invention is the technological deficiency for existing in prior art, and provide one to draw dark pipe construction method.
The technical scheme adopted for realizing object of the present invention is:
One draws dark pipe construction method, comprises the following steps,
1) utilize ejector apparatus to be inserted by sleeve pipe in soil layer along predetermined angle and make it penetrate back fill course,
2) utilize ejector apparatus to insert in sleeve pipe and deeply draw pipe, and until be inserted into precalculated position,
3) earth deeply drawn in pipe is drawn out and can carry out soil digging operation.
Also comprise sleeve pipe and the step deeply drawing pipe pull-out after having constructed.
Described ejector apparatus is excavator.
Described sleeve pipe and deeply draw pipe and be metal tube.
The described diameter deeply drawing pipe is at 10-30mm.
Described draws the galvanized pipe that pipe is 4 points or 6 points deeply.
Also comprise be fixedly installed on deeply draw pipe upper end hold cover, the described cover end that holds is provided with the universal wheel contacted with described ejector apparatus.
Compared with prior art, the invention has the beneficial effects as follows:
The present invention creatively changes first to hole and descends the technique of pipe again, directly penetrate back fill course at the lower sleeve pipe that holds energetically of excavator, namely top layer is until Soft Soil Layer, utilize sleeve pipe can continue predetermined place deep along predetermined angular under the holding of excavator to the guiding and effect of contraction of drawing dark pipe, within each engineering time of deeply drawing pipe foreshortens to one minute, greatly improve efficiency of construction, reduce construction cost, and excavator is common construction machinery, lifting construction convenience especially.
Accompanying drawing explanation
fig. 1the signal of dark pipe construction method is drawn for of the present invention figure.
Detailed description of the invention
Below in conjunction with specific embodiment, the present invention is described in further detail.Should be appreciated that specific embodiment described herein only in order to explain the present invention, be not intended to limit the present invention.
Of the present inventionly draw dark pipe construction method and comprise the following steps,
1) ejector apparatus is utilized along predetermined angle, sleeve pipe 2 to be inserted in soil layer as excavator 1 and make it penetrate the large back fill course of hardness, this sleeve pipe is preferably metal sleeve, it has very strong hardness, adopt tubular structure, when penetrating back fill course, little by resistance, be convenient to insert, wherein, backfill thickness is generally at several meters, impurity in it, as rubble is more, utilize sleeve pipe directly to insert to penetrate, crushing effect is had to it, ensure to insert smoothly, preferably, also comprise be fixedly installed on deeply draw pipe upper end hold cover, the described cover end that holds is provided with the universal wheel contacted with described ejector apparatus.Utilize the setting holding cover universal wheel, lateral force can be weakened as far as possible, realize the jacking of steady predetermined direction.
2) ejector apparatus is utilized, pipe 3 is deeply drawn as excavator inserts in sleeve pipe, and until be inserted into precalculated position, wherein, this draws pipe deeply can connect rear insertion section by section, in general, the described diameter deeply drawing pipe is at 10-30mm, directly can select the galvanized pipe of 4 points or 6 points, namely the tap water supply pipe purchased, because soil layer is softer after back fill course, little by resistance, around the bond stress of soil layer can effectively ensure linearly to be headed into during insertion simultaneously, and protection guiding is carried out by sleeve pipe in outer end, the gap of deeply drawing pipe and sleeve pipe meets inserts smoothly, general at 1-5mm,
3) drawn out by the earth deeply drawing pipe and can carry out soil digging operation to the region a below construction 4, soil digging operation is routine operation, does not repeat them here.Also by sleeve pipe and pipe pull-out can be deeply drawn to recycle after having constructed.
The present invention creatively changes first to hole and descends the technique of pipe again, directly penetrate back fill course at the lower sleeve pipe that holds energetically of excavator, namely sleeve pipe is utilized to penetrate topsoil until Soft Soil Layer, utilize sleeve pipe can continue predetermined place deep along predetermined angular under the holding of excavator to the guiding and effect of contraction of drawing dark pipe, within each engineering time of deeply drawing pipe foreshortens to one minute, greatly improve efficiency of construction, reduce construction cost, and excavator is common construction machinery, lifting construction convenience especially.
The above is only the preferred embodiment of the present invention; it should be pointed out that for those skilled in the art, under the premise without departing from the principles of the invention; can also make some improvements and modifications, these improvements and modifications also should be considered as protection scope of the present invention.

