CN106320162A - Prefabricated assembly cap beam structure with steel shear keys and construction method - Google Patents

Prefabricated assembly cap beam structure with steel shear keys and construction method Download PDF

Info

Publication number
CN106320162A
CN106320162A CN201610704462.0A CN201610704462A CN106320162A CN 106320162 A CN106320162 A CN 106320162A CN 201610704462 A CN201610704462 A CN 201610704462A CN 106320162 A CN106320162 A CN 106320162A
Authority
CN
China
Prior art keywords
shear connector
concrete component
steel
bent cap
male
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610704462.0A
Other languages
Chinese (zh)
Other versions
CN106320162B (en
Inventor
葛继平
梅德磊
闫兴非
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Institute of Technology
Original Assignee
Shanghai Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Institute of Technology filed Critical Shanghai Institute of Technology
Priority to CN201610704462.0A priority Critical patent/CN106320162B/en
Publication of CN106320162A publication Critical patent/CN106320162A/en
Application granted granted Critical
Publication of CN106320162B publication Critical patent/CN106320162B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

The invention relates to a prefabricated assembly cap beam structure with steel shear keys and a construction method. The steel shear keys of the prefabricated assembly cap beam structure adopt female and male pairing type shear keys, and are formed by casting nodular cast iron or high-quality carbon structural steel. The construction method comprises the following steps of dividing a cap beam into members which are respectively prefabricated in three sections, embedding a female type shear key at a splicing part of two outer hanging sections, and embedding a male type shear key at a splicing part of a middle section; enabling a crane to respectively lift the member in the middle section and the members in the two outside sections, calibrating positions, penetrating and tensioning a prestressed reinforcement in a first phase to connect the three sections into a whole, and completing the grouting, sealing and anchoring of a prestressed hole passage; by utilizing the reserved grouting hole passage, grouting the interior of the female type steel shear key at high pressure, and treating a joint between the female and male shear keys. Compared with the prior art, the prefabricated assembly cap beam structure and the construction method have the advantages that the complexity of formwork manufacturing in the prefabricating phase of the traditional large and small shear keys is decreased; by adopting the female and male pairing type, the positions in the lifting process are conveniently determined, and the engaging between the members is effectively promoted.

