CN105839920B - The construction method for end temporary steel support support replacement of standing - Google Patents

The construction method for end temporary steel support support replacement of standing Download PDF

Info

Publication number
CN105839920B
CN105839920B CN201610377579.2A CN201610377579A CN105839920B CN 105839920 B CN105839920 B CN 105839920B CN 201610377579 A CN201610377579 A CN 201610377579A CN 105839920 B CN105839920 B CN 105839920B
Authority
CN
China
Prior art keywords
support
cast
bearing
support system
continuous beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610377579.2A
Other languages
Chinese (zh)
Other versions
CN105839920A (en
Inventor
武鹏燕
章忠
沈灵友
李伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Priority to CN201610377579.2A priority Critical patent/CN105839920B/en
Publication of CN105839920A publication Critical patent/CN105839920A/en
Application granted granted Critical
Publication of CN105839920B publication Critical patent/CN105839920B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks

Abstract

The invention discloses a kind of construction method of station end temporary steel support support replacement, the second support system is set in the side for bearing the first support system of cast-in-situ continuous beam weight;Cast-in-situ continuous beam is propped up by the jack on the first support system, temporary support is set on second bearing system, the space that steel plate is used to fill up between temporary support and cast-in-situ continuous beam is placed, slowly falls beam body after rise, complete the conversion of first time bearing system;After the construction and construction of the 3rd support system of progress are finished on the cushion cap face, cast-in-situ continuous beam is propped up by the jack on the 3rd support system, bearing is set on the 3rd bearing system, place the space that steel plate is used to fill up between bearing and cast-in-situ continuous beam, slowly fall beam body after rise, complete second of bearing system conversion.The present invention is able to ensure that the two times transfer of stress during bracing members support replacement, it is ensured that the security of support replacement process, and then ensures the reliable and stable of the station end after changing into.

Description

The construction method for end temporary steel support support replacement of standing
Technical field
The invention belongs to end temporary steel support support replacement technical field of standing, and in particular to a kind of station end temporary steel support support replacement Construction method.
Background technology
When closing on the in-situ beam casting at station, station structure has to construction to station hall layer, and station end is used to support cast-in-place The bracket of beam is located above station hall layer, is missed the stop needs according to beam car, in the case where bracket is not constructed, Cast-in-situ Beam is temporarily used Arrangement form holds up beam body for the bracing members of single nine, after the completion for the treatment of that prefabricated box beam is all transported and set up, station end Portion position is constructed bracket component again, on the bracket that then end of continuous beam is fallen within to station stretching.
The stabilization of beam body stress when passing through temporary steel support in order to ensure beam car, and beam body end during construction in later period bracket There can be reliable and stable temporary support, the arrangement form of single nine bracing members is changed to double 10, but lack at present The construction method of few bracing members support replacement, it is impossible to complete more reliable and more stable bracing members.
The content of the invention
In view of this, it is a primary object of the present invention to provide a kind of construction method of station end temporary steel support support replacement.
To reach above-mentioned purpose, the technical proposal of the invention is realized in this way:
The embodiment of the present invention provides a kind of construction method of station end temporary steel support support replacement, and this method is real by following steps It is existing:
Step one:In the side for bearing the first support system of cast-in-situ continuous beam weight, the second support system is set;
Step 2:Cast-in-situ continuous beam is propped up by the jack on the first support system, then in the described second support Temporary support is set in system, and places the space that steel plate is used to fill up between temporary support and cast-in-situ continuous beam, now, slowly It is slow to fall beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located on second support system, complete first time bearing system Conversion;
Step 3:Remove first support system and be excavated to positioned at the cushion cap face of platform drilled pile, afterwards, in institute State the construction that the 3rd support system is carried out on cushion cap face;
Step 4:After 3rd support system construction is finished, shored by very heavy on the 3rd support system Play cast-in-situ continuous beam, then bearing be set on the 3rd support system, and place steel plate be used to filling up bearing with it is cast-in-place Space between continuous beam, now, slowly falls beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located at the 3rd supporter Fasten, complete second of bearing system conversion;
Step 5:Remove second support system.
In such scheme, first support system is nine steel support structures of single setting.
In such scheme, second support system is 2 steel support structures of single setting and reinforces diagonal brace.
In such scheme, the 3rd support system is ten steel support structures of double setting.
In such scheme, 2 steel support structures of second support system are arranged on original ground and extended to 40 meters of underground.
In such scheme, the jack is four groups of 200t jack, is laid in apart from the beam bottom both sides of cast-in-situ continuous beam In edge 20cm.
In such scheme, the cast-in-situ continuous beam is less than or equal to 1cm by jack stand, while static observation beam body is heavy Drop data, is determined after situation without exception, then place steel plate be used to filling up temporary support or bearing and cast-in-situ continuous beam it Between space and slowly fall beam body after rise.
Compared with prior art, beneficial effects of the present invention:
The present invention is able to ensure that the two times transfer of stress during bracing members support replacement, it is ensured that the security of support replacement process, enters And ensure the reliable and stable of the station end after changing into.
Brief description of the drawings
Fig. 1 provides a kind of initial schematic diagram of station end temporary steel support support replacement for the embodiment of the present invention;
The signal of the step of Fig. 2 provides a kind of construction method of station end temporary steel support support replacement for the embodiment of the present invention one Figure;
The schematic diagram of the step of Fig. 3 provides a kind of construction method of station end temporary steel support support replacement for the embodiment of the present invention three
The signal of the step of Fig. 4 provides a kind of construction method of station end temporary steel support support replacement for the embodiment of the present invention five Figure.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
The embodiment of the present invention provides a kind of construction method of station end temporary steel support support replacement, as Figure 1-4, and this method is led to Cross following steps realization:
Step one:The second support system is set in the side for bearing the first support system of cast-in-situ continuous beam weight, such as schemed 1st, shown in 2;
Step 2:Cast-in-situ continuous beam is propped up by the jack on the first support system, then in the described second support Temporary support is set in system, and places the space that steel plate is used to fill up between temporary support and cast-in-situ continuous beam, now, slowly It is slow to fall beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located on second support system, complete first time bearing system Conversion;
Step 3:Remove first support system and be excavated to positioned at the cushion cap face of platform drilled pile, afterwards, in institute The construction that the 3rd support system is carried out on cushion cap face is stated, as shown in Figure 3;
Step 4:After 3rd support system construction is finished, by described theThreeVery heavy on support system is shored Play cast-in-situ continuous beam, then bearing be set on the 3rd support system, and place steel plate be used to filling up bearing with it is cast-in-place Space between continuous beam, now, slowly falls beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located at the 3rd supporter Fasten, complete second of bearing system conversion;
Step 5:Second support system is removed, as shown in Figure 4.
First support system is nine steel support structures of single setting.
Second support system is 2 steel support structures of single setting and reinforces diagonal brace.
3rd support system is ten steel support structures of double setting.
2 steel support structures of second support system are arranged on original ground and extend to 40 meters of underground.
The jack is four groups of 200t jack, is laid in the beam bottom both sides of the edge 20cm of cast-in-situ continuous beam.
The cast-in-situ continuous beam is less than or equal to 1cm by jack stand, while the settling data of static observation beam body, it is determined that After situation without exception, then place steel plate and be used for the space filled up between temporary support or bearing and cast-in-situ continuous beam and slowly It is slow to fall beam body after rise.
The foregoing is only a preferred embodiment of the present invention, is not intended to limit the scope of the present invention.

Claims (7)

1. a kind of construction method of station end temporary steel support support replacement, it is characterised in that this method is realized by following steps:
Step one:In the side for bearing the first support system of cast-in-situ continuous beam weight, the second support system is set;
Step 2:Cast-in-situ continuous beam is propped up by the jack on the first support system, then in second support system Upper setting temporary support, and the space that steel plate is used to fill up between temporary support and cast-in-situ continuous beam is placed, now, slowly return Fall beam body so that the load-bearing of the cast-in-situ continuous beam is located on second support system, complete the conversion of first time bearing system;
Step 3:Remove first support system and be excavated to positioned at the cushion cap face of platform drilled pile, afterwards, held described The construction of the 3rd support system is carried out on table top;
Step 4:After the 3rd support system construction is finished, propped up by the jack on the 3rd support system existing Casting continuous beam, bearing is then set on the 3rd support system, and places steel plate is used to fill up bearing and cast-in-place continuous Space between beam, now, slowly falls beam body after rise so that the load-bearing of the cast-in-situ continuous beam is located at the 3rd support system On, complete second of bearing system conversion;
Step 5:Remove second support system.
2. the construction method of station end temporary steel support support replacement according to claim 1, it is characterised in that:First support System is nine steel support structures of single setting.
3. the construction method of station end temporary steel support support replacement according to claim 1 or 2, it is characterised in that:Described second Support system is 2 steel support structures of single setting and reinforces diagonal brace.
4. the construction method of station end temporary steel support support replacement according to claim 3, it is characterised in that:3rd support System is ten steel support structures of double setting.
5. the construction method of station end temporary steel support support replacement according to claim 4, it is characterised in that:Second support 2 steel support structures of system are arranged on original ground and extend to 40 meters of underground.
6. the construction method of station end temporary steel support support replacement according to claim 5, it is characterised in that:The jack is Four groups of 200t jack, are laid in the beam bottom both sides of the edge 20cm of cast-in-situ continuous beam.
7. the construction method of station end temporary steel support support replacement according to claim 6, it is characterised in that:It is described cast-in-place continuous Beam is less than or equal to 1cm by jack stand, while the settling data of static observation beam body, is determined after situation without exception, then carry out Placement steel plate is used for the space filled up between temporary support or bearing and cast-in-situ continuous beam and slowly falls beam body after rise.
CN201610377579.2A 2016-05-31 2016-05-31 The construction method for end temporary steel support support replacement of standing Active CN105839920B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610377579.2A CN105839920B (en) 2016-05-31 2016-05-31 The construction method for end temporary steel support support replacement of standing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610377579.2A CN105839920B (en) 2016-05-31 2016-05-31 The construction method for end temporary steel support support replacement of standing

Publications (2)

Publication Number Publication Date
CN105839920A CN105839920A (en) 2016-08-10
CN105839920B true CN105839920B (en) 2017-10-20

Family

ID=56595436

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610377579.2A Active CN105839920B (en) 2016-05-31 2016-05-31 The construction method for end temporary steel support support replacement of standing

Country Status (1)

Country Link
CN (1) CN105839920B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437157B (en) * 2016-11-11 2020-02-21 上海市机械施工集团有限公司 Grouping regulation and control method for axial force of steel support structure
CN109457708A (en) * 2018-12-14 2019-03-12 中冶天工集团有限公司 The construction method of temporary support in a kind of deep foundation ditch concrete structure construction procedure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001159232A (en) * 1999-12-01 2001-06-12 Hitachi Building Systems Co Ltd Moving scaffold device and installation method using moving scaffold device
JP4191235B1 (en) * 2007-12-28 2008-12-03 株式会社Just.Will Temporary support joint, temporary structure, and multi-story slab construction method
CN201762667U (en) * 2010-09-16 2011-03-16 中铁十九局集团第二工程有限公司 Fine adjustment system for moving beam
CN103075163A (en) * 2012-12-28 2013-05-01 成都中铁隆工程集团有限公司 Support change process of second liner construction of large-cross-section tunnel
CN104141383A (en) * 2014-07-16 2014-11-12 北京万兴建筑集团有限公司 Bailey beam suspension formwork supporting system and construction method thereof
CN105507168A (en) * 2015-12-30 2016-04-20 中交第三航务工程局有限公司 Multi-span box girder integral ultrahigh alternate jacking construction system and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001159232A (en) * 1999-12-01 2001-06-12 Hitachi Building Systems Co Ltd Moving scaffold device and installation method using moving scaffold device
JP4191235B1 (en) * 2007-12-28 2008-12-03 株式会社Just.Will Temporary support joint, temporary structure, and multi-story slab construction method
CN201762667U (en) * 2010-09-16 2011-03-16 中铁十九局集团第二工程有限公司 Fine adjustment system for moving beam
CN103075163A (en) * 2012-12-28 2013-05-01 成都中铁隆工程集团有限公司 Support change process of second liner construction of large-cross-section tunnel
CN104141383A (en) * 2014-07-16 2014-11-12 北京万兴建筑集团有限公司 Bailey beam suspension formwork supporting system and construction method thereof
CN105507168A (en) * 2015-12-30 2016-04-20 中交第三航务工程局有限公司 Multi-span box girder integral ultrahigh alternate jacking construction system and method

Also Published As

Publication number Publication date
CN105839920A (en) 2016-08-10

Similar Documents

Publication Publication Date Title
CN111259478B (en) Method for inhibiting deformation of existing cutting gravity type retaining wall
CN104294769B (en) A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement
CN102900076A (en) Continuous construction method for concrete pile steel pipe column
CN202595591U (en) Micro steel pipe pile network structure for tunnel cavern roadbed in karst region
CN105332380B (en) Strut changing structure and method for underground building
CN103243729A (en) Lifting method of large-scale caisson
CN105839920B (en) The construction method for end temporary steel support support replacement of standing
CN106854941B (en) A kind of construction method of big section Stand Inclined Beams and batter post
CN102444130A (en) Support replacing construction method in deep foundation pit project
CN209855277U (en) Conversion layer structure for underground added layer of existing building
CN102936897A (en) Steel bridge capable of being used as supporting and reinforcing structure
CN202530464U (en) Road drainage foundation-pit supporting structure for auxiliary steel sheet pile construction of dewatering wells
CN104652842B (en) Building integral error correcting and position, raise method for improving and its equipment
CN204097889U (en) A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement
CN106948386B (en) Soil filling side frictional resistance model test device and test method thereof
CN102535505A (en) Tower crane foundation formed by using external walls of basement and supporting piles of foundation pit
CN104963425B (en) A kind of construction method of vibration-isolating system suspension type elevator
CN105625184B (en) Bridge, station build the subway station construction method of pattern jointly
CN206245338U (en) The basic structure of construction elevator of double-deck raft plate
CN106592568B (en) A kind of terrace uniform settlement structure and construction method
CN106283949B (en) Medium-and low-speed maglev traffic engineering single line embankment location independence pier stud type support rail girder construction
CN106592626B (en) A kind of construction method of the retaining wall structure for superelevation embankment
CN205529734U (en) A U -shaped retaining structure for filling road bed
CN205012596U (en) Defense sector face is uniform settlement structure not
CN211227883U (en) Rock foundation existing high-speed rail fine-grained soil filling embankment side width structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant