CN106401206A - Construction method for reversed-hanging fastener steel structure mounting based on reconstruction project - Google Patents

Construction method for reversed-hanging fastener steel structure mounting based on reconstruction project Download PDF

Info

Publication number
CN106401206A
CN106401206A CN201610824291.5A CN201610824291A CN106401206A CN 106401206 A CN106401206 A CN 106401206A CN 201610824291 A CN201610824291 A CN 201610824291A CN 106401206 A CN106401206 A CN 106401206A
Authority
CN
China
Prior art keywords
steel
steel construction
building body
truss
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610824291.5A
Other languages
Chinese (zh)
Other versions
CN106401206B (en
Inventor
陈立
骆晓亮
王德学
王如婷
杨坤锋
刘博�
宋彦杰
余长海
吴杨
徐已礼
史玉凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201610824291.5A priority Critical patent/CN106401206B/en
Publication of CN106401206A publication Critical patent/CN106401206A/en
Application granted granted Critical
Publication of CN106401206B publication Critical patent/CN106401206B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3522Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by raising a structure and then adding structural elements under it

Abstract

The invention discloses a construction method for reversed-hanging fastener steel structure mounting based on a reconstruction project. The construction method comprises the following steps that a, a building main body needing to be reconstructed is provided, and primary structure reconstruction is conducted on the building main body based on design requirements; b, a truss is hoisted onto the top of the building main body subjected to primary structure reconstruction; and c, all layers of steel structures are hoisted in sequence from top to bottom by means of the truss, and all the layers of steel structures are connected. By adoption of the method for reversed-hanging steel structure mounting, interference of the structure of the building main body to be reconstructed to mounting of the steel structures is effectively avoided, and the time of mounting construction of the steel structures is shortened.

