CN106401206A - Construction method for reversed-hanging fastener steel structure mounting based on reconstruction project - Google Patents
Construction method for reversed-hanging fastener steel structure mounting based on reconstruction project Download PDFInfo
- Publication number
- CN106401206A CN106401206A CN201610824291.5A CN201610824291A CN106401206A CN 106401206 A CN106401206 A CN 106401206A CN 201610824291 A CN201610824291 A CN 201610824291A CN 106401206 A CN106401206 A CN 106401206A
- Authority
- CN
- China
- Prior art keywords
- steel
- steel construction
- building body
- truss
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
- E04B1/3522—Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by raising a structure and then adding structural elements under it
Abstract
The invention discloses a construction method for reversed-hanging fastener steel structure mounting based on a reconstruction project. The construction method comprises the following steps that a, a building main body needing to be reconstructed is provided, and primary structure reconstruction is conducted on the building main body based on design requirements; b, a truss is hoisted onto the top of the building main body subjected to primary structure reconstruction; and c, all layers of steel structures are hoisted in sequence from top to bottom by means of the truss, and all the layers of steel structures are connected. By adoption of the method for reversed-hanging steel structure mounting, interference of the structure of the building main body to be reconstructed to mounting of the steel structures is effectively avoided, and the time of mounting construction of the steel structures is shortened.
Description
Technical field
The present invention relates to a kind of construction method of installation of steel construction, more particularly, to a kind of drawn based on the reversely hung Yong of improvement project
Lock Steel Structure Installation construction method.
Background technology
The progress of society and development promote the transformation built and reinforcing to be on the increase, and the steel knot in building renovation and reinforcing
Structure is installed also more and more important, more and more generally.In current improvement project, neither one preferable Steel Structure Installation construction skill
Art, common Steel Structure Installation had not only been lost time but also waste of manpower.Accordingly, it would be desirable to a kind of convenient and accurate Steel Structure Installation
Construction method.
Content of the invention
The technical problem to be solved is to provide a kind of convenient accurate Steel Structure Installation construction method, realizes steel
The Fast Installation of structure.
For realizing above-mentioned technique effect, the invention discloses a kind of reversely hung Yong zip Steel Structure Installation based on improvement project
Construction method, comprises the following steps:
A. provide one to need to implement the building body of improvement project, based on design requirement, this building body is tentatively tied
Structure is transformed;
B. lift a truss at the top of the building body completing preliminary structure transformation;
C. utilize this truss, lift each layer steel construction from top to bottom successively, and complete the connection between each layer steel construction.
Being improved by of Steel Structure Installation construction method of the present invention, carries out preliminary structure based on design requirement to building body
The step of transformation further includes:
Remove and/or increase the horizontal structure of building body, make preliminary structure transform each layer horizontal structure coupling completing
In each layer steel construction to be lifted;
It is provided for connecting the embedded part of steel construction in setting position.
Being improved by of Steel Structure Installation construction method of the present invention, carries out preliminary structure based on design requirement to building body
The step of transformation further includes:
Setting diagonal brace is used for reinforcing the building body needing to implement improvement project, prevents this building during Steel Structure Installation construction
It is unexpected that main body topples over generation.
Being improved by of Steel Structure Installation construction method of the present invention, using truss, lifts each layer steel knot from top to bottom successively
Structure, and complete the step of the connection between each layer steel construction and further include:
Lift ground floor steel construction at next layer of horizontal structure of truss, and this ground floor steel construction is buried with corresponding
Part carries out spot welding to be fixed temporarily;
A plurality of lifting devices are installed on truss, by this ground floor steel structure connection in described lifting device;
Adjust the absolute altitude of this ground floor steel construction by lifting device, absolute altitude adjust after the completion of by this ground floor steel construction with
Embedded part carries out weld all around to be fixed;
This ground floor steel construction and the truss positioned at upper strata are connected by zip, completes the lifting of ground floor steel construction;
Repeat the above steps, are respectively completed the installation of each layer steel construction from top to bottom.
Further improvement is that of Steel Structure Installation construction method of the present invention, needs to implement the building body of improvement project
Both sides are provided with scaffold, facilitate workman's construction during Steel Structure Installation.
Further improvement is that of Steel Structure Installation construction method of the present invention, this lifting device can be electric hoist.
