CN108915764A - 一种预留巷道胶结充填回收房式煤柱的方法 - Google Patents
一种预留巷道胶结充填回收房式煤柱的方法 Download PDFInfo
- Publication number
- CN108915764A CN108915764A CN201810744190.6A CN201810744190A CN108915764A CN 108915764 A CN108915764 A CN 108915764A CN 201810744190 A CN201810744190 A CN 201810744190A CN 108915764 A CN108915764 A CN 108915764A
- Authority
- CN
- China
- Prior art keywords
- coal column
- working face
- tunnel
- coal
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000003245 coal Substances 0.000 title claims abstract description 105
- 238000000034 method Methods 0.000 title claims abstract description 23
- 238000004064 recycling Methods 0.000 title claims abstract description 21
- 238000011084 recovery Methods 0.000 claims abstract description 12
- 239000000463 material Substances 0.000 claims description 16
- 238000004519 manufacturing process Methods 0.000 claims description 11
- 238000000605 extraction Methods 0.000 claims description 5
- 238000005422 blasting Methods 0.000 claims description 4
- 238000012856 packing Methods 0.000 claims description 4
- 230000000149 penetrating effect Effects 0.000 claims description 3
- 239000011435 rock Substances 0.000 claims description 3
- 238000005065 mining Methods 0.000 abstract description 8
- 238000005516 engineering process Methods 0.000 abstract description 4
- 230000015572 biosynthetic process Effects 0.000 abstract description 2
- 239000004576 sand Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000002485 combustion reaction Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- COCAUCFPFHUGAA-MGNBDDOMSA-N n-[3-[(1s,7s)-5-amino-4-thia-6-azabicyclo[5.1.0]oct-5-en-7-yl]-4-fluorophenyl]-5-chloropyridine-2-carboxamide Chemical compound C=1C=C(F)C([C@@]23N=C(SCC[C@@H]2C3)N)=CC=1NC(=O)C1=CC=C(Cl)C=N1 COCAUCFPFHUGAA-MGNBDDOMSA-N 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 230000002269 spontaneous effect Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/005—Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/08—Filling-up hydraulically or pneumatically
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Remote Sensing (AREA)
- Lining And Supports For Tunnels (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明公开了一种预留巷道胶结充填回收房式煤柱的方法,尤其适用于西部生态脆弱矿区房式开采工作面内遗留煤柱安全、高效回收,通过在相邻两列煤房采空区构建预留巷道,在房式煤柱内开掘煤柱巷道,最终贯通预留巷道与煤柱巷道形成U形工作面,实现了房式遗留煤柱的回收,不仅减少了巷道掘进量,而且最大限度地提高了煤炭资源采出率,为我国西部矿区房式遗留煤柱的回收提供了一种全新的技术模式,科学与工程意义重大,应用前景广阔。
Description
技术领域
本发明涉及一种预留巷道胶结充填回收房式煤柱的方法,属于煤矿回收技术领域。
背景技术
随着我国煤炭资源的逐渐枯竭,西部矿区已成为我国煤炭资源开采的主体。由于受自身开采技术与开采设备落后等因素,该区域多数煤矿采用短壁房式或房柱式开采方法,造成大量优质煤炭资源遗留采空区,煤炭资源采出率不足40%,这不仅造成了煤炭资源的极大浪费,而且采空区煤柱失稳极易造成矿震、地表沉陷、突水溃沙等严重生态环境灾害。
胶结充填回收遗留煤柱是近年来发展起来的应用较为广泛的绿色环保的煤柱回收方法,已在条带煤柱回收过程中得到广泛应用。但由于房式采空区相互之间贯通,不存在合适的密闭充填环境,使得胶结充填技术在房式煤柱回收过程中应用比较困难。如果构建密闭挡墙形成密闭充填空间,后期煤柱回收过程中还需要重新开掘巷道,不仅成本较高,而且工艺复杂。因此,房式煤柱回收过程中,如何构建合适的密闭充填环境,并减少巷道的掘进量,已成为西部矿区亟需解决的一大难题。
发明内容
为解决现有技术的不足,本发明的目的在于提供一种预留巷道胶结充填回收房式煤柱的方法,不仅能够构建合适的密闭充填环境,而且减少了后期充填过程中的巷道掘进量,具有安全、高效、经济的技术特点。
为了实现上述目标,本发明采用如下的技术方案:
一种预留巷道胶结充填回收房式煤柱的方法,其特征是,包括如下步骤:
步骤a)以垂直于大巷的相邻两列煤柱为一工作面,分别在两列煤柱之间的煤房采空区内构筑预留巷道,并在沿远离大巷的边界煤柱位置处贯通两巷道,由煤柱与预留巷道组合形成U形工作面;
步骤b)胶结充填输送管路布置在胶结充填物料运输大巷中,胶结充填物料经胶结充填输送管路输送至U形工作面右侧采空区和中部采空区,实现当前U形工作面煤房采空区的充填;
步骤c)待胶结充填物料凝固并达到一定强度后,采用连续采煤机沿U形工作面预留巷道依次对各个煤柱开掘煤柱巷道,将预留巷道与煤柱巷道贯通为一回路;
步骤d)待上述工作全部完毕后,采用炮采工艺依次对形成回路的U形工作面内的煤柱巷道进行扩巷回采,并利用装载机和无轨胶轮车将回收的煤炭资源运送至地面;
步骤e)待U形工作面遗留煤柱回采完毕后,分别在U形工作面上下两端口与胶结充填物料运输大巷交界处砌筑密闭挡墙。
前述的一种预留巷道胶结充填回收房式煤柱的方法,其特征是,对U形工作面进行如步骤a)-e)的处理时,在进行到每一个步骤b)的充填作业的同时,以步骤a)中相同方式,在当前U形工作面旁进行下一个U形工作面的构筑工作,并对新的U形工作面进行步骤a)-e)的循环处理;直至完成整个房式遗留煤柱的回收工作。
前述的一种预留巷道胶结充填回收房式煤柱的方法,其特征是,所述步骤c)中用连续采煤机沿U形工作面预留巷道依次对各个煤柱开掘宽度为6m的煤柱巷道。
前述的一种预留巷道胶结充填回收房式煤柱的方法,其特征是,所述预留巷道的宽度根据矿井实际采掘设备、遗留煤柱尺寸以及围岩应力确定。
本发明所达到的有益效果:本发明尤其适用于西部生态脆弱矿区房式开采工作面内遗留煤柱安全、高效回收,通过在相邻两列煤房采空区构建预留巷道,在房式煤柱内开掘煤柱巷道,最终贯通预留巷道与煤柱巷道形成U形工作面,实现了房式遗留煤柱的回收,不仅减少了巷道掘进量,而且最大限度地提高了煤炭资源采出率,为我国西部矿区房式遗留煤柱的回收提供了一种全新的技术模式,科学与工程意义重大,应用前景广阔。
附图说明
图1是本发明煤柱与预留巷道组合形成01U形工作面的平面图;
图2是本发明01U形工作面右侧及中部采空区充填的平面图;
图3是本发明01U形工作面房式煤柱开掘煤柱巷道的平面图;
图4是本发明01U形工作面预留巷道与煤柱巷道贯通形成回路的平面图;
图5是本发明01U形工作面煤柱巷道扩巷工作的平面图;
图6是本发明01U形工作面完成所有煤柱巷道扩巷回采的平面图。
图中:
1-预留巷道,2-胶结充填物料运输大巷,3-胶结充填输送管路,4-01U形工作面右侧采空区,5-01U形工作面中部采空区,6-胶结充填物料,7-连续采煤机,8-煤柱巷道,9-02U形工作面右侧采空区,10-02U形工作面中部采空区,11-装载机,12-无轨胶轮车,13-密闭挡墙。
具体实施方式
下面结合附图对本发明作进一步描述。以下实施例仅用于更加清楚地说明本发明的技术方案,而不能以此来限制本发明的保护范围。
为实现上述目的,本发明主要包括如下步骤:
a. 以垂直于大巷的相邻两列煤柱为一工作面,分别在两列煤柱之间的煤房采空区内构筑预留巷道,并在沿远离大巷的边界煤柱位置处贯通两巷道,此时,由煤柱与预留巷道组合形成01U形工作面。预留巷道为U形断面,采用可回收的机械挡板,内部配以防漏风装置,密闭性好,抗变形能力强。预留巷道的宽度根据矿井实际采掘设备、遗留煤柱尺寸以及围岩应力确定。
b. 胶结充填输送管路布置在胶结充填物料运输大巷中,胶结充填物料经胶结充填输送管路输送至01U形工作面右侧采空区和中部采空区,实现01U形工作面煤房采空区的充填。在充填作业的同时,以步骤a中相同方式,进行02U形工作面的构筑工作;
c. 待胶结充填物料凝固并达到一定强度后,采用连续采煤机沿01U形工作面预留巷道依次对1#、2#、3#…N#煤柱开掘宽度为6m的煤柱巷道,最终预留巷道与煤柱巷道贯通为一回路。
在开掘煤柱巷道的同时,以步骤b中相同方式,进行02U形工作面右侧采空区和中部采空区的充填工作;
d. 待上述工作全部完毕后,采用炮采工艺依次对01U形工作面内1#、2#、3#…N#煤柱的煤柱巷道进行扩巷回采,并利用装载机、无轨胶轮车等设备将回收的煤炭资源运送至地面。在01U形工作面煤柱巷道扩巷回采的同时,进行03U形工作面的构筑工作;
e. 待01U形工作面遗留煤柱回采完毕后,分别在01U形工作面上下两端口与胶结充填物料运输大巷交界处砌筑密闭挡墙;
f. 重复上述步骤,完成整个房式遗留煤柱的回收工作。
本实施例的具体数据:陕北某矿井采用短壁房式开采,主采3#煤层,煤厚2.5m,平均倾角1゜,工作面走向长度150m,推进距离80m,煤柱大小11m×11m,煤房宽度7m,大量房式煤柱遗留井下,煤炭资源回采率不足35%,且近年来发现部分煤柱失稳破坏,并伴随自燃发火倾向,进而引发顶板大面积垮落等一系列灾害。
为解决上述难题,结合本专利发明内容,针对首采工作面遗留煤柱的回采,具体实施方式如下:
针对六盘区首采工作面房式采空区,分别在垂直于大巷方向的相邻两列煤柱之间的煤房采空区构筑宽度为6m预留巷道1,并在沿远离大巷的边界煤柱处贯通两列巷道,此时,由煤柱与预留巷道1组合形成3601U形工作面,如图1所示;
在胶结充填物料运输大巷2中布置胶结充填输送管路3,将地面配制好的以风积沙为主的胶结充填物料6依次输送至3601U形工作面右侧采空区4及中部采空区5,采用后退式充填方式,并合理调控泵送压力和管口高度使充填物料逐步密实接顶,实现全部充填。在开始进行充填作业时,进行3602U形工作面的构筑工作,如图2所示;
待胶结充填物料6凝固并达到一定强度后,在预留巷道1内装备连续采煤机7,并沿预留巷道1依次对3601U形工作面外围的1#、2#、3#…N#煤柱开掘与预留巷道1断面尺寸相同的煤柱巷道8,以使预留巷道1与煤柱巷道8贯通为一回路。当对1#煤柱开掘煤柱巷道8时,开始进行3602U形工作面右侧采空区9及中部采空区10的充填工作,如图3、图4所示;
待上述工作全部完毕后,采用打眼放炮的方式对3601U形工作面内1#、2#、3#…N#煤柱的煤柱巷道8进行扩巷回采,扩巷回采过程中,首先对煤柱巷道8一侧的残煤进行回采,待回采完毕见充填体后,转向对另一侧残煤进行回采,利用装载机11将落下的煤装入无轨胶轮车12运输至地面。当对1#煤柱巷道进行扩巷回采时,开始进行3603U形工作面的构筑工作,如图5所示;
当3601U形工作面遗留煤柱回采完毕后,分别在U形工作面上下两端口与胶结充填物料运输大巷交界处砌筑密闭挡墙13,至此,3601U形工作面采空区充填及煤柱回收工作完成,如图6所示。
重复上述步骤,完成整个房式采空区遗留煤柱的回收工作。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明技术原理的前提下,还可以做出若干改进和变形,这些改进和变形也应视为本发明的保护范围。
Claims (4)
1.一种预留巷道胶结充填回收房式煤柱的方法,其特征是,包括如下步骤:
步骤a)以垂直于大巷的相邻两列煤柱为一工作面,分别在两列煤柱之间的煤房采空区内构筑预留巷道,并在沿远离大巷的边界煤柱位置处贯通两巷道,由煤柱与预留巷道组合形成U形工作面;
步骤b)胶结充填输送管路布置在胶结充填物料运输大巷中,胶结充填物料经胶结充填输送管路输送至U形工作面右侧采空区和中部采空区,实现当前U形工作面煤房采空区的充填;
步骤c)待胶结充填物料凝固并达到一定强度后,采用连续采煤机沿U形工作面预留巷道依次对各个煤柱开掘煤柱巷道,将预留巷道与煤柱巷道贯通为一回路;
步骤d)待上述工作全部完毕后,采用炮采工艺依次对形成回路的U形工作面内的煤柱巷道进行扩巷回采,并利用装载机和无轨胶轮车将回收的煤炭资源运送至地面;
步骤e)待U形工作面遗留煤柱回采完毕后,分别在U形工作面上下两端口与胶结充填物料运输大巷交界处砌筑密闭挡墙。
2.根据权利要求1所述的一种预留巷道胶结充填回收房式煤柱的方法,其特征是,对U形工作面进行如步骤a)-e)的处理时,在进行到每一个步骤b)的充填作业的同时,以步骤a)中相同方式,在当前U形工作面旁进行下一个U形工作面的构筑工作,并对新的U形工作面进行步骤a)-e)的循环处理;直至完成整个房式遗留煤柱的回收工作。
3.根据权利要求1或2所述的一种预留巷道胶结充填回收房式煤柱的方法,其特征是,所述步骤c)中用连续采煤机沿U形工作面预留巷道依次对各个煤柱开掘宽度为6m的煤柱巷道。
4.根据权利要求1或2所述的一种预留巷道胶结充填回收房式煤柱的方法,其特征是,所述预留巷道的宽度根据矿井实际采掘设备、遗留煤柱尺寸以及围岩应力确定。
Priority Applications (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810744190.6A CN108915764B (zh) | 2018-07-09 | 2018-07-09 | 一种预留巷道胶结充填回收房式煤柱的方法 |
CA3054041A CA3054041A1 (en) | 2018-07-09 | 2018-09-20 | Method for recovering room-type coal pillars by cemented filling of reserved roadways |
PCT/CN2018/106591 WO2020010696A1 (zh) | 2018-07-09 | 2018-09-20 | 一种预留巷道胶结充填回收房式煤柱的方法 |
US16/613,926 US11339658B2 (en) | 2018-07-09 | 2018-09-20 | Method for recovering room-type coal pillars by cemented filling of reserved roadways |
AU2018431390A AU2018431390B2 (en) | 2018-07-09 | 2018-09-20 | Method for recovering room-type coal pillars by cemented filling of reserved roadways |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810744190.6A CN108915764B (zh) | 2018-07-09 | 2018-07-09 | 一种预留巷道胶结充填回收房式煤柱的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108915764A true CN108915764A (zh) | 2018-11-30 |
CN108915764B CN108915764B (zh) | 2019-04-30 |
Family
ID=64425597
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810744190.6A Active CN108915764B (zh) | 2018-07-09 | 2018-07-09 | 一种预留巷道胶结充填回收房式煤柱的方法 |
Country Status (5)
Country | Link |
---|---|
US (1) | US11339658B2 (zh) |
CN (1) | CN108915764B (zh) |
AU (1) | AU2018431390B2 (zh) |
CA (1) | CA3054041A1 (zh) |
WO (1) | WO2020010696A1 (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110410076A (zh) * | 2019-08-16 | 2019-11-05 | 山东科技大学 | 一种用于老房柱采空区遗留煤柱回收的充填开采方法 |
CN112412461A (zh) * | 2020-12-03 | 2021-02-26 | 中国煤炭科工集团太原研究院有限公司 | 一种露天矿端帮煤充填开采工艺方法 |
CN112593940A (zh) * | 2020-12-16 | 2021-04-02 | 中煤能源研究院有限责任公司 | 一种回采房式采煤法遗留煤柱和处理地面矸石的布置工艺 |
CN114687794A (zh) * | 2022-03-31 | 2022-07-01 | 中国矿业大学(北京) | 一种煤矿充填复采方法 |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114575845B (zh) * | 2022-03-01 | 2024-07-02 | 中煤能源研究院有限责任公司 | 一种房柱式悬顶采空区防爆隔离煤柱宽度校核方法 |
CN114961848B (zh) * | 2022-07-15 | 2023-05-26 | 福州大学 | 一种尾砂胶结充填过程中分部构筑巷道方法 |
CN114961731B (zh) * | 2022-07-28 | 2022-12-06 | 北京科技大学 | 一种倾斜薄矿体空场嗣后机制砂充填回收矿柱的方法 |
CN115355002B (zh) * | 2022-08-18 | 2024-06-04 | 中国煤炭科工集团太原研究院有限公司 | 一种连续采煤机宽煤柱窄条带中部点柱式采充方法 |
CN115370367B (zh) * | 2022-10-24 | 2023-02-17 | 华北科技学院 | 一种煤层群开采矿井采空区内煤柱留设方法和系统 |
CN117432410B (zh) * | 2023-10-23 | 2024-06-25 | 中国矿业大学 | 一种条带采空区遗留煤柱充填复采方法 |
CN117365474A (zh) * | 2023-11-20 | 2024-01-09 | 西安科技大学 | 一种大断面掘进充填留巷一体化方法及系统 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2123109C1 (ru) * | 1996-04-29 | 1998-12-10 | Акционерное общество "Угольная компания "Прокопьевскуголь" | Способ разработки свиты угольных пластов в приконтурных зонах карьера |
CN101725352A (zh) * | 2009-12-04 | 2010-06-09 | 中国矿业大学 | 一种固体充填综采回收房式煤柱方法 |
CN102061938A (zh) * | 2010-12-10 | 2011-05-18 | 天地科技股份有限公司 | 一种采用膏体充填采空区回收煤柱的充填工艺 |
CN103527196A (zh) * | 2013-10-28 | 2014-01-22 | 中国矿业大学 | 一种黄土充填回收房式煤柱的方法 |
CN103742146A (zh) * | 2014-01-17 | 2014-04-23 | 淄博王煤矿业有限公司 | 墩柱式充填法采煤工艺 |
CN105240014A (zh) * | 2015-11-12 | 2016-01-13 | 中国矿业大学 | 一种充填再造护巷煤柱条带回收房式遗留煤柱的方法 |
CN106321103A (zh) * | 2016-09-08 | 2017-01-11 | 中国矿业大学 | 一种固体充填协同人工矿柱回收房式煤柱方法 |
CN108087021A (zh) * | 2017-11-01 | 2018-05-29 | 中国矿业大学 | 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4219237A (en) * | 1977-09-30 | 1980-08-26 | The United States Of America As Represented By The United States Department Of Energy | Method for maximizing shale oil recovery from an underground formation |
US4174135A (en) * | 1978-04-10 | 1979-11-13 | Bechtel International Corporation | Underground formed wall single-entry mining method |
HU179378B (en) * | 1980-04-15 | 1982-10-28 | Tatabanyai Szenbanyak | Method for falling high coal bed |
CN101858217B (zh) | 2010-05-18 | 2012-03-21 | 中南大学 | 房柱变换式盘区上向分层充填采矿法 |
CN103104287A (zh) | 2013-01-28 | 2013-05-15 | 山东科技大学 | 一种条带采空区充填复采方法 |
CN103527197B (zh) | 2013-10-28 | 2016-01-06 | 中国矿业大学 | 一种特厚煤层固体胶结充填巷式开采方法 |
-
2018
- 2018-07-09 CN CN201810744190.6A patent/CN108915764B/zh active Active
- 2018-09-20 CA CA3054041A patent/CA3054041A1/en not_active Abandoned
- 2018-09-20 WO PCT/CN2018/106591 patent/WO2020010696A1/zh active Application Filing
- 2018-09-20 US US16/613,926 patent/US11339658B2/en active Active
- 2018-09-20 AU AU2018431390A patent/AU2018431390B2/en not_active Ceased
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2123109C1 (ru) * | 1996-04-29 | 1998-12-10 | Акционерное общество "Угольная компания "Прокопьевскуголь" | Способ разработки свиты угольных пластов в приконтурных зонах карьера |
CN101725352A (zh) * | 2009-12-04 | 2010-06-09 | 中国矿业大学 | 一种固体充填综采回收房式煤柱方法 |
CN102061938A (zh) * | 2010-12-10 | 2011-05-18 | 天地科技股份有限公司 | 一种采用膏体充填采空区回收煤柱的充填工艺 |
CN103527196A (zh) * | 2013-10-28 | 2014-01-22 | 中国矿业大学 | 一种黄土充填回收房式煤柱的方法 |
CN103742146A (zh) * | 2014-01-17 | 2014-04-23 | 淄博王煤矿业有限公司 | 墩柱式充填法采煤工艺 |
CN105240014A (zh) * | 2015-11-12 | 2016-01-13 | 中国矿业大学 | 一种充填再造护巷煤柱条带回收房式遗留煤柱的方法 |
CN106321103A (zh) * | 2016-09-08 | 2017-01-11 | 中国矿业大学 | 一种固体充填协同人工矿柱回收房式煤柱方法 |
CN108087021A (zh) * | 2017-11-01 | 2018-05-29 | 中国矿业大学 | 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110410076A (zh) * | 2019-08-16 | 2019-11-05 | 山东科技大学 | 一种用于老房柱采空区遗留煤柱回收的充填开采方法 |
CN110410076B (zh) * | 2019-08-16 | 2021-06-08 | 山东科技大学 | 一种用于老房柱采空区遗留煤柱回收的充填开采方法 |
CN112412461A (zh) * | 2020-12-03 | 2021-02-26 | 中国煤炭科工集团太原研究院有限公司 | 一种露天矿端帮煤充填开采工艺方法 |
CN112593940A (zh) * | 2020-12-16 | 2021-04-02 | 中煤能源研究院有限责任公司 | 一种回采房式采煤法遗留煤柱和处理地面矸石的布置工艺 |
CN114687794A (zh) * | 2022-03-31 | 2022-07-01 | 中国矿业大学(北京) | 一种煤矿充填复采方法 |
CN114687794B (zh) * | 2022-03-31 | 2023-11-17 | 中国矿业大学(北京) | 一种煤矿充填复采方法 |
Also Published As
Publication number | Publication date |
---|---|
WO2020010696A1 (zh) | 2020-01-16 |
AU2018431390A1 (en) | 2020-01-30 |
US20210355826A1 (en) | 2021-11-18 |
AU2018431390B2 (en) | 2021-05-06 |
US11339658B2 (en) | 2022-05-24 |
CA3054041A1 (en) | 2020-01-09 |
CN108915764B (zh) | 2019-04-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108915764B (zh) | 一种预留巷道胶结充填回收房式煤柱的方法 | |
WO2020211784A1 (zh) | 适用于厚煤层综采放顶煤的无煤柱自成巷开采方法 | |
CN103470261B (zh) | 综采放顶煤采空区原巷道顶板下沿空掘巷的方法 | |
CN104358572B (zh) | 大倾角急倾斜煤层自然垮落充填护巷无煤柱开采技术 | |
CN111828007B (zh) | 一种地下矿山采空区遗留间柱的回采方法 | |
WO2014187163A1 (zh) | 一种特厚煤层倾斜分层固体充填采煤方法 | |
CN104500070B (zh) | 一种连续采煤机膏体充填开采方法 | |
CN105317459A (zh) | 一种用于控制坚硬顶板大面积垮落灾害的分区充填方法 | |
AU2021106168A4 (en) | High-gas Coal Seam Group Pressure Relief Mining Method Based on Gob-side Entry Retaining in the First Mining Whole Rock Pressure Relief Working Face | |
CN108979638B (zh) | 采煤巷道楔形再生墙与单腿棚梁复合沿空留巷方法 | |
CN113738367B (zh) | 一种复杂破碎急倾斜薄矿脉分段崩矿下向充填采矿法 | |
CN109869152B (zh) | 煤与瓦斯突出煤层预留巷道开采方法 | |
CN111502662A (zh) | 一种冲击地压矿井超前煤体深部卸压浅部加固的防治方法 | |
CN105804748A (zh) | 一种露天运输系统下分区开采挂帮矿的方法 | |
CN104100271A (zh) | 预掘导硐充填人造帮二次复用巷旁支护成巷方法 | |
CN103161467B (zh) | 一种水平中厚矿体厢式充填采矿方法 | |
CN113153295A (zh) | 极厚硬煤开采方法 | |
CN105649673A (zh) | 一种大倾角煤层巷旁矸混充填沿空留巷方法 | |
CN104265294A (zh) | 大倾角煤层炮采面无煤柱开采技术 | |
CN113605893A (zh) | 一种预充填完全沿空掘巷围岩控制方法 | |
CN113356851A (zh) | 中厚矿体连续下向中深孔分段空场嗣后充填采矿方法 | |
CN108952715B (zh) | 一种倾斜厚/特厚煤层巷顶沿空掘巷顶煤支护加固方法 | |
CN108397196B (zh) | 一种基于格宾人工矿柱的缓倾斜矿体露天转地下采矿方法 | |
CN116044398A (zh) | 一种冲击地压矿井近水平煤层孤岛工作面开采方法 | |
CN115653602A (zh) | 一种预留间隔式矿柱上向进路充填采矿法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |