CN105839920B - The construction method for end temporary steel support support replacement of standing - Google Patents
The construction method for end temporary steel support support replacement of standing Download PDFInfo
- Publication number
- CN105839920B CN105839920B CN201610377579.2A CN201610377579A CN105839920B CN 105839920 B CN105839920 B CN 105839920B CN 201610377579 A CN201610377579 A CN 201610377579A CN 105839920 B CN105839920 B CN 105839920B
- Authority
- CN
- China
- Prior art keywords
- support
- cast
- bearing
- support system
- continuous beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
Abstract
The invention discloses a kind of construction method of station end temporary steel support support replacement, the second support system is set in the side for bearing the first support system of cast-in-situ continuous beam weight;Cast-in-situ continuous beam is propped up by the jack on the first support system, temporary support is set on second bearing system, the space that steel plate is used to fill up between temporary support and cast-in-situ continuous beam is placed, slowly falls beam body after rise, complete the conversion of first time bearing system;After the construction and construction of the 3rd support system of progress are finished on the cushion cap face, cast-in-situ continuous beam is propped up by the jack on the 3rd support system, bearing is set on the 3rd bearing system, place the space that steel plate is used to fill up between bearing and cast-in-situ continuous beam, slowly fall beam body after rise, complete second of bearing system conversion.The present invention is able to ensure that the two times transfer of stress during bracing members support replacement, it is ensured that the security of support replacement process, and then ensures the reliable and stable of the station end after changing into.
Description
Technical field
The invention belongs to end temporary steel support support replacement technical field of standing, and in particular to a kind of station end temporary steel support support replacement
Construction method.
Background technology
When closing on the in-situ beam casting at station, station structure has to construction to station hall layer, and station end is used to support cast-in-place
The bracket of beam is located above station hall layer, is missed the stop needs according to beam car, in the case where bracket is not constructed, Cast-in-situ Beam is temporarily used
Arrangement form holds up beam body for the bracing members of single nine, after the completion for the treatment of that prefabricated box beam is all transported and set up, station end
Portion position is constructed bracket component again, on the bracket that then end of continuous beam is fallen within to station stretching.
The stabilization of beam body stress when passing through temporary steel support in order to ensure beam car, and beam body end during construction in later period bracket
There can be reliable and stable temporary support, the arrangement form of single nine bracing members is changed to double 10, but lack at present
The construction method of few bracing members support replacement, it is impossible to complete more reliable and more stable bracing members.
The content of the invention
In view of this, it is a primary object of the present invention to provide a kind of construction method of station end temporary steel support support replacement.
To reach above-mentioned purpose, the technical proposal of the invention is realized in this way:
The embodiment of the present invention provides a kind of construction method of station end temporary steel support support replacement, and this method is real by following steps
It is existing:
Step one:In the side for bearing the first support system of cast-in-situ continuous beam weight, the second support system is set;
Step 2:Cast-in-situ continuous beam is propped up by the jack on the first support system, then in the described second support
Temporary support is set in system, and places the space that steel plate is used to fill up between temporary support and cast-in-situ continuous beam, now, slowly
It is slow to fall beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located on second support system, complete first time bearing system
Conversion;
Step 3:Remove first support system and be excavated to positioned at the cushion cap face of platform drilled pile, afterwards, in institute
State the construction that the 3rd support system is carried out on cushion cap face;
Step 4:After 3rd support system construction is finished, shored by very heavy on the 3rd support system
Play cast-in-situ continuous beam, then bearing be set on the 3rd support system, and place steel plate be used to filling up bearing with it is cast-in-place
Space between continuous beam, now, slowly falls beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located at the 3rd supporter
Fasten, complete second of bearing system conversion;
Step 5:Remove second support system.
In such scheme, first support system is nine steel support structures of single setting.
In such scheme, second support system is 2 steel support structures of single setting and reinforces diagonal brace.
In such scheme, the 3rd support system is ten steel support structures of double setting.
In such scheme, 2 steel support structures of second support system are arranged on original ground and extended to
40 meters of underground.
In such scheme, the jack is four groups of 200t jack, is laid in apart from the beam bottom both sides of cast-in-situ continuous beam
In edge 20cm.
In such scheme, the cast-in-situ continuous beam is less than or equal to 1cm by jack stand, while static observation beam body is heavy
Drop data, is determined after situation without exception, then place steel plate be used to filling up temporary support or bearing and cast-in-situ continuous beam it
Between space and slowly fall beam body after rise.
Compared with prior art, beneficial effects of the present invention:
The present invention is able to ensure that the two times transfer of stress during bracing members support replacement, it is ensured that the security of support replacement process, enters
And ensure the reliable and stable of the station end after changing into.
Brief description of the drawings
Fig. 1 provides a kind of initial schematic diagram of station end temporary steel support support replacement for the embodiment of the present invention;
The signal of the step of Fig. 2 provides a kind of construction method of station end temporary steel support support replacement for the embodiment of the present invention one
Figure;
The schematic diagram of the step of Fig. 3 provides a kind of construction method of station end temporary steel support support replacement for the embodiment of the present invention three
The signal of the step of Fig. 4 provides a kind of construction method of station end temporary steel support support replacement for the embodiment of the present invention five
Figure.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples
The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and
It is not used in the restriction present invention.
The embodiment of the present invention provides a kind of construction method of station end temporary steel support support replacement, as Figure 1-4, and this method is led to
Cross following steps realization:
Step one:The second support system is set in the side for bearing the first support system of cast-in-situ continuous beam weight, such as schemed
1st, shown in 2;
Step 2:Cast-in-situ continuous beam is propped up by the jack on the first support system, then in the described second support
Temporary support is set in system, and places the space that steel plate is used to fill up between temporary support and cast-in-situ continuous beam, now, slowly
It is slow to fall beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located on second support system, complete first time bearing system
Conversion;
Step 3:Remove first support system and be excavated to positioned at the cushion cap face of platform drilled pile, afterwards, in institute
The construction that the 3rd support system is carried out on cushion cap face is stated, as shown in Figure 3;
Step 4:After 3rd support system construction is finished, by described theThreeVery heavy on support system is shored
Play cast-in-situ continuous beam, then bearing be set on the 3rd support system, and place steel plate be used to filling up bearing with it is cast-in-place
Space between continuous beam, now, slowly falls beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located at the 3rd supporter
Fasten, complete second of bearing system conversion;
Step 5:Second support system is removed, as shown in Figure 4.
First support system is nine steel support structures of single setting.
Second support system is 2 steel support structures of single setting and reinforces diagonal brace.
3rd support system is ten steel support structures of double setting.
2 steel support structures of second support system are arranged on original ground and extend to 40 meters of underground.
The jack is four groups of 200t jack, is laid in the beam bottom both sides of the edge 20cm of cast-in-situ continuous beam.
The cast-in-situ continuous beam is less than or equal to 1cm by jack stand, while the settling data of static observation beam body, it is determined that
After situation without exception, then place steel plate and be used for the space filled up between temporary support or bearing and cast-in-situ continuous beam and slowly
It is slow to fall beam body after rise.
The foregoing is only a preferred embodiment of the present invention, is not intended to limit the scope of the present invention.
Claims (7)
1. a kind of construction method of station end temporary steel support support replacement, it is characterised in that this method is realized by following steps:
Step one:In the side for bearing the first support system of cast-in-situ continuous beam weight, the second support system is set;
Step 2:Cast-in-situ continuous beam is propped up by the jack on the first support system, then in second support system
Upper setting temporary support, and the space that steel plate is used to fill up between temporary support and cast-in-situ continuous beam is placed, now, slowly return
Fall beam body so that the load-bearing of the cast-in-situ continuous beam is located on second support system, complete the conversion of first time bearing system;
Step 3:Remove first support system and be excavated to positioned at the cushion cap face of platform drilled pile, afterwards, held described
The construction of the 3rd support system is carried out on table top;
Step 4:After the 3rd support system construction is finished, propped up by the jack on the 3rd support system existing
Casting continuous beam, bearing is then set on the 3rd support system, and places steel plate is used to fill up bearing and cast-in-place continuous
Space between beam, now, slowly falls beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located at the 3rd support system
On, complete second of bearing system conversion;
Step 5:Remove second support system.
2. the construction method of station end temporary steel support support replacement according to claim 1, it is characterised in that:First support
System is nine steel support structures of single setting.
3. the construction method of station end temporary steel support support replacement according to claim 1 or 2, it is characterised in that:Described second
Support system is 2 steel support structures of single setting and reinforces diagonal brace.
4. the construction method of station end temporary steel support support replacement according to claim 3, it is characterised in that:3rd support
System is ten steel support structures of double setting.
5. the construction method of station end temporary steel support support replacement according to claim 4, it is characterised in that:Second support
2 steel support structures of system are arranged on original ground and extend to 40 meters of underground.
6. the construction method of station end temporary steel support support replacement according to claim 5, it is characterised in that:The jack is
Four groups of 200t jack, are laid in the beam bottom both sides of the edge 20cm of cast-in-situ continuous beam.
7. the construction method of station end temporary steel support support replacement according to claim 6, it is characterised in that:It is described cast-in-place continuous
Beam is less than or equal to 1cm by jack stand, while the settling data of static observation beam body, is determined after situation without exception, then carry out
Placement steel plate is used for the space filled up between temporary support or bearing and cast-in-situ continuous beam and slowly falls beam body after rise.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610377579.2A CN105839920B (en) | 2016-05-31 | 2016-05-31 | The construction method for end temporary steel support support replacement of standing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610377579.2A CN105839920B (en) | 2016-05-31 | 2016-05-31 | The construction method for end temporary steel support support replacement of standing |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105839920A CN105839920A (en) | 2016-08-10 |
CN105839920B true CN105839920B (en) | 2017-10-20 |
Family
ID=56595436
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610377579.2A Active CN105839920B (en) | 2016-05-31 | 2016-05-31 | The construction method for end temporary steel support support replacement of standing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105839920B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106437157B (en) * | 2016-11-11 | 2020-02-21 | 上海市机械施工集团有限公司 | Grouping regulation and control method for axial force of steel support structure |
CN109457708A (en) * | 2018-12-14 | 2019-03-12 | 中冶天工集团有限公司 | The construction method of temporary support in a kind of deep foundation ditch concrete structure construction procedure |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001159232A (en) * | 1999-12-01 | 2001-06-12 | Hitachi Building Systems Co Ltd | Moving scaffold device and installation method using moving scaffold device |
JP4191235B1 (en) * | 2007-12-28 | 2008-12-03 | 株式会社Just.Will | Temporary support joint, temporary structure, and multi-story slab construction method |
CN201762667U (en) * | 2010-09-16 | 2011-03-16 | 中铁十九局集团第二工程有限公司 | Fine adjustment system for moving beam |
CN103075163A (en) * | 2012-12-28 | 2013-05-01 | 成都中铁隆工程集团有限公司 | Support change process of second liner construction of large-cross-section tunnel |
CN104141383A (en) * | 2014-07-16 | 2014-11-12 | 北京万兴建筑集团有限公司 | Bailey beam suspension formwork supporting system and construction method thereof |
CN105507168A (en) * | 2015-12-30 | 2016-04-20 | 中交第三航务工程局有限公司 | Multi-span box girder integral ultrahigh alternate jacking construction system and method |
-
2016
- 2016-05-31 CN CN201610377579.2A patent/CN105839920B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001159232A (en) * | 1999-12-01 | 2001-06-12 | Hitachi Building Systems Co Ltd | Moving scaffold device and installation method using moving scaffold device |
JP4191235B1 (en) * | 2007-12-28 | 2008-12-03 | 株式会社Just.Will | Temporary support joint, temporary structure, and multi-story slab construction method |
CN201762667U (en) * | 2010-09-16 | 2011-03-16 | 中铁十九局集团第二工程有限公司 | Fine adjustment system for moving beam |
CN103075163A (en) * | 2012-12-28 | 2013-05-01 | 成都中铁隆工程集团有限公司 | Support change process of second liner construction of large-cross-section tunnel |
CN104141383A (en) * | 2014-07-16 | 2014-11-12 | 北京万兴建筑集团有限公司 | Bailey beam suspension formwork supporting system and construction method thereof |
CN105507168A (en) * | 2015-12-30 | 2016-04-20 | 中交第三航务工程局有限公司 | Multi-span box girder integral ultrahigh alternate jacking construction system and method |
Also Published As
Publication number | Publication date |
---|---|
CN105839920A (en) | 2016-08-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111259478B (en) | Method for inhibiting deformation of existing cutting gravity type retaining wall | |
CN104294769B (en) | A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement | |
CN102900076A (en) | Continuous construction method for concrete pile steel pipe column | |
CN202595591U (en) | Micro steel pipe pile network structure for tunnel cavern roadbed in karst region | |
CN105332380B (en) | Strut changing structure and method for underground building | |
CN103243729A (en) | Lifting method of large-scale caisson | |
CN105839920B (en) | The construction method for end temporary steel support support replacement of standing | |
CN106854941B (en) | A kind of construction method of big section Stand Inclined Beams and batter post | |
CN102444130A (en) | Support replacing construction method in deep foundation pit project | |
CN209855277U (en) | Conversion layer structure for underground added layer of existing building | |
CN102936897A (en) | Steel bridge capable of being used as supporting and reinforcing structure | |
CN202530464U (en) | Road drainage foundation-pit supporting structure for auxiliary steel sheet pile construction of dewatering wells | |
CN104652842B (en) | Building integral error correcting and position, raise method for improving and its equipment | |
CN204097889U (en) | A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement | |
CN106948386B (en) | Soil filling side frictional resistance model test device and test method thereof | |
CN102535505A (en) | Tower crane foundation formed by using external walls of basement and supporting piles of foundation pit | |
CN104963425B (en) | A kind of construction method of vibration-isolating system suspension type elevator | |
CN105625184B (en) | Bridge, station build the subway station construction method of pattern jointly | |
CN206245338U (en) | The basic structure of construction elevator of double-deck raft plate | |
CN106592568B (en) | A kind of terrace uniform settlement structure and construction method | |
CN106283949B (en) | Medium-and low-speed maglev traffic engineering single line embankment location independence pier stud type support rail girder construction | |
CN106592626B (en) | A kind of construction method of the retaining wall structure for superelevation embankment | |
CN205529734U (en) | A U -shaped retaining structure for filling road bed | |
CN205012596U (en) | Defense sector face is uniform settlement structure not | |
CN211227883U (en) | Rock foundation existing high-speed rail fine-grained soil filling embankment side width structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |