CN106624631A - 门式起重机主梁轨道安装精度控制方法 - Google Patents
门式起重机主梁轨道安装精度控制方法 Download PDFInfo
- Publication number
- CN106624631A CN106624631A CN201611108416.0A CN201611108416A CN106624631A CN 106624631 A CN106624631 A CN 106624631A CN 201611108416 A CN201611108416 A CN 201611108416A CN 106624631 A CN106624631 A CN 106624631A
- Authority
- CN
- China
- Prior art keywords
- girder
- track
- line
- tracks
- welding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23P—METAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
- B23P15/00—Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C7/00—Runways, tracks or trackways for trolleys or cranes
- B66C7/08—Constructional features of runway rails or rail mountings
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Leg Units, Guards, And Driving Tracks Of Cranes (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明涉及一种门式起重机主梁轨道安装精度控制方法,属于门式起重机结构制作技术领域,首先,轨道划线,主梁合拢全部结束后,根据轨道地样线,在主梁两侧各返一条检查线;在地面上打出主梁两端的跨度心线及主梁横向中心线冲孔,施工前准备,检查轨道和方钢是否平直;将主梁上合拢焊缝与轨道交接处焊缝打磨平;与轨道连接处的主梁面板边缘变形过大需要效平处理;最后,装配焊接,轨道装配从中心向两端装配,先将轨道全部放到焊好的方钢槽内,将主梁中间的两根先装配,焊接结束后再向两端分散装配焊接,本发明降低起重机主梁轨道建造的施工难度,保证精度,节约成本,提高效率。
Description
技术领域
本发明涉及一种门式起重机主梁轨道安装精度控制方法,属于门式起重机结构制作技术领域。
背景技术
造船工业发展迅速,各大主力船厂承接的船舶吨位从几万吨发展到十几万吨,年造船能力也普遍跃上百万吨水平,造船模式也相继从船台造船转到船坞造船。所以国内起重机需求相当大,尤其是大吨位的门式起重机,而主梁上下小车轨道是门式起重机的重要部件。上下小车在主梁轨道上行驶。主梁轨道焊接、安装过程中的变形如果控制不利,将造成主梁轨道变形过大,影响主梁轨道的最终制造精度,造成上下小车啃轨等现象,影响门式起重机正常运行。
发明内容
鉴于已有技术存在的缺陷,本发明旨在降低起重机主梁轨道建造的施工难度,保证精度,节约成本,提高效率。
为达到上述目的,本发明提供的技术方案是一种门式起重机主梁轨道安装精度控制方法,首先,轨道划线,主梁合拢全部结束后,根据轨道地样线,在主梁两侧各返一条检查线,来确定轨道在主梁的位置;在地面上打出主梁两端的跨度心线及主梁横向中心线冲孔,作出标记;
其次,施工前准备,检查轨道和方钢是否平直;将主梁上合拢焊缝与轨道交接处焊缝打磨平;与轨道连接处的主梁面板边缘变形过大需要效平处理;
最后,装配焊接,轨道装配从中心向两端装配,先将轨道全部放到焊好的方钢槽内,将主梁中间的两根先装配,焊接结束后再向两端分散装配焊接;装配时用四个楔子将轨道抬高焊接间隙下坡口18mm,上坡口宽21mm,将上面和左右面对齐,用码板在离焊口50mm的地方将轨道和主梁牢固连接;并且在离坡口2米的地方用压码将轨道压倒主梁上,只固定一端的轨道,另一端自由变形;在坡口的下方加铜板,铜板一定要和轨道紧密结合。
优选地,返线和轨道定位使用全站仪进行测量。
优选地,划线要求如下:同时划出所有需要的安装定位线,因主梁安装后主梁要伸长,所以主梁的实际跨度应为166000mm减去主梁自重伸长量79mm为胎上跨度165921mm;由于主梁安装需要,主梁摆放的位置应向刚腿轨道跨外方向偏移660mm,划线时,主梁刚腿端的跨度心线向跨外偏离轨道中心660mm。
优选地,划线后自检合格后报监理甲方验收。
优选地,焊接前进行预热150-250°,层间温度控制在150-250°之间,焊接一次结束,焊后立即用石棉保温。
本发明的有益效果:降低起重机主梁轨道建造的施工难度,保证精度,节约成本,提高效率。
附图说明
图1是控制主梁轨道精度划线及尺寸示意图;
图2是控制主梁轨道精度划线及尺寸示意图;
图中:1、主梁钢腿端心线,2、钢腿轨道心线,3、两心线垂直,4、主梁纵向心线,5、A1A2塔架横向心线,6、B1B2塔架横向心线,7、主梁柔腿端心线,8、柔腿轨道心线,9、下小车轨道心线地样线,10、上小车轨道心线地样线,11、第一道筋板,12、各分段投影地样线。
具体实施方式
下面根据附图出示的一种控制起重机主梁轨道制造精度方法的结构图做具体如下说明:一种门式起重机主梁轨道制造精度控制方法,具体步骤是:
1、轨道划线,主梁合拢全部结束后,根据轨道地样线,在主梁两侧各返一条检查线,来确定轨道在主梁的位置。
2、施工前准备
a)检查轨道和方钢是否平直,每米3mm的偏差(不累计)如果不直应进行校直处理。;
b)将方钢上的坡口开好打磨处理好,轨道接口以及与方钢连接处20mm范围处的污物在焊接前打磨光亮;
c)将主梁上合拢焊缝与轨道交接处焊缝打磨平;
d)与轨道连接处的主梁面板边缘变形过大需要效平处理;
3、装配、焊接
a)方钢的安装、焊接;
b)轨道的装配-焊接;
首先,轨道划线,主梁合拢全部结束后,根据轨道地样线,在主梁两侧各返一条检查线,来确定轨道在主梁的位置。返线和轨道定位使用全站仪进行测量。划线要求如下:同时划出所有需要的安装定位线,因主梁安装后主梁要伸长,所以主梁的实际跨度应为166000mm-(主梁自重伸长量79mm ) = (胎上跨度165921mm)。由于主梁安装需要,主梁摆放的位置应向刚腿轨道跨外方向偏移660mm,划线时,主梁刚腿端的跨度心线向跨外偏离轨道中心660mm。
在地面上打出主梁两端的跨度心线及主梁横向中心线冲孔,用油漆作出标记,冲孔标记要保护好。划线要在早晨无日照的情况下进行。划线后自检合格后报监理甲方验收。其次施工前准备,检查轨道和方钢是否平直;将主梁上合拢焊缝与轨道交接处焊缝打磨平;与轨道连接处的主梁面板边缘变形过大需要效平处理。最后装配焊接,轨道装配从中心向两端装配,先将轨道全部放到焊好的方钢槽内,将主梁中间的两根先装配,焊接结束后再向两端分散装配焊接。装配时用四个楔子将轨道抬高焊接间隙下坡口18mm,上坡口宽21mm,将上面和左右面对齐,用码板在离焊口50mm的地方将轨道和主梁牢固连接(左右前后共4块)。并且在离坡口2米的地方,用压码将轨道压倒主梁上,主要起到反变形和刚性固定的作用。只用固定一端的轨道即可,另一端自由变形即可。在坡口的下方加铜板,铜板一定要和轨道结合好。焊接前进行预热150-250度,层间温度控制在150-250度之间,焊接一次结束,焊后立即用石棉保温。
Claims (6)
1.门式起重机主梁轨道安装精度控制方法,其特征在于:
首先,轨道划线,主梁合拢全部结束后,根据轨道地样线,在主梁两侧各返一条检查线,来确定轨道在主梁的位置;在地面上打出主梁两端的跨度心线及主梁横向中心线冲孔,作出标记;
其次,施工前准备,检查轨道和方钢是否平直;将主梁上合拢焊缝与轨道交接处焊缝打磨平;与轨道连接处的主梁面板边缘变形过大需要效平处理;
最后,装配焊接,轨道装配从中心向两端装配,先将轨道全部放到焊好的方钢槽内,将主梁中间的两根先装配,焊接结束后再向两端分散装配焊接;装配时用四个楔子将轨道抬高焊接间隙下坡口18mm,上坡口宽21mm,将上面和左右面对齐,用码板在离焊口50mm的地方将轨道和主梁牢固连接;并且在离坡口2米的地方用压码将轨道压倒主梁上,只固定一端的轨道,另一端自由变形;在坡口的下方加铜板,铜板一定要和轨道紧密结合。
2.根据权利要求1所述的门式起重机主梁轨道安装精度控制方法,其特征在于:返线和轨道定位使用全站仪进行测量。
3.根据权利要求1所述的门式起重机主梁轨道安装精度控制方法,其特征在于:划线要在早晨无日照的情况下进行。
4.根据权利要求1所述的门式起重机主梁轨道安装精度控制方法,其特征在于:划线要求如下:同时划出所有需要的安装定位线,因主梁安装后主梁要伸长,所以主梁的实际跨度应为166000mm减去主梁自重伸长量79mm为胎上跨度165921mm;由于主梁安装需要,主梁摆放的位置应向刚腿轨道跨外方向偏移660mm,划线时,主梁刚腿端的跨度心线向跨外偏离轨道中心660mm。
5.根据权利要求1所述的门式起重机主梁轨道安装精度控制方法,其特征在于:划线后自检合格后报监理甲方验收。
6.根据权利要求1所述的门式起重机主梁轨道安装精度控制方法,其特征在于:焊接前进行预热150-250°,层间温度控制在150-250°之间,焊接一次结束,焊后立即用石棉保温。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611108416.0A CN106624631B (zh) | 2016-12-06 | 2016-12-06 | 门式起重机主梁轨道安装精度控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611108416.0A CN106624631B (zh) | 2016-12-06 | 2016-12-06 | 门式起重机主梁轨道安装精度控制方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106624631A true CN106624631A (zh) | 2017-05-10 |
CN106624631B CN106624631B (zh) | 2019-12-27 |
Family
ID=58819786
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611108416.0A Active CN106624631B (zh) | 2016-12-06 | 2016-12-06 | 门式起重机主梁轨道安装精度控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106624631B (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107879248A (zh) * | 2017-07-21 | 2018-04-06 | 南通振华重型装备制造有限公司 | 一种大梁轨道制作工艺 |
CN109665441A (zh) * | 2018-12-20 | 2019-04-23 | 大连中远海运重工有限公司 | 浮船坞起重机轨道安装方法 |
CN110860768A (zh) * | 2019-10-31 | 2020-03-06 | 南通振华重型装备制造有限公司 | 一种轨道吊大梁承轨梁与方钢轨道焊接工艺 |
CN111099500A (zh) * | 2020-03-05 | 2020-05-05 | 招商局邮轮制造有限公司 | 一种端面为倒梯形单主梁龙门吊下小车轨道安装方法 |
CN113884049A (zh) * | 2021-10-08 | 2022-01-04 | 包头钢铁(集团)有限责任公司 | 一种使用全站仪测量起重机水平弯曲的方法 |
CN114275115A (zh) * | 2022-01-19 | 2022-04-05 | 江南造船(集团)有限责任公司 | 船舶设备基座阻振方钢的安装方法及安装精度控制系统 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3904113A (en) * | 1972-10-05 | 1975-09-09 | George Molyneux | Rail track assemblies |
CN102328731A (zh) * | 2011-05-31 | 2012-01-25 | 江苏熔盛造船有限公司 | 一种管子装卸起重机的超长导轨安装方法 |
CN202989711U (zh) * | 2013-01-07 | 2013-06-12 | 中建新疆工业设备安装有限公司 | 轨道焊接配套装置 |
CN105855780A (zh) * | 2016-06-29 | 2016-08-17 | 南通润邦重机有限公司 | 一种起重机轨道焊接工装及其焊接方法 |
CN106144907A (zh) * | 2016-06-20 | 2016-11-23 | 上海振华重工集团(南通)有限公司 | 一种轨道吊总装工艺 |
-
2016
- 2016-12-06 CN CN201611108416.0A patent/CN106624631B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3904113A (en) * | 1972-10-05 | 1975-09-09 | George Molyneux | Rail track assemblies |
CN102328731A (zh) * | 2011-05-31 | 2012-01-25 | 江苏熔盛造船有限公司 | 一种管子装卸起重机的超长导轨安装方法 |
CN202989711U (zh) * | 2013-01-07 | 2013-06-12 | 中建新疆工业设备安装有限公司 | 轨道焊接配套装置 |
CN106144907A (zh) * | 2016-06-20 | 2016-11-23 | 上海振华重工集团(南通)有限公司 | 一种轨道吊总装工艺 |
CN105855780A (zh) * | 2016-06-29 | 2016-08-17 | 南通润邦重机有限公司 | 一种起重机轨道焊接工装及其焊接方法 |
Non-Patent Citations (2)
Title |
---|
仇步新等: "焊接固定型起重机小车轨道安装工艺", 《起重运输机械》 * |
赵海炎: "岸边集装箱起重机小车轨道制造安装工艺", 《港口装卸》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107879248A (zh) * | 2017-07-21 | 2018-04-06 | 南通振华重型装备制造有限公司 | 一种大梁轨道制作工艺 |
CN109665441A (zh) * | 2018-12-20 | 2019-04-23 | 大连中远海运重工有限公司 | 浮船坞起重机轨道安装方法 |
CN109665441B (zh) * | 2018-12-20 | 2020-05-19 | 大连中远海运重工有限公司 | 浮船坞起重机轨道安装方法 |
CN110860768A (zh) * | 2019-10-31 | 2020-03-06 | 南通振华重型装备制造有限公司 | 一种轨道吊大梁承轨梁与方钢轨道焊接工艺 |
CN111099500A (zh) * | 2020-03-05 | 2020-05-05 | 招商局邮轮制造有限公司 | 一种端面为倒梯形单主梁龙门吊下小车轨道安装方法 |
CN113884049A (zh) * | 2021-10-08 | 2022-01-04 | 包头钢铁(集团)有限责任公司 | 一种使用全站仪测量起重机水平弯曲的方法 |
CN114275115A (zh) * | 2022-01-19 | 2022-04-05 | 江南造船(集团)有限责任公司 | 船舶设备基座阻振方钢的安装方法及安装精度控制系统 |
CN114275115B (zh) * | 2022-01-19 | 2023-01-20 | 江南造船(集团)有限责任公司 | 船舶设备基座阻振方钢的安装方法及安装精度控制系统 |
Also Published As
Publication number | Publication date |
---|---|
CN106624631B (zh) | 2019-12-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106624631A (zh) | 门式起重机主梁轨道安装精度控制方法 | |
CN103806660B (zh) | 劲性混凝土结构梁-柱节点施工方法 | |
CN106758856B (zh) | 分块预制的先张法预应力波形钢腹板组合箱梁的施工方法 | |
CN107498269B (zh) | 一种适用于干式船厢室的大型承船厢制造方法 | |
CN103741582B (zh) | 一种波形钢腹板pc组合箱梁及其施工方法 | |
CN203947771U (zh) | 一种贝雷梁悬吊模板支撑体系 | |
CN106703416A (zh) | 狭小空间中钢结构屋架拔杆吊装方法 | |
CN106812036B (zh) | 装配式悬挂单轨交通轨道梁及加工工艺 | |
CN107253026A (zh) | 一种多向四锚头整体钢锚梁制作方法 | |
CN107391811A (zh) | 一种钢桁梁桥杆件检算方法及系统 | |
CN106284838B (zh) | 一种格构式蜂窝梁节段和大跨度格构式钢梁及其制作安装方法 | |
CN106400675B (zh) | 一种钢锚箱及其安装方法 | |
CN205152802U (zh) | 一种提高拱桥劲性骨架工地现场制作精度的结构 | |
CN209941509U (zh) | 用于钢混叠合梁斜拉桥中跨合龙施工的临时连接装置 | |
CN206737145U (zh) | 用于安装立体车库钢结构的节点 | |
WO2020259469A1 (zh) | 一种焊接连接的接触网硬横梁及其施工方法 | |
CN104652828A (zh) | 重型钢结构铸钢节点高空散装施工方法 | |
CN202023298U (zh) | 适用于交叉式塔吊吊装的整榀分段式屋面钢梁结构 | |
CN107881914B (zh) | 一种分丝管式索鞍后场装配式定位装置及装配方法 | |
CN103835232A (zh) | 纵横梁结合桥面结构 | |
CN106869319A (zh) | 大跨度钢桁架安装方法 | |
CN107301309B (zh) | 基于构件极限承载比的大跨度斜拉桥内力监测设计方法 | |
CN110373990A (zh) | 双层结合钢桁梁整孔制造及架设施工方法 | |
CN108517779A (zh) | 低净空变截面曲线箱梁跨高速门洞装配化安装法 | |
CN105113801B (zh) | 一种大跨度钢结构吊装方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |