CN106626016A CN201611125231.0A CN201611125231A CN106626016A CN 106626016 A CN106626016 A CN 106626016A CN 201611125231 A CN201611125231 A CN 201611125231A CN 106626016 A CN106626016 A CN 106626016A
Authority
CN
China
Prior art keywords
formwork
template frame
disengaging
honour
wedge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611125231.0A
Other languages
Chinese (zh)
Inventor
薛德胜
马广达
薛山
丁威力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Shengda Machinery Manufacturing Co Ltd
Original Assignee
Jiangsu Shengda Machinery Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Shengda Machinery Manufacturing Co Ltd filed Critical Jiangsu Shengda Machinery Manufacturing Co Ltd
Priority to CN201611125231.0A priority Critical patent/CN106626016A/en
Publication of CN106626016A publication Critical patent/CN106626016A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/22Moulds for making units for prefabricated buildings, i.e. units each comprising an important section of at least two limiting planes of a room or space, e.g. cells; Moulds for making prefabricated stair units
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/04Discharging the shaped articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members

Abstract

The invention particularly relates to a T-beam prefabricating device and belongs to the technical field of bridge building. The T-beam prefabricating device comprises formwork frames and a formwork disengaging system. The formwork frames include a left formwork frame and a right formwork frame. A pedestal is arranged under the middle parts of the left formwork frame and the right formwork frame, a formwork cavity is defined by the left formwork frame, the right formwork frame and the pedestal. Partition plates are arranged at the formwork disengaging positions of the formwork frames. The formwork disengaging system is composed of formwork disengaging devices, a lifting device and a horizontal moving device. Each formwork disengaging device comprises a formwork disengaging main bases, a pull rod, a wedge block and a transverse ejector rod. The formwork disengaging main bases are arranged at the formwork disengaging positions on the side walls of the formwork frames, the wedge blocks are located in the formwork disengaging main bases, drive oil cylinders are arranged on end portions of the pull rods and can drive the pull rods to move in the longitudinal direction, and the pull rods can drive the wedge blocks to move. When the wedge blocks move, the transverse ejector rods gradually advance inwards in the movement of the wedge blocks, the push force of the transverse ejector rods acts on the partition plates, and the reactive force of the partition plate prompts the formwork frames to be separated from a prefabricated T-beam. By means of the T-beam prefabricating device, the labor intensity of constructors can be relieved, the construction time can be shortened, and construction safety and the appearance quality of the product are improved.

Description

The beam prefabricated equipment of T
Technical field
The invention belongs to technical field of bridge construction, refers in particular to a kind of beam prefabricated equipment of T.
Background technology
T beams as Transportation Infrastructure Construction in an important ring, with saving concrete, strong from heavy and light, span ability The features such as, need to use mould in the pouring of T beams, the punching block that mould is made up of side form, bed die and end mould etc., weight compared with Greatly, at present construction make T beams during need multiple demoulding matched moulds, need in this course consume it is larger Man power and material's cost, due to completely, by artificial operation, whole efficiency causes the prolongation of construction period, project to build than relatively low If it is relatively costly, and because side form has larger weight, also there is certain operational danger.
The content of the invention
It is an object of the invention to provide a kind of assembling duration for reducing template, reduces the beam prefabricated equipment of T of labour intensity.
The object of the present invention is achieved like this:The beam prefabricated equipment of T, including template frame and dismoulding system, the template frame Constituted by left and right two, the underface in the middle of left and right two template frames is pedestal, three surrounds to form die cavity, and in the mould The de-molding position of grillage is provided with dividing plate, and the dismoulding system is made up of stripper apparatus, lowering or hoisting gear and translating device;
The stripper apparatus includes the demoulding seat of honour, pull bar, wedge and horizontal push rod, and the demoulding seat of honour is arranged on the mould The de-molding position of grillage side wall, the wedge be located at the demoulding seat of honour in, the pull bar is parallel with the template frame, and with institute Wedge connection is stated, the end of the pull bar is provided with driving oil cylinder, and the driving oil cylinder can drive pull bar to vertically move, pull bar Wedge can be driven to move, the horizontal push rod is arranged on the demoulding seat of honour, and vertical with the pull bar, its one end effect On the dividing plate, the other end is acted in the wedge, and when wedge is moved, horizontal push rod is gradually inside in the motion of wedge Propulsion, on dividing plate, its reaction force promotes template frame to separate with Precast T-Beam to the thrust of horizontal push rod, realizes the demoulding;
The lowering or hoisting gear includes lifting top board and hoist cylinder, and the lifting top board is fixed with template frame side wall and connected Connect, and perpendicular to the side wall of the template frame, the hoist cylinder is located at the underface of the lifting top board;Before pouring, enter The structure of row die cavity, can adjust the height of the template frame by hoist cylinder, and laborsaving and efficiency high improves cavity dimension Precision, and pour and complete, after the demoulding, hoist cylinder declines, and template frame can be made to be kept completely separate with Precast T-Beam;
The translating device includes base and translation oil cylinder, the translation oil cylinder perpendicular to the template frame side wall, together Sample, translation oil cylinder can facilitate the structure of die cavity before pouring, and pour and complete, after the demoulding, can widen template frame with Distance between Precast T-Beam, is easy to hoisting prefabricated T beams, is shifted.
The beam prefabricated equipment of T mentioned above, further optimization:The bottom of the base is provided with walking carriage, by row Walk chassis, can convenient moving die plate frame, structure mould, demoulding efficiency are higher.
The beam prefabricated equipment of T mentioned above, further optimization:Track is provided with below the walking carriage, operation is made Track becomes apparent from understanding that structure mould, the demoulding are more convenient.
The beam prefabricated equipment of T mentioned above, further optimization:The side wall of the template frame is provided with some demoulding seat of honours, Pull bar and wedge between the adjacent demoulding seat of honour joins end to end, and is provided with connecting rod between the adjacent demoulding seat of honour, it is only necessary to Install in stem and drive oil cylinder, can just drive all of pull bar and wedge movement, make structure more simplified, and by connecting rod guarantee The linkage of pull bar and wedge in each demoulding seat of honour.
The present invention is prominent and beneficial compared to existing technology to be had the technical effect that:Compact conformation, it is reasonable in design, it is safe and reliable, Net synchronization capability is high, workable, integrates mechanical electronic hydraulic, is both manually operable, and the manipulation of PLC Based Intelligent Controls may also be employed, greatly The labour intensity of workmen greatly during mitigation site operation, instead of traditional artificial assembly that purely relies on and dismantles template History, improves the safety of site operation and the presentation quality of product, reduces the assembling duration of template and the work of site operation Amount, is widely used in modernizing large-scale precast beam field, the use of batch precast beam field.
Description of the drawings
Fig. 1 is the schematic top plan view of the present invention;
Fig. 2 is the cross-sectional schematic of the present invention;
Fig. 3 is the structural representation of stripper apparatus in the present invention;
In figure:10- template frames, 11- pedestals, the 12- demoulding seat of honours, 13- pull bars, 14- wedges, the horizontal push rods of 15-, 16- drives Dynamic oil cylinder, 17- connecting rods, 18- dividing plates, 19- hoist cylinders, 20- lifting top boards, 21- bases, 22- translation oil cylinders, 23- walkings Chassis, 24- tracks, 25-T beams, the upper wire drawings of 26-, wire drawing under 27-.
Specific embodiment
Below in conjunction with the accompanying drawings with specific embodiment, the invention will be further described, referring to Fig. 1-3:The beam prefabricated equipment of T, Including template frame 10 and dismoulding system, the template frame 10 is constituted by left and right two, in the middle of left and right two template frames 10 just Lower section is pedestal 11, and three surrounds to form die cavity, and the de-molding position in the template frame 10 is provided with dividing plate 18, the demoulding System is made up of stripper apparatus, lowering or hoisting gear and translating device;
The stripper apparatus includes the demoulding seat of honour 12, pull bar 13, wedge 14 and horizontal push rod 15, and the demoulding seat of honour 12 sets Put the de-molding position in the side wall of the template frame 10, the wedge 14 is located in the demoulding seat of honour 12, the pull bar 13 and institute State template frame 10 parallel, and be connected with the wedge 14, the end of the pull bar 13 is provided with driving oil cylinder 16, described to drive oil Cylinder 16 can drive pull bar 13 to vertically move, and pull bar 13 can drive wedge 14 to move, and the horizontal push rod 15 is arranged on described On the demoulding seat of honour 12 and vertical with the pull bar 13, its one end is acted on the dividing plate 18, and the other end acts on the wedge On 14, when wedge 14 is moved, horizontal push rod 15 is gradually inwardly advanced in the motion of wedge 14, the thrust of horizontal push rod 15 On dividing plate 18, its reaction force promotes template frame 10 to separate with Precast T-Beam 25, realizes the demoulding;
The lowering or hoisting gear includes lifting top board 20 and hoist cylinder 19, the lifting top board 20 and the side of the template frame 10 Wall is fixedly connected, and perpendicular to the side wall of the template frame 10, the hoist cylinder 19 be located at the lifting top board 20 just under Side;Before pouring, the structure of die cavity is carried out, the height that hoist cylinder 19 adjusts the template frame 10, laborsaving and effect can be passed through Rate is high, improves the precision of cavity dimension, and pours and complete, and after the demoulding, hoist cylinder 19 declines, can make template frame 10 with it is pre- T beams 25 processed are kept completely separate;
The translating device includes base 21 and translation oil cylinder 22, and the bottom of the base 21 is provided with walking carriage 23, By walking carriage 23, can convenient moving die plate frame 10, structure mould, demoulding efficiency be higher, the lower section of the walking carriage 23 Track 24 is provided with, makes running orbit become apparent from understanding, structure mould, the demoulding are more convenient, and the translation oil cylinder 22 is perpendicular to the mould The side wall of grillage 10, likewise, translation oil cylinder 22 can facilitate the structure of die cavity before pouring, and pours and completes, the demoulding Afterwards, the distance between template frame 10 and Precast T-Beam 25 can be widened, is easy to hoisting prefabricated T beams 25, be shifted.
The side wall of the template frame 10 is provided with some demoulding seat of honours 12, the pull bar 13 between the adjacent demoulding seat of honour 12 and carves Block 14 joins end to end, and is provided with connecting rod 17 between the adjacent demoulding seat of honour 12, it is only necessary to installs in stem and drives oil cylinder 16, Just all of pull bar 13 and wedge 14 can be driven to move, make structure more simplified, and each demoulding seat of honour has been ensured by connecting rod 17 The linkage of pull bar 13 and wedge 14 in 12.
Operation principle:Left and right two template frames 10 are moved to by the both sides of the pedestal 11 by walking carriage 23, then is led to The adjustment of translation oil cylinder 22 and hoist cylinder 19 is crossed, two template frames 10 and pedestal 11 are built into into die cavity, the port at two ends is used Template is blocked, and then framework of steel reinforcement is placed in die cavity, is led to respectively between the top and bottom of two template frames 10 Cross wire drawing 26 and lower wire drawing 27 is fixed, finally poured, shaping to be solidified;
The demoulding is carried out after shaping, first has to remove wire drawing 26 and lower wire drawing 27, started and drive oil cylinder 16 to be operated, can It is manually operated, it is possible to use remote controller operation, drive oil cylinder 16 to drive pull bar 13 to move, the wedge 14 in each demoulding seat of honour 12 exists Under the pulling of pull bar 13, start movement, now, horizontal push rod 15 is gradually inwardly advanced in the motion of wedge 14, laterally top On dividing plate 18, its reaction force promotes template frame 10 to separate with Precast T-Beam 25 to the thrust of bar 15, then starts lifting oil Cylinder 19, declines template frame 10, after dropping to initial position, starts translation oil cylinder 22, and template frame 10 is laterally pulled away from into T beams 25, Walking carriage 23 is finally started, the template frame 10 of arranged on left and right sides is removed into pedestal 11, complete the demoulding.
Above-described embodiment is only presently preferred embodiments of the present invention, is not limited the scope of the invention according to this, therefore:It is all according to The equivalence changes that the structure of the present invention, shape, principle are done, all should be covered by within protection scope of the present invention.

Claims (4)

  1. The beam prefabricated equipment of 1.T, including template frame and dismoulding system, the template frame is constituted by left and right two, left and right two moulds Underface in the middle of grillage is pedestal, and three surrounds to form die cavity, and the de-molding position in the template frame is provided with dividing plate, its It is characterised by:The dismoulding system is made up of stripper apparatus, lowering or hoisting gear and translating device;
    The stripper apparatus includes the demoulding seat of honour, pull bar, wedge and horizontal push rod, and the demoulding seat of honour is arranged on the template frame The de-molding position of side wall, the wedge is located in the demoulding seat of honour, and the pull bar is parallel with the template frame, and carves with described Block connects, and the end of the pull bar is provided with driving oil cylinder, and the horizontal push rod is arranged on the demoulding seat of honour, and with it is described Pull bar is vertical, and its one end is acted on the dividing plate, and the other end is acted in the wedge;
    The lowering or hoisting gear includes lifting top board and hoist cylinder, and the lifting top board is fixedly connected with template frame side wall, And perpendicular to the side wall of the template frame, the hoist cylinder is located at the underface of the lifting top board;
    The translating device includes base and translation oil cylinder, side wall of the translation oil cylinder perpendicular to the template frame.
  2. 2. the beam prefabricated equipment of T according to claim 1, it is characterised in that:The bottom of the base is provided with walking carriage.
  3. 3. the beam prefabricated equipment of T according to claim 2, it is characterised in that:Track is provided with below the walking carriage.
  4. 4. the beam prefabricated equipment of T according to claim 1, it is characterised in that:The side wall of the template frame is provided with some de- The mould seat of honour, the pull bar and wedge between the adjacent demoulding seat of honour joins end to end, and is provided with connecting rod between the adjacent demoulding seat of honour.
CN201611125231.0A 2016-12-08 2016-12-08 T-beam prefabricating device Pending CN106626016A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611125231.0A CN106626016A (en) 2016-12-08 2016-12-08 T-beam prefabricating device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611125231.0A CN106626016A (en) 2016-12-08 2016-12-08 T-beam prefabricating device