Description

Reversely hung Yong zip Steel Structure Installation construction method based on improvement project
Technical field
The present invention relates to a kind of construction method of installation of steel construction, more particularly, to a kind of drawn based on the reversely hung Yong of improvement project Lock Steel Structure Installation construction method.
Background technology
The progress of society and development promote the transformation built and reinforcing to be on the increase, and the steel knot in building renovation and reinforcing Structure is installed also more and more important, more and more generally.In current improvement project, neither one preferable Steel Structure Installation construction skill Art, common Steel Structure Installation had not only been lost time but also waste of manpower.Accordingly, it would be desirable to a kind of convenient and accurate Steel Structure Installation Construction method.
Content of the invention
The technical problem to be solved is to provide a kind of convenient accurate Steel Structure Installation construction method, realizes steel The Fast Installation of structure.
For realizing above-mentioned technique effect, the invention discloses a kind of reversely hung Yong zip Steel Structure Installation based on improvement project Construction method, comprises the following steps:
A. provide one to need to implement the building body of improvement project, based on design requirement, this building body is tentatively tied Structure is transformed;
B. lift a truss at the top of the building body completing preliminary structure transformation;
C. utilize this truss, lift each layer steel construction from top to bottom successively, and complete the connection between each layer steel construction.
Being improved by of Steel Structure Installation construction method of the present invention, carries out preliminary structure based on design requirement to building body The step of transformation further includes:
Remove and/or increase the horizontal structure of building body, make preliminary structure transform each layer horizontal structure coupling completing In each layer steel construction to be lifted;
It is provided for connecting the embedded part of steel construction in setting position.
Being improved by of Steel Structure Installation construction method of the present invention, carries out preliminary structure based on design requirement to building body The step of transformation further includes:
Setting diagonal brace is used for reinforcing the building body needing to implement improvement project, prevents this building during Steel Structure Installation construction It is unexpected that main body topples over generation.
Being improved by of Steel Structure Installation construction method of the present invention, using truss, lifts each layer steel knot from top to bottom successively Structure, and complete the step of the connection between each layer steel construction and further include:
Lift ground floor steel construction at next layer of horizontal structure of truss, and this ground floor steel construction is buried with corresponding Part carries out spot welding to be fixed temporarily;
A plurality of lifting devices are installed on truss, by this ground floor steel structure connection in described lifting device;
Adjust the absolute altitude of this ground floor steel construction by lifting device, absolute altitude adjust after the completion of by this ground floor steel construction with Embedded part carries out weld all around to be fixed;
This ground floor steel construction and the truss positioned at upper strata are connected by zip, completes the lifting of ground floor steel construction;
Repeat the above steps, are respectively completed the installation of each layer steel construction from top to bottom.
Further improvement is that of Steel Structure Installation construction method of the present invention, needs to implement the building body of improvement project Both sides are provided with scaffold, facilitate workman's construction during Steel Structure Installation.
Further improvement is that of Steel Structure Installation construction method of the present invention, this lifting device can be electric hoist.
Brief description
Fig. 1 is the schematic diagram of the building body of improvement project to be performed in Steel Structure Installation construction method of the present invention;
Fig. 2 is the schematic diagram of the building body completing preliminary structure transformation in Steel Structure Installation construction method of the present invention;
Fig. 3 is the schematic diagram of truss installa-tion in Steel Structure Installation construction method of the present invention;
Fig. 4 is the schematic diagram of ground floor steel structure hoisting in Steel Structure Installation construction method of the present invention;
Fig. 5 is the schematic diagram of the zip lifting of ground floor steel construction in Steel Structure Installation construction method of the present invention;
Fig. 6 is the schematic diagram of second layer steel structure hoisting in Steel Structure Installation construction method of the present invention;
Fig. 7 is the schematic diagram of the zip lifting of second layer steel construction in Steel Structure Installation construction method of the present invention;
Fig. 8 is the schematic diagram after the completion of Steel Structure Installation construction in Steel Structure Installation construction method of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment the present invention is further detailed explanation.
As shown in figure 1, providing one to need to implement the building body of improvement project, then this improvement project to be performed is built Build main body and carry out preliminary structure transformation.As shown in Fig. 2 when carrying out preliminary structure transformation, first removing and/or increase building body Horizontal structure 1, make preliminary structure transform each layer horizontal structure 1 of completing and be matched with each layer steel construction to be lifted;Then exist Setting position is provided for connecting the embedded part 11 of steel construction.In order to prevent building body in Steel Structure Installation work progress from will bear Larger pressure and there is accident, a diagonal brace 3 is thus set up on the bottom cushion cap 2 of building body, for building body and applying The steel construction that work is installed is supported.Additionally, the both sides of this building body are provided with scaffold 4, workman is facilitated to carry out steel construction The construction installed.
After the completion of the preliminary structure rebuilding construction of the building body of this improvement project to be performed, as shown in figure 3, preliminary at this Building body top after the completion of structure of modification lifts a truss 6 by crane 5 grade suspender, installs and be related between this truss 6 Rod member (not shown), this truss 6 is fixed by this contact rod member temporarily, and prevents truss 6 from toppling over.
After the completion of truss 6 lifting, using this truss 6, lift each layer steel construction from top to bottom successively, and complete each layer steel knot Connection between structure, and this steel construction by cantilever steel girder and contact girder steel form.First at next layer of horizontal structure 1 of truss 6 Lifting ground floor steel construction, as shown in figure 4, a cantilever steel girder 7 is transported next layer of horizontal structure 1 with truss 6 by crane 5 Put corresponding position, and cantilever steel girder 7 is carried out spot welding with embedded part 11 and fix temporarily;Plural number is installed between truss 6 and cantilever steel girder 7 Individual lifting device 8 such as electric hoist, makes cantilever steel girder 7 hang upside down on truss 6 by lifting device 8, now by crane 5 and overhang steel Beam 7 separates.Then contact girder steel (not shown) between cantilever steel girder 7 is installed, by lifting device 8 to cantilever steel girder 7 It is adjusted with the absolute altitude of contact girder steel, after the completion of this absolute altitude is adjusted, cantilever steel girder 7 and embedded part 11 are carried out weld all around and fixes.
After the completion of cantilever steel girder 7 lifting, as shown in figure 5, a plurality of zips 9 being transported by truss 6 by crane 5 and encorbelmenting Predetermined altitude between girder steel 7, and zip 9 is adjusted by lifting device 8, so that zip 9 is located between truss 6 and cantilever steel girder 7 Vertical position.Then zip 9 is fixed, cantilever steel girder 7 and truss 6 are connected by zip 9, zip 9 is first pacified when fixing Load onto portion's zip bolt, then by instruments such as crowbars, bottom zip bolt is fixed, then adjust the elasticity of zip, inspection is drawn Connection at lock node, thus completes the installation of zip 9, and then completes the projecting installation of ground floor steel construction.
Then lift second layer steel construction at next layer of horizontal structure 1 of the ground floor steel construction of above-mentioned installation. As shown in fig. 6, crane 5 second layer cantilever steel girder 10 is transported corresponding to next layer of horizontal structure 1 position of cantilever steel girder 7 Locate, and second layer cantilever steel girder 10 carried out spot welding with embedded part 11 to fix temporarily;Encorbelment in ground floor cantilever steel girder 7 and the second layer A plurality of lifting devices 8 are installed between girder steel 10, so that second layer cantilever steel girder 10 is hung upside down by lifting device 8 and encorbelment in ground floor On girder steel 7, now crane 5 and second layer cantilever steel girder 10 are separated.Then contact between second layer cantilever steel girder 10 is installed Girder steel (not shown), is adjusted to the absolute altitude of second layer cantilever steel girder 10 and contact girder steel by lifting device 8, this mark After the completion of top adjustment, second layer cantilever steel girder 10 and embedded part 11 are carried out weld all around and fixes.Then, as shown in fig. 7, passing through crane 5 A plurality of zips 12 are transported the predetermined altitude between ground floor cantilever steel girder 7 and second layer cantilever steel girder 10, and by carrying Rise device 8 and adjust zip 12, make the vertical position that zip 12 is located between ground floor cantilever steel girder 7 and second layer cantilever steel girder 10 Put, and ground floor cantilever steel girder 7 and second layer cantilever steel girder 10 are connected by this zip 12.Then zip 12 is fixed, When fixing, top zip bolt is first installed, then by instruments such as crowbars, bottom zip bolt is fixed, then adjust the pine of zip Tightness, checks the connection at zip node, thus completes the installation of zip 12, and then complete the projecting peace of second layer steel construction Dress.
That repeats above-mentioned second layer steel construction is flip-chip mounted step, and thus to lower floor, each steel construction is flip-chip mounted, directly It is flip-chip mounted to bottom steel construction and completes, as shown in figure 8, completing the reversely hung Yong zip Steel Structure Installation based on improvement project.
The reversely hung Yong zip Steel Structure Installation construction method based on improvement project for the present invention, first truss hoisting, then carry out Each layer reversely hung Yong zip Steel Structure Installation.The installation method of this reversely hung Yong zip steel construction, can eliminate improvement project to be performed Building body to the Steel Structure Installation interference that causes of construction, make steel construction and embedded part spot welding complete the Primary Location of steel construction Afterwards, directly by lifting device, steel construction is accurately positioned and steel construction is fixed with embedded part weld all around.Reversely hung Yong of the present invention The construction method of installation of zip steel construction is simple to operate, can save manpower and materials during improvement project construction.

Claims (6)

1. a kind of reversely hung Yong zip Steel Structure Installation construction method based on improvement project is it is characterised in that comprise the following steps:
A. provide one to need to implement the building body of improvement project, preliminary structure is carried out to described building body based on design requirement Transformation;
B. lift a truss at the top of the described building body completing preliminary structure transformation;
C. utilize described truss, lift each layer steel construction from top to bottom successively, and complete the connection between each layer steel construction.
2. the method for claim 1 is it is characterised in that carry out preliminary structure based on design requirement to described building body The step of transformation further includes:
Remove and/or increase the horizontal structure of described building body, make preliminary structure transform each layer horizontal structure coupling completing In each layer steel construction to be lifted;
It is provided for connecting the embedded part of steel construction in setting position.
3. the method for claim 1 is it is characterised in that carry out preliminary structure based on design requirement to described building body The step of transformation further includes:
Setting diagonal brace is used for reinforcing the described building body needing enforcement improvement project.
4. method as claimed in claim 2, it is characterised in that utilizing described truss, lifts each layer steel knot from top to bottom successively Structure, and complete the step of the connection between each layer steel construction and further include:
At next layer of horizontal structure of described truss lift ground floor steel construction, and by described ground floor steel construction with corresponding Described embedded part carries out spot welding to be fixed temporarily;
A plurality of lifting devices are installed on described truss, by described ground floor steel structure connection in described lifting device;
Adjust the absolute altitude of described ground floor steel construction by described lifting device, described ground floor steel is tied after the completion of adjusting by absolute altitude Structure and described embedded part carry out weld all around to be fixed;
Described ground floor steel construction and the described truss positioned at upper strata are connected by zip, completes hanging of described ground floor steel construction Dress;
Repeat the above steps, are respectively completed the installation of each layer steel construction from top to bottom.
5. the method for claim 1 it is characterised in that:The described both sides needing to implement the building body of improvement project set It is equipped with scaffold.
6. method as claimed in claim 4 it is characterised in that:Described lifting device is electric hoist.
CN201610824291.5A 2016-09-14 2016-09-14 Reversely hung Yong zipper Steel Structure Installation construction method based on improvement project Active CN106401206B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610824291.5A CN106401206B (en) 2016-09-14 2016-09-14 Reversely hung Yong zipper Steel Structure Installation construction method based on improvement project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610824291.5A CN106401206B (en) 2016-09-14 2016-09-14 Reversely hung Yong zipper Steel Structure Installation construction method based on improvement project