Claims (7)

1. draw a dark pipe construction method, it is characterized in that, comprise the following steps,
1) utilize machinery to be inserted by sleeve pipe in soil layer along predetermined angle and make it penetrate back fill course,
2) utilize machinery to insert in sleeve pipe and deeply draw pipe, and until be inserted into precalculated position,
3) earth deeply drawn in pipe is drawn out and can carry out soil digging operation.
2. draw dark pipe construction method as claimed in claim 1, it is characterized in that, also comprise sleeve pipe and the step deeply drawing pipe pull-out after having constructed.
3. draw dark pipe construction method as claimed in claim 1, it is characterized in that, described machinery is excavator.
4. draw dark pipe construction method as claimed in claim 1, it is characterized in that, described sleeve pipe and deeply draw pipe and be metal tube.
5. draw dark pipe construction method as claimed in claim 1, it is characterized in that, the described diameter deeply drawing pipe is at 10-30mm.
6. draw dark pipe construction method as claimed in claim 1, it is characterized in that, described draws the galvanized pipe that pipe is 4 points or 6 points deeply.
7. draw dark pipe construction method as claimed in claim 1, it is characterized in that, also comprise be fixedly installed on deeply draw pipe upper end hold cover, the described cover end that holds is provided with the universal wheel contacted with described ejector apparatus.
CN201510943207.7A 2015-12-14 2015-12-14 Construction method of deep digging pipe Pending CN105464154A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510943207.7A CN105464154A (en) 2015-12-14 2015-12-14 Construction method of deep digging pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510943207.7A CN105464154A (en) 2015-12-14 2015-12-14 Construction method of deep digging pipe

Publications (1)

Publication Number Publication Date
CN105464154A true CN105464154A (en) 2016-04-06

Family

ID=55602272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510943207.7A Pending CN105464154A (en) 2015-12-14 2015-12-14 Construction method of deep digging pipe

Country Status (1)

Country Link
CN (1) CN105464154A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109024648A (en) * 2016-12-13 2018-12-18 叶香竹 The deviation rectification construction method of open caisson

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1066902A (en) * 1992-06-13 1992-12-09 孔清华 High efficient dry soil removing bored pile piling method and device
JPH1082065A (en) * 1996-09-05 1998-03-31 Masaya Nagashima Differential settlement prevention method of house in soft soil by making use of soil pile consolidation method, unevenness adjusting method of differential settlement house, and device used therefor
CN1271045A (en) * 2000-03-03 2000-10-25 天津建岩岩土工程有限公司 Inclined building correcting method
CN101307609A (en) * 2008-06-06 2008-11-19 江苏华东建设基础工程有限公司 Deviation rectifying method for pile foundation architecture inclination
CN102966128A (en) * 2012-11-28 2013-03-13 三峡大学 Water and air jetting correction method with anchor rod static steel casing

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1066902A (en) * 1992-06-13 1992-12-09 孔清华 High efficient dry soil removing bored pile piling method and device
JPH1082065A (en) * 1996-09-05 1998-03-31 Masaya Nagashima Differential settlement prevention method of house in soft soil by making use of soil pile consolidation method, unevenness adjusting method of differential settlement house, and device used therefor
CN1271045A (en) * 2000-03-03 2000-10-25 天津建岩岩土工程有限公司 Inclined building correcting method
CN101307609A (en) * 2008-06-06 2008-11-19 江苏华东建设基础工程有限公司 Deviation rectifying method for pile foundation architecture inclination
CN102966128A (en) * 2012-11-28 2013-03-13 三峡大学 Water and air jetting correction method with anchor rod static steel casing

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109024648A (en) * 2016-12-13 2018-12-18 叶香竹 The deviation rectification construction method of open caisson

Similar Documents

Publication Publication Date Title
CN103306683B (en) A kind of construction method of comprehensive precipitation in hole when excavating deep tunnel
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN103867229B (en) A kind of coal mine large-mining is dark prevents and treats comprehensive treatment method for water with lower group of coal mining
CN105401606A (en) Deep drawing pipe type inclination correcting method and deep drawing device
CN104018512B (en) The caisson sinking construction method dynamic to environment micro-turbulence
CN106437798B (en) A kind of preprocess method of the anchor cable group across shield driving section
CN103485320B (en) U-shaped inclinometer and mounting and embedding method thereof
CN107489816A (en) Using the anti-construction method pulled out system processing push pipe jacking and be hampered of push pipe
CN105386452A (en) Construction method for assisting in sinking of open caisson through high-pressure water
CN103899351A (en) Filling and reinforcing method for processing complicated goafs
CN103742188A (en) Coal mine pump drainage gas well and drilling method thereof
CN108952776A (en) A kind of method of the equidistant horizontal orientation concordant bored grouting transformation dual limestone of roof and floor
CN104674828B (en) Tailing dam vertically arranges the construction method of seepage well
CN1848526A (en) Constituting method for DC transmission deep well grounding electrode
CN105464154A (en) Construction method of deep digging pipe
CN101864990A (en) Water intercepting and conducting device for shaft of vertical well
CN104695478B (en) Ultra-deep underground diaphragm wall built-in buried pipe structure and construction method thereof
CN204401615U (en) A kind of pile top being applicable to Denudation monadnock landforms tube pile construction
CN204125941U (en) Uplift pile structure
CN106245621A (en) A kind of electric osmose inverted well construction method
CN110486531A (en) It a kind of artificial push pipe and rams and manages united pipeline construction method
CN205049135U (en) Solve inclinometer card gauge head unit
CN105064384B (en) Vacuum tube well precipitation system
KR20090050562A (en) The installation method of long piles using steel pipe with taper shape
CN108150199B (en) The method of temporary support stability is improved in a kind of construction of tunnel top bar CD method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160406