Publications (1)

Publication Number Publication Date
CN106626016A true CN106626016A (en) 2017-05-10

Family

ID=58825417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611125231.0A Pending CN106626016A (en) 2016-12-08 2016-12-08 T-beam prefabricating device

Country Status (1)

Country Link
CN (1) CN106626016A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU72654U1 (en) * 2007-12-12 2008-04-27 Открытое акционерное общество "Долина" PLANT FOR MANUFACTURE OF BUILDING BLOCKS
CN201669773U (en) * 2010-05-04 2010-12-15 杨秋利 Mobile T-beam and I-beam template system
CN103878869A (en) * 2014-04-16 2014-06-25 江苏固丰管桩集团有限公司 Prefabricated concrete square pile mold facilitating mold releasing
CN105216101A (en) * 2015-10-10 2016-01-06 山东铁鹰建设工程有限公司 A kind of T-shaped beam prefabricated form device of self-propelled hydraulic and release method thereof
CN105291253A (en) * 2015-09-16 2016-02-03 中国葛洲坝集团第二工程有限公司 Method for simply and rapidly mounting and demounting side moulds and end moulds of diaphragm plates of T-beam
CN105965671A (en) * 2016-05-06 2016-09-28 中交二公局第四公路工程有限公司 Hydraulic T-beam formwork construction device and technology
CN106113229A (en) * 2016-06-28 2016-11-16 中国路桥工程有限责任公司 Railway T-shaped beam prefabricated form device and installation, release method
CN206264117U (en) * 2016-12-08 2017-06-20 江苏月生达机械制造有限公司 The beam prefabricated equipment of T

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU72654U1 (en) * 2007-12-12 2008-04-27 Открытое акционерное общество "Долина" PLANT FOR MANUFACTURE OF BUILDING BLOCKS
CN201669773U (en) * 2010-05-04 2010-12-15 杨秋利 Mobile T-beam and I-beam template system
CN103878869A (en) * 2014-04-16 2014-06-25 江苏固丰管桩集团有限公司 Prefabricated concrete square pile mold facilitating mold releasing
CN105291253A (en) * 2015-09-16 2016-02-03 中国葛洲坝集团第二工程有限公司 Method for simply and rapidly mounting and demounting side moulds and end moulds of diaphragm plates of T-beam
CN105216101A (en) * 2015-10-10 2016-01-06 山东铁鹰建设工程有限公司 A kind of T-shaped beam prefabricated form device of self-propelled hydraulic and release method thereof
CN105965671A (en) * 2016-05-06 2016-09-28 中交二公局第四公路工程有限公司 Hydraulic T-beam formwork construction device and technology
CN106113229A (en) * 2016-06-28 2016-11-16 中国路桥工程有限责任公司 Railway T-shaped beam prefabricated form device and installation, release method
CN206264117U (en) * 2016-12-08 2017-06-20 江苏月生达机械制造有限公司 The beam prefabricated equipment of T

Similar Documents

Publication Publication Date Title
CN106120563B (en) Construction method based on Combined movable mould bases cast-in-situ box girder
CN206264117U (en) The beam prefabricated equipment of T
CN108755434B (en) Control system of self-propelled hydraulic rail box girder external mold trolley
CN111809536A (en) Integrally-moving box culvert template and construction method thereof
CN212764049U (en) Plate stripping machine is grabbed to formwork erection in groups
CN209408814U (en) A kind of PC track beam form system
CN106593469A (en) Trolley for construction of inverted arch
CN107829370B (en) High pier is from climbing liquid press to turn over molds construction technology
CN202248860U (en) Hydraulic climbing formwork system
CN210969361U (en) Production line for precast concrete hollow anti-seismic wallboard
CN107829408B (en) Rectangular aqueduct construction steel mould trolley
CN206386132U (en) Tunnel casting concrete quick template supporting stripper apparatus
CN103669872A (en) Walling method and walling device
CN102001131A (en) Bridge girder body auxiliary production equipment and bridge girder body production system
CN211547804U (en) Cantilever type retaining wall rapid construction device
CN201816135U (en) Bridge body production auxiliary equipment and bridge body production system
CN111037721A (en) Precast beam type thin plate stair production device
CN108005684B (en) Separated steel mould trolley and construction method thereof
CN106626016A (en) T-beam prefabricating device
CN110714785A (en) Pipe gallery top plate construction trolley, trolley set and construction method
CN105216095B (en) A kind of concrete prefabricated building block multimode cavity forming machine
CN215395945U (en) Compact prefabricated component production line
CN204997809U (en) Prefabricated little case beam side device
CN113417219B (en) Hydraulic internal mold asynchronous traveling system and method for bridge suspension casting basket box chamber
CN206053965U (en) A kind of tunnel ditch cable trough construction trolley

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510