CN106436722A - Large-area backfill soil uniform settling method - Google Patents

Large-area backfill soil uniform settling method Download PDF

Info

Publication number
CN106436722A
CN106436722A CN201610908262.7A CN201610908262A CN106436722A CN 106436722 A CN106436722 A CN 106436722A CN 201610908262 A CN201610908262 A CN 201610908262A CN 106436722 A CN106436722 A CN 106436722A
Authority
CN
China
Prior art keywords
backfill
falls
native plate
hole
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610908262.7A
Other languages
Chinese (zh)
Other versions
CN106436722B (en
Inventor
李萍
赵志华
龚伟
沈颀
沈美华
虞丹
汪阳
沈志军
杨卫卫
殷奎剑
张海波
赵春锦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Industrial Park Garden Greening Engineering Co Ltd
Original Assignee
Suzhou Industrial Park Garden Greening Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Industrial Park Garden Greening Engineering Co Ltd filed Critical Suzhou Industrial Park Garden Greening Engineering Co Ltd
Priority to CN201610908262.7A priority Critical patent/CN106436722B/en
Publication of CN106436722A publication Critical patent/CN106436722A/en
Application granted granted Critical
Publication of CN106436722B publication Critical patent/CN106436722B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/046Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a large-area backfill soil uniform settling method. The large-area backfill soil uniform settling method comprises the following steps: multiple vibration columns with top end stoppers at the top ends are uniformly arranged at the pit bottom of a backfill pit; a first soil falling plate and a second soil falling plate with the vibration columns as guidance are arranged in the backfill pit in sequence from top to bottom; the area of the second soil filling plate is larger than the area of the first soil falling plate; soil falling holes are respectively formed in the first soil falling plate and the second soil falling plate; a stopper corresponding to the second soil falling plate is arranged on the side wall of the backfill pit; the vibration columns are connected with vibration equipment; the first soil falling plate is connected with lifting equipment; in the soil filling process, backfill soil enters the bottom of the backfill pit through the first soil falling plate and the second soil filling plate; at this time, the backfill soil enters the backfill pit through the soil falling holes respectively formed in the first soil falling plate and the second soil falling plate; the falling speed of the backfill soil is uniform; and in the falling process of the backfill soil, the vibration equipment vibrates through the vibration columns to guarantee the backfill uniformity of the backfill soil. The large-area backfill soil uniform settling method can guarantee no collapse gap in the backfill process.