Brief description
Fig. 1 is the schematic diagram of the building body of improvement project to be performed in Steel Structure Installation construction method of the present invention;
Fig. 2 is the schematic diagram of the building body completing preliminary structure transformation in Steel Structure Installation construction method of the present invention;
Fig. 3 is the schematic diagram of truss installa-tion in Steel Structure Installation construction method of the present invention;
Fig. 4 is the schematic diagram of ground floor steel structure hoisting in Steel Structure Installation construction method of the present invention;
Fig. 5 is the schematic diagram of the zip lifting of ground floor steel construction in Steel Structure Installation construction method of the present invention;
Fig. 6 is the schematic diagram of second layer steel structure hoisting in Steel Structure Installation construction method of the present invention;
Fig. 7 is the schematic diagram of the zip lifting of second layer steel construction in Steel Structure Installation construction method of the present invention;
Fig. 8 is the schematic diagram after the completion of Steel Structure Installation construction in Steel Structure Installation construction method of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment the present invention is further detailed explanation.
As shown in figure 1, providing one to need to implement the building body of improvement project, then this improvement project to be performed is built
Build main body and carry out preliminary structure transformation.As shown in Fig. 2 when carrying out preliminary structure transformation, first removing and/or increase building body
Horizontal structure 1, make preliminary structure transform each layer horizontal structure 1 of completing and be matched with each layer steel construction to be lifted;Then exist
Setting position is provided for connecting the embedded part 11 of steel construction.In order to prevent building body in Steel Structure Installation work progress from will bear
Larger pressure and there is accident, a diagonal brace 3 is thus set up on the bottom cushion cap 2 of building body, for building body and applying
The steel construction that work is installed is supported.Additionally, the both sides of this building body are provided with scaffold 4, workman is facilitated to carry out steel construction
The construction installed.
After the completion of the preliminary structure rebuilding construction of the building body of this improvement project to be performed, as shown in figure 3, preliminary at this
Building body top after the completion of structure of modification lifts a truss 6 by crane 5 grade suspender, installs and be related between this truss 6
Rod member (not shown), this truss 6 is fixed by this contact rod member temporarily, and prevents truss 6 from toppling over.
After the completion of truss 6 lifting, using this truss 6, lift each layer steel construction from top to bottom successively, and complete each layer steel knot
Connection between structure, and this steel construction by cantilever steel girder and contact girder steel form.First at next layer of horizontal structure 1 of truss 6
Lifting ground floor steel construction, as shown in figure 4, a cantilever steel girder 7 is transported next layer of horizontal structure 1 with truss 6 by crane 5
Put corresponding position, and cantilever steel girder 7 is carried out spot welding with embedded part 11 and fix temporarily;Plural number is installed between truss 6 and cantilever steel girder 7
Individual lifting device 8 such as electric hoist, makes cantilever steel girder 7 hang upside down on truss 6 by lifting device 8, now by crane 5 and overhang steel
Beam 7 separates.Then contact girder steel (not shown) between cantilever steel girder 7 is installed, by lifting device 8 to cantilever steel girder 7
It is adjusted with the absolute altitude of contact girder steel, after the completion of this absolute altitude is adjusted, cantilever steel girder 7 and embedded part 11 are carried out weld all around and fixes.
After the completion of cantilever steel girder 7 lifting, as shown in figure 5, a plurality of zips 9 being transported by truss 6 by crane 5 and encorbelmenting
Predetermined altitude between girder steel 7, and zip 9 is adjusted by lifting device 8, so that zip 9 is located between truss 6 and cantilever steel girder 7
Vertical position.Then zip 9 is fixed, cantilever steel girder 7 and truss 6 are connected by zip 9, zip 9 is first pacified when fixing
Load onto portion's zip bolt, then by instruments such as crowbars, bottom zip bolt is fixed, then adjust the elasticity of zip, inspection is drawn
Connection at lock node, thus completes the installation of zip 9, and then completes the projecting installation of ground floor steel construction.
Then lift second layer steel construction at next layer of horizontal structure 1 of the ground floor steel construction of above-mentioned installation.
As shown in fig. 6, crane 5 second layer cantilever steel girder 10 is transported corresponding to next layer of horizontal structure 1 position of cantilever steel girder 7
Locate, and second layer cantilever steel girder 10 carried out spot welding with embedded part 11 to fix temporarily;Encorbelment in ground floor cantilever steel girder 7 and the second layer
A plurality of lifting devices 8 are installed between girder steel 10, so that second layer cantilever steel girder 10 is hung upside down by lifting device 8 and encorbelment in ground floor
On girder steel 7, now crane 5 and second layer cantilever steel girder 10 are separated.Then contact between second layer cantilever steel girder 10 is installed
Girder steel (not shown), is adjusted to the absolute altitude of second layer cantilever steel girder 10 and contact girder steel by lifting device 8, this mark
After the completion of top adjustment, second layer cantilever steel girder 10 and embedded part 11 are carried out weld all around and fixes.Then, as shown in fig. 7, passing through crane 5
A plurality of zips 12 are transported the predetermined altitude between ground floor cantilever steel girder 7 and second layer cantilever steel girder 10, and by carrying
Rise device 8 and adjust zip 12, make the vertical position that zip 12 is located between ground floor cantilever steel girder 7 and second layer cantilever steel girder 10
Put, and ground floor cantilever steel girder 7 and second layer cantilever steel girder 10 are connected by this zip 12.Then zip 12 is fixed,
When fixing, top zip bolt is first installed, then by instruments such as crowbars, bottom zip bolt is fixed, then adjust the pine of zip
Tightness, checks the connection at zip node, thus completes the installation of zip 12, and then complete the projecting peace of second layer steel construction
Dress.
That repeats above-mentioned second layer steel construction is flip-chip mounted step, and thus to lower floor, each steel construction is flip-chip mounted, directly
It is flip-chip mounted to bottom steel construction and completes, as shown in figure 8, completing the reversely hung Yong zip Steel Structure Installation based on improvement project.
The reversely hung Yong zip Steel Structure Installation construction method based on improvement project for the present invention, first truss hoisting, then carry out
Each layer reversely hung Yong zip Steel Structure Installation.The installation method of this reversely hung Yong zip steel construction, can eliminate improvement project to be performed
Building body to the Steel Structure Installation interference that causes of construction, make steel construction and embedded part spot welding complete the Primary Location of steel construction
Afterwards, directly by lifting device, steel construction is accurately positioned and steel construction is fixed with embedded part weld all around.Reversely hung Yong of the present invention
The construction method of installation of zip steel construction is simple to operate, can save manpower and materials during improvement project construction.
Claims (6)
1. a kind of reversely hung Yong zip Steel Structure Installation construction method based on improvement project is it is characterised in that comprise the following steps:
A. provide one to need to implement the building body of improvement project, preliminary structure is carried out to described building body based on design requirement
Transformation;
B. lift a truss at the top of the described building body completing preliminary structure transformation;
C. utilize described truss, lift each layer steel construction from top to bottom successively, and complete the connection between each layer steel construction.
2. the method for claim 1 is it is characterised in that carry out preliminary structure based on design requirement to described building body
The step of transformation further includes:
Remove and/or increase the horizontal structure of described building body, make preliminary structure transform each layer horizontal structure coupling completing
In each layer steel construction to be lifted;
It is provided for connecting the embedded part of steel construction in setting position.
3. the method for claim 1 is it is characterised in that carry out preliminary structure based on design requirement to described building body
The step of transformation further includes:
Setting diagonal brace is used for reinforcing the described building body needing enforcement improvement project.
4. method as claimed in claim 2, it is characterised in that utilizing described truss, lifts each layer steel knot from top to bottom successively
Structure, and complete the step of the connection between each layer steel construction and further include:
At next layer of horizontal structure of described truss lift ground floor steel construction, and by described ground floor steel construction with corresponding
Described embedded part carries out spot welding to be fixed temporarily;
A plurality of lifting devices are installed on described truss, by described ground floor steel structure connection in described lifting device;
Adjust the absolute altitude of described ground floor steel construction by described lifting device, described ground floor steel is tied after the completion of adjusting by absolute altitude
Structure and described embedded part carry out weld all around to be fixed;
Described ground floor steel construction and the described truss positioned at upper strata are connected by zip, completes hanging of described ground floor steel construction
Dress;
Repeat the above steps, are respectively completed the installation of each layer steel construction from top to bottom.
5. the method for claim 1 it is characterised in that:The described both sides needing to implement the building body of improvement project set
It is equipped with scaffold.
6. method as claimed in claim 4 it is characterised in that:Described lifting device is electric hoist.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610824291.5A CN106401206B (en) | 2016-09-14 | 2016-09-14 | Reversely hung Yong zipper Steel Structure Installation construction method based on improvement project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610824291.5A CN106401206B (en) | 2016-09-14 | 2016-09-14 | Reversely hung Yong zipper Steel Structure Installation construction method based on improvement project |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106401206A true CN106401206A (en) | 2017-02-15 |
CN106401206B CN106401206B (en) | 2018-09-04 |
Family
ID=57996550
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610824291.5A Active CN106401206B (en) | 2016-09-14 | 2016-09-14 | Reversely hung Yong zipper Steel Structure Installation construction method based on improvement project |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106401206B (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0654571A4 (en) * | 1993-05-14 | 1996-06-05 | Mitsubishi Heavy Ind Ltd | Zone module construction method of steel structure construction. |
CN1263190A (en) * | 1999-06-14 | 2000-08-16 | 樊志 | Steel structure building method for renovation of old buildings |
CN103628680A (en) * | 2013-11-15 | 2014-03-12 | 天津三建建筑工程有限公司 | Construction method for large-area steel structure hanging layer |
CN104328922A (en) * | 2014-11-13 | 2015-02-04 | 中铁六局集团有限公司 | Down-top hoisting construction technology for high-level multi-layer suspension steel structure |
-
2016
- 2016-09-14 CN CN201610824291.5A patent/CN106401206B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0654571A4 (en) * | 1993-05-14 | 1996-06-05 | Mitsubishi Heavy Ind Ltd | Zone module construction method of steel structure construction. |
CN1263190A (en) * | 1999-06-14 | 2000-08-16 | 樊志 | Steel structure building method for renovation of old buildings |
CN103628680A (en) * | 2013-11-15 | 2014-03-12 | 天津三建建筑工程有限公司 | Construction method for large-area steel structure hanging layer |
CN104328922A (en) * | 2014-11-13 | 2015-02-04 | 中铁六局集团有限公司 | Down-top hoisting construction technology for high-level multi-layer suspension steel structure |
Non-Patent Citations (3)
Title |
---|
郭小明等: "接建钢结构悬挑梁节点构造设计与施工", 《施工技术》 * |
韩兴争等: "山东省新博物馆悬挑吊挂钢结构变形分析与施工", 《建筑》 * |
黄诚等: "国家奥林匹克体育中心体育场改扩建工程施工新技术综述", 《建筑技术》 * |
Also Published As
Publication number | Publication date |
---|---|
CN106401206B (en) | 2018-09-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104947926B (en) | A kind of Core Walls Structure inner core top formwork system hard protection device and its construction method | |
CN106087752B (en) | Multispan cable-carried arch bridge construction method | |
CN106836498A (en) | A kind of super-span Stadium roof system steel truss lifting construction engineering method | |
CN205955237U (en) | Plug -type platform of unloading of encorbelmenting | |
CN207294093U (en) | A kind of large span steel truss integral lifting apparatus | |
CN206692235U (en) | A kind of steel structure dome lifts by crane erecting device | |
CN105804400A (en) | Hoisting construction method of curved truss | |
CN103967284A (en) | Method for installing steel column in butt joint with reserved column head | |
CN104775363B (en) | The spelling method of upper king-post strut reinforcing bar sections | |
CN107059656A (en) | Active service bridge maintenance repairs the construction method of boat scaffold operating platform | |
CN109747775A (en) | The parallel building technology of FPSO modular unitization | |
CN208219384U (en) | A kind of overlapping girder segment | |
CN104499706B (en) | Hoistway formwork platform and construction method thereof | |
CN106120573B (en) | Multispan cable-carried arch bridge self-balancing button over strait hangs construction method | |
CN107217831B (en) | Super high-rise building Core Walls Structure horizontal structure construction method | |
CN203795311U (en) | Multi-leg high pier and slip form construction device | |
CN102691267A (en) | High pier construction method for external whole operation platform | |
CN106401206A (en) | Construction method for reversed-hanging fastener steel structure mounting based on reconstruction project | |
CN104314315B (en) | The construction method that steel arch-shelf is installed | |
CN105625732B (en) | Superelevation overhanging steel structure truss support free construction method | |
CN103669867B (en) | Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method | |
CN105887701B (en) | Suspension bridge superstructure is removed with changing installation method | |
CN103669219B (en) | Many limbs height pier is with sliding construction equipment | |
CN107161884A (en) | Mechanical device and its application method that tower crane climbing frame is unified with structural support beam | |
CN203640291U (en) | Height-difference adjustable double-layer operating platform for construction of building body and external ornaments |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |