CN106436596B - A kind of construction method for highway fiberglass sand inclusion pipe culverts - Google Patents

A kind of construction method for highway fiberglass sand inclusion pipe culverts Download PDF

Info

Publication number
CN106436596B
CN106436596B CN201611039972.7A CN201611039972A CN106436596B CN 106436596 B CN106436596 B CN 106436596B CN 201611039972 A CN201611039972 A CN 201611039972A CN 106436596 B CN106436596 B CN 106436596B
Authority
CN
China
Prior art keywords
tube
sand
frp
sand tube
frp sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201611039972.7A
Other languages
Chinese (zh)
Other versions
CN106436596A (en
Inventor
魏连雨
汪洋
梁筱
檀奥龙
郑彦军
陈兆南
张国盘
李娜
张静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei University of Technology
Original Assignee
Hebei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei University of Technology filed Critical Hebei University of Technology
Priority to CN201611039972.7A priority Critical patent/CN106436596B/en
Publication of CN106436596A publication Critical patent/CN106436596A/en
Application granted granted Critical
Publication of CN106436596B publication Critical patent/CN106436596B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to a kind of construction method for highway fiberglass sand inclusion pipe culverts, in the processing of substrate, if substrate soil property is poor or when water content is higher, it should be changed using natural soft-clay soil and fill out 30cm, substrate compactness should be controlled not less than 98%.When being filled on standard fine sand with loess, the depth of fill is not less than 30cm, it is desirable that compaction Control is 96%, so as to ensure the stability of subgrade soils.Before FRP sand tube placement, first away from fiberglass sand inclusion tube hub both sides not less than 1.5m place use on the inside of carry elastic tape steel ring sleeve in FRP sand tube, then steel ring is fixed on loess by anchor bolt, FRP sand tube is fixed using steel ring, ensure that FRP sand tube will not generate excessive offset in the later stage because flow when washing away.FRP sand tube both sides backfill material selects medium coarse sand, and control compactness reaches more than 96%, makes FRP sand tube uniform force, significantly improve construction quality.

Description

A kind of construction method for highway fiberglass sand inclusion pipe culverts
Technical field
The invention belongs to highway FRP sand tube culvert construction method and technology fields, are related to a kind of for highway glass The construction method of steel clamp sandpipe culvert.
Background technology
FRP sand tube is more and more extensive now is applied in road construction, and existing construction method is with push pipe Mode construct, take hand pick formula carry out working face excavation, carry out jacking with jack pair FRP sand tube later. After the completion of jacking, with the pipe outer void of cement concrete closed glass steel clamp sandpipe, by reserved injected hole from one end to another End is filled slip casting to every FRP sand tube one by one.Slip casting effect carries out dual control using grouting pressure and range estimation effect System.Such method easily leads to landslide due to full face tunneling and to the bad control of the uniform force of FRP sand tube.
Invention content
In view of the deficiencies of the prior art, the technical issues of present invention intends to solve be:It provides a kind of for highway glass steel clamp The construction method of sandpipe culvert.This method in the construction process, can be while subgrade soils stability be improved, and can guarantee glass The uniform force and overall stability of steel clamp sandpipe improve the scour resistance of FRP sand tube, and then improve construction quality.
The present invention solve the technical problem the technical solution adopted is that:It provides a kind of for highway fiberglass sand inclusion pipe culvert The construction method in hole, Specific construction process are:
The first step, excavation of foundation pit
Foundation pit form of fracture is digged pit mode using slope, and foundation pit both sides are according to side slope height:Width=1:1.5 ratio is put Slope;
Second step, base treatment
1) substrate is compacted using road roller, when substrate soil property is poor or water content is higher, is changed and filled out using natural soft-clay soil 30cm, substrate compaction Control are not less than 98%;
2) substrate is changed fill out after, in substrate with standard fine sand spread 10cm, no concave-convex, ensure standard fine sand it is smooth, make the later stage Uniform force when FRP sand tube is placed;
3) on standard fine sand, loess is selected to be filled as roadbed filling, and packed height is not less than 30cm, it is desirable that Compaction Control is 96%;
4) after compacting is smooth, grooving is carried out at the center of roadbed filling, is no less than by being dug under the radian of FRP sand tube 30cm;
Third step, pipeline are placed and are fixed
It is supported together every two meter amperes dress in FRP sand tube, then not small away from fiberglass sand inclusion tube hub both sides Steel ring sleeve of the inside with elastic tape is used then can to carry out the peace of FRP sand tube in FRP sand tube at 1.5m It puts, the position for placing FRP sand tube wants coincidence measurement person to require, after FRP sand tube places, by anchor bolt by steel ring It is fixed on loess, and then completes the fixation of FRP sand tube;
4th step, both sides backfill
After FRP sand tube placement fixation is appropriate, with medium coarse sand to the tube bottom edge of FRP sand tube and the sky of foundation pit It is carefully filled at gap, and with compacting tool hand compaction;In FRP sand tube both sides in medium coarse sand filling process, often Filling 20cm height is tamped with battering ram, and compactness reaches more than 96%, for the following glass of FRP sand tube radial height The medium coarse sand of steel clamp sandpipe adjacent edges needs progress hand compaction complete;
5th step, open to traffic
After both sides backfill highly reaches and flushed with the tube top of FRP sand tube, in the tube top of FRP sand tube End is filled, and is first filled with medium coarse sand, and the height for filling medium coarse sand is 20cm, is then gathered around according to practice of construction scene Some soil properties are filled, and are reached final filled height not less than after 50cm, are carried out upper end compacting with road roller, it is desirable that compactness Not less than 95%;Compacting finishes, and meet compactness and the depth of fill requirement after, can let pass traffic;
6th step, support dismounting
When the tube top upper end height to earth up of FRP sand tube is more than 1m, after clearance traffic 5 days, branch can be all removed Support;When the tube top upper end height to earth up of FRP sand tube is not more than 1m, after clearance traffic 5 days, retain intermediate and both sides 3 Road supports, remaining whole removes, and remaining 3 support is removed after 15 days in clearance traffic.
Compared with prior art, the beneficial effects of the invention are as follows:
In the construction process, moment control soil compaction degree can effectively ensure that the stability of subgrade soils, chooses the present invention Medium coarse sand is expected as backfill, and FRP sand tube is fixed with steel ring, ensure that the steady of FRP sand tube entirety Scour resistance that is qualitative and improving FRP sand tube in the later stage.
I.e. in the processing of substrate, if substrate soil property is poor or when water content is higher, it should be changed and filled out using natural soft-clay soil 30cm, substrate compactness should be controlled not less than 98%.When being filled on standard fine sand with loess, the depth of fill is not less than 30cm, it is desirable that compaction Control is 96%, so as to ensure the stability of subgrade soils.Before FRP sand tube placement, first It is being not less than the steel ring sleeve for carrying elastic tape at 1.5m on the inside of use in FRP sand tube away from fiberglass sand inclusion tube hub both sides, Then steel ring is fixed on loess by anchor bolt, FRP sand tube is fixed using steel ring, can ensure glass in this way Glass steel clamp sandpipe will not generate excessive offset in the use in later stage because flow when washing away.FRP sand tube both sides backfill Material selects medium coarse sand, because of the good water permeability of medium coarse sand particle equalization loess, can also provide required compactness and reach 96% More than, in this case, make FRP sand tube uniform force, and ensure FRP sand tube overall stability, so as to carry High construction quality, makes FRP sand tube that can preferably play effect in later stage use.
Description of the drawings
Fig. 1 is that steel ring position view is installed in the FRP sand tube of the present invention, and wherein Fig. 1 (a) is fiberglass sand inclusion The front view of pipe axial direction, Fig. 1 (b) are the front view of FRP sand tube radial direction;
Fig. 2 is the main view sectional view of a diameter of 1.5m FRP sand tube work progress;
Fig. 3 is the main view sectional view of a diameter of 1m FRP sand tube work progress.
In figure, 1 FRP sand tube, 2 steel rings, 3 anchor bolts.
Specific embodiment
The present invention is explained further, but do not protected in this, as to the application claim with reference to embodiment and attached drawing Protect the restriction of range.
The present invention is used for the construction method (abbreviation method) of highway fiberglass sand inclusion pipe culverts, and Specific construction process is:
The first step, excavation of foundation pit
Foundation pit form of fracture is digged pit mode using slope, and foundation pit both sides are according to side slope height:Width=1:1.5 ratio is put Slope.Specific excavation of foundation pit size can be required according to water supply and sewerage pipeline construction inspection rules, and excavation of foundation pit width ordinary circumstance is Twice of fiberglass sand inclusion pipe diameter can slightly be adjusted according to practice of construction situation;
Second step, base treatment
1) substrate is compacted using road roller, when substrate soil property is poor or water content is higher, is changed and filled out using natural soft-clay soil 30cm, substrate compaction Control are not less than 98%;
2) substrate is changed fill out after, in substrate with standard fine sand spread 10cm, no concave-convex, ensure standard fine sand it is smooth, make the later stage Uniform force when FRP sand tube is placed;
3) on standard fine sand, loess is selected to be filled as roadbed filling, and packed height is not less than 30cm, it is desirable that Compaction Control is 96%;
4) after compacting is smooth, grooving is carried out at the center of roadbed filling, is no less than by being dug under the radian of FRP sand tube 30cm;
Third step, pipeline are placed and are fixed
It is supported together every two meter amperes dress in FRP sand tube, then not small away from fiberglass sand inclusion tube hub both sides It is sleeved in FRP sand tube 1 with steel ring 2 of the inside with elastic tape at 1.5m, then can carry out FRP sand tube Placement;The position for placing FRP sand tube wants coincidence measurement person to require, and after FRP sand tube places, passes through anchor bolt 3 Steel ring is fixed on loess (referring to Fig. 1), and then completes the fixation of FRP sand tube;
4th step, both sides backfill
After FRP sand tube placement fixation is appropriate, with medium coarse sand to the tube bottom edge of FRP sand tube and the sky of foundation pit It is carefully filled at gap, and with compacting tool (waddy, spade etc.) hand compaction.In FRP sand tube both sides medium coarse sand In filling process, often fill 20cm height and tamped with battering ram, compactness reaches more than 96%, for FRP sand tube radius The medium coarse sand of the following FRP sand tube adjacent edges of height needs progress hand compaction complete, because being herein the work of battering ram Make dead angle, so wanting hand compaction complete, it is impossible to which there are gaps;
5th step, open to traffic
After both sides backfill highly reaches and flushed with the tube top of FRP sand tube, in the tube top of FRP sand tube It is filled at end.It is first filled with medium coarse sand, the height for filling medium coarse sand is 20cm, is then gathered around according to practice of construction scene Some soil properties are filled, and are reached final filled height not less than after 50cm, are carried out upper end compacting with road roller, it is desirable that compactness Not less than 95%.Compacting finishes, and meet compactness and the depth of fill requirement after, can let pass traffic;
6th step, support dismounting.
When the tube top upper end height to earth up of FRP sand tube is more than 1m, after clearance traffic 5 days, branch can be all removed Support;When the tube top upper end height to earth up of FRP sand tube is not more than 1m, after clearance traffic 5 days, retain 3 supports, i.e., in Between and both sides totally 3, remaining whole removes, and remaining 3 support is removed after 15 days in clearance traffic.
Burning into sand tube hub described in Fig. 1 (a) of the present invention refers to the axial centre position of entire FRP sand tube 1, The equal length of FRP sand tube at left and right sides of the burning into sand tube hub.
Embodiment 1
The a diameter of 1.5m of FRP sand tube of the present embodiment.For highway culvert draining, the soil property of construction site is glutinous Soil, FRP sand tube upper end height to earth up are less than 1m.
Specific construction process is:
Foundation pit form of fracture is digged pit mode using slope, and foundation pit both sides are according to side slope height:Width=1:1.5 ratio put Slope, as a diameter of 1.5m, foundation pit excavation width be 3m, substrate change fill out natural soft-clay width for 3.5m (in foundation pit excavation width On the basis of 3m plus 0.5m is 3.5m) (referring to Fig. 2).
It during base treatment, is changed and filled out using 30cm natural soft-clays, compactness 98% forms 30cm natural soft-clays basis.Base Bottom is changed fill out after, first in substrate with standard fine sand spread 10cm, then on standard fine sand, select loess as roadbed filling progress Filling, packed height 40cm, compactness 96%.Roadbed filling center after compaction, by the radian of FRP sand tube Lower digging 40cm.
It is supported together every two meter amperes dress in FRP sand tube, then away from fiberglass sand inclusion tube hub both sides 1.5m Steel ring sleeve of the inside with elastic tape is used in FRP sand tube in place;When placing FRP sand tube, the position of placement will Coincidence measurement person requires, and steel ring is fixed on loess finally by anchor bolt.
After FRP sand tube is placed, in its both sides hierarchical synchronization filling medium coarse sand, and per the punching of 20cm height Rammer compacting is hit, control compactness reaches more than 96%, needs to fill to tube top and flush.It should be noted that FRP sand tube half Diameter height needs hand compaction with the compacting of lower part tube edge medium coarse sand, it is impossible to which there are gaps.
When being filled to tube top top, placement in layers thickness is carried out according to roadbed filling code requirement, and compactness is 95%.Compacting finishes, and meet compactness and the depth of fill requirement after, can let pass traffic.
The FRP sand tube of diameter 1.5m, can only retain 3 supports after clearance traffic 5 days, i.e., intermediate and both sides totally 3 Road, remaining whole remove.Remaining 3 support is removed after 15 days in clearance traffic.
Embodiment 2
The a diameter of 1m of FRP sand tube of the present embodiment.For highway culvert draining, the soil property of construction site is clay, FRP sand tube upper end height to earth up is less than 1m.
Specific construction process is:
Foundation pit form of fracture is digged pit mode using slope, and foundation pit both sides are according to side slope height:Width=1:1.5 ratio is put Slope, as a diameter of 1m, foundation pit excavation width be 2.5m, substrate change fill out natural soft-clay width for 3m (in foundation pit excavation width On the basis of 2.5m plus 0.5m is 3m) (referring to Fig. 3).
It during base treatment, is changed and filled out using 30cm natural soft-clays, compactness 98% forms 30cm natural soft-clays basis.Base Bottom is changed fill out after, with standard fine sand paving 10cm or so in substrate, then on standard fine sand, select loess as roadbed filling into Row filling, packed height 30cm, compactness 96%.Roadbed filling center after compaction, by the arc of FRP sand tube Degree is lower to dig 30cm.
It is supported together every two meter amperes dress in FRP sand tube, then at away from fiberglass sand inclusion tube hub both sides 2m With steel ring sleeve of the inside with elastic tape in FRP sand tube, then when placing FRP sand tube, the position of placement Coincidence measurement person is wanted to require, steel ring is fixed on loess finally by anchor bolt.
After FRP sand tube is placed, in its both sides hierarchical synchronization filling medium coarse sand, and per the punching of 20cm height Rammer compacting is hit, control compactness reaches more than 96%, needs to fill to tube top and flush.It should be noted that FRP sand tube half Diameter height needs hand compaction with the compacting of lower part tube edge medium coarse sand, it is impossible to which there are gaps.
When being filled to tube top top, placement in layers thickness is carried out according to roadbed filling code requirement, and compactness is 96%.Compacting finishes, and meet compactness and the depth of fill requirement after, can let pass traffic.
The FRP sand tube of diameter 1m, can only retain 3 supports after clearance traffic 5 days, i.e., intermediate and both sides totally 3, Remaining whole removes.Remaining 3 support is removed after 15 days in clearance traffic.
By the practical application of the two examples, the actual effect of generation is:It, can by controlling soil compaction degree constantly The stability of subgrade soils is effectively ensured, chooses medium coarse sand and expects as backfill, and FRP sand tube is fixed with steel ring, It ensure that the stability of FRP sand tube entirety, and the antiscour of FRP sand tube significantly improved when applying in the later stage Property, so as to improve construction quality.
The present invention does not address part and is suitable for the prior art.

Claims (1)

1. a kind of construction method for highway fiberglass sand inclusion pipe culverts, Specific construction process are:
The first step, excavation of foundation pit
Foundation pit form of fracture is digged pit mode using slope, and foundation pit both sides are according to side slope height:Width=1:1.5 ratio slope;
Second step, base treatment
1) substrate is compacted using road roller, when substrate soil property is poor or water content is higher, is changed using natural soft-clay soil and is filled out 30cm, Substrate compaction Control is not less than 98%;
2) substrate is changed fill out after, in substrate with standard fine sand spread 10cm, no concave-convex, ensure standard fine sand it is smooth, make later stage glass Uniform force when steel clamp sandpipe is placed;
3) on standard fine sand, loess is selected to be filled as roadbed filling, and packed height is not less than 30cm, it is desirable that compacting Degree control is 96%;
4) after compacting is smooth, grooving is carried out at the center of roadbed filling, 30cm is no less than by being dug under the radian of FRP sand tube;
Third step, pipeline are placed and are fixed
It supports every two meter amperes dress in FRP sand tube, is then not less than away from fiberglass sand inclusion tube hub both sides together Steel ring sleeve of the inside with elastic tape is used then can to carry out the peace of FRP sand tube in FRP sand tube at 1.5m It puts;Coincidence measurement person's requirement want in the position for placing FRP sand tube, after FRP sand tube places, by anchor bolt by steel ring It is fixed on loess, and then completes the fixation of FRP sand tube;
4th step, both sides backfill
After FRP sand tube placement fixation is appropriate, with medium coarse sand to the tube bottom edge of FRP sand tube and the gap of foundation pit It is carefully filled, and with compacting tool hand compaction;In FRP sand tube both sides in medium coarse sand filling process, often fill 20cm height is tamped with battering ram, and compactness reaches more than 96%;For the following glass steel clamp of FRP sand tube radial height The medium coarse sand of sandpipe adjacent edges needs to carry out hand compaction;
5th step, open to traffic
After in both sides, backfill height reaches and is flushed with the tube top of FRP sand tube, to the tube top upper end of FRP sand tube into Row fills, and is first filled with medium coarse sand, and the height for filling medium coarse sand is 20cm, is then possessed according to practice of construction scene Soil property is filled, and is reached final filled height not less than after 50cm, is carried out upper end compacting with road roller, it is desirable that compactness is not low In 95%;Compacting finishes, and meet compactness and the depth of fill requirement after, can let pass traffic;
6th step, support dismounting
When the tube top upper end height to earth up of FRP sand tube is more than 1m, after clearance traffic 5 days, support is all removed;Work as glass When the tube top upper end height to earth up of glass steel clamp sandpipe is not more than 1m, after clearance traffic 5 days, retain intermediate and both sides 3 support, Remaining whole removes, and remaining 3 support is removed after 15 days in clearance traffic.
CN201611039972.7A 2016-11-24 2016-11-24 A kind of construction method for highway fiberglass sand inclusion pipe culverts Expired - Fee Related CN106436596B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611039972.7A CN106436596B (en) 2016-11-24 2016-11-24 A kind of construction method for highway fiberglass sand inclusion pipe culverts

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611039972.7A CN106436596B (en) 2016-11-24 2016-11-24 A kind of construction method for highway fiberglass sand inclusion pipe culverts

Publications (2)

Publication Number Publication Date
CN106436596A CN106436596A (en) 2017-02-22
CN106436596B true CN106436596B (en) 2018-06-19

Family

ID=58220506

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611039972.7A Expired - Fee Related CN106436596B (en) 2016-11-24 2016-11-24 A kind of construction method for highway fiberglass sand inclusion pipe culverts

Country Status (1)

Country Link
CN (1) CN106436596B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012802A (en) * 2017-02-27 2017-08-04 承德金丰建材有限责任公司 A kind of construction method of RPM highway culvert
CN107246503A (en) * 2017-04-26 2017-10-13 广西北海跃达玻璃钢制品有限公司 A kind of glass-reinforced plastic mortar pipe installation method
CN107218439A (en) * 2017-05-02 2017-09-29 广西北海跃达玻璃钢制品有限公司 One kind is used for drip irrigation glass fiber reinforced plastic sand-inclusion pipeline installation method
CN107841959B (en) * 2017-11-06 2019-08-23 山西正道工程技术咨询有限公司 The construction method of highway high filling section discharge culvert
CN108301336A (en) * 2018-01-18 2018-07-20 陇东学院 A kind of high roadbed culvert off-loading construction method based on two-ash soil and waste tire
CN108824240A (en) * 2018-07-16 2018-11-16 中交路桥北方工程有限公司 A kind of pipe culvert construction method and auxiliary device
CN109736351B (en) * 2019-02-22 2021-04-30 中煤科工集团西安研究院有限公司 Construction method for adapting large water pipeline to coal mine mining collapse deformation
CN110067216B (en) * 2019-05-15 2021-02-12 中国电建集团中南勘测设计研究院有限公司 Construction method of culvert in soft soil road section
CN112012114A (en) * 2020-08-20 2020-12-01 河北工业大学 Construction method of double-row glass fiber reinforced plastic sand inclusion pipe culvert

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU123017U1 (en) * 2012-08-20 2012-12-20 Общество с ограниченной ответственностью "СТЕКЛОНиТ Менеджмент" WATER GRAIN STRUCTURE FOR MUNCHES OF CAR AND RAILWAYS
CN104153304A (en) * 2014-04-08 2014-11-19 中交第二公路勘察设计研究院有限公司 Corrugated steel tube culvert filling structure and filling method thereof
CN104372749A (en) * 2014-11-25 2015-02-25 中铁第四勘察设计院集团有限公司 Drainage system of cut-type open cut tunnel
CN204401485U (en) * 2014-12-19 2015-06-17 山西省第三建筑工程公司 The construction structure of high roadbed draining Steel Corrugated Pipe Culvert
CN204825546U (en) * 2015-07-24 2015-12-02 唐硕 Road concrete road surface water collect structures that permeates water
CN105484172A (en) * 2015-12-31 2016-04-13 长安大学 Structure and method for repairing culvert pipe of corrugated steel pipe by adopting expanding annular steel strip
CN105735157A (en) * 2016-04-25 2016-07-06 杭州江润科技有限公司 Large-diameter steel corrugated pipe culvert structure for half-filled and half-dug roadbed in plateau high-cold region and method for constructing large-diameter steel corrugated pipe culvert structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU123017U1 (en) * 2012-08-20 2012-12-20 Общество с ограниченной ответственностью "СТЕКЛОНиТ Менеджмент" WATER GRAIN STRUCTURE FOR MUNCHES OF CAR AND RAILWAYS
CN104153304A (en) * 2014-04-08 2014-11-19 中交第二公路勘察设计研究院有限公司 Corrugated steel tube culvert filling structure and filling method thereof
CN104372749A (en) * 2014-11-25 2015-02-25 中铁第四勘察设计院集团有限公司 Drainage system of cut-type open cut tunnel
CN204401485U (en) * 2014-12-19 2015-06-17 山西省第三建筑工程公司 The construction structure of high roadbed draining Steel Corrugated Pipe Culvert
CN204825546U (en) * 2015-07-24 2015-12-02 唐硕 Road concrete road surface water collect structures that permeates water
CN105484172A (en) * 2015-12-31 2016-04-13 长安大学 Structure and method for repairing culvert pipe of corrugated steel pipe by adopting expanding annular steel strip
CN105735157A (en) * 2016-04-25 2016-07-06 杭州江润科技有限公司 Large-diameter steel corrugated pipe culvert structure for half-filled and half-dug roadbed in plateau high-cold region and method for constructing large-diameter steel corrugated pipe culvert structure

Also Published As

Publication number Publication date
CN106436596A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN106436596B (en) A kind of construction method for highway fiberglass sand inclusion pipe culverts
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN109881694A (en) A kind of constructing structure blocked for foundation pit substrate Sand and method
CN107587557A (en) Outdoor water engineering construction method
CN104499479B (en) It is a kind of to pass through the dug pile construction method that sand gravel backfills layer
CN108442382A (en) It crosses the pressure line in-situ conservation of deep basal pit and goes along with sb. to guard him soil-baffling structure and construction method
CN103911996B (en) Close on existing building steel sheet pile and pull out construction method
CN106948340B (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN103696416B (en) A kind of method for processing foundation
CN108412016A (en) Underground tube body assures construction method
CN110359540A (en) A kind of shallow earthing Large Diameter Pipeline high water level wears the artificial jacking construction engineering method of existing road
CN106761776A (en) Existing pipeline construction method is worn under super shallow-buried tunnel shield
CN105064335A (en) Ultrahigh pressure rotary jet grouting method suitable for sandy cobble stratum shield end well reinforcement
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
CN111365020A (en) Back-pressure backfill construction method suitable for biased hole entry under poor geological conditions
CN104480956B (en) A kind of minor diameter mold-bagged concrete pile composite foundation
CN106884427A (en) Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water
CN108071110A (en) Rotary drilling rig Pile method under complex geological condition
CN106836034B (en) High-fill cover plate culvert flexible load shedding system and construction method
CN207211176U (en) A kind of big open caisson of superelevation
CN217681768U (en) Ultra-long communication channel frozen wall melting and sinking grouting system
CN107060837B (en) A kind of Shallow-buried asymmetry formula shield arch construction method
CN206220108U (en) Cut Slopes of Expansive Soil reinforced earth back-pressure antiseepage supporting construction
CN206070573U (en) It is a kind of be applied under wear the big of heavily loaded highway and reinforce foundation ditch combinative structure across open trench tunnel and steel pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Wei Lianyu

Inventor after: Wang Yang

Inventor after: Liang Xiao

Inventor after: Tan Aolong

Inventor after: Zheng Yanjun

Inventor after: Chen Zhaonan

Inventor after: Zhang Guopan

Inventor after: Li Na

Inventor after: Zhang Jing

Inventor before: Wei Lianyu

Inventor before: Wang Yang

Inventor before: Chen Zhaonan

Inventor before: Zhang Jing

Inventor before: Zheng Yanjun

Inventor before: Liang Xiao

Inventor before: Zhang Guopan

Inventor before: Li Na

Inventor before: Tan Aolong