Prior art keywords
hole
top board
directional
wear
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610770283.7A
Other languages
Chinese (zh)
Other versions
CN106285477B (en
Inventor
李泉新
方俊
许超
刘建林
曹明
赵建国
王四
王四一
王鲜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Research Institute Co Ltd of CCTEG
Original Assignee
Xian Research Institute Co Ltd of CCTEG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Research Institute Co Ltd of CCTEG filed Critical Xian Research Institute Co Ltd of CCTEG
Priority to CN201610770283.7A priority Critical patent/CN106285477B/en
Publication of CN106285477A publication Critical patent/CN106285477A/en
Application granted granted Critical
Publication of CN106285477B publication Critical patent/CN106285477B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B10/00Drill bits
    • E21B10/26Drill bits with leading portion, i.e. drill bits with a pilot cutter; Drill bits for enlarging the borehole, e.g. reamers
    • E21B10/32Drill bits with leading portion, i.e. drill bits with a pilot cutter; Drill bits for enlarging the borehole, e.g. reamers with expansible cutting tools
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/06Deflecting the direction of boreholes
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention relates to a kind of underground coal mine adopt gas pumping top board and face upward and wear a layer directional hole construction method.The present invention utilizes and treats that mining face Adjacent Working Face has dug the drill site in intake, utilize the equipment such as guide's directional tool and impact compound expanding drill tool, use the compound chambering process of multi-stage rotary chambering process, slip directional drilling technique, compound directional drilling technique and impact to creep into obtain top board and face upward and wear a layer directional hole, make it enter in advance in top board mining induced fissure band and absciss layer district, and distance major diameter extends.After drilling construction, when mining face back production, roof strata by mining influence formed on face upward with top board to crack and to wear a layer directional hole and connect, adopt the raw gas of movable property to enter top board and face upward and wear a layer directional hole, thus realize adopting gas pumping and utilize, solve and currently adopt the deficiency such as aperture little, fissure zone extended distance is short, drilling efficiency is low, cost is high, long construction period that mash gas pumping drilling exists, improve and adopt gas pumping effect.

Description

Underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method
Technical field
The present invention relates to a kind of directional hole construction method and equipment, belong to underground coal mine tunnel drilling field, specifically relate to And a kind of underground coal mine adopts gas pumping top board and faces upward and wear a layer directional hole construction method.
Background technology
Coal mine gas disaster is one of main security disaster during mine construction and mining production, and its destructiveness is huge Greatly, the biggest hidden danger and loss are brought to Safety of Coal Mine Production.In recent years, this coal-bed gas pre-extraction technology significantly reduces work Making face coal seam gas-bearing capacity, but be as the development of colliery fully mechanized coal winning technology, the advance of the face is accelerated, during exploitation Gas emission sharply increases, and becomes the key factor restricting some mine safety high-efficiency mining.
Major part mine uses caving method management roof at present, after seam mining, at goaf overlying rock section On there is caving zone, fissure zone and warp damage the most successively, plane exists successively rib support the zone of influence, absciss layer District, again compacting zone.Wherein there are two class cracks in fissure zone and absciss layer district: a class is bedseparated fissures, is to exist with rock depression Layer and interlayer occur along slabbing gap, it makes coal seam generation dilatancy make gas release, and makes gas pressure relief gush along absciss layer Go out;Another kind of for vertical disrumpent feelings crack, it is to wear slabbing gap with the disrumpent feelings formation of rock depression, it defines between upper and lower rock stratum watt The passage of this flowing.Under the common effect of gas and atmospheric density difference and goaf air leaking so that face upper corner angle is attached The substantial amounts of high concentration gas of populated with in nearly goaf top plate crack.Effect and atmospheric pressure change situation in ventilation negative pressure Under, the gas of roof fracture band storage may increase logical by fire dam or entrance exploiting field, coal column crack or mine laneway Wind burden and unsafe factor.
Grow theoretical, gas migration rule for goaf top plate and gas pumping need, domestic carry out numerous studies, Define high-order goaf gas down-hole, lane pumping method, define high-order lane and two kinds of goaf gas down-holes of High Position Drilling are taken out Mining method, but high-order lane is owing to excavation cost is high, long construction period, and its Technique Popularizing is subject to certain restrictions;High Position Drilling exists A lot of mining area such as China Yangquan, Shenyang, iron processes, Huainan all carries out overtesting, and achieves good effect, but due to it not Possesses drilling track observation and control ability, it is impossible to guaranteeing that drilling track extends at goaf fissure zone, drilling depth is shallow and effective hole section Short, area coverage is little, and aperture is little, and quantities is big, and drilling efficiency is low, and long construction period and high in cost of production are not enough, efficient to ore deposit side Mine and bring certain resistance.
Therefore, the present invention combines minery and goaf gas extraction needs during seam mining, for current colliery Deficiency that down-hole High Position Drilling drilling method exists, a kind of underground coal mine of research design is adopted gas pumping top board and is faced upward and wear layer Directional hole construction method, overcomes drawbacks described above.
Summary of the invention
It is an object of the invention to for current underground coal mine adopt mash gas pumping drilling have that aperture is little, fissure zone extend away from From deficiencies such as short, drilling efficiency is low, cost is high, long construction periods, it is provided that a kind of underground coal mine is adopted on gas pumping top board Face upward and wear a layer directional hole construction method.
The above-mentioned technical problem of the present invention is mainly addressed by following technical proposals:
A kind of underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, including:
The Seam Mining fissure zone determined is analyzed in utilization and Cai Dong absciss layer district design top board is faced upward and worn the boring of floor directional hole Track;
Before working face extraction, treat that the Adjacent Working Face of mining face has dug intake according to described drilling track in down-hole In the coal seam of interior drill site, perforate top board of constructing are faced upward and are worn a layer directional hole, after overlying roof strata, enter mining induced fissure band And distance extends;
In the range of working face extraction to top board is faced upward and worn layer directional hole, utilize top board to face upward and wear a layer directional hole extraction and adopt The gas produced;Working face extraction to top board is faced upward after wearing beyond layer directional hole scope, stops extraction.
Optimizing, above-mentioned a kind of underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, described Top board is faced upward and is worn a layer directional hole and include:
From coal seam perforate to getting out the collar aperture section of facing upward in coal seam, perforate inclination angle is 12-20 °, enters fixed sleeving under being used for And moving casing, wherein, fixed sleeving internal diameter >=200mm, moving casing external diameter≤150mm;
From getting out coal seam to the directional inclination hole section entered between mining induced fissure band, its bending strength≤1 °/3m;
The orientation hold angle hole section extended along mining induced fissure band distance, its inclination angle >=0 °.
Optimizing, above-mentioned a kind of underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, described Top board face upward and wear layer directional hole construction quantity and be several and arrange in beaming type in the plane, and each top board is faced upward and is worn Layer directional hole is arranged in parallel between the orientation hold angle hole section that mining induced fissure band distance extends, adjacent spacing of wells 7m-10m, Orient hold angle hole section and treat that mining face has dug the distance >=15m of return aircourse, and being positioned at Cai Dong absciss layer district.
Optimizing, above-mentioned a kind of underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, described Distance between drill site is that top board is faced upward and worn the level of the orientation hold angle hole section that layer directional hole extends along mining induced fissure band distance Projected length.
Optimizing, above-mentioned a kind of underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method,
The construction of revolution chambering process, reaming step by step is used when coal seam perforate to the collar aperture section of facing upward getting out coal seam is constructed Entering sealing of hole sleeve pipe under after completing, then the annular gap from sealing of hole sleeve pipe Yu hole wall is inserted into exhaustor and Grouting Pipe, then uses The extra quality sealing material of rapid hardening polyurethane and Gypsum Fibrosum closed orifices annular gap, inject cement after gypsum sets in Grouting Pipe Slurry;Stop slip casting when exhaustor there being cement mortar flow out, wait solidifying some hours.
Guide's directional tool is used to use from getting out coal seam to the directional inclination hole section entered between mining induced fissure band Slip directional drilling technique carries out guide's directional hole construction;
Guide's directional tool is used to use compound directional drilling along the orientation hold angle hole section that mining induced fissure band distance extends Technique carries out guide's directional hole construction.
Optimizing, above-mentioned a kind of underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, guide Directional hole drilling diameter 120mm and carry out hole-enlarging hole-forming construction after reaching projected depth, uses impact compound expanding drill tool, adopts With the compound chambering process of impact, hole-enlarging hole-forming diameter >=200mm, reaming, to after at the bottom of hole, carries brill.
Optimizing, above-mentioned a kind of underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, described Guide's directional tool include being sequentially connected with rock stratum lead bit, level Four curved housing screw motor, non-magnetic drilling tool, unidirectional cutoff The outer flush drill stem of pipe nipple, hollow, rotation water feeder;Wherein: described level Four curved housing screw motor uses water under high pressure to drive, head band There is certain angle of bend;It is fixed with aquapulse measurement while-drilling instrument in described non-magnetic drilling tool, can measure in real time in drilling process Drilling track, and utilize and creep into and transmit signals to aperture with water under high pressure, it is thus achieved that boring drilling trajectory;Peace in unidirectional cutoff pipe nipple Equipped with inlet non return check valve.
Optimizing, above-mentioned a kind of underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, described Impact compound expanding drill tool include: the guider that is sequentially connected with, spiral reaming bit, straight-through screw motor, hydraulic impacter, The outer flush drill stem of centralizer, unidirectional cutoff pipe nipple, hollow, rotation water feeder;Wherein guider top is spherical structure, and surrounding milling is washed There is spiral wing, and welding-on has hard alloy gauge;Straight-through screw motor uses water under high pressure to drive, and angle of bend is 0 °, directly Logical have the external diameter of regulator, regulator and centralizer less than outside spiral reaming bit between screw motor elbow and motor assembly Footpath.
Therefore, the present invention utilizes and treats drill site in mining face return aircourse, establishes multi-stage rotary chambering process, slides and determine Creep into top board to the compound chambering process of drilling process, compound directional drilling technique and impact and corresponding construction equipment to face upward and wear layer The technical scheme of directional hole, it is achieved that major diameter directional drilling construction in top board mining induced fissure band and absciss layer district, and distance is big Diameter extends, and significantly improves and adopts gas pumping effect, and the safe and efficient back production in safeguard work face has the advantage that (1) is treating Can construct at a distance in Adjacent Working Face intake before mining face return aircourse is non-through, save work to be adopted The face back production preparatory period;(2) drilling diameter is big, and drilling efficiency is high;(3) boring area coverage is big, and probing workload is little, Shao Liangding Plate is faced upward and is worn layer directional hole and can realize work surface mined out gas region extraction;(4) add boring mining induced fissure band and from Effective hole section in floor district, improves boring utilization rate;(5) upper adjacent layers gas can be carried out extraction, to top board geology simultaneously Structure carries out detecting, carrying out unrestrained to top board water content.
Accompanying drawing explanation
Fig. 1 is that top board is faced upward and worn a layer directional hole site plan.
Fig. 2 is that top board is faced upward and worn a layer directional hole section layout drawing.
Fig. 3 is that guide's directional tool combines connection diagram.
Fig. 4 is impact compound expanding drill tool combination connection diagram.
Detailed description of the invention
Below by embodiment, and combine accompanying drawing, technical scheme is described in further detail.
In figure, treat that mining face 1, intake 2, return aircourse 3, drill site 4, top board are faced upward and wear layer directional hole 5, adopt and split Gap band 6, Cai Dong absciss layer district 7, rock stratum lead bit 8, level Four curved housing screw motor 9, non-magnetic drilling tool 10, unidirectional cutoff pipe nipple 11, the outer flush drill stem 12 of hollow, rotation water feeder 13, guider 14, spiral reaming bit 15, straight-through screw motor 16, punching of surging Hit device 17, centralizer 18, regulator 19, collar aperture of facing upward section a, directional inclination hole section b, orientation hold angle hole section c.
Embodiment:
Below by embodiment, in conjunction with accompanying drawing, embodiments of the present invention are described in detail.Wherein,
Embodiment:
Seeing Fig. 1, Fig. 2, a kind of colliery underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, its It is characterised by, comprises the following steps:
Step one: drill site 4 prepares.Treat in down-hole the Adjacent Working Face of mining face 1 dug open up in intake 2 multiple Drill site 4, the distance of adjacent drill site 4 is faced upward equal to top board and is worn layer directional hole 5 and orient hold angle hole section c floor projection length.
Step 2: drilling design.Compose according to mine coal seam top board and deposit situation and recovery scheme, use existing modeling to divide The methods such as analysis and theoretical formula method determine roof strata mining overburden Changing Pattern, draw roof strata section after seam mining On fissure zone 6 scope and absciss layer district 7 scope in plane, complete top board and face upward and wear layer directional hole 5 Trajectory Design.
Step 3: collar aperture of facing upward section a is constructed.Collar aperture of facing upward section a uses the construction of revolution chambering process, i.e. first profit step by step Creep into Φ 120mm guide's collar aperture with set pipe construction drilling tool one, then use set pipe construction drilling tool two reaming instead to Φ 153mm, then Use set pipe construction drilling tool three reaming to Φ 215mm.After reaming completes, enter down 9mPVC sealing of hole sleeve pipe, then from PVC sealing of hole Sleeve pipe is inserted into exhaustor and Grouting Pipe with the annular gap of hole wall, and exhaustor is inserted into sleeve bottom, and Grouting Pipe is inserted ring-type Gap, then use the extra quality sealing material of rapid hardening polyurethane and Gypsum Fibrosum closed orifices annular gap, from note after gypsum sets Cement mortar is injected in slurry pipe;Stop slip casting when exhaustor there being cement mortar flow out, wait solidifying 8 hours.
Step 4: guide's directional hole is constructed.Connecting opening arrangement, utilize guide's directional tool to construct, orientation is made Inclined hole section b uses slip directional drilling construction technology, orientation hold angle hole section c to use compound directional drilling construction technology;Guide is fixed To hole drilling diameter 120mm, after reaching projected depth, carry brill.
Step 5: hole-enlarging hole-forming.Utilize impact compound expanding drill tool combination to construct, use the compound reaming work of impact Skill, hole-enlarging hole-forming diameter >=200mm, reaming, to after at the bottom of hole, carries brill.
Step 6: the complete hole of sleeve pipe.Under enter movable steel sleeve pipe to entering rock stratum 3m, connect aperture gas pumping device.
Step 7: region overlay.Repeat step 3~step 6, complete to treat on whole top boards of all drill sites of mining face 14 Face upward and wear layer directional hole 5, cover and treat mining face 1 return side absciss layer district 7.
Step 8: adopt gas pumping.Working face extraction to top board is faced upward in the range of wearing layer directional hole 5, utilizes on top board Face upward and wear layer directional hole 5 extraction and adopt the gas that movable property is raw;Working face extraction to top board is faced upward after wearing beyond layer directional hole 5 scope, stops Only extraction, movable steel sleeve pipe in extraction hole.
Described top board is faced upward and is worn perforate of facing upward from coal seam on layer directional hole 5 section, after overlying roof strata, enters Enter mining induced fissure district and distance extends;Collar aperture section a of facing upward, directional inclination hole section b, orientation hold angle hole section c tri-can be divided into Point.Collar aperture of wherein facing upward section a refers to from coal seam perforate to the hole section got out between coal seam, perforate inclination angle 12~20 °, under enter one Level fixed sleeving and one-level moving casing, fixed sleeving internal diameter >=200mm, moving casing external diameter≤150mm;Directional inclination hole section B is to get out coal seam extremely to enter the hole section between mining induced fissure band 6, hole deviation intensity≤1 °/3m;Orientation hold angle hole section c For the hole section extended along mining induced fissure band 6 distance, inclination angle >=0 °;Top board is faced upward and is worn layer directional hole 5 and lap one another, adjacent drill site The 4 boring laps of splice are the floor projection length sum of collar aperture section a and directional inclination hole section b of facing upward.
Described top board is faced upward and is worn layer directional hole 5 and construct quantity >=3, and particular number is according to treating mining face 1 absciss layer district 7 Width determines;Arrange in beaming type in plane, be arranged in parallel between section c of orientation hold angle hole, adjacent spacing of wells 7m~10m, with Treat that mining face 1 has dug the distance >=15m of return aircourse 3, and be positioned at absciss layer district.
Set pipe construction BHA one described in step 3 is depended on by the outer flush drill stem 12 of Φ 120mm rock stratum lead bit 8 and hollow Secondary connection forms;Described set pipe construction BHA two by Φ 120mm guider, the common reaming bit of Φ 120/153mm and The outer flush drill stem 12 of hollow is sequentially connected with composition;Construction BHA three is by Φ 153mm guider, the common reaming of Φ 153/215mm Drill bit and the outer flush drill stem 12 of hollow are sequentially connected with composition.
Described top board is faced upward to wear and is treated when layer directional hole 5 is constructed that mining face 1 does not starts exploitation, mining induced fissure band 6 and adopting Dynamic absciss layer district 7 is for stablize rock stratum;After drilling construction completes, when mining face 1 back production, work surface top top board is by mining influence Slump ruptures formation mining induced fissure band 6 and Cai Dong absciss layer district 7, faces upward with top board to crack on it is interior and wears layer directional hole 5 and connect, Adopt the raw gas of movable property to ventilate and face upward along crack entrance top board under action of gravity wear layer directional hole 5 at negative pressure extraction, big flow, Thus realize gas pumping and utilize.
Seeing Fig. 3, the guide's directional tool described in step 4 combines by Φ 120mm rock stratum lead bit 8, the curved housing of level Four The outer flush drill stem 12 of screw motor 9, non-magnetic drilling tool 10, unidirectional cutoff pipe nipple 11, hollow, rotation water feeder 13 are sequentially connected with composition, Described Φ 89mm level Four curved housing screw motor 9 uses water under high pressure to drive, and external diameter is Φ 89mm, and angle of bend is 1.25 °, turns round Square >=1000Nm;It is fixed with aquapulse measurement while-drilling instrument in non-magnetic drilling tool 10, boring rail can be measured in drilling process in real time Mark, and utilize and creep into and transmit signals to aperture with water under high pressure, it is thus achieved that boring drilling trajectory, provide reference for directional drilling;Single In cut-off pipe nipple 11, inlet non return check valve is installed, the outer flush drill stem 12 of hollow and top board can be avoided to face upward and wear water in layer directional hole 5 From hollow, flush drill stem 12 flows backwards, and adds one every 100m;Outer flush drill stem 12 external diameter of hollow is Φ 89mm, anti-twisting property >= 35000Nm, resistance to tension >=1500kN.Described slip directional drilling technique refers in drilling process, the outer flush drill stem 12 of hollow Not rotating, level Four curved housing screw motor 9 drives Φ 120mm rock stratum lead bit 8 to turn round detritus towards assigned direction.Described answers Closing directional drilling and refer in drilling process, aperture rig drives the outer flush drill stem 12 of hollow to drive Φ 120mm rock stratum lead bit 8 times While turning detritus, in hole, level Four curved housing screw motor 9 drives Φ 120mm rock stratum lead bit 8 times under water under high pressure drives Turn detritus.
Seeing Fig. 4, the impact compound expanding drill tool described in step 5 combines by guider 14, spiral reaming bit 15, leads directly to The outer flush drill stem 12 of screw motor 16, hydraulic impacter 17, centralizer 18, unidirectional cutoff pipe nipple 11, hollow, rotation water feeder 13 depend on Secondary connection forms;Wherein guider 14 length >=0.4m, external diameter is 110mm, and top is spherical structure, and circular knife has been washed in surrounding milling The wing, and welding-on has hard alloy gauge;Spiral reaming bit 15 external diameters >=200mm;Straight-through screw motor 16 uses high pressure water drive Dynamic, external diameter is 89mm, and angle of bend is 0 °, has regulator 19 between its elbow and motor assembly, the external diameter ratio of regulator 19 The little 1mm of external diameter of spiral reaming bit 15;The external diameter 1mm less than the external diameter of spiral reaming bit 15 of centralizer 18;Unidirectional cutoff Pipe nipple 11 adds one every 100m.Described impact is combined chambering process and refers in reaming procedure, and aperture rig drives and in hole Straight-through screw motor 16 drives and combines, and while spiral reaming bit 15 turns round detritus, in hole, hydraulic impacter 17 drives spiral Reaming bit 15 impacts detritus.
Treat that mining face 1, intake 2, return aircourse 3, drill site 4, top board are faced upward and worn although the most more employing Floor directional hole 5, mining induced fissure band 6, Cai Dong absciss layer district 7, rock stratum lead bit 8, level Four curved housing screw motor 9, non-magnetic drilling tool 10, unidirectional cutoff pipe nipple 11, the outer flush drill stem 12 of hollow, rotation water feeder 13, guider 14, spiral reaming bit 15, straight-through spiral shell Bar motor 16, hydraulic impacter 17, centralizer 18, regulator 19, collar aperture of facing upward section a, directional inclination hole section b, orientation hold angle The terms such as hole section c, but it is not precluded from using the probability of other term.Use these terms to be only used to more easily to describe With the essence explaining the present invention;It is all contrary with spirit of the present invention for being construed as any additional restriction.

Claims (8)

1. a underground coal mine is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, it is characterised in that including:
The Seam Mining fissure zone (6) determined is analyzed in utilization and Cai Dong absciss layer district (7) design top board is faced upward and worn floor directional hole (5) Drilling track;
Before working face extraction, treat that the Adjacent Working Face of mining face (1) has dug intake according to described drilling track in down-hole (2) in the coal seam of interior drill site (4), perforate top board of constructing are faced upward and are worn a layer directional hole (5), and after overlying roof strata, entrance is adopted Dynamic fissure zone (6) distance extend;
In the range of working face extraction to top board is faced upward and worn a layer directional hole (5), utilize top board to face upward and wear a layer directional hole (5) extraction and adopt The gas that movable property is raw;Working face extraction to top board is faced upward after wearing beyond a layer directional hole (5) scope, stops extraction.
A kind of underground coal mine the most according to claim 1 is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, It is characterized in that, described top board is faced upward and is worn a layer directional hole (5) and including:
From coal seam perforate to getting out the collar aperture section of facing upward in coal seam, perforate inclination angle is 12-20 °, enters fixed sleeving and work under being used for Dynamic sleeve pipe, wherein, fixed sleeving internal diameter >=200mm, moving casing external diameter≤150mm;
From getting out coal seam to the directional inclination hole section entered between mining induced fissure band, its bending strength≤1 °/3m;
The orientation hold angle hole section extended along mining induced fissure band distance, its inclination angle >=0 °.
A kind of underground coal mine the most according to claim 1 is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method one Plant down-hole and adopt gas pumping method, it is characterised in that described top board is faced upward and worn a layer directional hole (5) construction quantity is several And arrange in beaming type in the plane, and each top board is faced upward and worn what a layer directional hole (5) extended along mining induced fissure band distance It is arranged in parallel between the section of orientation hold angle hole, adjacent spacing of wells 7m-10m, orient hold angle hole section and treat that mining face (1) is dug back Distance >=the 15m in air way road (3), and it is positioned at Cai Dong absciss layer district (7).
A kind of underground coal mine the most according to claim 1 is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, It is characterized in that, the distance between described drill site (4) be top board face upward wear a layer directional hole (5) along mining induced fissure band distance extend The floor projection length of orientation hold angle hole section.
A kind of underground coal mine the most according to claim 1 is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, It is characterized in that,
Using revolution chambering process construction step by step when coal seam perforate to the collar aperture section of facing upward getting out coal seam is constructed, reaming completes Entering sealing of hole sleeve pipe under Hou, then the annular gap from sealing of hole sleeve pipe Yu hole wall is inserted into exhaustor and Grouting Pipe, then uses rapid hardening The extra quality sealing material of polyurethane and Gypsum Fibrosum closed orifices annular gap, inject cement mortar after gypsum sets in Grouting Pipe;When Stop slip casting when exhaustor having cement mortar flow out, wait solidifying some hours.
Guide's directional tool is used to use slip from getting out coal seam to the directional inclination hole section entered between mining induced fissure band Directional drilling technique carries out guide's directional hole construction;
Guide's directional tool is used to use compound directional drilling technique along the orientation hold angle hole section that mining induced fissure band distance extends Carry out guide's directional hole construction.
A kind of underground coal mine the most according to claim 5 is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, It is characterized in that guide directional hole drilling diameter 120mm and carry out hole-enlarging hole-forming construction after reaching projected depth uses impact Compound expanding drill has, and uses the compound chambering process of impact, hole-enlarging hole-forming diameter >=200mm, and reaming, to after at the bottom of hole, carries brill.
A kind of underground coal mine the most according to claim 5 is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, It is characterized in that, described guide's directional tool includes rock stratum lead bit (8), the level Four curved housing screw motor being sequentially connected with (9), non-magnetic drilling tool (10), unidirectional cutoff pipe nipple (11), the outer flush drill stem (12) of hollow, rotation water feeder (13);Wherein: described four The curved housing screw motor (9) of level uses water under high pressure to drive, and head is with certain angle of bend;Fix in described non-magnetic drilling tool (10) There is aquapulse measurement while-drilling instrument, drilling track can be measured in drilling process in real time, and utilization is crept into signal with water under high pressure It is transferred to aperture, it is thus achieved that boring drilling trajectory;Unidirectional cutoff pipe nipple is provided with inlet non return check valve in (11).
A kind of underground coal mine the most according to claim 6 is adopted gas pumping top board and is faced upward and wear a layer directional hole construction method, It is characterized in that, described impact compound expanding drill tool includes: the guider (14) that is sequentially connected with, spiral reaming bit (15), The outer flush drill stem (12) of straight-through screw motor (16), hydraulic impacter (17), centralizer (18), unidirectional cutoff pipe nipple (11), hollow, Rotate water feeder (13);Wherein guider (14) top is spherical structure, and spiral wing has been washed in surrounding milling, and welding-on has hard to close Gold gauge;Straight-through screw motor (16) uses water under high pressure to drive, and angle of bend is 0 °, straight-through screw motor (16) elbow and horse Reaching and have regulator (19) between assembly, the external diameter of regulator (19) and centralizer (18) is less than outside spiral reaming bit (15) Footpath.
CN201610770283.7A 2016-08-30 2016-08-30 Underground coal mine adopt gas pumping top plate face upward wear layer orientation hole construction method Active CN106285477B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610770283.7A CN106285477B (en) 2016-08-30 2016-08-30 Underground coal mine adopt gas pumping top plate face upward wear layer orientation hole construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610770283.7A CN106285477B (en) 2016-08-30 2016-08-30 Underground coal mine adopt gas pumping top plate face upward wear layer orientation hole construction method

Publications (2)

Publication Number Publication Date
CN106285477A true CN106285477A (en) 2017-01-04
CN106285477B CN106285477B (en) 2018-06-19

Family

ID=57675220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610770283.7A Active CN106285477B (en) 2016-08-30 2016-08-30 Underground coal mine adopt gas pumping top plate face upward wear layer orientation hole construction method

Country Status (1)

Country Link
CN (1) CN106285477B (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869791A (en) * 2017-03-24 2017-06-20 中煤科工集团西安研究院有限公司 Underground coal mine air screw motor is oriented hole drill tool combination and construction method
CN107676078A (en) * 2017-11-03 2018-02-09 中煤科工集团重庆研究院有限公司 Underground coal mine water pulse wireless measurement-while-drilling system and measuring method
CN108180035A (en) * 2018-01-30 2018-06-19 中煤科工集团重庆研究院有限公司 The gas pumping method that high gassy and low permeability coal seam drills with anti-reflection integration of operation
CN108518182A (en) * 2018-04-16 2018-09-11 中煤科工集团西安研究院有限公司 Method and device is put in the advanced region water body spy of the dendritic directional drilling of top plate multi-aquifer
CN108571341A (en) * 2018-04-26 2018-09-25 淮南矿业(集团)有限责任公司 A kind of automatic water drainage device floating ball and preparation method thereof
CN109403867A (en) * 2018-10-15 2019-03-01 西山煤电(集团)有限责任公司 Outburst elimination method is taken out in advance across the progressive pectination drilling driving band of face deep camber is adopted
CN109441349A (en) * 2018-10-31 2019-03-08 淮南矿业(集团)有限责任公司 A kind of gas drainage drilling group and its construction method
CN109899106A (en) * 2019-05-05 2019-06-18 辽宁工程技术大学 A kind of turning long drilled holes the next layer gas pumping method for evading caving zone
CN110173301A (en) * 2019-05-09 2019-08-27 中煤科工集团西安研究院有限公司 Fully mechanized mining goaf grouting method based on cluster type multilateral well directional drilling
CN110259503A (en) * 2019-06-14 2019-09-20 华北理工大学 A kind of expansion rock stratum high position horizontal bore gas pumping method
CN110566120A (en) * 2019-09-11 2019-12-13 中煤科工集团西安研究院有限公司 Multi-power directional combined drilling tool for hard rock of coal mine underground coal seam bottom plate and hole forming method thereof
CN110685734A (en) * 2019-10-24 2020-01-14 中煤科工集团西安研究院有限公司 Panel gas treatment method based on partition step-by-step increasing tree-shaped directional long drilling
CN111485825A (en) * 2020-04-07 2020-08-04 中煤科工集团西安研究院有限公司 Design construction and data processing method for coal face coal rock interface detection directional hole
CN111677447A (en) * 2020-06-17 2020-09-18 平安煤炭开采工程技术研究院有限责任公司 Directional drilling method for upward rock climbing section
CN112160728A (en) * 2020-09-02 2021-01-01 中煤科工集团西安研究院有限公司 Treatment method for mine water exploration and drainage drill hole
CN112682090A (en) * 2020-12-30 2021-04-20 中煤科工集团重庆研究院有限公司 Coal seam drilling interconnection method and system based on impact process and gas extraction method
CN113482701A (en) * 2021-08-16 2021-10-08 淮南矿业(集团)有限责任公司 Gas extraction method for high-position drilling of complex stratum of high-gas working face
CN113586134A (en) * 2021-09-08 2021-11-02 晋能控股山西科学技术研究院有限公司 Method for treating gas by hole-lane-replacement combined drainage on coal seam working face
CN117759159A (en) * 2024-01-05 2024-03-26 中煤科工集团重庆研究院有限公司 Complicated roof major diameter drilling fracturing gas drainage device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6688702B1 (en) * 2002-12-16 2004-02-10 Grigori A. Abramov Borehole mining method
CN101251028A (en) * 2008-04-03 2008-08-27 淮南矿业(集团)有限责任公司 Method for taking out and picking high gassy seam group dislodging gob-side entry retaining Y type ventilated decompression firedamp
CN102031950A (en) * 2010-12-06 2011-04-27 煤炭科学研究总院西安研究院 Hole-forming process method for comb gas extraction borehole in coal seam roof
CN102226413A (en) * 2011-05-24 2011-10-26 中国矿业大学 Gas extraction method of cross hole drilling area of gas discharge laneway
CN103061798A (en) * 2012-12-30 2013-04-24 中北大学 Method for extracting coal bed methane through down-hole bedding long borehole consecutive cave building
CN104775787A (en) * 2015-02-27 2015-07-15 河南工程学院 Hydraulic fracturing crossing hole pitchup hole sealing method of broken surrounding rock
CN104832208A (en) * 2015-03-25 2015-08-12 宁夏煤炭勘察工程公司 Anti-collapse method for long-distance horizontal hole drilling in soft coal seam of underground coal mine

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6688702B1 (en) * 2002-12-16 2004-02-10 Grigori A. Abramov Borehole mining method
CN101251028A (en) * 2008-04-03 2008-08-27 淮南矿业(集团)有限责任公司 Method for taking out and picking high gassy seam group dislodging gob-side entry retaining Y type ventilated decompression firedamp
CN102031950A (en) * 2010-12-06 2011-04-27 煤炭科学研究总院西安研究院 Hole-forming process method for comb gas extraction borehole in coal seam roof
CN102226413A (en) * 2011-05-24 2011-10-26 中国矿业大学 Gas extraction method of cross hole drilling area of gas discharge laneway
CN103061798A (en) * 2012-12-30 2013-04-24 中北大学 Method for extracting coal bed methane through down-hole bedding long borehole consecutive cave building
CN104775787A (en) * 2015-02-27 2015-07-15 河南工程学院 Hydraulic fracturing crossing hole pitchup hole sealing method of broken surrounding rock
CN104832208A (en) * 2015-03-25 2015-08-12 宁夏煤炭勘察工程公司 Anti-collapse method for long-distance horizontal hole drilling in soft coal seam of underground coal mine

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869791A (en) * 2017-03-24 2017-06-20 中煤科工集团西安研究院有限公司 Underground coal mine air screw motor is oriented hole drill tool combination and construction method
CN107676078A (en) * 2017-11-03 2018-02-09 中煤科工集团重庆研究院有限公司 Underground coal mine water pulse wireless measurement-while-drilling system and measuring method
CN108180035A (en) * 2018-01-30 2018-06-19 中煤科工集团重庆研究院有限公司 The gas pumping method that high gassy and low permeability coal seam drills with anti-reflection integration of operation
CN108518182A (en) * 2018-04-16 2018-09-11 中煤科工集团西安研究院有限公司 Method and device is put in the advanced region water body spy of the dendritic directional drilling of top plate multi-aquifer
CN108571341A (en) * 2018-04-26 2018-09-25 淮南矿业(集团)有限责任公司 A kind of automatic water drainage device floating ball and preparation method thereof
CN109403867A (en) * 2018-10-15 2019-03-01 西山煤电(集团)有限责任公司 Outburst elimination method is taken out in advance across the progressive pectination drilling driving band of face deep camber is adopted
CN109441349A (en) * 2018-10-31 2019-03-08 淮南矿业(集团)有限责任公司 A kind of gas drainage drilling group and its construction method
CN109899106A (en) * 2019-05-05 2019-06-18 辽宁工程技术大学 A kind of turning long drilled holes the next layer gas pumping method for evading caving zone
CN110173301B (en) * 2019-05-09 2020-11-24 中煤科工集团西安研究院有限公司 Fully mechanized goaf grouting method based on cluster multilateral well directional drilling
CN110173301A (en) * 2019-05-09 2019-08-27 中煤科工集团西安研究院有限公司 Fully mechanized mining goaf grouting method based on cluster type multilateral well directional drilling
CN110259503A (en) * 2019-06-14 2019-09-20 华北理工大学 A kind of expansion rock stratum high position horizontal bore gas pumping method
CN110566120A (en) * 2019-09-11 2019-12-13 中煤科工集团西安研究院有限公司 Multi-power directional combined drilling tool for hard rock of coal mine underground coal seam bottom plate and hole forming method thereof
CN110685734A (en) * 2019-10-24 2020-01-14 中煤科工集团西安研究院有限公司 Panel gas treatment method based on partition step-by-step increasing tree-shaped directional long drilling
CN110685734B (en) * 2019-10-24 2021-01-29 中煤科工集团西安研究院有限公司 Panel gas treatment method based on partition step-by-step increasing tree-shaped directional long drilling
CN111485825A (en) * 2020-04-07 2020-08-04 中煤科工集团西安研究院有限公司 Design construction and data processing method for coal face coal rock interface detection directional hole
CN111677447A (en) * 2020-06-17 2020-09-18 平安煤炭开采工程技术研究院有限责任公司 Directional drilling method for upward rock climbing section
CN112160728A (en) * 2020-09-02 2021-01-01 中煤科工集团西安研究院有限公司 Treatment method for mine water exploration and drainage drill hole
CN112160728B (en) * 2020-09-02 2023-04-28 中煤科工集团西安研究院有限公司 Treatment method for mine water drainage drilling
CN112682090A (en) * 2020-12-30 2021-04-20 中煤科工集团重庆研究院有限公司 Coal seam drilling interconnection method and system based on impact process and gas extraction method
CN113482701A (en) * 2021-08-16 2021-10-08 淮南矿业(集团)有限责任公司 Gas extraction method for high-position drilling of complex stratum of high-gas working face
CN113586134A (en) * 2021-09-08 2021-11-02 晋能控股山西科学技术研究院有限公司 Method for treating gas by hole-lane-replacement combined drainage on coal seam working face
CN113586134B (en) * 2021-09-08 2024-04-26 晋能控股山西科学技术研究院有限公司 Method for controlling gas by hole-instead-of-lane combined drainage on coal seam working face
CN117759159A (en) * 2024-01-05 2024-03-26 中煤科工集团重庆研究院有限公司 Complicated roof major diameter drilling fracturing gas drainage device

Also Published As

Publication number Publication date
CN106285477B (en) 2018-06-19

Similar Documents

Publication Publication Date Title
CN106285477B (en) Underground coal mine adopt gas pumping top plate face upward wear layer orientation hole construction method
CN102797465B (en) Underground ultra-thin virtual protection layer hydraulic coal mining method
CN113464121B (en) Method for determining gamma geosteering drilling track of azimuth while drilling
CN110397428B (en) Displacement coalbed methane yield increasing method for coalbed methane jointly mined by vertical well and U-shaped butt well
CN105909254B (en) Projecting coal bed bottom plate, which is faced upward, wears the advanced area cover coal roadway tunneling method of layer directional hole
CN104790918B (en) Method for mining coal bed gas from cluster well and horizontal well combined ground under complex terrain condition
CN102392678A (en) Gas drainage method combining surface and underground fracturing and permeability improvement
CN102392677A (en) Permeability improvement technology for coal bed gas reservoir cap by using three-dimensional fracture network modification
CN111963109B (en) Multi-branch horizontal well coal mining goaf gas extraction process
CN102799955B (en) Water bursting coefficient is less than 0.06MPa/m district Water Inrush and evaluates three figure methods
CN104975868A (en) Top plate high-position boring large-diameter long-drill-hole gas extraction method based on directional drilling
CN110067592B (en) Roof gas cooperative control method based on hard roof ground fracturing
CN107620581B (en) Construction method of one-well dual-purpose coal mine shaft inspection hole
CN111827878B (en) Method for quickly and accurately probing hidden water inrush channel of coal seam floor
Li et al. A new pattern of underground space‐time tridimensional gas drainage: a case study in Yuwu coal mine, China
CN110645039A (en) Comprehensive control method for rock burst and gas composite disaster of thick and hard roof
CN104895531A (en) Single thick coal seam ground mining well extraction process
CN112240221B (en) Gas extraction method based on directional long drill hole
CN114294046B (en) Coal mine area full-coverage underground three-dimensional extraction method
CN106285731A (en) The little courtyard radiant type of a kind of high Large chamber and the mixed construction method of step
CN104989330A (en) Coalbed gas recovery method
CN113236340A (en) Method for realizing continuous gas extraction by high-position drilling in working face extraction process
CN109917463A (en) Slip casting working face Water Inrush hazard assessment system based on drill hole information library
CN114439428B (en) Enhanced extraction method for coal bed gas horizontal well of coal group under goaf group
CN215109009U (en) Drilling system for realizing continuous gas extraction in working face extraction process

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant