CN106321103A - 一种固体充填协同人工矿柱回收房式煤柱方法 - Google Patents

一种固体充填协同人工矿柱回收房式煤柱方法 Download PDF

Info

Publication number
CN106321103A
CN106321103A CN201610812671.7A CN201610812671A CN106321103A CN 106321103 A CN106321103 A CN 106321103A CN 201610812671 A CN201610812671 A CN 201610812671A CN 106321103 A CN106321103 A CN 106321103A
Authority
CN
China
Prior art keywords
room
pillars
coal
artificial ore
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610812671.7A
Other languages
English (en)
Other versions
CN106321103B (zh
Inventor
张吉雄
张强
梅贤丞
方坤
韩晓乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Zhonan Science&technology Co ltd
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201610812671.7A priority Critical patent/CN106321103B/zh
Priority to PCT/CN2016/106614 priority patent/WO2018045632A1/zh
Priority to US16/300,586 priority patent/US10612378B2/en
Priority to CA3022748A priority patent/CA3022748C/en
Priority to RU2018146262A priority patent/RU2685357C1/ru
Priority to AU2016422571A priority patent/AU2016422571B2/en
Publication of CN106321103A publication Critical patent/CN106321103A/zh
Application granted granted Critical
Publication of CN106321103B publication Critical patent/CN106321103B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D23/00Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
    • E21D23/04Structural features of the supporting construction, e.g. linking members between adjacent frames or sets of props; Means for counteracting lateral sliding on inclined floor
    • E21D23/0481Supports specially adapted for use in combination with the placing of filling-up materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/005Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/02Supporting means, e.g. shuttering, for filling-up materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/06Filling-up mechanically
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

本发明公开了一种固体充填协同人工矿柱回收房式煤柱方法,采用投料井和管道将地面固体物料和胶结物料运送至房柱式采空区,在煤房区域按一定距离浇筑多个人工矿柱,并采用抛矸机对煤房其他区域抛矸充填;在多个人工矿柱和煤房充填体联合支护的条件下,采用连续采煤机进行煤柱的回收,再在回采后在原煤柱区域浇筑人工矿柱,并采用抛矸机对原煤柱区域进行抛矸充填;固体充填协同人工矿柱回收房式煤柱系统主要包括物料输送系统、联合支护系统和煤柱回收系统,通过柱槽的构建、人工矿柱的浇筑、采空区的抛矸充填和煤柱的回采,不仅能提高煤炭资源回采率,而且能在推进环境保护和资源开采协调发展的同时丰富我国房式煤柱回采理论与技术。

Description

一种固体充填协同人工矿柱回收房式煤柱方法
技术领域
本发明涉及一种房式煤柱回采的方法,尤其是一种适用于房式煤柱资源回收、预防房式遗留煤柱引发灾害的房式煤柱回采方法。
背景技术
我国西部矿区长期以来多采用房柱式开采,导致大量的煤柱无法回采;仅以陕西榆林地区为例,榆林地区共有煤矿247座,其中采用房柱式开采的煤矿占矿井总数的75%,共计201座。房柱式采煤方法煤炭采出率仅为30%~50%,仅鄂尔多斯地区房柱煤量近70亿吨,造成国家资源的极大浪费。另一方面,由于长期载荷作用,煤柱强度弱化问题越来越凸现,造成严重的安全隐患。
目前,国内外学者对房式煤柱回收方法的研究取得一定的成果,但多数方法存在回收率低、机械化程度不高的缺点;另外,采用传统的回填方法置换房式煤柱的方法,煤柱的回收成本高,充填回采工艺较为复杂。因此,研究一种既能安全回收房式煤柱,提高煤炭资源回收率,又能节约回收成本的房式煤柱回收方法,具有重要的现实意义和广阔的应用前景。
发明内容
技术问题:本发明的目的是针对现有技术的不足之处,提供一种操作简单的、高效的和高回采率的固体充填协同人工矿柱回收房式煤柱方法。
技术方案:本发明的固体充填协同人工矿柱回收房式煤柱方法,包括如下步骤:
a.在充填体协同人工矿柱联合支护覆岩的条件下,采用连续采煤机对房式煤柱进行回采,首先通过投料井和输送管道将地面的固体物料和胶结料运输至房柱式采空区;
b.在房式煤柱之间的房柱式采空区内间隔距离浇筑多个人工矿柱,在浇筑完成的多个人工矿柱之间进行充填,并进行夯实加固,构成煤房充填体;
c.在浇筑的多个人工矿柱和煤房充填体联合支护的条件下,采用连采机逐一对联合支护区域内的房式煤柱进行回收,直至完成所有房式煤柱的整体回收。
所述房式煤柱的回采工艺包括如下步骤:
a.首先在房式煤柱一侧的房柱式采空区内间隔距离构筑边长为4m的正方形柱槽,在构筑的正方形柱槽中安装挡板墙,要求各挡板墙必须封闭严实并且与顶板完全紧密接触;
b.向构筑的正方形柱槽中注浆构筑人工矿柱,当浇筑人工矿柱的浆体高度达到顶板下方50mm位置时,提高浆液浓度,对人工矿柱进行接顶充填;
c.人工矿柱浇筑完成后,采用抛矸机对房柱式采空区进行抛矸充填,同时使用推土机进行夯实加固;
d.重复步骤a至c完成房式煤柱另一侧房柱式采空区的充填;
e.在人工矿柱与煤房充填体的强度达到原岩应力后,利用连采机采用水平回收的方式进行房式煤柱的回收,回收的顺序呈“十”字穿梭状;
f.在回采后的房式煤柱区域内先浇筑人工矿柱,然后采用抛矸机对房式煤柱区域进行抛矸充填,在工作面同时实现“前方采煤,后方充填”。
所述浇筑的多个人工矿柱的间隔距离为15-17m,最佳距离为16m。
有益效果:由于采用了上述技术方案,本发明可以实现房式遗留煤柱资源的安全高效回收,经济和工程研究意义重大。尤其适用于房式煤柱资源回收、预防房式遗留煤柱引发灾害的房式煤柱回采,与现有技术相比,在确保房式遗留煤柱安全回收、高煤炭资源采出率的基础上显著地降低了房柱回收的资金投入,简化了充填回采工艺,为我国类似条件下房式开采遗留煤柱的回收开创一种新的解决途径,不仅能提高煤炭资源回采率,而且能在推进环境保护和资源开采协调发展的同时丰富我国房式煤柱回采理论与技术,科学与工程意义重大。其方法简单,操作方便,在本技术领域内具有广泛的实用性。
附图说明
图1是本发明的固体充填协同人工矿柱回收房式煤柱方法的技术原理图;
图2(a)是本发明的固体充填协同人工矿柱回收房式煤柱方法的人工矿柱布置俯视图;
图2(b)是本发明的固体充填协同人工矿柱回收房式煤柱方法的人工矿柱布置剖面图;
图3(a)是本发明的固体充填协同人工矿柱回收房式煤柱方法的加固充填状态俯视图;
图3(b)是本发明的固体充填协同人工矿柱回收房式煤柱方法的加固充填状态剖面图;
图4(a)是本发明的固体充填协同人工矿柱回收房式煤柱方法的回采充填状态俯视图;
图4(b)是本发明的固体充填协同人工矿柱回收房式煤柱方法的回采充填状态剖面图。
图中:1-投料井,2-输送管道,3-固体物料,4-胶结料,5-房式煤柱,6-人工矿柱,7-煤房充填体,8-抛矸机,9-房柱式采空区,10-连采机,11-柱槽,12-顶板。
具体实施方式
下面结合附图对本发明的实施例作进一步的描述:
本发明的固体充填协同人工矿柱回收房式煤柱方法,包括如下步骤:
a.在充填体协同人工矿柱联合支护覆岩的条件下,采用连续采煤机对房式煤柱5进行回采的方法,首先通过投料井1和输送管道2将地面的固体物料3和胶结料4运输至房柱式采空区9;
b.在房式煤柱5之间的房柱式采空区9内间隔距离浇筑多个人工矿柱6,同时在浇筑完成的多个人工矿柱6之间采用抛矸机8对房柱式采空区进行抛矸充填,并利用推土机进行夯实加固,构成煤房充填体7;所述浇筑的多个人工矿柱6的间隔距离为15-17m,最佳距离为16m;
c.在浇筑的多个人工矿柱6和煤房充填体7联合支护的条件下,采用连采机10逐一对联合支护区域内的各个房式煤柱5进行回收,再在回采后在原煤柱区域浇筑人工矿柱6,并采用抛矸机对原煤柱区域进行抛矸充填,直至完成所有房式煤柱的整体回收。固体充填协同人工矿柱回收房式煤柱系统主要包括物料输送系统、联合支护系统和煤柱回收系统;
单个房式煤柱的回采工艺包括如下步骤:
a.首先在房式煤柱5一侧的房柱式采空区9内间隔距离构筑边长为4m的正方形柱槽11,用于安装挡板墙并进行人工浇筑,在构筑的正方形柱槽11中安装挡板墙,要求各挡板墙必须封闭严实并且与顶板12完全紧密接触;
b.向构筑的正方形柱槽11中注浆构筑人工矿柱6,浇筑人工矿柱6时,为避免出现由于一次充填浆液离析而导致人工矿柱6上下强度不均的现象,浇筑按从下到上的顺序分多次进行,当浇筑人工矿柱6的浆体高度达到顶板12下方50mm位置时,提高浆液浓度,对人工矿柱6进行接顶充填;
c.人工矿柱6浇筑完成后,采用抛矸机8对房柱式采空区9进行抛矸充填,同时使用推土机进行夯实加固;
d.重复步骤a至c完成房式煤柱5另一侧房柱式采空区9的充填;
e.在人工矿柱6与煤房充填体7的强度达到原岩应力后,利用连采机10采用水平回收的方式进行房式煤柱5的回收,回收的顺序呈“十”字穿梭状;
f.在回采后的房式煤柱5区域内先浇筑人工矿柱6,然后采用抛矸机8对房式煤柱5区域进行抛矸充填,在工作面同时实现“前方采煤,后方充填”。

Claims (3)

1.一种固体充填协同人工矿柱回收房式煤柱方法,其特征在于包括如下步骤:
a. 在充填体协同人工矿柱联合支护覆岩的条件下,采用连续采煤机对房式煤柱(5)进行回采,首先通过投料井(1)和输送管道(2)将地面的固体物料(3)和胶结料(4)运输至房柱式采空区(9);
b. 在房式煤柱(5)之间的房柱式采空区(9)内间隔距离浇筑多个人工矿柱(6),在浇筑完成的多个人工矿柱(6)之间进行充填,并进行夯实加固,构成煤房充填体(7);
c. 在多个浇筑的人工矿柱(6)和煤房充填体(7)联合支护的条件下,采用连采机(10)逐一对联合支护区域内的房式煤柱(5)进行回收,直至完成所有房式煤柱的整体回收。
2.根据权利要求1所述的固体充填协同人工矿柱回收房式煤柱方法,其特征在于:单个房式煤柱的回采工艺包括如下步骤:
a. 首先在房式煤柱(5)一侧的房柱式采空区(9)内间隔距离构筑边长为4m的正方形柱槽(11),在构筑的正方形柱槽(11)中安装挡板墙,要求各挡板墙必须封闭严实并且与顶板(12)完全紧密接触;
b. 向构筑的正方形柱槽(11)中注浆构筑人工矿柱(6),当浇筑人工矿柱(6)的浆体高度达到顶板(12)下方50mm位置时,提高浆液浓度,对人工矿柱(6)进行接顶充填;
c. 人工矿柱(6)浇筑完成后,采用抛矸机(8)对房柱式采空区(9)进行抛矸充填,同时使用推土机进行夯实加固;
d. 重复步骤a至c完成房式煤柱(5)另一侧房柱式采空区(9)的充填;
e. 在人工矿柱(6)与煤房充填体(7)的强度达到原岩应力后,利用连采机(10)采用水平回收的方式进行房式煤柱(5)的回收,回收的顺序呈“十”字穿梭状;
f.在回采后的房式煤柱(5)区域内先浇筑人工矿柱(6),然后采用抛矸机(8)对房式煤柱(5)区域进行抛矸充填,在工作面同时实现“前方采煤,后方充填”。
3.根据权利要求2所述的固体充填协同人工矿柱回收房式煤柱方法,其特征在于:所述浇筑的多个人工矿柱(6)的间隔距离为15-17m,最佳距离为16m。
CN201610812671.7A 2016-09-08 2016-09-08 一种固体充填协同人工矿柱回收房式煤柱方法 Expired - Fee Related CN106321103B (zh)

Priority Applications (6)

Application Number Priority Date Filing Date Title
CN201610812671.7A CN106321103B (zh) 2016-09-08 2016-09-08 一种固体充填协同人工矿柱回收房式煤柱方法
PCT/CN2016/106614 WO2018045632A1 (zh) 2016-09-08 2016-11-21 一种固体充填协同人工矿柱回收房式煤柱方法
US16/300,586 US10612378B2 (en) 2016-09-08 2016-11-21 Method for recovering room-mining coal pillars by solid filling in synergy with artificial pillars
CA3022748A CA3022748C (en) 2016-09-08 2016-11-21 Method for recovering room-mining coal pillars by solid filling in synergy with artificial pillars
RU2018146262A RU2685357C1 (ru) 2016-09-08 2016-11-21 Способ извлечения угольных целиков при камерной разработке с помощью монолитного заполнения и использования искусственных целиков
AU2016422571A AU2016422571B2 (en) 2016-09-08 2016-11-21 Method for recovering room-mining coal pillars by solid filling in synergy with artificial pillars

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610812671.7A CN106321103B (zh) 2016-09-08 2016-09-08 一种固体充填协同人工矿柱回收房式煤柱方法

Publications (2)

Publication Number Publication Date
CN106321103A true CN106321103A (zh) 2017-01-11
CN106321103B CN106321103B (zh) 2018-04-13

Family

ID=57786953

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610812671.7A Expired - Fee Related CN106321103B (zh) 2016-09-08 2016-09-08 一种固体充填协同人工矿柱回收房式煤柱方法

Country Status (6)

Country Link
US (1) US10612378B2 (zh)
CN (1) CN106321103B (zh)
AU (1) AU2016422571B2 (zh)
CA (1) CA3022748C (zh)
RU (1) RU2685357C1 (zh)
WO (1) WO2018045632A1 (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869994A (zh) * 2017-03-17 2017-06-20 中国矿业大学 一种回收房式煤柱的人工矿柱尺寸和间距的确定方法
CN108397196A (zh) * 2018-01-16 2018-08-14 中蓝长化工程科技有限公司 一种基于格宾人工矿柱的缓倾斜矿体露天转地下采矿方法
CN108915764A (zh) * 2018-07-09 2018-11-30 中国矿业大学 一种预留巷道胶结充填回收房式煤柱的方法
CN109113744A (zh) * 2018-09-04 2019-01-01 中国矿业大学 一种外部支护替代式房式煤柱回收方法
CN111206956A (zh) * 2020-01-10 2020-05-29 中国矿业大学 一种房式采煤法采空区遗留煤柱充填加固方法
CN113216967A (zh) * 2021-05-28 2021-08-06 西安科技大学 浅埋近距房柱式采空区下相邻工作面相向安全开采方法
US11143025B2 (en) * 2018-09-30 2021-10-12 China University Of Mining And Technology Mine exploitation based on stoping, separation and filling control
CN117662234A (zh) * 2023-12-22 2024-03-08 中煤科工开采研究院有限公司 一种房柱式采空区充填率的确定方法

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356582B (zh) * 2018-11-15 2019-09-03 山东科技大学 一种用于综采放顶煤工作面的充填开采方法
CN112433205A (zh) * 2020-11-12 2021-03-02 北京科技大学 开采充填空顶高度探测装置、及其安装方法和探测方法
CN112576302B (zh) * 2020-11-24 2022-08-30 河南理工大学 一种防跑浆提高充填效果的隔断膏体充填方法
CN113847056B (zh) * 2021-09-14 2023-08-18 太原理工大学 一种极近距离上下煤层巷道布置及支护方法
CN114233293B (zh) * 2021-11-11 2023-09-29 中煤科工生态环境科技有限公司 煤矿无区段煤柱开采及固废充填方法
CN114215592A (zh) * 2021-11-30 2022-03-22 中国矿业大学 一种长壁工作面矸石与超高水材料充填绿色开采方法
CN115355002B (zh) * 2022-08-18 2024-06-04 中国煤炭科工集团太原研究院有限公司 一种连续采煤机宽煤柱窄条带中部点柱式采充方法
CN116658163B (zh) * 2023-07-03 2023-10-20 中国矿业大学(北京) 无煤柱自成巷采空区坚硬顶板垮落矸石块度调控方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725352A (zh) * 2009-12-04 2010-06-09 中国矿业大学 一种固体充填综采回收房式煤柱方法
CN103527196A (zh) * 2013-10-28 2014-01-22 中国矿业大学 一种黄土充填回收房式煤柱的方法
CN103758568A (zh) * 2014-02-14 2014-04-30 中国矿业大学 露天煤矿端帮充填开采方法
CN103821558A (zh) * 2014-02-14 2014-05-28 安徽理工大学 煤矿采空区充填采矿系统及沿空留巷充填工艺

Family Cites Families (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2634960A (en) * 1948-02-06 1953-04-14 Walter B Lang Method of mining and apparatus therefor
US3999804A (en) * 1976-03-08 1976-12-28 Atlantic Richfield Company Longwall mining with chain pillar recovery
US4378132A (en) * 1981-02-17 1983-03-29 Klaus Spies Mining method and apparatus
US4440449A (en) * 1982-02-05 1984-04-03 Chevron Research Company Molding pillars in underground mining of oil shale
US4522537A (en) * 1982-05-07 1985-06-11 Iceberg Cribs, Inc. Ice crib
EP0184720A1 (en) * 1984-11-28 1986-06-18 Potash Corporation Of Saskatchewan Mining Limited Underground mining method for mineral deposits
RU2013549C1 (ru) * 1991-10-03 1994-05-30 Виктор Иванович Фукс Способ возведения искусственного межгоризонтального целика при разработке крутых и наклонных пластов
US5567018A (en) * 1995-04-17 1996-10-22 Cyprus Amax Minerals Company Continuous mining linear advance system
RU2083833C1 (ru) * 1995-06-01 1997-07-10 Акционерное общество открытого типа "Угольная компания "Прокопьевскуголь" Способ разработки крутых угольных пластов с закладкой выработанного пространства
AU781313B2 (en) * 2000-05-19 2005-05-12 Eskom Mining method
CN101487392A (zh) 2008-01-16 2009-07-22 中国神华能源股份有限公司 房柱式采煤方法
RU2390633C1 (ru) 2009-02-05 2010-05-27 Учреждение Российской академии наук Институт горного дела Сибирского отделения РАН Способ разработки крутых пластов угля
RU2398966C1 (ru) * 2009-05-12 2010-09-10 Виктор Николаевич Кулаков Способ разработки мощных крутонаклонных и крутых угольных пластов
CN103291303B (zh) * 2013-06-27 2016-02-17 山东科技大学 一种留设条带煤柱的开采方法
CN105971606B (zh) 2016-05-05 2018-08-17 湖南科技大学 一种巨厚煤层长壁工作面开采方法
CN106014412B (zh) * 2016-06-24 2018-05-04 太原理工大学 一种梯式构造充填复采残采区遗留煤柱群的方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725352A (zh) * 2009-12-04 2010-06-09 中国矿业大学 一种固体充填综采回收房式煤柱方法
CN103527196A (zh) * 2013-10-28 2014-01-22 中国矿业大学 一种黄土充填回收房式煤柱的方法
CN103758568A (zh) * 2014-02-14 2014-04-30 中国矿业大学 露天煤矿端帮充填开采方法
CN103821558A (zh) * 2014-02-14 2014-05-28 安徽理工大学 煤矿采空区充填采矿系统及沿空留巷充填工艺

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018166243A1 (zh) * 2017-03-17 2018-09-20 中国矿业大学 一种回收房式煤柱的人工矿柱尺寸和间距的确定方法
CN106869994A (zh) * 2017-03-17 2017-06-20 中国矿业大学 一种回收房式煤柱的人工矿柱尺寸和间距的确定方法
CN108397196B (zh) * 2018-01-16 2019-10-18 中蓝长化工程科技有限公司 一种基于格宾人工矿柱的缓倾斜矿体露天转地下采矿方法
CN108397196A (zh) * 2018-01-16 2018-08-14 中蓝长化工程科技有限公司 一种基于格宾人工矿柱的缓倾斜矿体露天转地下采矿方法
CN108915764A (zh) * 2018-07-09 2018-11-30 中国矿业大学 一种预留巷道胶结充填回收房式煤柱的方法
CN108915764B (zh) * 2018-07-09 2019-04-30 中国矿业大学 一种预留巷道胶结充填回收房式煤柱的方法
WO2020010696A1 (zh) * 2018-07-09 2020-01-16 中国矿业大学 一种预留巷道胶结充填回收房式煤柱的方法
CN109113744A (zh) * 2018-09-04 2019-01-01 中国矿业大学 一种外部支护替代式房式煤柱回收方法
CN109113744B (zh) * 2018-09-04 2019-11-05 中国矿业大学 一种外部支护替代式房式煤柱回收方法
US11143025B2 (en) * 2018-09-30 2021-10-12 China University Of Mining And Technology Mine exploitation based on stoping, separation and filling control
CN111206956A (zh) * 2020-01-10 2020-05-29 中国矿业大学 一种房式采煤法采空区遗留煤柱充填加固方法
CN113216967A (zh) * 2021-05-28 2021-08-06 西安科技大学 浅埋近距房柱式采空区下相邻工作面相向安全开采方法
CN113216967B (zh) * 2021-05-28 2024-01-26 西安科技大学 浅埋近距房柱式采空区下相邻工作面相向安全开采方法
CN117662234A (zh) * 2023-12-22 2024-03-08 中煤科工开采研究院有限公司 一种房柱式采空区充填率的确定方法
CN117662234B (zh) * 2023-12-22 2024-05-31 中煤科工开采研究院有限公司 一种房柱式采空区充填率的确定方法

Also Published As

Publication number Publication date
US10612378B2 (en) 2020-04-07
RU2685357C1 (ru) 2019-04-17
CN106321103B (zh) 2018-04-13
WO2018045632A1 (zh) 2018-03-15
AU2016422571A1 (en) 2018-11-15
CA3022748C (en) 2019-09-03
AU2016422571B2 (en) 2020-10-01
CA3022748A1 (en) 2018-03-15
US20190301283A1 (en) 2019-10-03

Similar Documents

Publication Publication Date Title
CN106321103A (zh) 一种固体充填协同人工矿柱回收房式煤柱方法
WO2021068691A1 (zh) 一种煤矿强弱强全采全充方法
CN103527195B (zh) 一种厚夹矸煤层分采分运矸石回填采空区方法
CN103089266B (zh) 露天转地下过渡期无底柱分段空场崩落采矿方法
CN103016053B (zh) 一种采空区局部充填控制地表沉陷的方法
CN102493838B (zh) 一种急倾斜煤层综采连续充填采煤方法
CN102261262B (zh) 矿山采场的高性能泡沫砂浆充填方法
WO2020062432A1 (zh) 近距离煤层群井下采选充协同开采方法
CN105298496B (zh) 设置预留工作面煤柱的全采全充采煤方法
CA2986062C (en) Fully mechanized mining-filling mixed mining working face filling section length determination method
WO2018176892A1 (zh) 一种薄煤层综合开采与瓦斯治理网络一体协同控制系统及方法
CN102155260A (zh) 一种急倾斜煤层采空区充填方法
CN101915100B (zh) 煤矿井下黄土充填采煤方法
CN105507947B (zh) 一种网络化矸石充填方法
CN101598031A (zh) 废石就地回填并能提高矿石回收率的采矿方法
CN201982137U (zh) 以矸石为骨料混凝土充填材料的井下制备装置
CN106968671A (zh) 煤矿井下采煤工作面回撤通道充填回撤方法
CN103557001B (zh) 一种低段高无底柱留矿嗣后充填采矿法
CN201474347U (zh) 一种分段矿房
CN103161498B (zh) 急倾斜煤层区段煤柱巷旁充填方法
CN106121649A (zh) 采用阶段矿房法回采矿房的存窿矿石的回采方法
CN105971605B (zh) 一种井下矿山无废开采方法
CN106088107B (zh) 一种尾矿堆存于崩落法生产矿山地表塌陷坑的方法
AU2018208634B2 (en) Clean and efficient coal mining method
CN102943689A (zh) 一种煤矿散料充填开采的方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhang Jixiong

Inventor after: Zhang Qiang

Inventor after: Chen Yadong

Inventor after: Mei Xiancheng

Inventor after: Fang Kun

Inventor after: Han Xiaole

Inventor before: Zhang Jixiong

Inventor before: Zhang Qiang

Inventor before: Mei Xiancheng

Inventor before: Fang Kun

Inventor before: Han Xiaole

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20170315

Address after: 221116 Research Institute of China University of Mining and Technology,, Jiangsu

Applicant after: CHINA University OF MINING AND TECHNOLOGY

Applicant after: XUZHOU ZHONAN SCIENCE&TECHNOLOGY Co.,Ltd.

Address before: 221116 Research Institute of China University of Mining and Technology,, Jiangsu

Applicant before: CHINA University OF MINING AND TECHNOLOGY

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180413

CF01 Termination of patent right due to non-payment of annual fee