CN207714114U - A kind of prefabricated high-strength concrete bridge pier - Google Patents

A kind of prefabricated high-strength concrete bridge pier Download PDF

Info

Publication number
CN207714114U
CN207714114U CN201721812848.XU CN201721812848U CN207714114U CN 207714114 U CN207714114 U CN 207714114U CN 201721812848 U CN201721812848 U CN 201721812848U CN 207714114 U CN207714114 U CN 207714114U
Authority
CN
China
Prior art keywords
pier shaft
pier
cage
concrete bridge
bridge pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721812848.XU
Other languages
Chinese (zh)
Inventor
毛由田
毛永平
李志高
马进元
姚栋
安雄飞
陈巧
王卫民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jianhua Construction Materials China Co Ltd
Original Assignee
Jianhua Construction Materials China Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jianhua Construction Materials China Co Ltd filed Critical Jianhua Construction Materials China Co Ltd
Priority to CN201721812848.XU priority Critical patent/CN207714114U/en
Application granted granted Critical
Publication of CN207714114U publication Critical patent/CN207714114U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a kind of prefabricated high-strength concrete bridge pier.The bridge pier includes pier shaft, steel reinforcement framework cage and hole for hoist, and the cross section outer contour shape of pier shaft is composed of the arc section of four or more straightways and four or more, and all arc sections are located on same circumference;Tongue and groove section is provided on the outer surface of pier shaft bottom end;Hole for hoist is circumferentially disposed along pier shaft circumference and runs through pier shaft;Two layers or more of steel reinforcement framework cage is equipped in pier shaft, outermost layer steel reinforcement framework cage is abnormity, and main reinforcement is arranged in the inside of stirrup, and main reinforcement head end is provided with screw thread, and tail end is equipped with tapped sleeve;The steel reinforcement framework cage of remainder layer is circle, and main reinforcement is arranged in the outside of stirrup, and main reinforcement head end and tail end are equipped with tapped sleeve;It is attached by connector between the steel reinforcement framework cage of adjacent two layers.The precast concrete bridge pier of the utility model has many advantages, such as that mechanical property is excellent, strength grade of concrete is high, production technology is easy.

Description

A kind of prefabricated high-strength concrete bridge pier
Technical field
The utility model is related to the technical fields that builds a bridge, and in particular to a kind of prefabricated high-strength concrete bridge pier shape and knot The improvement of structure.
Background technology
In overhead bridge pier in highway and town road, cast in situs formula is mostly used greatly.The concrete bridge of cast in situs Pier is affected by site environment, and if the rainy day constructs, the quality and construction period of the overhead bridge pier in urban district can not be ensured, right The environment of surrounding also will produce certain destruction.In addition, since the bridge pier of cast in situs formula is at the construction field (site) directly by concrete It is filled into prefabricated reinforcing bar, is molded through natural curing, concrete strength influence factor is more.When bridge pier is hollow section When, using the structure type of bimodulus, mold installation is complicated, long in time limit, and there are steel reinforcement cages for this technique productions concrete pier To make that complicated, pile concrete resistance to compression and impermeability are poor, there are durabilities poor, easily the problems such as crack, matter occurs Amount cannot be guaranteed, and the materials such as consumption concrete, steel are excessive when pouring making and waste national resources.
The bridge pier of part engineering is transformed into prefabrication by cast-in-place as a result, but in the manufacture craft of precast pier, generally It is not high that there are mechanization degrees, and especially in the making of steel reinforcement framework cage, still more dependence manually binds progress, this is not Working efficiency is only influenced, it is poor to also result in the reason of steel reinforcement cage is because of human factor there are fastnesses, and main reinforcement is easy sliding, prefabricated bridge In pier forming process, it is easy to happen main reinforcement dislocation, or even the serious quality problems such as main reinforcement is exposed occur.
Invention content
To overcome problem above, a kind of mechanical property of the utility model offer is excellent, strength grade of concrete is high, factory's system Work, simple production process are convenient, hoisting transportation is convenient, economical and efficient precast concrete bridge pier, to solve the mixed of cast in situs Solidifying soil bridge pier there are the problem of.
To solve technical problem, the utility model is realized in the following way:
A kind of prefabricated high-strength concrete bridge pier, including pier shaft, steel reinforcement framework cage and hole for hoist, pier shaft are elongated hollow knot Structure, the cross section outer contour shape of the pier shaft be combined by the arc section of four or more straightways and four or more and At all arc sections are located on same circumference;It is provided with tongue and groove section on the outer surface of the pier shaft bottom end;The hole for hoist It is circumferentially disposed along pier shaft circumference and run through pier shaft;Two layers or more of steel reinforcement framework cage, every layer of framework of steel reinforcement are equipped in the pier shaft Cage includes main reinforcement and stirrup, wherein outermost steel reinforcement framework cage is abnormity, and main reinforcement is arranged in the inside of stirrup, main reinforcement Head end is provided with screw thread, and main reinforcement tail end is provided with tapped sleeve;The steel reinforcement framework cage of remainder layer is circle, and main reinforcement is set It sets in the outside of stirrup, main reinforcement head end and tail end are both provided with tapped sleeve;Between the steel reinforcement framework cage of adjacent two layers It is attached by connector.
Further, diameter of a circle where the arc section is 1.5 times~2.5 times of the length of straigh line.
Further, the tongue and groove section is arranged in pier shaft length range of 0.4 times away from pier shaft bottom end.
Further, the hole for hoist is arranged in pier shaft length range of 0.3 times away from pier shaft top, the hole for hoist Quantity is more than two and circumferentially symmetrically and evenly arranges.
Further, the top of the outermost steel reinforcement framework cage is longer than pier shaft top, and bottom end and pier shaft bottom end are neat In flat or shorter than pier shaft bottom end 10cm;The top and bottom end of the steel reinforcement framework cage of remainder layer and flushing for pier shaft.
Further, the shape of the outermost steel reinforcement framework cage is by four or more straightways and four or more Arc section be composed, all arc sections are located on same circumference.Diameter of a circle where the arc section is the straight line 1.5 times of segment length~2.5 times.
Further, the reach of the main reinforcement head end setting of the outermost steel reinforcement framework cage is not more than 40cm.
Further, the both ends of the connector are hook-shaped.
The beneficial effects of the utility model are:
(1) by prefabrication, the mode of on-site consolidation can shorten the construction period, can be to avoid mixed using field cast-in-place Solidifying soil constructing structure there are the problem of, live manpower and construction cost can be greatly lowered, shorten construction period, meet green ring Protect the requirement of construction.
(2) effectively save national resources.Concrete amount per linear meter(lin.m.) bridge pier is less than existing square, circular cross-section bridge The concrete amount of pier, and anti-bending strength can reach the bridge pier of former section form.
(3) tongue and groove section is set in the bottom of pier shaft, keeps the bonding of bridge pier bottom and concrete more firm, makes pedestal Better contact is installed, improves interface roughness so that bridge pier more fastens.
(4) outer reinforcement framework cage is more than pier shaft length, and the connection for later stage and superstructure provides Bar Anchorage.Together When, the main reinforcement of outer reinforcement framework cage is arranged in the inside of stirrup, the main reinforcement of internal layer steel reinforcement framework cage is arranged in the outer of stirrup Side, this more meets bridge pier in actual stress, it is ensured that the stability of bridge pier structure.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model bridge pier, wherein 1- pier shafts, 2- steel reinforcement framework cages, 3- holes for hoist, 4- Tongue and groove section, 5- outer layer main reinforcements, 6- internal layer main reinforcements.
Fig. 2 is the schematic cross-section of the utility model bridge pier, wherein 7- outer reinforcement framework cages, 8- internal layer frameworks of steel reinforcement Cage, 9- outer layer stirrups, 10- internal layer stirrups, 11- screw threads, 12- sleeves, 13- connectors.
Fig. 3 is the steel reinforcement framework cage schematic diagram of the utility model bridge pier.
Specific implementation mode
The preferred embodiment that according to the present invention will be described in detail below with reference to the accompanying drawings.
A kind of prefabricated high-strength concrete bridge pier of the present embodiment, as shown in Figure 1, including pier shaft 1, steel reinforcement framework cage 2 and hanging Fill hole 3.Pier shaft 1 is elongated hollow structure, and the cross section outer contour shape of pier shaft 1 is by four straightways and four arc section groups It closes, on the same circumference, place diameter of a circle is 1.5 times~2.5 times of length of straigh line to arc section.In pier shaft 1 Bottom end more than be provided with tongue and groove section 4 on outer surface in 0.4 times of long range of pier.Hole for hoist 3 is arranged in 0.3 times away from pier top pier It is circumferentially disposed along 1 circumference of pier shaft and run through pier shaft 1 within the scope of body length, quantity be 2 and it is symmetrical, be evenly arranged.
As shown in Figure 2,3, steel reinforcement framework cage 2 is arranged in pier shaft 1, is made of inside and outside two layers of steel reinforcement framework cage, every layer of steel Tendons skeleton cage includes main reinforcement and stirrup, and wherein outer reinforcement framework cage 7 is abnormity, and contour shape is also by four straightways It is composed with four arc sections, on the same circumference, the profile of internal layer steel reinforcement framework cage 8 is circle to arc section.Outer layer steel The top of tendons skeleton cage 7 is longer than 1 top of pier shaft, bottom end flushed with 1 bottom end of pier shaft or shorter than pier shaft bottom end 10cm in;Internal layer steel The length of tendons skeleton cage 8 is equal to 1 length of pier shaft, and top and bottom end are flushed with the top of pier shaft 1 and bottom end.For outer reinforcement Framework cage 7, outer layer main reinforcement 5 are arranged in the inside of outer layer stirrup 9, and 5 head end of outer layer main reinforcement is provided with screw thread 11, and reach is not More than 40cm, female sleeve 12 is arranged in tail end;For internal layer steel reinforcement framework cage 8, internal layer main reinforcement 6 is arranged in internal layer stirrup Female sleeve 12 is arranged in 10 outside, head end, the tail end of internal layer main reinforcement 6.Pass through between inside and outside two layers of steel reinforcement framework cage Connector 13 is attached, and the both ends of the connector 13 in the present embodiment are equipped with hook.

Claims (9)

1. a kind of prefabricated high-strength concrete bridge pier, including pier shaft, steel reinforcement framework cage and hole for hoist, pier shaft is elongated hollow structure, It is characterized in that, the cross section outer contour shape of the pier shaft is by the arc section of four or more straightways and four or more It is composed, all arc sections are located on same circumference;It is provided with tongue and groove section on the outer surface of the pier shaft bottom end;It is described Hole for hoist is circumferentially disposed along pier shaft circumference and runs through pier shaft;Two layers or more of steel reinforcement framework cage, every layer of steel are equipped in the pier shaft Tendons skeleton cage includes main reinforcement and stirrup, wherein outermost steel reinforcement framework cage is abnormity, and main reinforcement is arranged in stirrup Side, main reinforcement head end are provided with screw thread, and main reinforcement tail end is provided with tapped sleeve;The steel reinforcement framework cage of remainder layer is circle, Its main reinforcement is arranged in the outside of stirrup, and main reinforcement head end and tail end are both provided with tapped sleeve;The reinforcing bar of adjacent two layers It is attached by connector between frame cage.
2. a kind of prefabricated high-strength concrete bridge pier according to claim 1, which is characterized in that circle where the arc section 1.5 times of a diameter of length of straigh line~2.5 times.
3. a kind of prefabricated high-strength concrete bridge pier according to claim 1, which is characterized in that the tongue and groove section setting exists In pier shaft length range of 0.4 times away from pier shaft bottom end.
4. a kind of prefabricated high-strength concrete bridge pier according to claim 1, which is characterized in that hole for hoist setting away from In the pier shaft length range on 0.3 times of pier shaft top, the quantity of the hole for hoist is more than two and circumferentially symmetrically and evenly arranges.
5. a kind of prefabricated high-strength concrete bridge pier according to claim 1, which is characterized in that the outermost reinforcing bar The top of frame cage is longer than pier shaft top, bottom end flushed with pier shaft bottom end or shorter than pier shaft bottom end 10cm in;The reinforcing bar of remainder layer The top and bottom end of framework cage and flushing for pier shaft.
6. a kind of prefabricated high-strength concrete bridge pier according to claim 1, which is characterized in that the outermost reinforcing bar The shape of frame cage is composed of the arc section of four or more straightways and four or more, and all arc sections are located at same On one circumference.
7. a kind of prefabricated high-strength concrete bridge pier according to claim 6, which is characterized in that circle where the arc section 1.5 times of a diameter of length of straigh line~2.5 times.
8. a kind of prefabricated high-strength concrete bridge pier according to claim 1, which is characterized in that the outermost reinforcing bar The reach of the main reinforcement head end setting of frame cage is not more than 40cm.
9. a kind of prefabricated high-strength concrete bridge pier according to claim 1, which is characterized in that the both ends of the connector are It is hook-shaped.
CN201721812848.XU 2017-12-22 2017-12-22 A kind of prefabricated high-strength concrete bridge pier Active CN207714114U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721812848.XU CN207714114U (en) 2017-12-22 2017-12-22 A kind of prefabricated high-strength concrete bridge pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721812848.XU CN207714114U (en) 2017-12-22 2017-12-22 A kind of prefabricated high-strength concrete bridge pier

Publications (1)

Publication Number Publication Date
CN207714114U true CN207714114U (en) 2018-08-10

Family

ID=63057219

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721812848.XU Active CN207714114U (en) 2017-12-22 2017-12-22 A kind of prefabricated high-strength concrete bridge pier

Country Status (1)

Country Link
CN (1) CN207714114U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235236A (en) * 2018-08-28 2019-01-18 中交第二公路勘察设计研究院有限公司 The hollow pipe pier of assembled and its construction method based on flanged joint
CN112030727A (en) * 2020-08-26 2020-12-04 绍兴文理学院 Assembled prefabricated steel-concrete combined pier and construction method thereof
CN112112180A (en) * 2020-08-26 2020-12-22 绍兴文理学院 Connecting system of assembled combined pier and bearing platform and construction method thereof
CN114293475A (en) * 2021-12-31 2022-04-08 中交路桥华南工程有限公司 Split ring sleeving construction method for variable-section large-section pier tower reinforcement cage segment

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235236A (en) * 2018-08-28 2019-01-18 中交第二公路勘察设计研究院有限公司 The hollow pipe pier of assembled and its construction method based on flanged joint
CN109235236B (en) * 2018-08-28 2020-08-07 中交第二公路勘察设计研究院有限公司 Assembly type hollow pipe pier based on flange connection and construction method thereof
CN112030727A (en) * 2020-08-26 2020-12-04 绍兴文理学院 Assembled prefabricated steel-concrete combined pier and construction method thereof
CN112112180A (en) * 2020-08-26 2020-12-22 绍兴文理学院 Connecting system of assembled combined pier and bearing platform and construction method thereof
CN114293475A (en) * 2021-12-31 2022-04-08 中交路桥华南工程有限公司 Split ring sleeving construction method for variable-section large-section pier tower reinforcement cage segment

Similar Documents

Publication Publication Date Title
CN207714114U (en) A kind of prefabricated high-strength concrete bridge pier
CN205576723U (en) Adoption is excelled in prefabrication of fibre mortar and bellows joint and is assembled pier
CN101831875A (en) Precast assembly process of prestressed concrete cylindrical hollow pier
CN107060117A (en) The continuous construction method of seam crossing fiber is realized in concrete gradation casting process
CN102383418A (en) Anti-seismic prefabricated concrete solid square pile and production method thereof
CN104947603B (en) A kind of rc beam bridge girder reinforcing construction and reinforcement means
CN108560544A (en) A kind of sleeve connection assembled pile foundation and its construction method
CN107326810A (en) The reserved grout hole connection method of precast assembly bridge pier
CN103924525B (en) Urban interchange industrialization short-term precast assembly construction method
CN103306432B (en) High-strength concrete cushion block and manufacturing method thereof
CN110029599A (en) Prefabricated culvert steel connecting structure and construction method
CN106638313A (en) Large-scale bent cap semi-prefabrication construction technical method
CN102383420A (en) High-strength concrete prefabricated pile doped with fiber-reinforced plastic bar
CN208685438U (en) A kind of wet seam type of attachment of sectional type floorings
CN102808414B (en) Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
CN208151833U (en) A kind of construction of novel RC-masonry combination arch bridge
CN107932700A (en) Prefabricated high-strength concrete bridge pier and its molding die and manufacture method
CN112211052A (en) Long and short pile-plate structure for controlling uneven settlement of transition section of highway and construction method thereof
CN107988895A (en) A kind of bridge and its construction method
CN110004791A (en) A kind of prestressing without bondn assembled road and its construction method
CN108708452A (en) The U-shaped integral prefabricated window member that floats, assembled float window joint structure and its construction method
CN102051980A (en) Prestress structure with tendon simultaneously acting as inner and outer elements
CN208235310U (en) A kind of hollow concrete bridge pier of prefabricated centrifugal forming
CN204589831U (en) A kind of rc beam bridge girder reinforcing construction
CN107299711A (en) The late poured band structure of prestressed concrete panel

Legal Events