CN106401173A - Sliding reverse formwork device and construction method thereof - Google Patents

Sliding reverse formwork device and construction method thereof Download PDF

Info

Publication number
CN106401173A
CN106401173A CN201610814820.3A CN201610814820A CN106401173A CN 106401173 A CN106401173 A CN 106401173A CN 201610814820 A CN201610814820 A CN 201610814820A CN 106401173 A CN106401173 A CN 106401173A
Authority
CN
China
Prior art keywords
wall
template
arc line
line shaped
purlin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610814820.3A
Other languages
Chinese (zh)
Inventor
杨翔虎
黄贤斌
王金星
杨晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHENJIANG CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHENJIANG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHENJIANG CONSTRUCTION GROUP CO Ltd filed Critical ZHENJIANG CONSTRUCTION GROUP CO Ltd
Priority to CN201610814820.3A priority Critical patent/CN106401173A/en
Publication of CN106401173A publication Critical patent/CN106401173A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention provides a sliding reverse formwork device and a construction method thereof. A climbing stand column is arranged in a wall and sleeved with a lifting support through a core-crossing jack. Formworks are installed on the lifting support through screw traction mechanisms. The formworks are adjusted to reach the set wall height through the lifting support. The distance between the formworks is adjusted to reach the wall width position through the screw traction mechanisms. A scaffold is suspended to the lifting support so that building workers can construct while standing. An arc-shaped formwork, circuit purlin and a guide column adjusting device which are matched with an arc-shaped wall are arranged in a matched mode, and dismounting, transferring and installing of a formwork each time of a traditional sliding frame reverse formwork technique are avoided. The structure is simple, operation is convenient, and the construction efficiency of the reverse formwork technique is greatly improved.

Description

Sliding sky reverse mould device and its construction method
Technical field
The present invention relates to a kind of sliding sky reverse mould device and its construction method are and in particular to concrete wall in building trade Construction technology.
Background technology
Fixed form, template middle setting reinforcing bar need to be set in body of wall both sides during building concrete wall construction, pouring is mixed Coagulation forming after solidifying soil, template is supported by support, and builder also needs placing concrete on support of standing, building masonry wall Substantially there is high, long characteristic, need segmentation to water in short transverse, traditional architecture industry is passed through manual segmentation frame mould, pouring, coagulated Gu, also need dismounting, transporting supports and template to next section to repeat modeling pouring after one section of pouring solidification, lead to work progress numerous Trivial, the cycle is long, and labor strength is big, and building efficiency is low, also manual manipulative techniques is had higher requirements;Though part engineering adopts Sliding reverse mould equipment, template and jacking equipment are connected as a single entity a lifting, and after concrete setting, frictional resistance is big, and template sliding is stranded Difficult;Also has a kind of slip-framed reverse mould construction technology at present, support can be lifted in segmentation, but template needs manual removal, support lift Manual installation form again after putting in place, dismounting, installs loaded down with trivial details, carrying trouble, and labor strength is big, easily causes potential safety hazard.
Content of the invention
The technical problem to be solved is to provide one kind and conveniently can carry out construction wall reverse mould construction, and applies Work efficiency high, easy to operate, time saving and energy saving slides sky reverse mould device and its construction method.
The sliding sky reverse mould device of the present invention, including the template positioned at body of wall both sides to be onstructed, for installation form lifting Support, the support beam being connected to lifting bracket top is provided with centre-hole jack, and centre-hole jack is provided centrally with climbing Rise column, the column that climbs be fixed in body of wall and with concrete casting solidification it is characterised in that:Company in vertical template Connect horizontal screw bolt haulage gear, the screw front end of screw rod haulage gear is fixedly connected with the purlin that encloses in template, and screw rod stage casing passes through It is fixedly welded on the steel pipe guide pin bushing on lifting bracket, guide pin bushing two ends outside screw rod is installed with before and after's nut, template passes through guide pin bushing It is connected with lifting bracket, can be movable under in front and back's nut with screw rod cooperation traction;
Multiple screw rod haulage gears are distributed with described template
3m is spaced between adjacent screws haulage gear on described template;
Described lifting bracket is provided with scaffold cradle;
The template of described body of wall both sides to be applied is two sections of concentric arc line shapeds, and concentric arc line shaped template has and is similarly camber line The segmentation arc line shaped of shape encloses purlin, and each section of arc line shaped encloses and have gap between purlin, is fixed by bearing plus bolt connection;
Described screw rod haulage gear is radially arranged, and each screw rod haulage gear controls one section of template, and multiple template is assembled into Circular arc;
It is steel-tube construction that described arc line shaped encloses purlin, and adjacent two sections of arc line shapeds enclose and have gap between purlin, have circular arc in gap Shape guide pillar, guide pillar encloses the nested installation of purlin with arc line shaped, and guide pillar one end and one of arc line shaped enclose the purlin mouth of pipe and be welded and fixed, another End is nested into another arc line shaped and encloses in purlin body, and guide pillar encloses purlin for arc line shaped provides guide and limit, can adapt to arc formwork, Arc line shaped body of wall.
The invention still further relates to a kind of sliding sky reverse mould device construction method, by the above sliding sky reverse mould device construction, tool Body step is:
A. climb column in the center fixed in position setting body of wall position;
B. the column that climbs passes through centre-hole jack center, makes lifting bracket be located at setting wall by centre-hole jack Above body;
C. template passes through screw rod haulage gear traction arrival setting wall displacement;
D. orlop wall steel bar filling concrete construction;
E. after body of wall solidification, template is drawn by screw rod haulage gear and depart from the good concrete wall of casting solidification;
F. lifting bracket is lifted by centre-hole jack and template is raised to second segment body of wall position upwards;
G. repeat step c~f, by that analogy until body of wall highly meets design requirement, completes wall construction;
During cast arc line shaped body of wall, template, to enclose purlin be corresponding arc line shaped, and step c~f needs segmentation to carry out, in step c, e also Need to be adjusted by carrier setting bolt and enclose purlin gap.
The sliding sky reverse mould device of the present invention and its construction method, arrange the column that climbs inside body of wall, and lifting bracket passes through Punching jack is sleeved on and climbs on column, and template is arranged on lifting bracket by screw rod haulage gear, by lifting bracket Adjustment template reaches setting body of wall height, adjusts the distance between body of wall two side template by screw rod haulage gear and reaches body of wall width Degree position, the construction so that builder stands of lifting bracket scaffold cradle, and supporting being provided with are fitted with arc line shaped body of wall phase The arc line shaped template answered, enclose purlin and guide post regulating device, it is to avoid traditional dismounting of each template of slip-framed reverse mould technique, carrying And installation, structure is simple and convenient to operate, and substantially increases the efficiency of construction of sliding sky reverse mould technique.
Brief description
Fig. 1 is the sliding sky reverse mould device planar structure schematic diagram of the embodiment of the present invention;
Fig. 2 is the screw rod hitch structure planar structure enlarged diagram of the sliding sky reverse mould device of the embodiment of the present invention;
Fig. 3 be the sliding sky reverse mould device of the embodiment of the present invention screw rod hitch structure on body of wall distribution schematic diagram;
Fig. 4 is that the sliding sky reverse mould device of the embodiment of the present invention is applied to template and screw rod hitch structure during arc line shaped body of wall and exists Distribution schematic diagram on body of wall;
Fig. 5 is that the sliding sky reverse mould device of the embodiment of the present invention is applied to adjacent arc line shaped during arc line shaped body of wall and encloses purlin connect knot Structure schematic diagram.
Specific embodiment
As illustrated, a kind of sliding sky reverse mould device, including the template 1 positioned at body of wall both sides to be onstructed, it is used for installation form 1 Lifting bracket 2, the support beam 3 being connected to lifting bracket 2 top is provided with centre-hole jack 4, in centre-hole jack 4 The heart is provided with the column 5 that climbs, and the column 5 that climbs is fixed in body of wall and with concrete casting solidification, every side of body of wall both sides Two or more horizontal screw bolt haulage gears 6 up and down are connected with vertical form 1, in template 1 between adjacent screws haulage gear 6 It is about 3m along body of wall length or radian direction interval;Purlin 8 is enclosed in screw rod 7 front end of each screw rod haulage gear 6 and template 1 It is fixedly connected, each screw rod 7 stage casing passes through the corresponding guide pin bushing 9 being fixedly welded on lifting bracket 2, guide pin bushing 9 two ends outside screw rod 7 On be installed with before and after's nut 10, template 1 is connected with lifting bracket 2 by screw rod 7, can be movable under screw rod 7 traction;Carry Rise support 2 and be provided with scaffold cradle 11, the placing concrete so that builder stands, and check body of wall coagulation grade, pour Note effect.
In order to pour into a mould arc line shaped body of wall, also it is provided with body of wall both sides to be onstructed and be there are two being adapted with body of wall arc line shaped Duan Tongxin arc line shaped template 12, the screw rod haulage gear 6 of arc line shaped body of wall is disposed radially, and each screw rod haulage gear 6 controls One section of arc line shaped template 12, multistage arc line shaped template 12 is assembled into the circular arc setting body of wall length;Arc line shaped template 12 with one heart Have and be similarly the segmentation arc line shaped of arc line shaped and enclose purlin 13, it is steel-tube construction that arc line shaped encloses purlin 13, each section of arc line shaped enclose purlin 13 it Between there is gap, adjacent two sections of arc line shapeds enclose and are provided with circular arc guide pillar 15, guide pillar 15 and arc line shaped in gap between purlin (13) Enclose the nested installation of purlin 13, guide pillar 15 one end and one of arc line shaped enclose purlin 13 mouth of pipe and be welded and fixed, and the other end is nested into another Individual arc line shaped encloses in purlin 13 body;Enclose purlin because of concentric arc line shaped template 12 and pass through screw rod haulage gear 6 radially to body of wall both sides Leave when pouring the body of wall being poured in, between each section of arc line shaped template 12 of inner side, gap, each section of arc line shaped enclose gap meeting between purlin 13 Reduce, between each section of arc line shaped template 12 in outside, gap, each section of arc line shaped enclose gap between purlin 13 and can expand, and in concentric arc Linear template enclose purlin pass through screw rod haulage gear 6 radially to set body of wall center close in case model cast wall when, inner side Each section of arc line shaped template 12 between gap, each section of arc line shaped enclose gap between purlin 13 and can expand, each section of arc line shaped mould in outside Between plate 12, gap, each section of arc line shaped enclose gap between purlin 13 and can reduce, thus adjacent arc line shaped encloses purlin 13 junction and is provided with Bearing 14 is used for the arc line shaped template 12 adjusting and arc line shaped encloses gap between purlin 13, is fixed by bearing 14 plus bolt connection; It is steel-tube construction that arc line shaped encloses purlin 13, and adjacent arc line shaped encloses and be provided with circular arc guide pillar 15 between purlin 13, guide pillar 15 and arc line shaped Enclose the nested installation of purlin 13, guide pillar 15 encloses purlin 13 for arc line shaped provides guide and limit, and two sections of arc line shapeds enclose and have gap between purlin 13, Can adapt to arc line shaped template 12, body of wall;Adjust adjacent arc line shaped by the bolt of bearing 14 when dismounting, installation to enclose between purlin 13 Gap, adjacent arc line shaped encloses purlin along guide pillar 15 mobile adjustment gap, so that arc line shaped pipe encloses purlin 13 and radially dismantles, installs.
The invention still further relates to a kind of sliding sky reverse mould device construction method, by the above sliding sky reverse mould device construction, tool Body step is:
A. climb column in the center fixed in position setting body of wall position;
B. the column that climbs passes through centre-hole jack center, makes lifting bracket be located at setting by centre-hole jack
Above body of wall;
C. template passes through screw rod haulage gear traction arrival setting wall displacement;
D. orlop wall steel bar filling concrete construction;
E. after body of wall solidification, template is drawn by screw rod haulage gear and depart from the good concrete wall of casting solidification;
F. lifting bracket is lifted by centre-hole jack and template is raised to second segment body of wall position upwards;
G. repeat step c~f, by that analogy until body of wall highly meets design requirement, completes wall construction;
During cast arc line shaped body of wall, template, to enclose purlin be corresponding arc line shaped, and step c~f needs segmentation to carry out, in step c, e also Need to be adjusted by carrier setting bolt and enclose purlin gap.
The sliding sky reverse mould device of the present embodiment and its construction method, lifting bracket passes through centre-hole jack in the column that climbs On climb, lifting bracket by screw rod haulage gear band moving platen move up and down to set body of wall height, screw rod haulage gear adjust Horizontal range between the template of whole body of wall both sides to be onstructed, can be in system using this device to reach setting width of wall body Pour the concrete wall of certain altitude (generally 1.5m about) under static state, reach just in the walls concrete pouring After solidifying or final set, template is integrally departed from by concrete surface by screw rod haulage gear, then in template with concrete surface no In the case of friction, easily template system is lifted certain height using lifting bracket equipment, then pass through screw rod traction machine Template integral position is resetted by structure, continues to pour the construction method of top concrete, device and method can be widely applied to straight line The construction of the concrete wall of type and circular arc type and reinforced concrete tube Kuku wall moreover it can be used to trapezoid cross section, variable cross-section or its The concrete walls body construction in its geometry section.

Claims (10)

1. a kind of sliding sky reverse mould device, including the template (1) positioned at body of wall both sides to be onstructed, for installation form (1) lifting Support (2), is connected in the support beam (3) on lifting bracket (2) top and is provided with centre-hole jack (4), centre-hole jack (4) it is provided centrally with the column (5) that climbs, the column that climbs (5) is fixed in body of wall and with concrete casting solidification, its feature It is:Vertical template (1) is upper to connect horizontal screw bolt haulage gear (6), screw rod (7) front end of screw rod haulage gear (6) and mould The purlin (8) that encloses on plate (1) is fixedly connected, and screw rod (7) stage casing passes through the guide pin bushing (9) being fixedly connected on lifting bracket (2), guide pin bushing (9) before and after's nut (10) is installed with two ends outside screw rod (7), template (1) is connected with lifting bracket (2) by screw rod (7), energy Enough movable under in front and back's nut (10) with screw rod (7) cooperation traction.
2. sliding sky reverse mould device according to claim 1 it is characterised in that:Multiple screw rods are distributed with described template (1) Haulage gear (6).
3. sliding sky reverse mould device according to claim 2 it is characterised in that:The upper adjacent screws traction machine of described template (1) Horizontally spaced 3m between structure (6).
4. sliding sky reverse mould device according to claim 1 it is characterised in that:Described lifting bracket (2) is provided with suspension foot Hand cradle (11).
5. sliding sky reverse mould device according to claim 1 it is characterised in that:The template of described body of wall both sides to be onstructed is two Duan Tongxin arc line shaped template (12) is adapted therewith, and concentric arc line shaped template (12) has the segmentation arc line shaped being similarly arc line shaped Enclose purlin (13), each section of arc line shaped encloses and have gap between purlin (13), fixed by bearing (14) plus bolt connection.
6. sliding sky reverse mould device according to claim 5 it is characterised in that:Described screw rod haulage gear (6) is radially arranged, Each screw rod haulage gear (6) controls one section of arc line shaped template (12), and multiple arc line shaped templates (12) are assembled in the arc-shaped.
7. sliding sky reverse mould device according to claim 6 it is characterised in that:Described arc line shaped encloses purlin (13) and ties for steel pipe Structure, adjacent two sections of arc line shapeds enclose and have gap between purlin (13), are provided with circular arc guide pillar (15), guide pillar (15) and arc in gap Linear purlin (13) nesting of enclosing is installed, and guide pillar (15) one end and one of arc line shaped enclose purlin (13) mouth of pipe and be welded and fixed, the other end It is nested into another arc line shaped and encloses in purlin (13) body, guide pillar (15) encloses purlin (13) for arc line shaped provides guide and limit.
8. a kind of sliding sky reverse mould device construction method, by sky reverse mould device construction sliding described in claim 1~7, concrete steps For:
A. climb column in the center fixed in position setting body of wall position;
B. the column that climbs passes through centre-hole jack center, by centre-hole jack, lifting bracket is located on setting body of wall Side;
C. template passes through screw rod haulage gear traction arrival setting wall displacement;
D. orlop wall steel bar filling concrete construction;
E. after body of wall solidification, template is drawn by screw rod haulage gear and depart from the good concrete wall of casting solidification;
F. lifting bracket is lifted by centre-hole jack and template is raised to second segment body of wall position upwards;
G. repeat step c~f, by that analogy until body of wall highly meets design requirement, completes wall construction;
9. sliding sky reverse mould device construction method according to claim 8 it is characterised in that:During cast arc line shaped body of wall, mould Plate, to enclose purlin be corresponding arc line shaped, and step c~f needs segmentation to carry out.
10. sliding sky reverse mould device construction method according to claim 9 it is characterised in that:Also need in step c, e by propping up Seat bolt adjusts and encloses purlin gap.
CN201610814820.3A 2016-09-09 2016-09-09 Sliding reverse formwork device and construction method thereof Pending CN106401173A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610814820.3A CN106401173A (en) 2016-09-09 2016-09-09 Sliding reverse formwork device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610814820.3A CN106401173A (en) 2016-09-09 2016-09-09 Sliding reverse formwork device and construction method thereof

Publications (1)

Publication Number Publication Date
CN106401173A true CN106401173A (en) 2017-02-15

Family

ID=57999371

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610814820.3A Pending CN106401173A (en) 2016-09-09 2016-09-09 Sliding reverse formwork device and construction method thereof

Country Status (1)

Country Link
CN (1) CN106401173A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989361A (en) * 2017-11-29 2018-05-04 江苏阿尔博装饰工程有限公司 A kind of construction hydraulic formwork climbing device
CN108532466A (en) * 2018-04-24 2018-09-14 成都华川公路建设集团有限公司 A kind of bridge pier over-form construction technique
CN109610320A (en) * 2018-11-13 2019-04-12 柳州煜乾机械装备股份公司 A kind of band crane slip form construction device and construction method
CN111706075A (en) * 2020-06-22 2020-09-25 银广厦集团有限公司 Prefabricated template building system based on BIM technology
CN112709194A (en) * 2020-12-28 2021-04-27 云南建投第二水利水电建设有限公司 Hydraulic sliding formwork construction complete equipment for gate pier and construction method
CN114000700A (en) * 2021-11-17 2022-02-01 广西建工集团冶金建设有限公司 Sliding frame mold inserting device and construction method
CN114165048A (en) * 2021-12-15 2022-03-11 山东方大工程有限责任公司 Raw coal bunker slip form system
WO2022134529A1 (en) * 2021-06-08 2022-06-30 中建三局第二建设工程有限责任公司 Adjusting system for slipform deviation and torsion correction, and method for using adjusting system

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1031413A (en) * 1962-02-02 1966-06-02 Byggforbattring Ab Improvements relating to the casting of building structures
CN2275615Y (en) * 1996-01-25 1998-03-04 张良杰 Hydraulic raising shuttering device
CN200968056Y (en) * 2006-11-17 2007-10-31 山西焦煤集团有限责任公司 Slipping form
CN201109996Y (en) * 2007-09-13 2008-09-03 江苏通州四建集团有限公司 Hydraulic climbing formwork device
CN103075001A (en) * 2013-03-01 2013-05-01 镇江四建建设有限公司 Steel tube fastener slip form platform system
CN103104090A (en) * 2012-10-09 2013-05-15 中国葛洲坝集团股份有限公司 Silo house concrete whole sliding and ascending module
CN103114718A (en) * 2013-03-05 2013-05-22 杨晨 Collecting and separating machine of sliding form formwork and construction method of variable cross-section cylinder silo sliding form
CN104372947A (en) * 2014-11-14 2015-02-25 富于安(福建)环保模板有限公司 Integral mold plate feeding and retreating construction method for elevator shaft
CN206128625U (en) * 2016-09-09 2017-04-26 镇江建工建设集团有限公司 Smooth empty reverse mould device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1031413A (en) * 1962-02-02 1966-06-02 Byggforbattring Ab Improvements relating to the casting of building structures
CN2275615Y (en) * 1996-01-25 1998-03-04 张良杰 Hydraulic raising shuttering device
CN200968056Y (en) * 2006-11-17 2007-10-31 山西焦煤集团有限责任公司 Slipping form
CN201109996Y (en) * 2007-09-13 2008-09-03 江苏通州四建集团有限公司 Hydraulic climbing formwork device
CN103104090A (en) * 2012-10-09 2013-05-15 中国葛洲坝集团股份有限公司 Silo house concrete whole sliding and ascending module
CN103075001A (en) * 2013-03-01 2013-05-01 镇江四建建设有限公司 Steel tube fastener slip form platform system
CN103114718A (en) * 2013-03-05 2013-05-22 杨晨 Collecting and separating machine of sliding form formwork and construction method of variable cross-section cylinder silo sliding form
CN104372947A (en) * 2014-11-14 2015-02-25 富于安(福建)环保模板有限公司 Integral mold plate feeding and retreating construction method for elevator shaft
CN206128625U (en) * 2016-09-09 2017-04-26 镇江建工建设集团有限公司 Smooth empty reverse mould device

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989361A (en) * 2017-11-29 2018-05-04 江苏阿尔博装饰工程有限公司 A kind of construction hydraulic formwork climbing device
CN108532466A (en) * 2018-04-24 2018-09-14 成都华川公路建设集团有限公司 A kind of bridge pier over-form construction technique
CN109610320A (en) * 2018-11-13 2019-04-12 柳州煜乾机械装备股份公司 A kind of band crane slip form construction device and construction method
CN111706075A (en) * 2020-06-22 2020-09-25 银广厦集团有限公司 Prefabricated template building system based on BIM technology
CN112709194A (en) * 2020-12-28 2021-04-27 云南建投第二水利水电建设有限公司 Hydraulic sliding formwork construction complete equipment for gate pier and construction method
WO2022134529A1 (en) * 2021-06-08 2022-06-30 中建三局第二建设工程有限责任公司 Adjusting system for slipform deviation and torsion correction, and method for using adjusting system
CN114000700A (en) * 2021-11-17 2022-02-01 广西建工集团冶金建设有限公司 Sliding frame mold inserting device and construction method
CN114000700B (en) * 2021-11-17 2022-12-13 广西建工集团冶金建设有限公司 Sliding frame mold inserting device and construction method
CN114165048A (en) * 2021-12-15 2022-03-11 山东方大工程有限责任公司 Raw coal bunker slip form system

Similar Documents

Publication Publication Date Title
CN106401173A (en) Sliding reverse formwork device and construction method thereof
CN105799056B (en) The prefabricated formwork system of T beam batch production and construction method
CN102071798B (en) Hydraulic climbing system for wall-attached support frame
CN104727545A (en) Large water tower cylinder hydraulic slip-form vertical-transportation system and method
CN201401005Y (en) Template sliding and lifting device
CN203113793U (en) Large formwork installation system of oblique structure
CN103774842A (en) Lifting type square vertical shaft formwork
CN202064281U (en) Slip form frame
CN206128625U (en) Smooth empty reverse mould device
CN106639303B (en) Elevator dedicated hydraulic creeping formwork frame body
CN111042835B (en) Tunnel cable ditch and ditch construction trolley and construction method thereof
CN110409803B (en) Hoisting method for disassembling central drum ring of hydraulic mold lifting device
CN211421171U (en) Cast-in-place utility tunnel movable support platform truck formwork system
CN216787815U (en) Slip form system suitable for variable cross-section vertical structure
CN216515141U (en) Novel cantilever construction creeping formwork device
CN203144909U (en) Bridge high pier roller die construction device
CN203361735U (en) Sliding mode system with function of efficient adjustment
CN214885625U (en) Multi-point prefabricated part mounting platform
CN215486052U (en) Tunnel lining concrete press-in type pouring system
CN205934962U (en) A system of sliding for underground pipe gallery cast -in -situ construction
CN205296829U (en) Superelevation super large cross -section batter post integrally lift up formula template reinforcerment system
CN211522886U (en) Cast-in-place bent cap formwork system
CN108005684A (en) Separated steel mould trolley and its construction method
CN211737150U (en) Tunnel cable ditch and ditch construction trolley
CN208168895U (en) A kind of hydraulic elevation type tunnel cable groove overall movement template system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170215

RJ01 Rejection of invention patent application after publication