CN106320162B - Using the precast assembly bent cap structure and construction method of steel shear connector - Google Patents

Using the precast assembly bent cap structure and construction method of steel shear connector Download PDF

Info

Publication number
CN106320162B
CN106320162B CN201610704462.0A CN201610704462A CN106320162B CN 106320162 B CN106320162 B CN 106320162B CN 201610704462 A CN201610704462 A CN 201610704462A CN 106320162 B CN106320162 B CN 106320162B
Authority
CN
China
Prior art keywords
shear connector
concrete component
steel
bent cap
male
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610704462.0A
Other languages
Chinese (zh)
Other versions
CN106320162A (en
Inventor
葛继平
梅德磊
闫兴非
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Institute of Technology
Original Assignee
Shanghai Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Institute of Technology filed Critical Shanghai Institute of Technology
Priority to CN201610704462.0A priority Critical patent/CN106320162B/en
Publication of CN106320162A publication Critical patent/CN106320162A/en
Application granted granted Critical
Publication of CN106320162B publication Critical patent/CN106320162B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

The present invention relates to a kind of precast assembly bent cap structure and construction method using steel shear connector, the steel shear connector of precast assembly bent cap uses male and female pairing type shear connector, and material is that spheroidal graphite cast-iron or carbon constructional quality steel casting form.Bent cap is divided into the prefabricated component of three sections of difference, in the pre-buried parent form shear connector in two plug-in sections of stitching portions, the pre-buried male shear connector in interlude stitching portion;Lift interlude component respectively with crane, two segmentum laterale components, after calibrating position, wear and put and tensioning first stage presstressed reinforcing steel makes three-stage structure connection integral, complete prestressed pore passage slip casting closing and sealing off and covering anchorage;By reserved slip casting duct, to parent form steel shear connector internal high pressure slip casting, the seam between male and female shear connector is handled, the present invention compared with prior art, reduces complexity of the large and small shear connector of tradition in prefabrication phase template construct;By the way of male and female pairing, not only facilitate the position in hoisting process to determine, and more efficiently promote the occlusion between component.

Description

Using the precast assembly bent cap structure and construction method of steel shear connector
Technical field
It is especially a kind of using the preform lid girder construction of steel shear connector and construction the present invention relates to a kind of preform lid girder construction Method.
Background technology
The cast-in-place construction of concrete-bridge is, it is necessary to which substantial amounts of template and support system, under bad execution conditions, set up full Hall mount approach is infeasible.Coping Construction belongs to work high above the ground, cast-in-place a large amount of concrete, and construction risk is big.Using precast assembly The mode of bent cap can accelerate speed of application, ensure quality, while have good economy in view of scale effect.
At this stage, the shear Design in terms of precast bridge assembly is specific to divide mainly using the shear connector of key teeth formula For big shear connector and small shear connector.Its deficiency is to need to do concavo-convex corner angle moulding during prefab-form, and construction is complicated, and occlusion It is not high with spending.Therefore, it is necessary to which a kind of new male and female pairing steel shear connector, melts forged steel iron easy-formation, component precision can arrive millimeter, High with degree, pre-buried processing can avoid problem above without the special careful processing of template,
The content of the invention
The present invention proposes a kind of precast assembly bent cap structure and construction method using steel shear connector, and the structure is using new The steel shear connector of male and female pairing, and applied in the precast assembly construction of bent cap.The construction not only facilitates assembled positioning, Er Qieke To improve the shear resistance of Mosaic face.
To achieve the above object, the technical scheme is that:A kind of precast assembly bent cap structure using steel shear connector, Concrete component including steel shear connector, prefabricated bent cap, pass through pre-buried steel shear connector between the concrete component of prefabricated bent cap Connection, each steel shear connector are made up of male shear connector and the pairing use of parent form shear connector;Male shear connector and parent form shear connector Crescent moon line is provided with concrete surface, for producing mechanical snap power between the concrete component of prefabricated bent cap;It is described Injected hole is provided with parent form shear connector tail end, injected hole is connected to the outside of the concrete component of prefabricated bent cap by pvc pipe, side Just the seam of slip casting closure tolerance parent form shear connector.
The steel shear connector is formed by spheroidal graphite cast-iron or carbon constructional quality steel casting.
A kind of construction method of precast assembly bent cap using steel shear connector, is concretely comprised the following steps:
Step 1, the template construct of prefabricated bent cap
Prefabricated bent cap is divided into three section concrete component A, B, C, and erecting template respectively;
Step 2, pre-buried steel shear connector and casting concrete
In the stitching portion of two plug-in concrete component A, C prefab-form, the pre-buried interlude of parent form shear connector 2 is mixed The pre-buried male shear connector in stitching portion of native component B prefab-form is coagulated, with level meter to horizontal direction position correction, cuts male Power key and parent form shear connector are matched and coincide, then are fixed with reinforcement location, prevent from misplacing during concreting;Then coagulation Soil pours, and during concreting since at steel shear connector, two stage cultivation pours, and ensures preform lid beam quality;
Step 3, the concrete component of hoisting prefabricated bent cap
1)Lift concrete component B:The concrete component B of crane hanging component interlude, according to predetermined bridge pier 7 and centre Section assembling scheme, slowly lay up to being completely attached to bridge pier 7, recall crane, cement grout is injected in assembled interface position Closing;
2)Lift concrete component A, C:Crane lifts concrete component A, C simultaneously, is applied at three sections of member interfaces Brush epoxy resin, using male and female shaped steel shear connector as calibration point, parent form shear connector is docked with male shear connector and assigned, has been docked Cheng Hou, stop the lifting work of crane;
Step 4, tensioning first stage presstressed reinforcing steel
Preprepared presstressed reinforcing steel is pierced along concrete component mesopore and put, using post stretching both ends tension reinforcing steel bar, Tensioning first stage presstressed reinforcing steel simultaneously anchors, and is brought into close contact concrete component A, C and concrete component B, then removes lifting Machine, the prestressed pore passage slip casting closing to the first stage;
Pneumatic mortar machine is connected by step 5, shear connector joint treatment using small leather hose with PVC pipeline, and interface is fixed with fixture Prevent that leather hose departs from PVC pipeline under high pressure conditions, starts pneumatic mortar machine and is opened to PVC pipeline inner high voltage Epoxy Resin For Automatic Pressure Gelation Process, until Seam crossing of the slurries along concrete component A and concrete component B, concrete component A and concrete component C oozes out, and closes mud jacking Machine, small leather hose is removed, erasing cleaning is done to the resin liquid oozed out;
Step 6, tensioning second stage presstressed reinforcing steel
Block is laid on concrete component A, C, anti-shock rubber support base is laid on concrete component A, B, C, then tensioning Second stage presstressed reinforcing steel, prestressing force hole slip casting closing, sealing off and covering anchorage and seam are finally completed, complete whole assembled process.
The beneficial effects of the invention are as follows:It is prefabricated in bent cap using new male and female pairing steel shear connector on precast assembly bent cap It is pioneering in terms of assembling technique shearing resistance construction.The large and small shear connector difference of key teeth formula used with general prefabricated bridge exists In:Shear connector needs in the present invention are pre-buried, reduce complicated journey of the large and small shear connector of tradition in prefabrication phase template construct Degree;By the way of male and female pairing, the position in hoisting process is not only facilitated to determine, and more efficiently between promotion component Occlusion.
The present invention has following advantage in practical engineering application:Steel shear connector structure casts easy-formation, and dimensional accuracy is high, hangs The matching degree for filling splicing is high;In the case of reasonable in design, spheroidal graphite cast-iron or carbon constructional quality steel casting can be used to form; Shear connector is directly embedded in assembling members, and the requirement made to template refinement is low, and template material is saved in work is produced in batches Material and a large amount of human resources;Tension of prestressed tendon anchorage style, shorten the working time needed for traditional Cast-in-place Bent Cap, it is whole, big, On middle or long line grade separation science of bridge building, engineering total lever factor is greatly shortened, lifts aging performance;The shear connector docking of male and female pairing, The effect of interim fulcrum is not only acted as, while the function of thering is key teeth to be engaged, greatly improve Mosaic face shearing resistance reliability.
Brief description of the drawings
Fig. 1 is male and female pairing type steel shear connector structure schematic diagram;
Fig. 2 is Fig. 1 top view;
Fig. 3 is precast assembly bent cap overall structure diagram;
Fig. 4 is place's close-up schematic view of being punctuated in Fig. 3;
Fig. 5 is top view at concrete component A, B interface;
Fig. 6 is concrete component A interface schematic diagrames;
Fig. 7 is the FB(flow block) of the construction method of the precast assembly bent cap using steel shear connector of the present invention.
Embodiment
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
As shown in Figures 1 to 6, the precast assembly bent cap structure of the invention using steel shear connector, including prefabricated bent cap Concrete component, steel shear connector, injected hole 4, PVC pipeline 5 etc..Cut between the concrete component of prefabricated bent cap by pre-buried steel Power key connection, single steel shear connector are divided into male shear connector 1 and parent form shear connector 2, and the boss on male shear connector 1 is cut with parent form Groove male and female pairing connection on power key 2, steel shear connector are formed by spheroidal graphite cast-iron or carbon constructional quality steel casting;Male shears Key 1 and parent form shear connector 2 on concrete surface with having crescent moon line 3, it is therefore an objective to machinery is produced between concrete component A, B, C Snap-in force;There is injected hole 4 at the tail end of parent form shear connector 2, injected hole 4 is connected to outside concrete component A, C by PVC pipeline 5 Side, facilitate the seam 6 of slip casting closing male and female shear connector.
As shown in fig. 7, the construction method of the precast assembly bent cap using steel shear connector of the present invention, with longitudinal overall length 31m Prefabricated bent cap exemplified by, the present invention in prefabricated bent cap by tri- sections of components of concrete component A, B, C(Fig. 3), construction procedure and will Ask as follows:
A, prefabricated bent cap is divided into concrete component A, B, C tri- into section, it is prefabricated that three one-tenth sections set up template respectively, concrete Component A, C are two plug-in sections, and the pre-buried parent form shear connector 2 in stitching portion, concrete component B is interlude, and the pre-buried male in stitching portion is cut Power key 1, pre-buried position is only in compressive zone domain;Steel shear connector is needed with level meter to horizontal direction position school when pre-buried Standard, it is connected with PVC pipeline 5 at the tail end injected hole 4 of parent form shear connector 2, with reinforcing bar to steel shear connector and the fixed position of PVC pipeline 5, Prevent from misplacing during concreting;When pouring since at steel shear connector, two stage cultivation pours, and ensures preform lid beam Quality;Component leaves three layers as shown in Figure 6 symmetrical presstressed reinforcing steel duct S in prefabrication process, and presstressed reinforcing steel sleeve pipe uses modeling Expect bellows.
B, behind component conveying to assembling construction scene, first with the concrete component B of crane hanging component interlude, handed over bridge pier Interface brushwork epoxy resin makees tack coat, after finding assembled position accurately, slowly lay until with bridge pier 7 it is completely assembled, recall lifting Device, in interface position injection cement grout closing.
C, concrete component A, C are lifted simultaneously using crane, the brushwork epoxy resin at three sections of member interfaces, with Male and female type shear connector 1,2 is calibration point, and parent form shear connector 2 is docked with male shear connector 1 and assigned, and after the completion of docking, is stopped The lifting work of heavy-duty machine;
D, prestress wire is interted along three layers of symmetrical presstressed reinforcing steel duct S hole, steel beam specification is used uniformly 15- ф S15.20 steel strand wires, using the tensioning of post stretching both ends, tensioning first stage presstressed reinforcing steel, anchor plate must hang down with steel beam center line Directly, the symmetrical tensioning in both ends, double-direction control tension stress and elongation, fixed anchorage, make concrete component A, C and concrete component B is brought into close contact, and removes hoisting apparatus, the prestressed pore passage slip casting closing to the first stage, strength of cement grout C45;
E, small-sized pneumatic mortar machine is connected with PVC pipeline 5 using rubber tube, interface is fixed with fixture prevents high pressure conditions Lower leather hose departs from PVC pipeline 5, starts pneumatic mortar machine and is opened to the inner high voltage Epoxy Resin For Automatic Pressure Gelation Process of PVC pipeline 5, until slurries are along coagulation Native component A, B, concrete component A, C seam crossing ooze out, and close pneumatic mortar machine, remove small leather hose, the resin liquid oozed out is wiped Cleaning;
F, block 8 and anti-shock rubber support base 9 in laying as shown in Figure 3, after block 8 completes assembly, antidetonation rubber is installed Glue bearing needs to be symmetrically installed from structure centre toward both sides, with post-stretching second stage presstressed reinforcing steel, i.e., the middle the superiors shown in Fig. 6 Presstressed reinforcing steel, anchor plate must in advance should with steel beam median perpendicular, the symmetrical tensioning in both ends, double-direction control tension stress and elongation Power, which reaches, fixes anchorage after design requirement value, removes hoisting apparatus, mud jacking in duct, strength of cement grout C45, face joint mouth Brushwork epoxy resin closing and sealing off and covering anchorage.

Claims (2)

1. a kind of construction method of precast assembly bent cap structure using steel shear connector, the precast assembly lid of the steel shear connector of use Girder construction includes steel shear connector, the concrete component of prefabricated bent cap, passes through pre-buried steel between the concrete component of prefabricated bent cap Key connection is sheared, each steel shear connector is made up of male shear connector (1) and parent form shear connector (2) pairing use;Male shear connector (1) and parent form shear connector (2) and concrete surface are provided with crescent moon line (3), for the concrete component with prefabricated bent cap it Between produce mechanical snap power;Injected hole (4) is provided with parent form shear connector (2) tail end, injected hole (4) passes through PVC pipeline (5) Being connected to the concrete component of prefabricated bent cap has outside, facilitates the seam (6) of slip casting closure tolerance parent form shear connector, and its feature exists In concretely comprising the following steps:
Step 1, the template construct of prefabricated bent cap
Prefabricated bent cap is divided into three section concrete component A, B, C, and erecting template respectively;
Step 2, pre-buried steel shear connector and casting concrete
In the pre-buried parent form shear connector (2) in the stitching portion of two plug-in concrete component A, C prefab-form, the coagulation of interlude The pre-buried male shear connector (1) in stitching portion of native component B prefab-form, with level meter to horizontal direction position correction, makes male Shear connector (1) and parent form shear connector (2) are matched and coincide, then are fixed with reinforcement location, prevent from misplacing during concreting; Then concreting, during concreting since at steel shear connector, two stage cultivation pours, and ensures preform lid beam matter Amount;
Step 3, the concrete component of hoisting prefabricated bent cap
1)Lift concrete component B:The concrete component B of crane hanging component interlude, according to predetermined bridge pier (7) and interlude Assembling scheme, is slowly laid until with bridge pier (7) full contact, recalls crane, and cement grout is injected in assembled interface position Closing;
2)Lift concrete component A, C:Crane lifts concrete component A, C simultaneously, and brush ring is applied at three sections of member interfaces Oxygen tree fat, with male and female type shear connector(1,2)For calibration point, parent form shear connector (2) is docked with male shear connector (1) and assigned, it is right After the completion of connecing, stop the lifting work of crane;
Step 4, tensioning first stage presstressed reinforcing steel
Preprepared presstressed reinforcing steel is pierced along concrete component mesopore and put, using post stretching both ends tension reinforcing steel bar, tensioning First stage presstressed reinforcing steel simultaneously anchors, and is brought into close contact concrete component A, C and concrete component B, then removes crane, Prestressed pore passage slip casting closing to the first stage;
Step 5, shear connector joint treatment
Pneumatic mortar machine is connected with PVC pipeline (5) using small leather hose, interface fixed with fixture prevent under high pressure conditions leather hose with PVC pipeline (5) departs from, and starts pneumatic mortar machine and is opened to PVC pipeline (5) inner high voltage Epoxy Resin For Automatic Pressure Gelation Process, until slurries are along concrete structure Part A and concrete component B, concrete component A and concrete component C seam crossing ooze out, and close pneumatic mortar machine, remove small leather hose, Erasing cleaning is done to the resin liquid oozed out;
Step 6, tensioning second stage presstressed reinforcing steel
Block (8) is laid on concrete component A, C, anti-shock rubber support base (9) is laid on concrete component A, B, C, then opens Second stage presstressed reinforcing steel is drawn, finally completes prestressing force hole slip casting closing, sealing off and covering anchorage and seam, completes whole assembled process.
2. the construction method of the precast assembly bent cap structure according to claim 1 using steel shear connector, it is characterised in that: The steel shear connector is formed by spheroidal graphite cast-iron or carbon constructional quality steel casting.
CN201610704462.0A 2016-08-22 2016-08-22 Using the precast assembly bent cap structure and construction method of steel shear connector Expired - Fee Related CN106320162B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610704462.0A CN106320162B (en) 2016-08-22 2016-08-22 Using the precast assembly bent cap structure and construction method of steel shear connector

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610704462.0A CN106320162B (en) 2016-08-22 2016-08-22 Using the precast assembly bent cap structure and construction method of steel shear connector

Publications (2)

Publication Number Publication Date
CN106320162A CN106320162A (en) 2017-01-11
CN106320162B true CN106320162B (en) 2018-01-26

Family

ID=57741491

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610704462.0A Expired - Fee Related CN106320162B (en) 2016-08-22 2016-08-22 Using the precast assembly bent cap structure and construction method of steel shear connector

Country Status (1)

Country Link
CN (1) CN106320162B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560819A (en) * 2018-05-30 2018-09-21 中国建筑第八工程局有限公司 Box beam is adjustable Alveolus type connecting node and its construction method
CN109853362B (en) * 2019-03-29 2021-02-26 上海应用技术大学 Temporary prestressed anchoring segmented prefabricated capping beam and temporary prestress applying method
CN110106779A (en) * 2019-05-05 2019-08-09 北京市市政专业设计院股份公司 A kind of prefabrication type bent cap and its construction method
CN111851323B (en) * 2020-07-07 2022-03-22 汕头大学 Construction process for manufacturing concrete joint structure
CN112458925A (en) * 2020-12-02 2021-03-09 中交路桥建设有限公司 Segment precast beam structure and construction method for splicing and combining bridge thereof
CN113931057B (en) * 2021-03-19 2023-01-24 宁波市政工程建设集团股份有限公司 Tenon-and-mortise connected prefabricated small box girder type hidden cover beam and construction method thereof
CN113684751B (en) * 2021-08-16 2022-12-30 北京市市政一建设工程有限责任公司 Prefabricated bridge and construction process thereof

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5771518A (en) * 1989-06-16 1998-06-30 Roberts; Michael Lee Precast concrete bridge structure and associated rapid assembly methods
CN1316127C (en) * 2004-05-27 2007-05-16 同济大学 Totally assembled type prefabricated concrete structure system
CN103194983A (en) * 2013-04-26 2013-07-10 上海市城市建设设计研究总院 Segmental precast assembly method and segmental precast assembly structure for cantilever arm of large capping beam
CN203451986U (en) * 2013-09-13 2014-02-26 上海市城市建设设计研究总院 Full-prefabricated assembly bent cap
CN103603435B (en) * 2013-12-06 2015-11-04 金陵科技学院 A kind of assembly concrete antidetonation beam column frame and construction method thereof
CN105484109B (en) * 2015-11-21 2017-04-12 隔而固(青岛)振动控制有限公司 Easy-to-assemble floating track bed precast slab and application thereof
CN205329526U (en) * 2016-01-19 2016-06-22 张正东 Pier is assembled to precast concrete

Also Published As

Publication number Publication date
CN106320162A (en) 2017-01-11

Similar Documents

Publication Publication Date Title
CN106320162B (en) Using the precast assembly bent cap structure and construction method of steel shear connector
CN106320164B (en) Using the large scale prefabricated assembled bent cap and construction method of " bracket " construction
CN105544385B (en) A kind of seam construction of prefabricated subsection formula concrete-bridge
CN106592440B (en) A kind of construction method of prefabricated subsection type bridge pier
CN109487707A (en) A kind of precast assembly expanded letter box beam and its assembling method
CN109457599B (en) Splicing structure of hollow pier and bearing platform and construction method
CN102828468B (en) Construction method for controlling prefabricated crack of high-strength thin-walled box girder under high-temperature dry condition
CN108560544A (en) A kind of sleeve connection assembled pile foundation and its construction method
CN107856178B (en) The assembled freely-supported box girder construction and production method of PVA fiber cement composites
CN109440627A (en) A kind of precast segment assembly seam system and method based on early strong UHPC
CN209443571U (en) A kind of large span fabricated construction self-balancing tenon-prestressing combination connecting node
CN102808414B (en) Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
CN205557302U (en) Section section precast box girder's a seam connection structure is assembled to short line method
CN206174195U (en) Assembled concrete shear force wall split, assemble connection structure
CN213709144U (en) Bridge pier structure
CN112853946A (en) Grouting sleeve, grouting sleeve connected assembled pier and construction method thereof
CN104805772B (en) A kind of shaped form Tower Bridge toughened internal stress construction method
CN109235637A (en) A kind of large span fabricated construction self-balancing tenon-prestressing combination connecting node
CN207714114U (en) A kind of prefabricated high-strength concrete bridge pier
CN109853362A (en) A kind of interim prestress anchoraging prefabricated bent cap of segmentation and interim method for applying prestressing force
CN206408515U (en) Precast pier section assembling structure
CN108301425A (en) Prefabricated quick mounting type lattice girder system and its construction method
CN108468379A (en) A kind of novel precast prestressed continuous beam connecting node of assembly concrete
CN108774947B (en) Ultra-high-strength concrete connection structure of assembled bridge pier column and construction method
CN207582460U (en) A kind of super-large diameter splices hollow pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180126

Termination date: 20200822

CF01 Termination of patent right due to non-payment of annual fee