Description

Large area backfill uniform settlement method
Technical field
The present invention relates to City Plaza technical field, specifically, which shows a kind of large area backfill uniform settlement Method.
Background technology
In City Plaza technical field, part occasion needs to hollow out construction area after the feature of carrying out foundation construction The soil that excavates is backfilled, the backfill occasion of larger area is especially gone up, back-filling way at this stage cannot be ensured backfill Uniform settlement, cause in backfill, the presence of larger space, be easily caused and build up rear square subregion and subside.
Therefore, it is necessary to provide a kind of large area backfill uniform settlement method to solve the above problems.
Content of the invention
It is an object of the invention to provide a kind of can guarantee that there is no the large area for causing to subside gap in backfilling process backfills Native uniform settlement method.
The present invention is achieved through the following technical solutions above-mentioned purpose:
A kind of large area backfill uniform settlement method, comprises the steps:
1) in the low some vibration columns for being evenly arranged with and arranging top end stop in top of cheating in backfill hole, and in backfill hole Set gradually the first native plate and second that falls with the vibration column as being oriented to from top to bottom to fall native plate, described second falls native plate suqare Fall native plate more than described first, all offers native hole on the two, and described first falls native plate and the described second native plate that falls passes through Connecting rod connects;
2) the side wall in the backfill hole is arranged and is fallen the corresponding stopper of native plate with described second, vibration column connection vibration Equipment, described first fall native plate connection jacking equipment;
3) pit bankets:During banketing, backfill by described first fall native plate and described second fall native plate enter institute Backfill hole bottom is stated, now backfill falls native plate by described first and described second the fall native hole that falls that opened up on native plate respectively is entered Enter the backfill hole, backfill falls into speed uniformly, and during backfill falls into, the vibratory equipment passes through the vibration column Carry out vibrating the backfill uniformity for ensureing backfill;
4) during backfill is inserted, by the jacking equipment, described first fall native plate and described second fall native plate with The rhythm that bankets is slow to be risen, and when reaching the stopper position, by the stopper, the described second native plate that falls departs from described first and falls Native plate;
5) upper hole is banketed:During backfill is inserted, by the jacking equipment, described first falls native plate with the rhythm that bankets Slow rise, backfill falls within described second and falls native plate upper end, is vibrated by the vibration column, and part backfill falls by described second Native plate described fall native hole enter described second and fall below native plate, most of backfill is filled at described second and falls above native plate, And the native plate that falls to described second carries out downward pressure holding, it is ensured that the described second backfill density for falling the backfill below native plate;
6) during backfill is inserted, by the jacking equipment, the described first native plate that falls rises with the rhythm that bankets and arrives Stop rising after reaching the top end stop position;
7) continue backfill to insert, until filling up the backfill hole, vibratory equipment completes backfill after continuing vibration 4h-8h.
Further, step 1) in, backfill hole bottom offers drainage, and backfill hole bottom is equipped with and covers Cover the geotextiles of the drainage.
Further, the side wall in the backfill hole is provided with anti-erosion wall.
Further, the anti-erosion wall by the grid member for being arranged at the side wall vertical that the backfill is cheated and is filled out Anti-erosion body between the side wall that cheats located at the grid member and the backfill.
Further, the grid member is made up of grid cloth or wire gauze.
Further, the anti-erosion body is made up of cobblestone.
Further, the distance between the side wall in the grid member and backfill hole is not less than 30mm.
Compared with prior art, the beneficial effect of the large area backfill uniform settlement method of the present invention is:
1) by arranging vibration column, which is connected with vibratory equipment, is vibrated during backfill is inserted, it is ensured that backfill The backfill uniformity of soil;
2) fallen native plate by arranging the first native plate and second that falls, second fall native plate suqare fall more than first native plate and the two on All offer native hole, first fall native plate and second fall native plate in jacking equipment effect under with vibration column as be oriented to and with the section that bankets Play corresponding carry out slow rise, now backfill falls native plate by first and second the fall native hole that falls that opened up on native plate respectively enters back Hole is filled out, it is uniform that backfill falls into speed;
3) by arranging stopper, which is used for limiting the described second climb for falling native plate, and the second native plate that falls reaches resistance During stop location, with first fall native plate disengaging;
4) by arranging top end stop, which is used for limiting the described first climb for falling native plate, it is to avoid first falls native plate Depart from backfill hole;
5) by offering drainage in backfill hole bottom and backfilling the geotextiles that hole bottom is equipped with covering drainage, its Anti-erosion in the draining and drainage procedure that use for the backfill hole later stage;
6) the anti-water and soil by arranging anti-erosion wall, in draining and drainage procedure that its convenient backfill hole later stage uses It is lost in.
Description of the drawings
Fig. 1 is one of structural representation of embodiments of the invention;
Fig. 2 is the two of the structural representation of embodiments of the invention;
In figure numeral represents:
100 backfill holes;
1 vibration column, 11 top end stops;
2 first fall native plate;
3 second fall native plate;
4 stoppers;
5 drainage;
6 geotextiles;
7 anti-erosion walls, 71 grid member, 72 anti-erosion bodies.
Specific embodiment
Embodiment:
Fig. 1-2 is referred to, its displaying is a kind of to can guarantee that there is no the large area for causing to subside gap in backfilling process backfills Native uniform settlement method;
Large area backfill uniform settlement method, comprises the steps:
1) in backfill hole 100 hole low be evenly arranged with top arrange top end stop 11 vibration column 1, and in backfill hole Set gradually in 100 from top to bottom with vibration column 1 to fall native plate 3 for the first of the guiding native plate 2 and second that falls, second falls 3 face of native plate Product falls more than first native plate 2, all offers native hole (in figure does not show) on the two, and the first native plate 2 and second that falls falls native plate 3 Connected by connecting rod 21;
2) the side wall in backfill hole 100 is arranged and is fallen the corresponding stopper 4 of native plate 3 with second, and the connection vibration of vibration column 1 sets Standby (in figure does not show), the first native plate 2 that falls connects jacking equipment (in figure does not show);
3) pit bankets:During banketing, backfill by first fall native plate 2 and second fall native plate 3 enter backfill hole 100 Bottom, now backfill fallen native hole (in figure does not show) entrance that falls that opened up on native plate 3 respectively by the first native plate 2 and second that falls Backfill hole 100, backfill falls into speed uniformly, and during backfill falls into, vibratory equipment (in figure does not show) is by vibration Post 1 carries out vibrating the backfill uniformity for ensureing backfill;
4) during backfill is inserted, by jacking equipment (in figure does not show), the first native plate 2 and second that falls falls native plate 3 Rise with the rhythm that bankets is slow, when reaching 4 position of stopper, by stopper 4, the second native plate 3 that falls departs from first and falls native plate 2;
5) upper hole is banketed:During backfill is inserted, by jacking equipment (in figure does not show), first falls native plate 2 with filling out Native rhythm is slow to be risen, and backfill falls within second and falls 3 upper end of native plate, is vibrated by vibration column 1, and part backfill falls native plate by second The 3 native hole (in figure does not show) that falls enters second and falls the lower section of native plate 3, and most of backfill is filled at second and falls 3 top of native plate, and The native plate 3 that falls to second carries out downward pressure holding, it is ensured that second fall the lower section of native plate 3 backfill backfill density;
6) during backfill is inserted, by jacking equipment (in figure does not show), first falls native plate 2 with rhythm rising of banketing And stop rising behind 11 position of block that outreaches;
7) continue backfill to insert, until backfill hole is filled up, complete after vibratory equipment (in figure does not show) continuation vibration 4h-8h Become backfill.
Wherein:
The quantity of vibration column 1 can be according to backfill 100 specification of hole and the power setting of vibratory equipment (in figure does not show), this Embodiment is not defined;
Step 7) in, continue time of vibration the present embodiment and be not defined, the present embodiment only propose one relatively reasonable Time period;
Step 1) in, 100 bottoms of backfill hole offer drainage 5, and 100 bottoms of backfill hole are equipped with covering drainage 5 Geotextiles 6;
The side wall in backfill hole 100 is provided with anti-erosion wall 7;
Anti-erosion wall 7 by the grid member 71 for being arranged at the side wall vertical for backfilling hole 100 and is filled at grid member 71 And the anti-erosion body 72 between the side wall in backfill hole 100;
Grid member 71 is made up of grid cloth or wire gauze;
Anti-erosion body 72 is made up of cobblestone;
Distance between the side wall in grid member 71 and backfill hole 100 is at least 30mm;
The grid member 71 that enumerates in the present embodiment and anti-erosion body 72 are only the form of expression of the present embodiment, rather than will The body that constitutes of grid member 71 and anti-erosion body 72 is defined in the species that the present embodiment is enumerated;
Distance between the side wall in grid member 71 and backfill hole 100 can be configured according to backfill hole specification, and the present embodiment is only Point out that the distance between the side wall in grid member 71 and backfill hole 100 can cause the anti-erosion of anti-erosion wall 7 less than 30mm Effect is poor.
Compared with prior art, a kind of beneficial effect of large area backfill uniform settlement method of the present embodiment is:
1) by arranging vibration column 1, which is connected with vibratory equipment (in figure does not show), is vibrated during backfill is inserted Equipment (in figure does not show) is vibrated and is transmitted these vibrations to vibration column 1, it is ensured that the backfill uniformity of backfill;
2) fallen native plate 3 by arranging the first native plate 2 and second that falls, second 3 area of native plate that falls falls more than first native plate 3 and two All offer native hole (in figure does not show) on person, the first native plate 2 and second that falls falls native plate 3 in jacking equipment (in figure does not show) Under effect with vibration column 1 as be oriented to and corresponding with the rhythm that bankets carry out slow rise, now backfill falls native plate 2 and the by first The native hole (in figure does not show) that falls that two fall opens up on native plate 3 respectively enters backfill hole 100, and it is uniform that backfill falls into speed;
3) by arranging stopper 4, which is used for limiting the second climb for falling native plate 3, and the second native plate 3 that falls is reached and stopped During 4 position of block, with 3 first fall native plate disengaging;
4) by arranging top end stop 11, which is used for limiting the first climb for falling native plate 2, it is to avoid first falls native plate 2 Depart from backfill hole 100;
5) by cheating in backfill, 100 bottoms offer drainage 5 and 100 bottoms of backfill hole are equipped with and cover drainage 5 Geotextiles 6, which is used for backfilling anti-erosion in the draining and drainage procedure that use of 100 later stages of hole;
6) by arranging anti-erosion wall 7, anti-in draining and drainage procedure that its convenient backfill 100 later stage of hole uses Soil erosion.
Above-described is only some embodiments of the present invention.For the person of ordinary skill of the art, not On the premise of departing from the invention design, some deformation can also be made and improved, these belong to the protection model of the present invention Enclose.

Claims (7)

1. a kind of large area backfill uniform settlement method, it is characterised in that:Comprise the steps:
1) in backfill hole hole low be evenly arranged with some vibration columns that top end stop is set in top, and from upper in backfill hole To under the first native plate and second that falls that sets gradually with the vibration column as being oriented to fall native plate, the described second native plate suqare that falls is more than Described first falls native plate, all offers native hole on the two, and the described first native plate and described second that falls falls native plate by connection Bar connects;
2) the side wall in the backfill hole is arranged and is fallen the corresponding stopper of native plate with described second, and vibration column connection vibration sets Standby, described first fall native plate connection jacking equipment;
3) pit bankets:During banketing, backfill falls native plate by described first and the described second native plate that falls enters described returning Hole bottom is filled out, now backfill is fallen the native hole entrance institute that falls that opened up on native plate respectively by the described first native plate and described second that falls Backfill hole is stated, backfill falls into speed uniformly, and during backfill falls into, the vibratory equipment is carried out by the vibration column Vibration ensures the backfill uniformity of backfill;
4) during backfill is inserted, by the jacking equipment, the described first native plate and described second that falls falls native plate with banketing Rhythm is slow to be risen, and when reaching the stopper position, by the stopper, the described second native plate that falls departs from described first and falls soil Plate;
5) upper hole is banketed:During backfill is inserted, by the jacking equipment, described first fall native plate with banket rhythm delay Rise, backfill falls within described second and falls native plate upper end, is vibrated by the vibration column, part backfill falls soil by described second Plate described fall native hole enter described second and fall below native plate, most of backfill is filled at described second and falls above native plate, and The native plate that falls to described second carries out downward pressure holding, it is ensured that the described second backfill density for falling the backfill below native plate;
6) during backfill is inserted, by the jacking equipment, the described first native plate that falls rises with the rhythm that bankets and reaches institute Stop rising after stating top end stop position;
7) continue backfill to insert, until filling up the backfill hole, vibratory equipment completes backfill after continuing vibration 4h-8h.
2. large area backfill uniform settlement method according to claim 1, it is characterised in that:Step 1) in, described time Fill out hole bottom and drainage is offered, and backfill hole bottom is equipped with the geotextiles for covering the drainage.
3. large area backfill uniform settlement method according to claim 1, it is characterised in that:The side wall in the backfill hole It is provided with anti-erosion wall.
4. the large area backfill uniform settlement method according to claim 1-3 any one, it is characterised in that:Described anti- Soil erosion wall by the grid member for being arranged at the side wall vertical that the backfill is cheated and is filled at the grid member and the backfill Anti-erosion body between the side wall in hole.
5. large area backfill uniform settlement method according to claim 4, it is characterised in that:The grid member is by grid Cloth or wire gauze are constituted.
6. large area backfill uniform settlement method according to claim 5, it is characterised in that:The anti-erosion body It is made up of cobblestone.
7. large area backfill uniform settlement method according to claim 6, it is characterised in that:The grid member and described Distance between the side wall in backfill hole is not less than 30mm.
CN201610908262.7A 2016-10-19 2016-10-19 Large area backfill uniform settlement method Active CN106436722B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610908262.7A CN106436722B (en) 2016-10-19 2016-10-19 Large area backfill uniform settlement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610908262.7A CN106436722B (en) 2016-10-19 2016-10-19 Large area backfill uniform settlement method

Publications (2)

Publication Number Publication Date
CN106436722A true CN106436722A (en) 2017-02-22
CN106436722B CN106436722B (en) 2018-08-14

Family

ID=58176650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610908262.7A Active CN106436722B (en) 2016-10-19 2016-10-19 Large area backfill uniform settlement method

Country Status (1)

Country Link
CN (1) CN106436722B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958121A (en) * 2019-04-24 2019-07-02 中建七局第四建筑有限公司 A kind of compacted device of collapsible loess

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1083167A (en) * 1992-07-08 1994-03-02 亨利维达民用证书公司 Domes
JPH0949223A (en) * 1995-08-04 1997-02-18 San & Shii Consultant Kk Soil improvement method, soil improvement device, storage bag of water permeable material for soil improvement device and use of storage bag of water permeable material therefor
CN101691755A (en) * 2009-03-31 2010-04-07 卢如年 Method for constructing liquified discarded soil in construction of subaqueous structure
CN103981882A (en) * 2014-06-05 2014-08-13 中建五局蚌埠建筑工程有限公司 Large-area-plate-less-foundation-settlement-resisting construction method
CN104895039A (en) * 2015-04-10 2015-09-09 成军 Construction method for water-saturated soft soil foundations

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1083167A (en) * 1992-07-08 1994-03-02 亨利维达民用证书公司 Domes
JPH0949223A (en) * 1995-08-04 1997-02-18 San & Shii Consultant Kk Soil improvement method, soil improvement device, storage bag of water permeable material for soil improvement device and use of storage bag of water permeable material therefor
CN101691755A (en) * 2009-03-31 2010-04-07 卢如年 Method for constructing liquified discarded soil in construction of subaqueous structure
CN103981882A (en) * 2014-06-05 2014-08-13 中建五局蚌埠建筑工程有限公司 Large-area-plate-less-foundation-settlement-resisting construction method
CN104895039A (en) * 2015-04-10 2015-09-09 成军 Construction method for water-saturated soft soil foundations

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958121A (en) * 2019-04-24 2019-07-02 中建七局第四建筑有限公司 A kind of compacted device of collapsible loess
CN109958121B (en) * 2019-04-24 2020-10-16 中建七局第四建筑有限公司 Collapsible loess compaction device

Also Published As

Publication number Publication date
CN106436722B (en) 2018-08-14

Similar Documents

Publication Publication Date Title
CN108489892B (en) Submarine shield tunnel excavation test device and method under seepage condition
CN106644336B (en) A kind of frame structure crosses over ground fissure experimental system and method
CN105951747B (en) A kind of construction method of the pre-buried lattice column of contrary sequence method
GB965240A (en) Method for making a reinforced concrete structure and concrete structure made according to the said method
CN110044710A (en) Soil cave collapse experiment simulator under a kind of precipitation funnel
CN108049313A (en) A kind of anchor body construction method
CN107916676A (en) Stake two layers of retaining wall structure of support and construction method
CN106436722A (en) Large-area backfill soil uniform settling method
CN105586985A (en) Construction method of subway envelop enclosure structure and subway envelop enclosure structure
RU2466239C1 (en) Method to manufacture cast-in-place piles
CN109322313B (en) Foundation pit enclosure structure system and its construction method
CN105544991A (en) Concrete column hoisting in situ method
CN104404958A (en) Construction method for precast hollow pedestal piles
CN105926630B (en) A kind of annular support replacement and jump storehouse construction method for accelerating deep big Underground Construction
CN105133568A (en) Improved dynamic compaction hammer
CN208455659U (en) A kind of lower margin pre-embedded device of large scale equipment
CN106592568B (en) A kind of terrace uniform settlement structure and construction method
CN205999907U (en) Pile load retaining wall wall retaining structure
CN105839920B (en) The construction method for end temporary steel support support replacement of standing
CN206053320U (en) Sizing can be had enough to meet the need to exempt to pick chisel embedded board muscle protector
CN206887985U (en) Isolated footing under a kind of photovoltaic generation support reinforced column
CN103397668A (en) Method for treatment of differential settlement of foundations of all sections of railway tunnel
CN107299596A (en) Support beam template system and its construction method under concrete support trestle plate
CN207093638U (en) A kind of damping device for being used to forge
CN106192980A (en) A kind of method of dither closely knit sandstone ground

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant