CN106289192A - 光伏电站支架灌注桩定位方法 - Google Patents

光伏电站支架灌注桩定位方法 Download PDF

Info

Publication number
CN106289192A
CN106289192A CN201610622288.5A CN201610622288A CN106289192A CN 106289192 A CN106289192 A CN 106289192A CN 201610622288 A CN201610622288 A CN 201610622288A CN 106289192 A CN106289192 A CN 106289192A
Authority
CN
China
Prior art keywords
bored concrete
concrete pile
extra
line
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610622288.5A
Other languages
English (en)
Inventor
杨杰
邓忠
黄利银
莫小飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Sichuan Engineering Corp Ltd
Original Assignee
Sichuan Electric Power Engineering No 3 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Electric Power Engineering No 3 Co Ltd filed Critical Sichuan Electric Power Engineering No 3 Co Ltd
Priority to CN201610622288.5A priority Critical patent/CN106289192A/zh
Publication of CN106289192A publication Critical patent/CN106289192A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明光伏电站支架灌注桩定位方法,属于建筑测绘领域。目的是提供一种简单、快捷的光伏电站支架灌注桩定位方法。包括以下步骤:1)根据设计图纸提供的坐标确定控制点;2)以控制点为基准,利用全站仪放出1号外侧灌注桩、2号外侧灌注桩、3号外侧灌注桩和4号外侧灌注桩的平面位置;3)以外侧灌注桩的平面位置为基准,放出内侧灌注桩的平面位置;4)检验灌注桩间的间距。该光伏电站支架灌注桩定位方法定位程序更简单,从而定位速度得到提高,同时,利用全站仪工作,减少了测量人工的投入。

Description

光伏电站支架灌注桩定位方法
技术领域
本发明属于建筑测绘技术领域,具体的是光伏电站支架灌注桩定位方法。
背景技术
光伏电站项目通常在每年的下半年开工,12月完工,施工周期基本为3个多月,开工时间晚,竣工时间短。光伏电站施工流程为:灌注桩施工→支架安装→光伏组件安装→汇流箱安装→逆变、箱变安装→电缆敷设→接线。灌注桩施工决定施工工期的长短和支架、光伏组件的安装质量。而光伏组件支架钢管灌注桩施工包括测量定位→钻孔→浇筑三道工序。
目前,光伏组件支架钢管灌注桩的测量定位施工方法通常为:首先,采用全站仪放出组串的中轴线;接着,依据设计图纸以及厂家资料给出的尺寸,用皮尺从中轴线往两边放出组串4个角处灌注桩的平面位置;然后,再用皮尺放出其余灌注桩的平面位置;最后,用水平仪进行高程调整。该种定位放线方法有三个缺点:
1)定位放线程序较繁琐,采用4-5人进行施工;
2)容易产生对角线偏差较大,难以控制;
3)定位放线速度较缓慢。
发明内容
本发明所要解决的技术问题是提供一种简单、快捷的光伏电站支架灌注桩定位方法。
本发明采用的技术方案是:光伏电站支架灌注桩定位方法,所述灌注桩包括外侧灌注桩和内侧灌注桩,所述外侧灌注桩包括1号外侧灌注桩、2号外侧灌注桩、3号外侧灌注桩和4号外侧灌注桩;所述1号外侧灌注桩、2号外侧灌注桩、3号外侧灌注桩和4号外侧灌注桩分布于组串的四个角;所述内侧灌注桩位于1号外侧灌注桩、2号外侧灌注桩、3号外侧灌注桩和4号外侧灌注桩围成的四边形内;包括以下步骤:
1)根据设计图纸提供的坐标确定控制点;
2)以控制点为基准,利用全站仪放出1号外侧灌注桩、2号外侧灌注桩、3号外侧灌注桩和4号外侧灌注桩的平面位置;
3)以外侧灌注桩的平面位置为基准,放出内侧灌注桩的平面位置;
4)检验灌注桩间的间距。
进一步的,步骤2)中,待放出外侧灌注桩的平面位置后,由1号外侧灌注桩至2号外侧灌注桩拉第一横向定位线,由3号外侧灌注桩至4号外侧灌注桩拉第二横向定位线;由2号外侧灌注桩至3号外侧灌注桩以及1号外侧灌注桩至4号外侧灌注桩拉纵向定位线。
进一步的,步骤3)中,拉辅助纵向定位线,所述辅助纵向定位线与第一横向定位线和第二横向定位线相交,辅助纵向定位线与第一横向定位线和第二横向定位线相交的交汇点即为内侧灌注桩的平面位置。
进一步的,在步骤4)中,灌注桩的间距包括相1号外侧灌注桩与4号外侧灌注桩之间、2号外侧灌注桩与3号外侧灌注桩之间以及邻灌注桩间之间的距离。
进一步的,所述第一横向定位线和第二横向定位线、纵向定位线和辅助纵向定位线为迪尼玛线。
本发明的有益效果是:该光伏电站支架灌注桩定位方法的定位依据为控制点,与传统的定位依据为中轴线相比,由于控制点仅需测设一个点,而要确定一条中轴线至少需要测设两个点,因此,节约了定位依据的确定时间;并且,由于一条中轴线上有很多点,在以中轴线为依据,定位组串四个角的灌注桩的平面位置时,通常是通过测量灌注桩的平面位置到中轴线的垂直距离,然而,满足到中轴线垂直距离一定的点有很多,无法通过中轴线直接得到灌注桩的平面位置。而以控制点为依据,通过全站仪可以同时灌注柱的平面位置与控制点的距离,以及灌注桩与控制点的角度关系,从而确定灌注桩的准确位置,定位程序更简单,定位速度得到提高,同时,利用全站仪工作,减少了测量人工的投入。
附图说明
图1为该发明的示意图。
图中,内侧灌注桩1,1号外侧灌注桩21、2号外侧灌注桩22、3号外侧灌注桩23、4号外侧灌注桩24、全站仪、第一横向定位线41、第二横向定位线42、纵向定位线43、辅助纵向定位线44
具体实施方式
下面结合附图和实施例对本发明做进一步的说明如下:
光伏电站支架灌注桩定位方法,所述灌注桩包括外侧灌注桩和内侧灌注桩1,所述外侧灌注桩包括1号外侧灌注桩21、2号外侧灌注桩22、3号外侧灌注桩23和4号外侧灌注桩24;所述1号外侧灌注桩21、2号外侧灌注桩22、3号外侧灌注桩23和4号外侧灌注桩24分布于组串的四个角;所述内侧灌注桩1位于1号外侧灌注桩21、2号外侧灌注桩22、3号外侧灌注桩23和4号外侧灌注桩24围成的四边形内;包括以下步骤:
1根据设计图纸提供的坐标确定控制点;
2以控制点为基准,利用全站仪放出1号外侧灌注桩21、2号外侧灌注桩22、3号外侧灌注桩23和4号外侧灌注桩24的平面位置;
3以外侧灌注桩的平面位置为基准,放出内侧灌注桩1的平面位置;
4检验灌注桩间的间距。
该光伏电站支架灌注桩定位方法,通过全站仪根据设计图纸提供的坐标放出控制点;控制点作为放线的依据;以外侧灌注桩与控制点的相对位置关系,定出外侧灌注桩的平面位置;所谓外侧灌注桩的平面位置即为外侧灌注桩在地表面的正投影;然后,再根据内侧灌注桩与已经定位完成的外侧灌注桩的相对位置关系,定位内侧灌注桩的位置;最后复核灌注桩的间距。
该光伏电站支架灌注桩定位方法的定位依据为控制点,与传统的定位依据为中轴线相比,由于控制点仅需测设一个点,而要确定一条中轴线至少需要测设两个点,因此,节约了定位依据的确定时间;并且,由于一条中轴线上有很多点,在以中轴线为依据,定位组串四个角的灌注桩的平面位置时,通常是通过测量灌注桩的平面位置到中轴线的垂直距离,然而,满足到中轴线垂直距离一定的点有很多,无法通过中轴线直接得到灌注桩的平面位置。而以控制点为依据,通过全站仪可以同时灌注柱的平面位置与控制点的距离,以及灌注桩与控制点的角度关系,从而确定灌注桩的准确位置,定位程序更简单,定位速度得到提高,同时,利用全站仪工作,减少了测量人工的投入。
优选的,步骤2中,待放出外侧灌注桩的平面位置后,由1号外侧灌注桩21至2号外侧灌注桩22拉第一横向定位线41,由3号外侧灌注桩23至4号外侧灌注桩24拉第二横向定位线42;由2号外侧灌注桩22至3号外侧灌注桩23以及1号外侧灌注桩21至4号外侧灌注桩24拉纵向定位线43。
第一横向定位线41、第二横向定位线42和纵向定位线43起到标识的作用,表示该处已经测量定位完成,而第一横向定位线41、第二横向定位线42与纵向定位线43的4个交汇点即为1号外侧灌注桩21、2号外侧灌注桩22、3号外侧灌注桩23和4号外侧灌注桩24的安装位置;同时,用于指导后期的施工灌注桩安装孔,使外侧灌注桩安装孔的中心与第一横向定位线41、第二横向定位线42与纵向定位线43的交汇点重合,还可以起到检测内侧灌注桩1的平面位置的作用。
优选的,步骤3中,拉辅助纵向定位线44,所述辅助纵向定位线44与第一横向定位线41和第二横向定位线42相交,辅助纵向定位线44与第一横向定位线41和第二横向定位线42相交的交汇点即为内侧灌注桩1的平面位置。
辅助纵向定位线44起到标识内侧灌注桩1平面位置的作用。辅助纵向定位线44、第一横向定位线41、第二横向定位线42和纵向定位线43还便于在准确钻灌注桩安装孔时复查灌注桩的平面位置的作用。
优选的,在步骤4中,灌注桩的间距包括相1号外侧灌注桩21与4号外侧灌注桩24之间、2号外侧灌注桩22与3号外侧灌注桩23之间以及邻灌注桩间之间的距离。
检测对角线上灌注桩的距离,使对角线偏差控制在10mm以内,使灌注桩平面投影为标准矩形,有利于提高支架的安装精度。
第一横向定位线41和第二横向定位线42、纵向定位线43和辅助纵向定位线44可以为铅线,优选的,所述第一横向定位线41和第二横向定位线42、纵向定位线43和辅助纵向定位线44为迪尼玛线。
与铅线相比,迪尼玛线强度高、重量轻、易操作且环保。
实施例1:
某一20MW光伏电站,每个组串包括8根支架灌注桩。按原方法进行放线定位,需要投入5名施工人员,需要施工时间为50天。采用该光伏电站支架灌注桩定位方法进行定位,实际投入3名施工人员进行放线定位,31天完成定位放线工作,节约人工费用总计43960元,比预计定位放线工期提前19天。

Claims (5)

1.光伏电站支架灌注桩定位方法,所述灌注桩包括外侧灌注桩和内侧灌注桩(1),所述外侧灌注桩包括1号外侧灌注桩(21)、2号外侧灌注桩(22)、3号外侧灌注桩(23)和4号外侧灌注桩(24);所述1号外侧灌注桩(21)、2号外侧灌注桩(22)、3号外侧灌注桩(23)和4号外侧灌注桩(24)分布于组串的四个角;所述内侧灌注桩(1)位于1号外侧灌注桩(21)、2号外侧灌注桩(22)、3号外侧灌注桩(23)和4号外侧灌注桩(24)围成的四边形内;其特征在于:包括以下步骤:
1)根据设计图纸提供的坐标确定控制点;
2)以控制点为基准,利用全站仪放出1号外侧灌注桩(21)、2号外侧灌注桩(22)、3号外侧灌注桩(23)和4号外侧灌注桩(24)的平面位置;
3)以外侧灌注桩的平面位置为基准,放出内侧灌注桩(1)的平面位置;
4)检验灌注桩间的间距。
2.如权利要求1所述的光伏电站支架灌注桩定位方法,其特征在于:步骤2)中,待放出外侧灌注桩的平面位置后,由1号外侧灌注桩(21)至2号外侧灌注桩(22)拉第一横向定位线(41),由3号外侧灌注桩(23)至4号外侧灌注桩(24)拉第二横向定位线(42);由2号外侧灌注桩(22)至3号外侧灌注桩(23)以及1号外侧灌注桩(21)至4号外侧灌注桩(24)拉纵向定位线(43)。
3.如权利要求2所述的光伏电站支架灌注桩定位方法,其特征在于:步骤3)中,拉辅助纵向定位线(44),所述辅助纵向定位线(44)与第一横向定位线(41)和第二横向定位线(42)相交,辅助纵向定位线(44)与第一横向定位线(41)和第二横向定位线(42)相交的交汇点即为内侧灌注桩(1)的平面位置。
4.如权利要求1-3中任意一项权利要求所述的光伏电站支架灌注桩定位方法,其特征在于:在步骤4)中,灌注桩的间距包括相1号外侧灌注桩(21)与4号外侧灌注桩(24)之间、2号外侧灌注桩(22)与3号外侧灌注桩(23)之间以及邻灌注桩间之间的距离。
5.如权利要求1-3中任意一项权利要求所述的光伏电站支架灌注桩定位方法,其特征在于:所述第一横向定位线(41)和第二横向定位线(42)、纵向定位线(43)和辅助纵向定位线(44)为迪尼玛线。
CN201610622288.5A 2016-08-01 2016-08-01 光伏电站支架灌注桩定位方法 Pending CN106289192A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610622288.5A CN106289192A (zh) 2016-08-01 2016-08-01 光伏电站支架灌注桩定位方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610622288.5A CN106289192A (zh) 2016-08-01 2016-08-01 光伏电站支架灌注桩定位方法

Publications (1)

Publication Number Publication Date
CN106289192A true CN106289192A (zh) 2017-01-04

Family

ID=57664031

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610622288.5A Pending CN106289192A (zh) 2016-08-01 2016-08-01 光伏电站支架灌注桩定位方法

Country Status (1)

Country Link
CN (1) CN106289192A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108827253A (zh) * 2018-03-29 2018-11-16 上海宝冶集团有限公司 雪车雪橇赛道的管道支架的安装及定位测量方法

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003078743A1 (en) * 2002-03-15 2003-09-25 Raunisto Yrjoe Method for alignment of piles or wall profiles
JP2011117803A (ja) * 2009-12-02 2011-06-16 Ohbayashi Corp 鋼管の建入誤差の測定方法、鋼管
CN202969387U (zh) * 2012-12-26 2013-06-05 中建海峡建设发展有限公司 桩孔格构柱定位装置
CN203334279U (zh) * 2013-07-05 2013-12-11 大同泰瑞集团建设有限公司 混凝土灌注桩组合基础桩头定位装置
CN103526747A (zh) * 2013-09-26 2014-01-22 浙江钱塘江水利建筑工程公司 潮汐环境冲击成孔灌注桩施工工法
CN203475418U (zh) * 2013-09-23 2014-03-12 云南建工基础工程有限责任公司 一种辅助灌注桩护筒定位的支架
CN203622615U (zh) * 2013-11-27 2014-06-04 吉林省电力勘测设计院 光伏发电组件支架混凝土灌注桩基础模具
CN104895056A (zh) * 2015-06-02 2015-09-09 杭州江润科技有限公司 防冲刷大直径钻孔灌注桩施工方法
CN204919554U (zh) * 2015-05-11 2015-12-30 广东力特工程机械有限公司 一种光伏螺旋桩定位装置
CN205105148U (zh) * 2015-11-10 2016-03-23 海宁创源太阳能科技有限公司 一种可快速安装的光伏系统支架
CN205249126U (zh) * 2015-12-23 2016-05-18 江苏兆鋆新材料股份有限公司 复合式复合材料光伏支架
CN205249127U (zh) * 2015-12-22 2016-05-18 羲和太阳能电力有限公司 一种光伏组件的预张力安装结构
CN105672882A (zh) * 2016-02-26 2016-06-15 中国一冶集团有限公司 一种光伏支架桩基础成组定位钻孔装置及钻孔方法

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003078743A1 (en) * 2002-03-15 2003-09-25 Raunisto Yrjoe Method for alignment of piles or wall profiles
JP2011117803A (ja) * 2009-12-02 2011-06-16 Ohbayashi Corp 鋼管の建入誤差の測定方法、鋼管
CN202969387U (zh) * 2012-12-26 2013-06-05 中建海峡建设发展有限公司 桩孔格构柱定位装置
CN203334279U (zh) * 2013-07-05 2013-12-11 大同泰瑞集团建设有限公司 混凝土灌注桩组合基础桩头定位装置
CN203475418U (zh) * 2013-09-23 2014-03-12 云南建工基础工程有限责任公司 一种辅助灌注桩护筒定位的支架
CN103526747A (zh) * 2013-09-26 2014-01-22 浙江钱塘江水利建筑工程公司 潮汐环境冲击成孔灌注桩施工工法
CN203622615U (zh) * 2013-11-27 2014-06-04 吉林省电力勘测设计院 光伏发电组件支架混凝土灌注桩基础模具
CN204919554U (zh) * 2015-05-11 2015-12-30 广东力特工程机械有限公司 一种光伏螺旋桩定位装置
CN104895056A (zh) * 2015-06-02 2015-09-09 杭州江润科技有限公司 防冲刷大直径钻孔灌注桩施工方法
CN205105148U (zh) * 2015-11-10 2016-03-23 海宁创源太阳能科技有限公司 一种可快速安装的光伏系统支架
CN205249127U (zh) * 2015-12-22 2016-05-18 羲和太阳能电力有限公司 一种光伏组件的预张力安装结构
CN205249126U (zh) * 2015-12-23 2016-05-18 江苏兆鋆新材料股份有限公司 复合式复合材料光伏支架
CN105672882A (zh) * 2016-02-26 2016-06-15 中国一冶集团有限公司 一种光伏支架桩基础成组定位钻孔装置及钻孔方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙玉才: "《中国电力建设工法汇编(2012年度)上册》", 30 November 2012, 中国电力出版社 *
潘全祥: "根据控制点定位测量", 《施工现场十大员技术管理手册 测量员(第二版)》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108827253A (zh) * 2018-03-29 2018-11-16 上海宝冶集团有限公司 雪车雪橇赛道的管道支架的安装及定位测量方法

Similar Documents

Publication Publication Date Title
CN110375711B (zh) 一种地铁隧道内环网无轨测量施工方法
CN107869249B (zh) 弧形结构高支模施工方法
CN106638318B (zh) 斜拉桥梁端锚固点的定位方法及索导管安装方法
CN105091852A (zh) 一种顶管开挖激光导向测量施工工法
CN111623757A (zh) 带有接收井的长大隧道洞内cpii控制网测量方法
CN109358353B (zh) 一种集电线路基础快速分坑放样方法
CN109000625A (zh) 用于圆形沉井下沉姿态自动测量系统及方法
CN102095401A (zh) 长距离盾构法隧道贯通测量方法
WO2023174439A1 (zh) 一种浅埋隧道洞口大管棚导向墙施工工法
CN112049648B (zh) 一种顶管施工监测控制方法
CN109443327A (zh) 一种测量控制网的布设方法
CN104674860B (zh) 海底隧道中的导线贯通测量方法
CN108360582A (zh) 建筑施工钻孔灌注桩中心精确定位器
CN107630478A (zh) 桩‑土‑锚组合支护体系作用机理的模拟试验装置及方法
CN106289192A (zh) 光伏电站支架灌注桩定位方法
CN109211183A (zh) 长大隧道深竖井边角交会测量方法
CN103628511B (zh) 一种用于桩基护筒的放样投点方法
CN104153353B (zh) 一种利用激光投线仪确定钻孔灌注桩标高的方法
CN208266940U (zh) 建筑施工钻孔灌注桩中心精确定位器
CN102636161B (zh) 利用吊线法测设平面控制点的方法
CN205808407U (zh) 开挖施工辅助装置
CN113865559B (zh) 用于超深竖井自动联系测量的方法
CN110106911A (zh) 一种管廊浅埋暗挖标高控制的方法
CN104612156B (zh) 一种静钻根植桩桩平面位移控制工具的控制方法
CN108978647A (zh) 道路水泥搅拌桩测量定位工具及定位方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 641005 138 Road, Baima Town, Central District, Neijiang, Sichuan

Applicant after: Sichuan Power Construction Third Engineering Co.,Ltd.

Address before: 641005 138 street, Baima Town, Shizhong District, Neijiang, Sichuan

Applicant before: SICHUAN NO.3 ELECTRIC POWER CONSTRUCTION Co.

CB02 Change of applicant information
TA01 Transfer of patent application right

Effective date of registration: 20180802

Address after: 610058 38 Huai Shu Dian Road, Chenghua District, Chengdu, Sichuan

Applicant after: POWERCHINA SICHUAN ENGINEERING Co.,Ltd.

Address before: 641005 138 Road, Baima Town, Central District, Neijiang, Sichuan

Applicant before: Sichuan Power Construction Third Engineering Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20170104