Description

Use precast assembly bent cap structure and the construction method of steel shear connector
Technical field
The present invention relates to a kind of preform lid girder construction, a kind of preform lid girder construction using steel shear connector and construction Method.
Background technology
The cast-in-place construction of concrete-bridge, needs substantial amounts of template and support system, under bad execution conditions, sets up full Hall mount approach is infeasible.Coping Construction belongs to work high above the ground, and cast-in-place a large amount of concrete, construction risk is big.Use precast assembly The mode of bent cap can accelerate speed of application, it is ensured that quality, simultaneously takes account of scale effect and has good economy.
Present stage, the shear Design in terms of precast bridge assembly mainly uses the shear connector that key is tooth-like, specifically divides For big shear connector and little shear connector.Its deficiency is during prefab-form to need to do concavo-convex corner angle moulding, construction complexity, and occlusion Degree of joining is the highest.Accordingly, it would be desirable to a kind of novel male and female pairing steel shear connector, molten forged steel ferrum easy-formation, component precision can arrive millimeter, Joining degree high, pre-buried process, without the special careful process of template, can avoid problem above.
Summary of the invention
The present invention proposes a kind of precast assembly bent cap structure using steel shear connector and construction method, and this structure uses novel The steel shear connector of male and female pairing, and be applied in the precast assembly construction of bent cap.This structure not only convenient assembly location, Er Qieke To improve the shear resistance of Mosaic face.
For achieving the above object, the technical scheme is that a kind of precast assembly bent cap structure using steel shear connector, Including steel shear connector, the concrete component of prefabricated bent cap, by pre-buried steel shear connector between the concrete component of prefabricated bent cap Connecting, each steel shear connector is made up of male shear connector and the pairing use of parent form shear connector;Male shear connector and parent form shear connector It is provided with crescent moon stricture of vagina with concrete surface, is used for producing mechanical snap power between the concrete component of prefabricated bent cap;Described Being provided with injected hole at parent form shear connector tail end, injected hole is connected to the outside of the concrete component of prefabricated bent cap by pvc pipe, side Just the seam of slip casting closure tolerance parent form shear connector.
Described steel shear connector is cast by spheroidal graphite cast-iron or carbon constructional quality steel and forms.
The construction method of a kind of precast assembly bent cap using steel shear connector, concretely comprises the following steps:
Step one, the template construct of prefabricated bent cap
Prefabricated bent cap is divided into three section concrete component A, B, C, and erecting template respectively;
Step 2, pre-buried steel shear connector and casting concrete
The concrete of stitching portion pre-buried parent form shear connector 2 interlude at the prefab-form of two plug-in concrete component A, C The stitching portion pre-buried male shear connector of the prefab-form of component B, by level indicator to horizontal direction position correction, makes male shear connector Match with parent form shear connector and coincide, then fixing with reinforcement location, preventing from misplacing during concreting;Then concrete waters Building, during concreting from the beginning of at steel shear connector, two stage cultivation pours, it is ensured that preform lid beam quality;
Step 3, the concrete component of hoisting prefabricated bent cap
1) lift the concrete component B of concrete component B: crane hanging component interlude, spell with interlude according to predetermined bridge pier 7 Dress scheme, slowly laying until completely attaching to bridge pier 7, recalling crane, closes in assembled interface position injection water slurry liquid;
2) lifting concrete component A, C: crane lifts concrete component A, C simultaneously, is coated with brush ring at three sections of member interface Epoxy resins, with male and female shaped steel shear connector as calibration point, docks parent form shear connector with male shear connector and assigns, after having docked, Stop the lifting work of crane;
Step 4, stretch-draw first stage presstressed reinforcing steel
Preprepared presstressed reinforcing steel is pierced along concrete component mesopore and puts, use post stretching two ends tension reinforcing steel bar, stretch-draw First stage presstressed reinforcing steel also anchors, and makes concrete component A, C fit tightly with concrete component B, then removes crane, Prestressed pore passage slip casting to the first stage is closed;
Step 5, shear connector joint treatment utilizes little leather hose to be connected with PVC pipeline by pneumatic mortar machine, and seam fixture is fixing to be prevented High pressure conditions hypodermis tube and tube road departs from, and starts pneumatic mortar machine and is opened to pipeline inner high voltage Epoxy Resin For Automatic Pressure Gelation Process, until serosity is along coagulation Soil component A and concrete component B, concrete component A ooze out with the seam crossing of concrete component C, close pneumatic mortar machine, take off cuticle Pipe, does erasing cleaning to the resin liquid oozed out;
Step 6, stretch-draw second stage presstressed reinforcing steel
Concrete component A, C lay block, concrete component A, B, C lay box beam holder base plate, then stretch-draw second Stage presstressed reinforcing steel, finally completes prestressing force hole slip casting closing, sealing off and covering anchorage and seam, completes whole assembled process.
The invention has the beneficial effects as follows: on precast assembly bent cap, use novel male and female pairing steel shear connector, prefabricated at bent cap Assembling technique shearing resistance structure aspect is pioneering.Large and small shear connector difference tooth-like with the key that general prefabricated bridge uses exists In: the shear connector in the present invention needs pre-buried, reduces traditional large and small shear connector complicated journey at prefabrication phase template construct Degree;Use the mode of male and female pairing, not only facilitate the position in hoisting process to determine, and more efficiently promote between component Occlusion.
The present invention has following advantage in practical engineering application: steel shear connector structure casting readily molding, dimensional accuracy is high, hangs The matching degree of dress splicing is high;In the case of reasonable in design, spheroidal graphite cast-iron or carbon constructional quality steel casting can be used to form; Shear connector is directly embedded in assembling members, and the requirement making template refinement is low, saves template material in batch production work Material and a large amount of human resourcess;Tension of prestressed tendon anchorage style, shortens the working time needed for tradition Cast-in-place Bent Cap, omnidistance, big, On middle or long line grade separation science of bridge building, greatly shorten engineering total lever factor, promote aging performance;The shear connector docking of male and female pairing, Not only act as the effect of interim fulcrum, the function simultaneously having key tooth to be engaged, be greatly improved Mosaic face shearing resistance reliability.
Accompanying drawing explanation
Fig. 1 is male and female pairing type steel shear connector structure schematic diagram;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is precast assembly bent cap overall structure schematic diagram;
Fig. 4 is place's close-up schematic view of punctuating in Fig. 3;
Fig. 5 is top view at concrete component A, B interface;
Fig. 6 is concrete component A interface schematic diagram;
Fig. 7 is the FB(flow block) of the construction method of the precast assembly bent cap using steel shear connector of the present invention.
Detailed description of the invention
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
As shown in Figures 1 to 6, the precast assembly bent cap structure using steel shear connector of the present invention, including prefabricated bent cap Concrete component, steel shear connector, injected hole 4, pvc pipe 5 etc..By pre-buried steel shearing between the concrete component of prefabricated bent cap Bonded, single steel shear connector is divided into male shear connector 1 and parent form shear connector 2, the boss on male shear connector 1 and parent form shearing Groove male and female pairing on key 2 connects, and steel shear connector is cast by spheroidal graphite cast-iron or carbon constructional quality steel and forms;Male shear connector 1 and parent form shear connector 2 have crescent moon stricture of vagina 3 on concrete surface, it is therefore an objective to and produce machinery between concrete component A, B, C and sting Make a concerted effort;Injected hole 4, injected hole 4 is had to be connected to outside concrete component A, C by pvc pipe 5 at parent form shear connector 2 tail end, side Just the seam 6 of male and female shear connector is closed in slip casting.
As it is shown in fig. 7, the construction method of the precast assembly bent cap using steel shear connector of the present invention, with longitudinal overall length 31m Prefabricated bent cap as a example by, the prefabricated bent cap in the present invention by tri-sections of components (Fig. 3) of concrete component A, B, C, construction procedure and wanting Ask as follows:
A, prefabricated bent cap being divided into concrete component A, B, C tri-section of one-tenth, it is prefabricated that three one-tenth sections set up template respectively, concrete component A, C are two plug-in sections, stitching portion pre-buried parent form shear connector 2, and concrete component B is interlude, stitching portion pre-buried male shear connector 1, pre-buried position is only in territory, compressive zone;Steel shear connector needs by level indicator horizontal direction position correction when pre-buried, female It is connected with pvc pipe 5 at type shear connector 2 tail end injected hole 4, with reinforcing bar to steel shear connector and pvc pipe fixed position, prevents concrete Misplace when pouring;When pouring from the beginning of at steel shear connector, two stage cultivation pours, it is ensured that preform lid beam quality;Component All leaving three layers of symmetrical presstressed reinforcing steel duct S as shown in Figure 6 in prefabrication process, presstressed reinforcing steel sleeve pipe uses plastic film capicitor.
B, component conveying, to behind assembling construction scene, first with the concrete component B of crane hanging component interlude, are handed over bridge pier Interface brushwork epoxy resin makees tack coat, after finding assembled position accurately, slowly lays until assembly complete with bridge pier 7, recalls lifting Device, closes in interface position injection water slurry liquid.
C, use crane lift concrete component A, C simultaneously, brushwork epoxy resin at three sections of member interface, with Male and female type shear connector 1,2 is calibration point, is docked with male shear connector 1 by parent form shear connector 2 and assigns, after having docked, stops The lifting work of heavy-duty machine;
D, hole along three layers of symmetrical presstressed reinforcing steel duct S intert prestress wire, and steel beam specification is used uniformly across 15-ф S15.20 steel strand wires, use the stretch-draw of post stretching two ends, stretch-draw first stage presstressed reinforcing steel, and anchor plate must hang down with steel bundle center line Directly, two ends symmetry stretch-draw, double-direction control tension stress and elongation, fixing anchorage, make concrete component A, C and concrete component B fits tightly, and removes hoisting apparatus, and the prestressed pore passage slip casting to the first stage is closed, and strength of cement grout is C45;
E, utilizing rubber tube to be connected with PVC pipeline 5 by small-sized pneumatic mortar machine, seam fixture is fixing prevents high pressure conditions hypodermis Tube and tube road 5 departs from, start pneumatic mortar machine be opened to pipeline 5 inner high voltage Epoxy Resin For Automatic Pressure Gelation Process, until serosity along concrete component A, B, Concrete component A, C seam crossing oozes out, and closes pneumatic mortar machine, takes off little leather hose, and the resin liquid oozed out is done erasing cleaning;
F, lay as shown in Figure 3 in block 8 and anti-shock rubber support base 9, after block 8 completes assembly, install antidetonation rubber prop up Seat needs to install toward lateral symmetry from structure centre, and with post-stretching second stage presstressed reinforcing steel, i.e. shown in Fig. 6, the middle the superiors in advance should Power muscle, anchor plate must be with steel bundle median perpendicular, and two ends symmetry stretch-draw, double-direction control tension stress and elongation, prestressing force reaches Fixing anchorage after design required value, remove hoisting apparatus, mud jacking in duct, strength of cement grout is C45, face joint mouth brushing Epoxy resin sealing sealing off and covering anchorage.

Claims (3)

1. use a precast assembly bent cap structure for steel shear connector, including steel shear connector, the concrete component of prefabricated bent cap, in advance Connected by pre-buried steel shear connector between the concrete component of bent cap processed, it is characterised in that: each steel shear connector is cut by male Power key (1) and parent form shear connector (2) pairing use and constitute;Male shear connector (1) and parent form shear connector (2) and concrete surface It is provided with crescent moon stricture of vagina (3), is used for producing mechanical snap power between the concrete component of prefabricated bent cap;Described parent form shear connector (2) being provided with injected hole (4) at tail end, the concrete component that injected hole (4) is connected to prefabricated bent cap by pvc pipe (5) has outside, Facilitate the seam (6) of slip casting closure tolerance parent form shear connector.
The precast assembly bent cap structure of employing steel shear connector the most according to claim 1, it is characterised in that: described steel shearing Key is cast by spheroidal graphite cast-iron or carbon constructional quality steel and forms.
3. the construction method of the precast assembly bent cap using steel shear connector, it is characterised in that concretely comprise the following steps:
Step one, the template construct of prefabricated bent cap
Prefabricated bent cap is divided into three section concrete component A, B, C, and erecting template respectively;
Step 2, pre-buried steel shear connector and casting concrete
At the stitching portion pre-buried parent form shear connector (2) of the prefab-form of two plug-in concrete component A, C, the coagulation of interlude The stitching portion pre-buried male steel shear connector (1) of the prefab-form of soil component B, by level indicator to horizontal direction position correction, makes public affairs Type shear connector (1) and parent form shear connector (2) match and coincide, then fix with reinforcement location, prevent from, during concreting, mistake occurs Position;Then concreting, during concreting from the beginning of at steel shear connector, two stage cultivation pours, it is ensured that preform lid beam Quality;
Step 3, the concrete component of hoisting prefabricated bent cap
1) the concrete component B of concrete component B: crane hanging component interlude is lifted, according to predetermined bridge pier (7) and interlude Assembling scheme, slowly laying until completely attaching to bridge pier (7), recalling crane, in assembled interface position injection water slurry liquid Close;
2) lifting concrete component A, C: crane lifts concrete component A, C simultaneously, is coated with brush ring at three sections of member interface Epoxy resins, with male and female type shear connector 1,2 for calibration point, docks parent form shear connector (2) with male shear connector (1) and assigns, docking After completing, stop the lifting work of crane;
Step 4, stretch-draw first stage presstressed reinforcing steel
Preprepared presstressed reinforcing steel is pierced along concrete component mesopore and puts, use post stretching two ends tension reinforcing steel bar, stretch-draw First stage presstressed reinforcing steel also anchors, and makes concrete component A, C fit tightly with concrete component B, then removes crane, Prestressed pore passage slip casting to the first stage is closed;
Step 5, shear connector joint treatment
Utilizing little leather hose to be connected with PVC pipeline (5) by pneumatic mortar machine, seam fixture is fixing prevents high pressure conditions hypodermis tube and tube Road (5) departs from, and starts pneumatic mortar machine and is opened to pipeline (5) inner high voltage Epoxy Resin For Automatic Pressure Gelation Process, until serosity is along concrete component A and coagulation Soil component B, concrete component A ooze out with the seam crossing of concrete component C, close pneumatic mortar machine, take off little leather hose, to the tree oozed out Fat liquid does erasing cleaning;
Step 6, stretch-draw second stage presstressed reinforcing steel
Concrete component A, C lay block (8), concrete component A, B, C lays box beam holder base plate (9), then opens Draw second stage presstressed reinforcing steel, finally complete prestressing force hole slip casting closing, sealing off and covering anchorage and seam, complete whole assembled process.
CN201610704462.0A 2016-08-22 2016-08-22 Using the precast assembly bent cap structure and construction method of steel shear connector Expired - Fee Related CN106320162B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610704462.0A CN106320162B (en) 2016-08-22 2016-08-22 Using the precast assembly bent cap structure and construction method of steel shear connector

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610704462.0A CN106320162B (en) 2016-08-22 2016-08-22 Using the precast assembly bent cap structure and construction method of steel shear connector

Publications (2)

Publication Number Publication Date
CN106320162A true CN106320162A (en) 2017-01-11
CN106320162B CN106320162B (en) 2018-01-26

Family

ID=57741491

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610704462.0A Expired - Fee Related CN106320162B (en) 2016-08-22 2016-08-22 Using the precast assembly bent cap structure and construction method of steel shear connector

Country Status (1)

Country Link
CN (1) CN106320162B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560819A (en) * 2018-05-30 2018-09-21 中国建筑第八工程局有限公司 Box beam is adjustable Alveolus type connecting node and its construction method
CN109853362A (en) * 2019-03-29 2019-06-07 上海应用技术大学 A kind of interim prestress anchoraging prefabricated bent cap of segmentation and interim method for applying prestressing force
CN110106779A (en) * 2019-05-05 2019-08-09 北京市市政专业设计院股份公司 A kind of prefabrication type bent cap and its construction method
CN111851323A (en) * 2020-07-07 2020-10-30 汕头大学 Novel concrete joint structure and construction process
CN112458925A (en) * 2020-12-02 2021-03-09 中交路桥建设有限公司 Segment precast beam structure and construction method for splicing and combining bridge thereof
CN113684751A (en) * 2021-08-16 2021-11-23 北京市市政一建设工程有限责任公司 Prefabricated bridge and construction process thereof
CN113931057A (en) * 2021-03-19 2022-01-14 宁波市政工程建设集团股份有限公司 Tenon-and-mortise connected prefabricated small box girder type hidden cover beam and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5771518A (en) * 1989-06-16 1998-06-30 Roberts; Michael Lee Precast concrete bridge structure and associated rapid assembly methods
CN1704537A (en) * 2004-05-27 2005-12-07 同济大学 Totally assembled type prefabricated concrete structure system
CN103194983A (en) * 2013-04-26 2013-07-10 上海市城市建设设计研究总院 Segmental precast assembly method and segmental precast assembly structure for cantilever arm of large capping beam
CN103603435A (en) * 2013-12-06 2014-02-26 金陵科技学院 Assembled concrete seismic beam-column frame and construction method thereof
CN203451986U (en) * 2013-09-13 2014-02-26 上海市城市建设设计研究总院 Full-prefabricated assembly bent cap
CN105484109A (en) * 2015-11-21 2016-04-13 隔而固(青岛)振动控制有限公司 Easy-to-assemble floating track bed precast slab and application thereof
CN205329526U (en) * 2016-01-19 2016-06-22 张正东 Pier is assembled to precast concrete

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5771518A (en) * 1989-06-16 1998-06-30 Roberts; Michael Lee Precast concrete bridge structure and associated rapid assembly methods
CN1704537A (en) * 2004-05-27 2005-12-07 同济大学 Totally assembled type prefabricated concrete structure system
CN103194983A (en) * 2013-04-26 2013-07-10 上海市城市建设设计研究总院 Segmental precast assembly method and segmental precast assembly structure for cantilever arm of large capping beam
CN203451986U (en) * 2013-09-13 2014-02-26 上海市城市建设设计研究总院 Full-prefabricated assembly bent cap
CN103603435A (en) * 2013-12-06 2014-02-26 金陵科技学院 Assembled concrete seismic beam-column frame and construction method thereof
CN105484109A (en) * 2015-11-21 2016-04-13 隔而固(青岛)振动控制有限公司 Easy-to-assemble floating track bed precast slab and application thereof
CN205329526U (en) * 2016-01-19 2016-06-22 张正东 Pier is assembled to precast concrete

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560819A (en) * 2018-05-30 2018-09-21 中国建筑第八工程局有限公司 Box beam is adjustable Alveolus type connecting node and its construction method
CN109853362A (en) * 2019-03-29 2019-06-07 上海应用技术大学 A kind of interim prestress anchoraging prefabricated bent cap of segmentation and interim method for applying prestressing force
CN109853362B (en) * 2019-03-29 2021-02-26 上海应用技术大学 Temporary prestressed anchoring segmented prefabricated capping beam and temporary prestress applying method
CN110106779A (en) * 2019-05-05 2019-08-09 北京市市政专业设计院股份公司 A kind of prefabrication type bent cap and its construction method
CN111851323A (en) * 2020-07-07 2020-10-30 汕头大学 Novel concrete joint structure and construction process
CN112458925A (en) * 2020-12-02 2021-03-09 中交路桥建设有限公司 Segment precast beam structure and construction method for splicing and combining bridge thereof
CN113931057A (en) * 2021-03-19 2022-01-14 宁波市政工程建设集团股份有限公司 Tenon-and-mortise connected prefabricated small box girder type hidden cover beam and construction method thereof
CN113684751A (en) * 2021-08-16 2021-11-23 北京市市政一建设工程有限责任公司 Prefabricated bridge and construction process thereof
CN113684751B (en) * 2021-08-16 2022-12-30 北京市市政一建设工程有限责任公司 Prefabricated bridge and construction process thereof

Also Published As

Publication number Publication date
CN106320162B (en) 2018-01-26

Similar Documents

Publication Publication Date Title
CN106320162A (en) Prefabricated assembly cap beam structure with steel shear keys and construction method
CN106320164B (en) Using the large scale prefabricated assembled bent cap and construction method of " bracket " construction
CN102425310B (en) Assembly-type residential shear wall structural wall body vertical connection construction method
CN107044177A (en) A kind of assembly concrete shear wall fractionation, assembled attachment structure and connection method
CN108560544A (en) A kind of sleeve connection assembled pile foundation and its construction method
CN109487707A (en) A kind of precast assembly expanded letter box beam and its assembling method
CN107964948A (en) A kind of super-large diameter pin-connected panel hollow pile and its joining method
CN104153287A (en) Segmental assembled concrete frame pier system with self-reset function and method
CN109440627A (en) A kind of precast segment assembly seam system and method based on early strong UHPC
CN206174195U (en) Assembled concrete shear force wall split, assemble connection structure
CN102808414B (en) Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
CN106894587A (en) Precast stair connection method
CN207714114U (en) A kind of prefabricated high-strength concrete bridge pier
CN105369987A (en) Steel bar lap joint structure containing FRP constraint ring
CN102808422A (en) Bonded post-tensioned prestressed construction method for cast-in-place reinforced concrete structure
EP3744921B1 (en) Intermediate anchor for a post-tensioning tendon
CN109853362A (en) A kind of interim prestress anchoraging prefabricated bent cap of segmentation and interim method for applying prestressing force
CN110700439B (en) Prefabricated assembly type shear wall rapid formwork erecting connection construction method
CN108442227A (en) One kind preventing deck crack hollow slab bridge structure and attaching method thereof
CN110295552A (en) A kind of gate-type assembled box culvert and construction method
CN205259460U (en) Extrusion sleeve leads nipple
CN207582460U (en) A kind of super-large diameter splices hollow pile
CN208981316U (en) Variable-section steel pipe concrete column structure is connect on a kind of steel core concrete column
CN205116564U (en) Bar splicing connection structure who contains FRP confinement ring
CN205918129U (en) A cast -in -place section template reinforced structure for prefabricated concrete structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180126

Termination date: 20200822

CF01 Termination of patent right due to non-payment of annual fee