CN106523032A - Sudden-change early-warning device for weak surrounding rock excavating through tunnel machine - Google Patents
Sudden-change early-warning device for weak surrounding rock excavating through tunnel machine Download PDFInfo
- Publication number
- CN106523032A CN106523032A CN201611241806.5A CN201611241806A CN106523032A CN 106523032 A CN106523032 A CN 106523032A CN 201611241806 A CN201611241806 A CN 201611241806A CN 106523032 A CN106523032 A CN 106523032A
- Authority
- CN
- China
- Prior art keywords
- laser
- vault
- fixing bolt
- inductor
- surrounding rock
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000011435 rock Substances 0.000 title claims abstract description 17
- 230000035772 mutation Effects 0.000 claims description 5
- 238000009434 installation Methods 0.000 claims description 4
- 238000005286 illumination Methods 0.000 claims description 3
- 230000008054 signal transmission Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 5
- 238000000034 method Methods 0.000 abstract description 4
- 238000012544 monitoring process Methods 0.000 abstract 1
- 238000009412 basement excavation Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/003—Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Earth Drilling (AREA)
Abstract
The invention relates to a device used for conducting sudden-change early-warning on weak surrounding rock in the tunnel machine excavating construction process, in particular to a sudden-change early-warning device for weak surrounding rock excavating through a tunnel machine. The sudden-change early-warning device is designed mainly for solving the problem that currently, the monitoring and early-warning time for tunnel weak surrounding rock deformation and support structures is long. Two fixing bolts are mounted on a vault, two haunches are each provided with a fixing bolt, lower laser reflecting sensing plates are mounted on the fixing bolts at the haunches, and an upper laser reflecting sensing plate is mounted on the front fixing bolt at the vault. A laser receiving and sending sensor is mounted at the vault, three laser emitting heads of the laser receiving and sending sensor are aligned with the centers of the laser reflecting sensing plates at the vault and the haunches correspondingly, a data line on the laser receiving and sending sensor is connected with a lighting power line in a tunnel, and a sensor early-warning loudspeaker is connected to the joint of the data line and the lighting power line. The sudden-change early-warning device has the advantage that safety early-warning is provided for a site in time.
Description
Technical field:
The present invention relates to a kind of device for being mutated early warning during tunnel machine excavation construction to weak surrounding rock.
Background technology:
During for tunnel machine excavation construction, according to many changes of geological condition, great uncertain factor can be run into, be led to
In often constructing when deforming to tunnel weak surrounding rock and supporting construction is monitored early warning, it is, by manual work mode, to take
The measuring apparatus such as spirit level, total powerstation, will be analyzed after data acquisition, and this process is very long, but the weakness in tunnel
Wall damage occurs to occur in the short period of time, and the country rock mutation in tunnel can produce serious to in-cavity construction personal security
Threaten.
The content of the invention:
The technical problem to be solved is to provide a kind of tunnel machine and excavates weak surrounding rock mutation prior-warning device, its solution
Because tunnel machine is excavated can not the problem of early warning in time after weak surrounding rock mutation.
What above-mentioned purpose was realized in:First, the vault for excavating country rock in tunnel machine is installed former and later two and fixes spiral shell
Bolt, the two described fixing bolt will respectively install a fixing bolt, after just propping up at two haunches on same straight line
Lower laser reflection tablet is respectively mounted on the fixing bolt at two haunches, is located on anterior fixing bolt in vault and is pacified
Laser reflection tablet is loaded onto, is pacified on second fixing bolt at the vault apart from vault laser reflection tablet 10-20m
Dress laser transmitting-receiving inductor, ensures during installation that balance is firm, and three on laser transmitting-receiving inductor laser beam emitting head is respectively aligned to
Laser reflection tablet center at vault, haunch, the data wire on laser transmitting-receiving inductor are connected with tunnel intraoral illumination power line
Connect, be connected with data wire and mains lighting supply line in junction connection inductor early warning loudspeaker, i.e. the inductor early warning loudspeaker,
After weak surrounding rock is mutated, after the laser signal of laser transmitting-receiving inductor irradiation departs from reflection tablet, immediately signal can be passed
Pass inductor early warning loudspeaker and send alarm, act on there is provided safe early warning to scene.
It is an advantage of the invention that:After weak surrounding rock is mutated, the laser signal of laser transmitting-receiving inductor irradiation departs from reflection
After tablet, signal transmission can be sent into alarm to inductor early warning loudspeaker immediately, be acted on there is provided safe early warning to scene,
Workmen is made to receive early warning information.Accurately, method is simple for its early warning information.
Description of the drawings:
Fig. 1 is the installment state schematic diagram of the present invention.
Specific embodiment:
With reference to Fig. 1, first, the vault 7 for excavating country rock in tunnel machine installs former and later two fixing bolts, and the two described are solid
Determine bolt and a fixing bolt will be respectively installed after just propping up on same straight line at two haunches 8, consolidating at two haunches
Determine on bolt, to be respectively mounted lower laser reflection tablet 1, be located on anterior fixing bolt in vault and install laser reflection sense
Plate 2 is answered, laser transmitting-receiving sense is installed on second fixing bolt at the vault apart from vault laser reflection tablet 10-20m
Device 3 is answered, during installation, ensures that balance is firm, three on laser transmitting-receiving inductor laser beam emitting head is respectively aligned at vault, haunch
Laser reflection tablet center, the data wire 4 on laser transmitting-receiving inductor is connected with tunnel intraoral illumination power line 5, in the company
Place's connection inductor early warning loudspeaker 6 is connect, i.e. inductor early warning loudspeaker is connected with data wire and mains lighting supply line, when weakness is enclosed
After petrosal process becomes, after the laser signal of laser transmitting-receiving inductor irradiation departs from reflection tablet, can be immediately by signal transmission to sensing
Device early warning loudspeaker sends alarm, acts on there is provided safe early warning to scene.
Claims (1)
1. a kind of tunnel machine excavates weak surrounding rock mutation prior-warning device, it is characterized in that:Country rock is excavated in tunnel machine first
Vault(7)Former and later two fixing bolts are installed, the two described fixing bolt will be on same straight line, at two after just propping up
Haunch(8)One fixing bolt of each installation in place, is respectively mounted lower laser reflection tablet on the fixing bolt at two haunches
(1), it is located on anterior fixing bolt in vault and installs laser reflection tablet(2), sensing apart from vault laser reflection
On second fixing bolt of the vault of plate 10-20m, laser transmitting-receiving inductor is installed at place(3), during installation, ensure that balance is firm, swashs
Three laser beam emitting heads on light transmitting-receiving inductor are respectively aligned to the laser reflection tablet center at vault, haunch, and laser is received
Send out the data wire on inductor(4)With tunnel intraoral illumination power line(5)Connection, connects inductor early warning loudspeaker in the junction
(6), i.e. inductor early warning loudspeaker is connected with data wire and mains lighting supply line, after weak surrounding rock is mutated, laser transmitting-receiving sensing
After the laser signal of device irradiation departs from reflection tablet, signal transmission can be sent into alarm to inductor early warning loudspeaker immediately.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611241806.5A CN106523032A (en) | 2016-12-29 | 2016-12-29 | Sudden-change early-warning device for weak surrounding rock excavating through tunnel machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611241806.5A CN106523032A (en) | 2016-12-29 | 2016-12-29 | Sudden-change early-warning device for weak surrounding rock excavating through tunnel machine |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106523032A true CN106523032A (en) | 2017-03-22 |
Family
ID=58339159
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611241806.5A Pending CN106523032A (en) | 2016-12-29 | 2016-12-29 | Sudden-change early-warning device for weak surrounding rock excavating through tunnel machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106523032A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100717849B1 (en) * | 2006-03-08 | 2007-05-14 | 주식회사 도담이앤씨 | Construction method of 2-arch tunnel |
CN101458069A (en) * | 2008-12-30 | 2009-06-17 | 中铁二十四局集团福建铁路建设有限公司 | Tunnel wall rock deformation monitoring method and monitoring system thereof |
CN201463843U (en) * | 2009-07-10 | 2010-05-12 | 上海同岩土木工程科技有限公司 | Digital photography-based geotechnical engineering deformation remote monitoring system |
CN201680823U (en) * | 2010-05-21 | 2010-12-22 | 中国矿业大学 | Dynamic measuring device for roadway surrounding rock deformation |
CN102564335A (en) * | 2012-01-16 | 2012-07-11 | 苏州临点三维科技有限公司 | Method for measuring deformation of large-scale tunnel |
CN103335596A (en) * | 2013-06-26 | 2013-10-02 | 同济大学 | Tunnel convergence displacement and arch crown settlement measuring device and measuring method |
CN103646527A (en) * | 2013-12-24 | 2014-03-19 | 山东大学 | Automatic monitoring and early-warning system and method for monitoring and measuring interior of tunnel |
CN104373129A (en) * | 2014-10-24 | 2015-02-25 | 合肥工业大学 | Shield tunnel vault crown settlement monitoring device |
CN205445677U (en) * | 2016-03-29 | 2016-08-10 | 福建高新源工程科技有限公司 | Tunnel safety precaution and automatic control system of measurationing |
-
2016
- 2016-12-29 CN CN201611241806.5A patent/CN106523032A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100717849B1 (en) * | 2006-03-08 | 2007-05-14 | 주식회사 도담이앤씨 | Construction method of 2-arch tunnel |
CN101458069A (en) * | 2008-12-30 | 2009-06-17 | 中铁二十四局集团福建铁路建设有限公司 | Tunnel wall rock deformation monitoring method and monitoring system thereof |
CN201463843U (en) * | 2009-07-10 | 2010-05-12 | 上海同岩土木工程科技有限公司 | Digital photography-based geotechnical engineering deformation remote monitoring system |
CN201680823U (en) * | 2010-05-21 | 2010-12-22 | 中国矿业大学 | Dynamic measuring device for roadway surrounding rock deformation |
CN102564335A (en) * | 2012-01-16 | 2012-07-11 | 苏州临点三维科技有限公司 | Method for measuring deformation of large-scale tunnel |
CN103335596A (en) * | 2013-06-26 | 2013-10-02 | 同济大学 | Tunnel convergence displacement and arch crown settlement measuring device and measuring method |
CN103646527A (en) * | 2013-12-24 | 2014-03-19 | 山东大学 | Automatic monitoring and early-warning system and method for monitoring and measuring interior of tunnel |
CN104373129A (en) * | 2014-10-24 | 2015-02-25 | 合肥工业大学 | Shield tunnel vault crown settlement monitoring device |
CN205445677U (en) * | 2016-03-29 | 2016-08-10 | 福建高新源工程科技有限公司 | Tunnel safety precaution and automatic control system of measurationing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2667986C2 (en) | System and method for detection of dumbbel lock destruction of scraper conveyor | |
CN203283810U (en) | Underground belt conveyor detecting system based on image processing technique | |
CN108350684A (en) | Method and system for detecting heavy-duty machinery abrasion | |
CN110439618B (en) | Mining optical fiber roof dynamic monitoring and crushing treatment system | |
CN104330819A (en) | Recyclable installation device of microseism sensor and installation method | |
WO2014121643A1 (en) | Advanced detection system and method for tunnelling disasters | |
CN110158673A (en) | A kind of foundation pit deformation real-time monitoring system | |
CN106291661A (en) | Intelligent early-warning instrument and method for early warning thereof are monitored in stope microseism continuously | |
CN102889075B (en) | Coal mine drilling angle measuring system and method | |
CN104088620A (en) | Intelligent pneumatic supporting leg type vibrating anchor drilling rig capable of recognizing looseness range of surrounding rock | |
CN106523032A (en) | Sudden-change early-warning device for weak surrounding rock excavating through tunnel machine | |
CN110984255A (en) | Foundation pit support structure horizontal displacement monitoring and early warning system | |
CN110738825A (en) | open TBM broken stratum early warning method and system | |
CN103512527B (en) | The on-line measuring device of hard rock tunnel development machine disk cutter wearing and tearing | |
CN206397545U (en) | A kind of tunnel machine excavates weak surrounding rock mutation prior-warning device | |
CN203025912U (en) | Anti-sloughing alarming system for high-danger side slope | |
CN104265184A (en) | Intelligent on-line drill rod | |
CN105443157A (en) | Coal mine roof collapse prevention early warning device based on laser detection technology | |
CN105003293A (en) | Gas drainage system for high-gas-content coal mine | |
CN116434491A (en) | Underground cable vibration alarm device and system capable of preventing external damage | |
KR20130016890A (en) | On line monitoring system of underground utility | |
CN102705012A (en) | Monitoring system of coal roadway roof separation based on M-BUS | |
CN110080823A (en) | Tunnel support structure safety monitoring and warning method based on steelframe stress identification | |
CN110186417A (en) | A kind of corner monitoring device for push pipe electric power tunnel | |
CN110824552B (en) | Unfavorable geology detection system and method carried on shield machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |