CN106368706A - 一种抛掷爆破拉斗铲倒堆开采程序 - Google Patents
一种抛掷爆破拉斗铲倒堆开采程序 Download PDFInfo
- Publication number
- CN106368706A CN106368706A CN201610812145.0A CN201610812145A CN106368706A CN 106368706 A CN106368706 A CN 106368706A CN 201610812145 A CN201610812145 A CN 201610812145A CN 106368706 A CN106368706 A CN 106368706A
- Authority
- CN
- China
- Prior art keywords
- coal seam
- area
- changed
- main access
- bank
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005065 mining Methods 0.000 title claims abstract description 21
- 238000005266 casting Methods 0.000 title claims abstract description 6
- 238000000034 method Methods 0.000 title abstract description 6
- 239000003245 coal Substances 0.000 claims abstract description 63
- 238000005422 blasting Methods 0.000 claims abstract description 56
- 238000000605 extraction Methods 0.000 claims description 11
- 238000004880 explosion Methods 0.000 claims description 3
- 239000000843 powder Substances 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 claims description 2
- 230000001680 brushing effect Effects 0.000 claims 1
- 238000004519 manufacturing process Methods 0.000 abstract description 14
- 239000011435 rock Substances 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C47/00—Machines for obtaining or the removal of materials in open-pit mines
- E21C47/02—Machines for obtaining or the removal of materials in open-pit mines for coal, brown coal, or the like
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Piles And Underground Anchors (AREA)
Abstract
一种抛掷爆破拉斗铲倒堆开采程序,属于露天矿开采技术领域。在开采过程中,将采场平均划分为三个区域,在中间区域与出入沟另一侧的区域之间布置中间沟,在出入沟一侧端帮布置端帮沟,根据煤层厚度将煤层划分为若干个台阶,并在下部煤台阶上布置斜坡道。在三个区域依次循环进行岩石穿孔抛掷爆破、拉斗铲倒堆、煤层穿孔爆破和采煤作业,采出的煤层经斜坡道、中间沟、斜出入沟,或者斜坡道、端帮沟、出入沟运至地表。本发明能够增大各生产环节的工作线长度,扩大生产设备的作业空间,提高生产设备的作业效率及作业安全性,并能缩短煤炭运输距离,降低生产成本,提高经济效益。
Description
技术领域
本发明属于露天矿开采技术领域,具体涉及一种抛掷爆破拉斗铲倒堆开采程序。
背景技术
抛掷爆破拉斗铲倒堆工艺条件下,为了采出底部煤层,需要完成岩石穿孔抛掷爆破、拉斗铲倒堆、煤层穿孔爆破和采煤四个生产环节。大型露天煤矿采用抛掷爆破拉斗铲倒堆工艺时,通常把采场划分为四个区域,每个区域进行一个生产环节,进行追踪式开采。这种开采程序导致各生产环节的工作线长度较短,生产设备作业空间狭小、生产效率低,煤炭运输距离大。
发明内容
针对已有技术存在的问题,本发明提供一种能够增大工作线长度,扩大生产设备作业空间,缩短煤炭运输距离,降低生产成本的抛掷爆破拉斗铲倒堆开采程序。
本发明采用的技术方案是:一种抛掷爆破拉斗铲倒堆开采程序,包括以下步骤:
a.沿工作线布置方向把采场平均划分为三个区域,首先将出入沟另一侧的区域设置为穿孔抛掷爆破区,进行穿孔、装药、连线、起爆,将部分剥离物抛掷到采空区;
b.穿孔抛掷爆破区实施抛掷爆破之后变为拉斗铲倒堆区,中间区域变为穿孔抛掷爆破区,在拉斗铲倒堆区,拉斗铲将剥离物倒堆至内排土场,揭露出煤层;
c.拉斗铲倒堆完区域内的全部剥离物之后,准备进入中间区域,此时,拉斗铲倒堆区变为煤层穿孔爆破区,穿孔抛掷爆破区变为拉斗铲倒堆区,出入沟一侧的区域变为穿孔抛掷爆破区,在煤层穿孔爆破区,对煤层进行穿孔、松动爆破;
d.煤层松动爆破之后,煤层穿孔爆破区变为采煤区,拉斗铲倒堆区变为煤层穿孔爆破区,穿孔抛掷爆破区变为拉斗铲倒堆区,采煤区前方区域变为穿孔抛掷爆破区,在采煤区,将煤层划分为若干个台阶,并在煤台阶上设置斜坡道,采出的煤层经斜坡道、中间沟和斜出入沟运至地表;
e.采煤区的煤层采完之后,采煤区变为采空区,中间区域变为采煤区,采出的煤层同样经斜坡道、中间沟和斜出入沟运至地表,其他区域追踪推进;
f.中间区域煤层采出之后,出入沟一侧的区域变为采煤区,采出的煤层经斜坡道、端帮沟和出入沟运至地表,其他区域追踪推进;
如此重复步骤d、e、f,三个区域交替向前推进,直至采区内的煤层全部采完。
其中,所述的中间沟布置在中间区域与出入沟另一侧的区域之间,端帮沟布置在出入沟一侧端帮,中间沟、斜出入沟、端帮沟的坡度均不大于10%。
所述的穿孔抛掷爆破区始终在采煤区前方,采煤区煤层采完之后穿孔抛掷爆破区才能实施抛掷爆破。
本发明所达到的技术效果是:克服传统抛掷爆破拉斗铲倒堆开采程序的不足,增大岩石穿孔抛掷爆破、拉斗铲倒堆、煤层穿孔爆破和采煤四个环节的工作线长度,从而扩大生产设备的作业空间,提高生产设备的作业效率及作业安全性,并缩短煤炭运输距离,降低生产成本,提高经济效益。
附图说明
图1为本发明的抛掷爆破拉斗铲倒堆开采程序示意图;
图2为本发明的抛掷爆破拉斗铲倒堆采剥工程平面图。
图中:1-出入沟,2-穿孔抛掷爆破区,3-采空区,4-拉斗铲倒堆区,5-作业平台,6-内排土场,7-煤层穿孔爆破区,8-采煤区,9-斜坡道,10-中间沟,11-斜出入沟,12-端帮沟。
具体实施方式
下面结合附图对本发明的实施方式作进一步描述。
本发明的抛掷爆破拉斗铲倒堆开采程序,具体步骤如下:
a.如图1(a)所示,沿工作线布置方向把采场平均划分为三个区域,首先将出入沟1另一侧的区域设置为穿孔抛掷爆破区2,进行穿孔、装药、连线、起爆,将部分剥离物抛掷到采空区3,并形成爆堆;
b.穿孔抛掷爆破区2实施抛掷爆破之后变为拉斗铲倒堆区4,中间区域变为穿孔抛掷爆破区2,如图1(b)所示。在拉斗铲倒堆区4,首先利用单斗挖掘机、推土机进行平整、刷帮、降段等作业,为拉斗铲准备作业平台5,然后,拉斗铲站立在作业平台5上将剥离物倒堆至内排土场6,揭露出煤层;
c.拉斗铲倒堆完区域内的全部剥离物之后,准备进入中间区域,此时,拉斗铲倒堆区4变为煤层穿孔爆破区7,穿孔抛掷爆破区2变为拉斗铲倒堆区4,出入沟1一侧的区域变为穿孔抛掷爆破区2,如图1(c)所示。在煤层穿孔爆破区7,对煤层进行穿孔、松动爆破;
d.煤层松动爆破之后,煤层穿孔爆破区7变为采煤区8,拉斗铲倒堆区4变为煤层穿孔爆破区7,穿孔抛掷爆破区2变为拉斗铲倒堆区4,采煤区8前方区域变为穿孔抛掷爆破区2,如图1(d)所示。在采煤区8,根据煤层厚度将煤层划分为若干个台阶,并在煤台阶上设置斜坡道9,采出的煤层经斜坡道9、中间沟10和斜出入沟11运至地表,如图2所示;
e.采煤区8的煤层采完之后,采煤区8变为采空区3,中间区域变为采煤区8,如图1(e)所示,采出的煤层同样经斜坡道9、中间沟10和斜出入沟11运至地表,其他区域追踪推进;
f.中间区域煤层采出之后,出入沟1一侧的区域变为采煤区8,如图1(f)所示,采出的煤层经斜坡道9、端帮沟12和出入沟1运至地表,其他区域追踪推进;
如此重复步骤d、e、f,三个区域交替向前推进,直至采区内的煤层全部采完。
Claims (4)
1.一种抛掷爆破拉斗铲倒堆开采程序,其特征是包括如下步骤:
a.沿工作线布置方向把采场平均划分为三个区域,首先将出入沟(1)另一侧的区域设置为穿孔抛掷爆破区(2),进行穿孔、装药、连线、起爆,将部分剥离物抛掷到采空区(3),并形成爆堆;
b.穿孔抛掷爆破区(2)实施抛掷爆破之后变为拉斗铲倒堆区(4),中间区域变为穿孔抛掷爆破区(2),在拉斗铲倒堆区(4),首先利用单斗挖掘机、推土机进行平整、刷帮、降段等作业,为拉斗铲准备作业平台(5),然后,拉斗铲站立在作业平台(5)上将剥离物倒堆至内排土场(6),揭露出煤层;
c.拉斗铲倒堆完区域内的全部剥离物之后,准备进入中间区域,此时,拉斗铲倒堆区(4)变为煤层穿孔爆破区(7),穿孔抛掷爆破区(2)变为拉斗铲倒堆区(4),出入沟(1)一侧的区域变为穿孔抛掷爆破区(2),在煤层穿孔爆破区(7),对煤层进行穿孔、松动爆破;
d.煤层松动爆破之后,煤层穿孔爆破区(7)变为采煤区(8),拉斗铲倒堆区(4)变为煤层穿孔爆破区(7),穿孔抛掷爆破区(2)变为拉斗铲倒堆区(4),采煤区(8)前方区域变为穿孔抛掷爆破区(2),在采煤区(8),根据煤层厚度将煤层划分为若干个台阶,并在煤台阶上设置斜坡道(9),采出的煤层经斜坡道(9)、中间沟(10)和斜出入沟(11)运至地表;
e.采煤区(8)的煤层采完之后,采煤区(8)变为采空区(3),中间区域变为采煤区(8),采出的煤层同样经斜坡道(9)、中间沟(10)和斜出入沟(11)运至地表,其他区域追踪推进;
f.中间区域煤层采出之后,出入沟(1)一侧的区域变为采煤区(8),采出的煤层经斜坡道(9)、端帮沟(12)和出入沟(1)运至地表,其他区域追踪推进;
如此重复步骤d、e、f,三个区域交替向前推进,直至采区内的煤层全部采完。
2.根据权利要求1所述的抛掷爆破拉斗铲倒堆开采程序,其特征是:沿工作线布置方向把采场平均划分为三个区域。
3.根据权利要求1所述的抛掷爆破拉斗铲倒堆开采程序,其特征是:中间沟(10)布置在中间区域与出入沟(1)另一侧的区域之间,端帮沟(12)布置在出入沟(1)一侧端帮,中间沟(10)、斜出入沟(11)、端帮沟(12)的坡度均不大于10%。
4.根据权利要求1所述的抛掷爆破拉斗铲倒堆开采程序,其特征是:穿孔抛掷爆破区(2)始终在采煤区(8)前方,采煤区(8)煤层采完之后穿孔抛掷爆破区(2)才能实施抛掷爆破。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610812145.0A CN106368706A (zh) | 2016-08-27 | 2016-08-27 | 一种抛掷爆破拉斗铲倒堆开采程序 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610812145.0A CN106368706A (zh) | 2016-08-27 | 2016-08-27 | 一种抛掷爆破拉斗铲倒堆开采程序 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106368706A true CN106368706A (zh) | 2017-02-01 |
Family
ID=57899405
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610812145.0A Pending CN106368706A (zh) | 2016-08-27 | 2016-08-27 | 一种抛掷爆破拉斗铲倒堆开采程序 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106368706A (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107144192A (zh) * | 2017-06-16 | 2017-09-08 | 西安科技大学 | 一种抛掷爆破智能施工方法 |
CN107542464A (zh) * | 2017-09-28 | 2018-01-05 | 西安科技大学 | 一种露天煤矿单斗卡车工艺条件下抛掷爆破方法 |
CN107687342A (zh) * | 2017-08-21 | 2018-02-13 | 中国矿业大学 | 一种露天煤矿拉斗铲工作线分段交替式采区转向方法 |
CN109630120A (zh) * | 2019-01-25 | 2019-04-16 | 中南大学 | 一种用于缓倾斜贫富共层矿体的采矿方法 |
CN109899072A (zh) * | 2019-03-22 | 2019-06-18 | 华北科技学院 | 一种露天煤矿拉斗铲工作面循环走行作业方法 |
CN109931065A (zh) * | 2019-04-03 | 2019-06-25 | 华北科技学院 | 一种露天煤矿抛掷爆破-松动爆破分区开采方法 |
CN109944592A (zh) * | 2019-03-28 | 2019-06-28 | 辽宁工程技术大学 | 拉斗铲倒堆工艺抛掷爆破台阶高度设计方法 |
CN110700837A (zh) * | 2019-11-29 | 2020-01-17 | 神华准格尔能源有限责任公司 | 拉斗铲作业方法 |
CN115977642A (zh) * | 2022-10-28 | 2023-04-18 | 国能经济技术研究院有限责任公司 | 拉斗铲双工作面往返走行倒堆作业方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103216238A (zh) * | 2012-12-28 | 2013-07-24 | 中国神华能源股份有限公司 | 一种露天煤矿开采工艺 |
CN103726849A (zh) * | 2012-10-10 | 2014-04-16 | 马力 | 一种露天煤矿坑底境界外薄煤层回采技术 |
CN104420876A (zh) * | 2013-09-02 | 2015-03-18 | 张崇欣 | 露天矿留帮陡帮开采方法 |
CN105781554A (zh) * | 2016-04-11 | 2016-07-20 | 中国矿业大学(北京) | 一种露天煤矿拉斗铲无运输倒堆工艺开采方法 |
-
2016
- 2016-08-27 CN CN201610812145.0A patent/CN106368706A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103726849A (zh) * | 2012-10-10 | 2014-04-16 | 马力 | 一种露天煤矿坑底境界外薄煤层回采技术 |
CN103216238A (zh) * | 2012-12-28 | 2013-07-24 | 中国神华能源股份有限公司 | 一种露天煤矿开采工艺 |
CN104420876A (zh) * | 2013-09-02 | 2015-03-18 | 张崇欣 | 露天矿留帮陡帮开采方法 |
CN105781554A (zh) * | 2016-04-11 | 2016-07-20 | 中国矿业大学(北京) | 一种露天煤矿拉斗铲无运输倒堆工艺开采方法 |
Non-Patent Citations (6)
Title |
---|
张平宽 等: "拉斗铲倒堆工艺在黑岱沟露天煤矿的应用", 《露天采矿技术》 * |
王桂林 等: "抛掷爆破—拉斗铲倒堆工艺的应用与创新", 《露天采矿技术》 * |
程鹏 等: "黑岱沟露天煤矿拉斗铲扩展平盘高度确定", 《煤炭工程》 * |
郭昭华: "露天煤矿抛掷爆破技术研究与应用", 《煤炭工程》 * |
韩万东 等: "黑岱沟露天煤矿吊斗铲工艺应用研究", 《煤炭技术》 * |
马军 等: "抛掷爆破与拉斗铲倒堆工艺研究", 《中国矿业》 * |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107144192A (zh) * | 2017-06-16 | 2017-09-08 | 西安科技大学 | 一种抛掷爆破智能施工方法 |
CN107144192B (zh) * | 2017-06-16 | 2018-08-14 | 西安科技大学 | 一种抛掷爆破智能施工方法 |
CN107687342A (zh) * | 2017-08-21 | 2018-02-13 | 中国矿业大学 | 一种露天煤矿拉斗铲工作线分段交替式采区转向方法 |
CN107687342B (zh) * | 2017-08-21 | 2019-05-21 | 中国矿业大学 | 一种露天煤矿拉斗铲工作线分段交替式采区转向方法 |
CN107542464A (zh) * | 2017-09-28 | 2018-01-05 | 西安科技大学 | 一种露天煤矿单斗卡车工艺条件下抛掷爆破方法 |
CN109630120A (zh) * | 2019-01-25 | 2019-04-16 | 中南大学 | 一种用于缓倾斜贫富共层矿体的采矿方法 |
CN109899072A (zh) * | 2019-03-22 | 2019-06-18 | 华北科技学院 | 一种露天煤矿拉斗铲工作面循环走行作业方法 |
CN109899072B (zh) * | 2019-03-22 | 2020-08-18 | 华北科技学院 | 一种露天煤矿拉斗铲工作面循环走行作业方法 |
CN109944592A (zh) * | 2019-03-28 | 2019-06-28 | 辽宁工程技术大学 | 拉斗铲倒堆工艺抛掷爆破台阶高度设计方法 |
CN109931065A (zh) * | 2019-04-03 | 2019-06-25 | 华北科技学院 | 一种露天煤矿抛掷爆破-松动爆破分区开采方法 |
CN109931065B (zh) * | 2019-04-03 | 2020-09-25 | 华北科技学院 | 一种露天煤矿抛掷爆破-松动爆破分区开采方法 |
CN110700837A (zh) * | 2019-11-29 | 2020-01-17 | 神华准格尔能源有限责任公司 | 拉斗铲作业方法 |
CN115977642A (zh) * | 2022-10-28 | 2023-04-18 | 国能经济技术研究院有限责任公司 | 拉斗铲双工作面往返走行倒堆作业方法 |
CN115977642B (zh) * | 2022-10-28 | 2023-08-29 | 国能经济技术研究院有限责任公司 | 拉斗铲双工作面往返走行倒堆作业方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106368706A (zh) | 一种抛掷爆破拉斗铲倒堆开采程序 | |
CN106121648B (zh) | 一种分段空场采矿底盘进路放矿嗣后充填采矿法 | |
CN102493806B (zh) | 一种壁式缓倾斜薄矿体机械化连续采矿方法 | |
CN103939102B (zh) | 一种固体充填回收露天矿终帮下压煤的采煤方法 | |
CN103470262A (zh) | 一种露天煤田近水平矿床倒堆内排的开采方法 | |
CN103216238A (zh) | 一种露天煤矿开采工艺 | |
CN108222941B (zh) | 一种露天矿连续开采方法 | |
CN103216237A (zh) | 一种露天煤矿开采工艺 | |
CN102889084A (zh) | 露天煤矿薄煤层的连续开采工艺方法 | |
CN106869936A (zh) | 一种适于陡坡地形的露天采矿新方法 | |
CN104265297B (zh) | 一种多层易碎缓倾斜极薄矿脉的开采方法 | |
CN107687342A (zh) | 一种露天煤矿拉斗铲工作线分段交替式采区转向方法 | |
CN105134221A (zh) | 一种硬岩无炮机械化掘进工艺 | |
CN101718199B (zh) | 煤矿大断面硐室施工方法 | |
CN104806247A (zh) | 露天矿采场中间搭建纵向组合桥运输方法 | |
CN102562071B (zh) | 一种露天矿山倾斜矿体的采矿工艺 | |
CN105370280B (zh) | 一种地下缓倾斜双层薄玉石矿无损爆破采矿方法 | |
CN106321104A (zh) | 一种切割槽无损失无贫化回采工艺 | |
CN102777184B (zh) | 矿山的开采系统和方法 | |
CN107542464B (zh) | 一种露天煤矿单斗卡车工艺条件下抛掷爆破方法 | |
RU2444625C1 (ru) | Способ разработки трубкообразных и мощных рудных тел | |
CN102748032B (zh) | 岩巷普掘机械化快速施工方法 | |
CN104879128A (zh) | 基于顶煤超前预爆弱化的急倾斜特厚煤层采煤工艺 | |
CN104121022A (zh) | 煤矿巷道开口掘进工艺 | |
CN106089204B (zh) | 一种正向深孔大爆破放顶实现残矿回收的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170201 |