Publications (2)

Publication Number Publication Date
CN106401206A true CN106401206A (en) 2017-02-15
CN106401206B CN106401206B (en) 2018-09-04

Family

ID=57996550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610824291.5A Active CN106401206B (en) 2016-09-14 2016-09-14 Reversely hung Yong zipper Steel Structure Installation construction method based on improvement project

Country Status (1)

Country Link
CN (1) CN106401206B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0654571A4 (en) * 1993-05-14 1996-06-05 Mitsubishi Heavy Ind Ltd Zone module construction method of steel structure construction.
CN1263190A (en) * 1999-06-14 2000-08-16 樊志 Steel structure building method for renovation of old buildings
CN103628680A (en) * 2013-11-15 2014-03-12 天津三建建筑工程有限公司 Construction method for large-area steel structure hanging layer
CN104328922A (en) * 2014-11-13 2015-02-04 中铁六局集团有限公司 Down-top hoisting construction technology for high-level multi-layer suspension steel structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0654571A4 (en) * 1993-05-14 1996-06-05 Mitsubishi Heavy Ind Ltd Zone module construction method of steel structure construction.
CN1263190A (en) * 1999-06-14 2000-08-16 樊志 Steel structure building method for renovation of old buildings
CN103628680A (en) * 2013-11-15 2014-03-12 天津三建建筑工程有限公司 Construction method for large-area steel structure hanging layer
CN104328922A (en) * 2014-11-13 2015-02-04 中铁六局集团有限公司 Down-top hoisting construction technology for high-level multi-layer suspension steel structure

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
郭小明等: "接建钢结构悬挑梁节点构造设计与施工", 《施工技术》 *
韩兴争等: "山东省新博物馆悬挑吊挂钢结构变形分析与施工", 《建筑》 *
黄诚等: "国家奥林匹克体育中心体育场改扩建工程施工新技术综述", 《建筑技术》 *

Also Published As

Publication number Publication date
CN106401206B (en) 2018-09-04

Similar Documents

Publication Publication Date Title
CN104947926B (en) A kind of Core Walls Structure inner core top formwork system hard protection device and its construction method
CN106087752B (en) Multispan cable-carried arch bridge construction method
CN106836498A (en) A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN205955237U (en) Plug -type platform of unloading of encorbelmenting
CN207294093U (en) A kind of large span steel truss integral lifting apparatus
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN105804400A (en) Hoisting construction method of curved truss
CN103967284A (en) Method for installing steel column in butt joint with reserved column head
CN104775363B (en) The spelling method of upper king-post strut reinforcing bar sections
CN107059656A (en) Active service bridge maintenance repairs the construction method of boat scaffold operating platform
CN109747775A (en) The parallel building technology of FPSO modular unitization
CN208219384U (en) A kind of overlapping girder segment
CN104499706B (en) Hoistway formwork platform and construction method thereof
CN106120573B (en) Multispan cable-carried arch bridge self-balancing button over strait hangs construction method
CN107217831B (en) Super high-rise building Core Walls Structure horizontal structure construction method
CN203795311U (en) Multi-leg high pier and slip form construction device
CN102691267A (en) High pier construction method for external whole operation platform
CN106401206A (en) Construction method for reversed-hanging fastener steel structure mounting based on reconstruction project
CN104314315B (en) The construction method that steel arch-shelf is installed
CN105625732B (en) Superelevation overhanging steel structure truss support free construction method
CN103669867B (en) Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method
CN105887701B (en) Suspension bridge superstructure is removed with changing installation method
CN103669219B (en) Many limbs height pier is with sliding construction equipment
CN107161884A (en) Mechanical device and its application method that tower crane climbing frame is unified with structural support beam
CN203640291U (en) Height-difference adjustable double-layer operating platform for construction of building body and external ornaments

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant