CN106437762A - 一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法 - Google Patents

一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法 Download PDF

Info

Publication number
CN106437762A
CN106437762A CN201610742510.5A CN201610742510A CN106437762A CN 106437762 A CN106437762 A CN 106437762A CN 201610742510 A CN201610742510 A CN 201610742510A CN 106437762 A CN106437762 A CN 106437762A
Authority
CN
China
Prior art keywords
sides
hopper
construction
lining
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610742510.5A
Other languages
English (en)
Inventor
陈力
刘昌盛
吴海龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority to CN201610742510.5A priority Critical patent/CN106437762A/zh
Publication of CN106437762A publication Critical patent/CN106437762A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Abstract

一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法,其中的装置包括料斗(1),所述料斗(1)的上端设置有进料口(2),料斗(1)底部中间设置有分流槽(3),料斗(1)底部对称两侧分别设置有出料管口(4);其中的方法包括以下步骤:步骤一,在衬砌台车门架上方安装固定支架,并将料斗(1)置于支架上并进行固定;步骤二,将混凝土送入料斗(1)的进料口(2),由料斗(1)底部的分流槽(3)将混凝土分离至两侧;步骤三,通过两侧出料管口(4)处溜槽将混凝土输送至两侧布料窗口,从而同时进行浇筑混凝土施工。结构简单,操作简便,能有效的通过分流实现二衬两侧对称性浇筑施工。

Description

一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法
技术领域
本发明涉及一种分流料斗装置,更具体的说涉及一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法,属于铁路及公路隧道衬砌施工技术领域。
背景技术
隧道二衬的施工关系到工程最终的施工质量,其施工进度也关系到整个隧道工程建设的周期。目前,随着长大隧道在国内的建设增多,对隧道二衬的施工质量和建设周期要求越来越高。
施工时,隧道二衬要求从下往上、左右两侧对称浇筑施工。现有传统的施工方式采用泵管直接接入一侧窗口浇筑,待浇筑高度达到约1m高后,再通过拆管移装至另一侧窗口,依次交换进行直至拱顶。但是,这种施工方式存在以下明显弊端:1、衬砌台车结构复杂,要求泵管拐弯部位多,泵送过程中产生堵管几率增大;2、施工时间较长,功效低,主要体现在泵管左右侧交替拆装过程耗时长;3、难以较好的控制左右侧施工的对称性,易产生偏压,加固不牢的情况下容易产生端头跑模现象。同时,这些问题均会造成二衬混凝土施工进度缓慢,严重拖延工期。
发明内容
本发明的目的在于针对现有的隧道二衬施工方式存在的难以较好的控制左右侧施工的对称性、施工进度缓慢等问题,提供一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法。
为实现上述目的,本发明的技术解决方案是:一种隧道二衬两侧同步浇筑施工分流料斗装置,包括料斗,所述料斗的上端设置有进料口,料斗底部中间设置有分流槽,料斗底部对称两侧分别设置有出料管口。
所述出料管口的直径为200mm。
所述的出料管口连接有溜槽。
所述料斗的顶部设置有手柄。
一种隧道二衬两侧同步浇筑施工分流料斗装置的施工方法,包括以下步骤:
步骤一,在衬砌台车门架上方安装固定支架,使支架高度高于两侧布料窗口不小于1米,以利于混凝土的流动,将料斗置于支架上并进行固定;
步骤二,通过地泵将混凝土送入料斗的进料口,由料斗底部的分流槽将混凝土分离至两侧;
步骤三,通过两侧出料管口处溜槽将混凝土输送至两侧布料窗口,从而同时进行浇筑混凝土施工。
与现有技术相比较,本发明的有益效果是:
1、结构简单,操作简便,能有效的通过分流实现二衬两侧对称性浇筑施工。施工时,本发明通过分流槽3将混凝土左右分开、再经过与出料管口连接的溜槽将混凝土送至左右侧衬砌窗口,从而有效的通过分流实现二衬两侧同时对称性浇筑施工。
2、拆装程序大大减少,节约施工时间,施工速度快,功效高。
附图说明
图1是本发明结构示意图。
图2是料斗安装施工示意图。
图中,料斗1,进料口2,分流槽3,出料管口4,手柄5。
具体实施方式
以下结合附图说明和具体实施方式对本发明作进一步的详细描述。
参见图1,一种隧道二衬两侧同步浇筑施工分流料斗装置,能够实现二衬两侧同步对称均匀浇筑混凝土,包括料斗1。所述料斗1的上端设置有进料口2,料斗1底部中间设置有分流槽3,料斗1底部对称两侧分别设置有出料管口4。
参见图1,所述出料管口4的直径为200mm。
参见图1,所述的出料管口4连接有溜槽。
参见图1,所述料斗1的顶部设置有手柄5。手柄5便于抬装。
参见图1-图2,施工时,混凝土由进料口2进入料斗1后落入底部,由底部的分流槽3将混凝土左右分开;通过两侧的出料管口4、再经过与出料管口4连接的溜槽将混凝土送至左右侧衬砌窗口,从而实现同步浇筑过程。
参见图1-图2,一种隧道二衬两侧同步浇筑施工分流料斗装置的施工方法,包括以下步骤:
步骤一,在衬砌台车门架上方安装固定支架,使支架高度高于两侧布料窗口不小于1米,以利于混凝土的流动,将料斗1置于支架上并进行固定。此处的窗口即指在模板开一洞,用于施工,通称为窗口。
步骤二,通过地泵将混凝土送入料斗1的进料口2,由料斗1底部的分流槽3将混凝土分离至两侧。
步骤三,通过两侧出料管口4处溜槽将混凝土输送至两侧窗口,从而同时进行浇筑混凝土施工。
以上内容是结合具体的优选实施方式对本发明所作的进一步详细说明,不能认定本发明的具体实施只局限于这些说明。对于本发明所属技术领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干简单推演或替换,上述结构都应当视为属于本发明的保护范围。

Claims (5)

1.一种隧道二衬两侧同步浇筑施工分流料斗装置,其特征在于:包括料斗(1),所述料斗(1)的上端设置有进料口(2),料斗(1)底部中间设置有分流槽(3),料斗(1)底部对称两侧分别设置有出料管口(4)。
2.根据权利要求1所述的一种隧道二衬两侧同步浇筑施工分流料斗装置,其特征在于:所述出料管口(4)的直径为200mm。
3.根据权利要求1所述的一种隧道二衬两侧同步浇筑施工分流料斗装置,其特征在于:所述的出料管口(4)连接有溜槽。
4.根据权利要求1所述的一种隧道二衬两侧同步浇筑施工分流料斗装置,其特征在于:所述料斗(1)的顶部设置有手柄(5)。
5.一种隧道二衬两侧同步浇筑施工分流料斗装置的施工方法,其特征在于,包括以下步骤:
步骤一,在衬砌台车门架上方安装固定支架,使支架高度高于两侧布料窗口不小于1米,以利于混凝土的流动,将料斗(1)置于支架上并进行固定;
步骤二,通过地泵将混凝土送入料斗(1)的进料口(2),由料斗(1)底部的分流槽(3)将混凝土分离至两侧;
步骤三,通过两侧出料管口(4)处溜槽将混凝土输送至两侧布料窗口,从而同时进行浇筑混凝土施工。
CN201610742510.5A 2016-08-26 2016-08-26 一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法 Pending CN106437762A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610742510.5A CN106437762A (zh) 2016-08-26 2016-08-26 一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610742510.5A CN106437762A (zh) 2016-08-26 2016-08-26 一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法

Publications (1)

Publication Number Publication Date
CN106437762A true CN106437762A (zh) 2017-02-22

Family

ID=58182758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610742510.5A Pending CN106437762A (zh) 2016-08-26 2016-08-26 一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法

Country Status (1)

Country Link
CN (1) CN106437762A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107091104A (zh) * 2017-06-20 2017-08-25 中铁隧道集团二处有限公司 单线铁路隧道中拱墙衬砌台车的砼浇筑装置及其安装方法
CN107816058A (zh) * 2017-10-13 2018-03-20 中国十七冶集团有限公司 料仓分配槽砼浇筑设备及施工方法
CN108150194A (zh) * 2017-12-25 2018-06-12 洛阳高飞桥隧机械有限公司 一种隧道衬砌台车混凝土分流管道装置的浇筑方法
CN108839203A (zh) * 2018-07-10 2018-11-20 佛山市公路桥梁工程监测站有限公司 Uhpc预制箱梁的模板系统
CN108890851A (zh) * 2018-07-10 2018-11-27 佛山市路桥建设有限公司 Uhpc预制箱梁的施工方法
CN109707409A (zh) * 2019-01-11 2019-05-03 中铁十一局集团第四工程有限公司 一种隧道二衬混凝土振捣系统
CN116254739A (zh) * 2023-02-01 2023-06-13 中国一冶集团有限公司 一种公路排水沟整体现浇工具及其施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1144199A (ja) * 1997-07-29 1999-02-16 Penta Ocean Constr Co Ltd Natm工法における吹付面形状計測装置
CN201292672Y (zh) * 2008-10-22 2009-08-19 中国建筑第七工程局有限公司 一种建筑用入模分料器
CN103032082A (zh) * 2012-12-14 2013-04-10 中铁隧道集团一处有限公司 隧道衬砌台车分料机构
CN203306499U (zh) * 2013-05-07 2013-11-27 上海住总工程材料有限公司 一种隧道施工干粉型同步注浆现场筒仓破拱装置
CN206035504U (zh) * 2016-08-26 2017-03-22 中铁十一局集团第四工程有限公司 一种隧道二衬两侧同步浇筑施工分流料斗装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1144199A (ja) * 1997-07-29 1999-02-16 Penta Ocean Constr Co Ltd Natm工法における吹付面形状計測装置
CN201292672Y (zh) * 2008-10-22 2009-08-19 中国建筑第七工程局有限公司 一种建筑用入模分料器
CN103032082A (zh) * 2012-12-14 2013-04-10 中铁隧道集团一处有限公司 隧道衬砌台车分料机构
CN203306499U (zh) * 2013-05-07 2013-11-27 上海住总工程材料有限公司 一种隧道施工干粉型同步注浆现场筒仓破拱装置
CN206035504U (zh) * 2016-08-26 2017-03-22 中铁十一局集团第四工程有限公司 一种隧道二衬两侧同步浇筑施工分流料斗装置

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107091104A (zh) * 2017-06-20 2017-08-25 中铁隧道集团二处有限公司 单线铁路隧道中拱墙衬砌台车的砼浇筑装置及其安装方法
CN107091104B (zh) * 2017-06-20 2019-12-27 中铁隧道集团二处有限公司 单线铁路隧道中拱墙衬砌台车的砼浇筑装置及其安装方法
CN107816058A (zh) * 2017-10-13 2018-03-20 中国十七冶集团有限公司 料仓分配槽砼浇筑设备及施工方法
CN108150194A (zh) * 2017-12-25 2018-06-12 洛阳高飞桥隧机械有限公司 一种隧道衬砌台车混凝土分流管道装置的浇筑方法
CN108839203A (zh) * 2018-07-10 2018-11-20 佛山市公路桥梁工程监测站有限公司 Uhpc预制箱梁的模板系统
CN108890851A (zh) * 2018-07-10 2018-11-27 佛山市路桥建设有限公司 Uhpc预制箱梁的施工方法
CN109707409A (zh) * 2019-01-11 2019-05-03 中铁十一局集团第四工程有限公司 一种隧道二衬混凝土振捣系统
CN109707409B (zh) * 2019-01-11 2023-08-22 中铁十一局集团第四工程有限公司 一种隧道二衬混凝土振捣系统
CN116254739A (zh) * 2023-02-01 2023-06-13 中国一冶集团有限公司 一种公路排水沟整体现浇工具及其施工方法

Similar Documents

Publication Publication Date Title
CN106437762A (zh) 一种隧道二衬两侧同步浇筑施工分流料斗装置及施工方法
CN104260185B (zh) 多功能混凝土预制构件成组立模生产设备及生产线
CN206035504U (zh) 一种隧道二衬两侧同步浇筑施工分流料斗装置
CN105927249B (zh) 一种浇筑隧道二衬自密实混凝土的施工方法
CN204298828U (zh) 基坑混凝土浇筑溜管缓冲控制结构
CN104384485B (zh) 一种定向空心涡轮工作叶片用双缓冲浇注系统
CN206769918U (zh) 隧道衬砌台车混凝土逐窗浇筑溜槽
CN107803467A (zh) 一种大型阀壳类铸钢件的浇注系统
CN206874291U (zh) 一种二衬滑槽逐窗入模系统
CN102383352A (zh) 泡沫轻质混凝土浇筑路基的施工方法
CN208743624U (zh) 一种针织机大盘浇注系统
CN104562184B (zh) 一种氩气填充稳流装置
CN104746875B (zh) 一种移动式块体型废弃混凝土的浇筑装置
CN207431217U (zh) 一种路灯灯具铝合金高速高压压铸成型的浇道系统
CN208343130U (zh) 一种路面水泥砖的脱模系统
CN206329043U (zh) 一种混凝土分流槽装置
CN110524676A (zh) 全断面预制混凝土浇筑方法
CN202882929U (zh) 立井分灰系统
CN202894310U (zh) 扇形包铁水等压等量的倾动角和切出角参数控制的自动浇注机
CN208039845U (zh) 一种新型混凝土垂直下料装置
CN207453987U (zh) 一种用于隧道二次衬砌模板台车的混凝土分料器
CN207660620U (zh) 一种二衬混凝土施工分流装置
CN107489075B (zh) 一种板式无砟轨道自密实混凝土负压灌注施工方法
CN209112840U (zh) 消失模专用改性可发性聚苯乙烯共聚颗粒间隔出料装置
CN105971285A (zh) 一种混凝土搅拌浇筑装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20170222

Address after: 430074 Hubei city of Wuhan province East Lake Development Zone Road No. 21

Applicant after: The Fourth Engineering Co., Ltd. of China Railway 11 Civil

Applicant after: China Railroad 11 Bureau Group Co., Ltd.

Address before: 430074 Hubei city of Wuhan province East Lake Development Zone Road No. 21

Applicant before: The Fourth Engineering Co., Ltd. of China Railway 11 Civil

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170222