CN106284976A - A kind of aluminum alloy mould plate based on Revit joins mould method - Google Patents

A kind of aluminum alloy mould plate based on Revit joins mould method Download PDF

Info

Publication number
CN106284976A
CN106284976A CN201610853427.5A CN201610853427A CN106284976A CN 106284976 A CN106284976 A CN 106284976A CN 201610853427 A CN201610853427 A CN 201610853427A CN 106284976 A CN106284976 A CN 106284976A
Authority
CN
China
Prior art keywords
mould
aluminum alloy
joins
revit
mould plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610853427.5A
Other languages
Chinese (zh)
Inventor
李保汀
李浪
林晨毓
邵志峰
郑永坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201610853427.5A priority Critical patent/CN106284976A/en
Publication of CN106284976A publication Critical patent/CN106284976A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/02Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for rooms as a whole by which walls and floors are cast simultaneously, whole storeys, or whole buildings
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of aluminum alloy mould plate based on Revit and join mould method, comprise the following steps: use Revit software, set up parametrization building basal body structure model, set up parametrization aluminum alloy mould plate race file;According to joining mould rule, aluminum alloy mould plate race file is spliced on building basal body structure model according to engineering realistic simulation, form simulation splicing component;Check whether simulation splicing component exists interference, check whether itself and other cross-operation models exist interference, depending on aluminum alloy mould plate race file being optimized design;Statistics aluminum alloy mould plate joins mould model information, generates model component detail list, flat deep cutting three-view diagram and template manuscript.The aluminum alloy mould plate based on Revit that the present invention provides joins mould method, more traditional Auto CAD joins mould method, no longer depending on the three dimensions visionary of operator unduly, aluminum alloy mould plate efficiency with mold is high, accuracy rate is higher, shortens the design cycle of aluminum alloy mould plate.

Description

A kind of aluminum alloy mould plate based on Revit joins mould method
Technical field
The present invention relates to technical field of buildings, particularly relate to a kind of aluminum alloy mould plate based on Revit and join mould method.
Background technology
Aluminum alloy mould plate is a kind of new material, and it has, and construction is quick, convenient, efficiency is high, manually saves with facility, becomes The advantages such as quality is good, security civilization degree is high, integrated cost is low, are the good green formwork systems of a kind of comprehensive benefit.
Along with China's low-carbon environment-friendly, the continuous lifting of green building idea, aluminum alloy mould plate also has wide in China Development space.More traditional plank sheathing and steel form, aluminum alloy mould plate is with the obvious advantage.
At present, aluminum alloy mould plate is in the stage of promoting the use of, and the template configuration design majority of current aluminum alloy pattern plate uses The CAD design of conventional two-dimensional, comparatively laborious, easily to make mistakes, flat, vertical, profile conversion complexity, efficiency with mold is the highest;Furthermore, this After job demand designer possesses stronger three dimensions imaginative power, and aluminum alloy mould plate joins mould, check that difficulty is relatively big, meter Calculation process is complicated, the problems such as template conflict or dimensional error easily occurs, and aluminum alloy mould plate is joined mould accuracy and cannot be ensured, needs Expend designer's great effort.
And by combining BIM technology, utilize the three-dimensional visualization of Revit software, publishing picture property, flat deep cutting bumpless transfer with And the advantage such as quantities Information Statistics are fast, aluminum alloy mould plate can be greatly improved joins mould design degree of accuracy and work efficiency.
Therefore, need a kind of suitable aluminum alloy mould plate based on Revit of design badly and join mould method, improve efficiency with mold and just join mould Really rate.
Summary of the invention
It is an object of the invention to for above-mentioned technical problem, it is provided that a kind of aluminum alloy mould plate based on Revit joins mould side Method, more traditional Auto CAD joins mould method, no longer depends on the three dimensions visionary of operator unduly, has aluminium alloy The advantage that Compound of the formworks efficiency is high, and aluminum alloy mould plate to join mould accuracy rate higher, shorten the process-cycle of aluminum alloy mould plate.
Technical scheme
For solving above-mentioned technical problem, the aluminum alloy mould plate based on Revit that the present invention provides joins mould method, including following step Rapid:
S1, uses Revit software, sets up parametrization building basal body structure model;
S2, uses Revit software, sets up parametrization aluminum alloy mould plate race file;
S3, according to joining mould rule, splices aluminum alloy mould plate race file at building basal body structure mould according to engineering realistic simulation In type, form simulation splicing component;
S4, checks whether simulation splicing component exists interference, and checks whether are simulation splicing component and other cross-operation models Exist and interfere, depending on aluminum alloy mould plate race file being optimized design;
S5, statistics aluminum alloy mould plate joins mould model information, and generates model component detail list, puts down, stands, cuts open three-view diagram and template adds Work figure.
Further, in step sl, building basal body structure model include the absolute altitude of building, floor height, axle net, wall, Post, beam, plate, stair.
Further, in step sl, including the secondary structure design to building basal body structure model.
Further, in step s 2, the parameter of aluminum alloy mould plate race file include the length of aluminum alloy mould plate, width, Highly, material.
Further, in step s 2, aluminum alloy mould plate race file is set up on same benchmark job face.
Further, in step s3, described in join mould rule and include joining mould order and computation rule, described in join mould rule and relate to And aluminum alloy pattern plate, support system join mould.
Further, described aluminum alloy pattern plate includes plane template, corner formwork, and wherein plane template includes wall column formwork, beam Template die plate and undertaking template;Described support system includes early-dismantling device, adjustable steel support.
Further, its join mould order join mould for wall column formwork, adjustable steel support joins mould, beam-slab template joins mould, stair mould Mould joined by plate and other accessories join mould.
The method have the benefit that
The aluminum alloy mould plate based on Revit that the present invention provides joins mould method, has the advantages that
(1) join mould degree of accuracy to improve, join mould increased quality
Tradition CAD two dimension is joined mould drawing and is become more solid image by the present invention, and the peace mode of tearing open for complex node becomes more Add visual and clear.On the one hand greatly reducing the level requirement that template peace is torn open personnel, the peace reducing form work engineering splits into this; On the other hand can reduce complex node and design the risk made mistakes, it is to avoid rejection and waste material;And it is more traditional to join mould accuracy rate CAD join mould and improve a lot.
(2) speed of publishing picture is fast, and efficiency is high
Tradition CAD joins after mould figure completes, and still needs to repaint each template in-depth manuscript by calculating, the most loaded down with trivial details, and pole Error-prone.And Revit joins Mo Tu and directly can generate template flat deep cutting manuscript according to race's file detail drawing, remove from and repaint ring Joint, also improves efficiency.According to existing aluminum alloy mould plate race file, efficiency with mold joins mould compared to tradition CAD, effect of publishing picture Rate can improve more than 1 times.
(3) quantities statistics is accurately
The aluminum alloy pattern plate quantities accurate count difficult problem that always puzzlement aluminum alloy pattern plate is promoted the use of because CAD join mould drawing cannot be right Template area is directly added up, and is all to be processed drawing by aluminum alloy pattern plate designer, works out aluminum alloy pattern plate outbound inventory, logical Cross outbound inventory and determine that aluminum alloy pattern plate purchases area.Owing to aluminum alloy pattern plate area is excessive, aluminum alloy pattern plate substantial amounts, cause checking work pole Difficulty is carried out, and final checked result accuracy is the highest.BIM threedimensional model can carry out all-round statistics by detail list function, really Fixed each specification aluminum alloy pattern plate quantity and area.On the one hand provide convenient for project templet quantities statistics, it is also possible to by project Aluminum alloy pattern plate list is uploaded to aluminum alloy pattern plate and enters, deposits, sells platform, accurate count projects lease aluminum alloy pattern plate area, gives back area, Reach company's target to aluminum alloy pattern plate fine-grained management.
(4) aluminum dipping form use cost is reduced
If aluminum alloy pattern plate has enough to meet the need between disparity items, turnover scheme is dominated by aluminum alloy pattern plate producer.On the one hand, CAD Join mould figure thorough to changing plate program analysis, and producer provide to change plate scheme the most most economical the most reasonable;On the other hand, newly Old CAD joins mould figure Accurate Analysis cannot change plate gauge lattice and quantity, so the template area data of aluminum alloy pattern plate producer offer is accurate Property cannot be verified.Independently join mould can effectively take on a new look the monopoly position of aluminum dipping form producer, greatly aluminum dipping form is had enough to meet the need expense transparence.
(5) virtual preassembling, time-consuming, cost-effective
The present invention simulates preassembling process, can complete aluminum alloy pattern plate preassembling by threedimensional model and structural drawings being compared Work, can check assembled situation in advance.Both shortened the duration, and also saved preassembling levelling of the land expense simultaneously and peace tears expense open With.Joining mold process to generate in computer completely, Meteorological is few, and particularly after setting up race, similar engineering can be applied mechanically, after The time of continuous Engineering Modeling is greatly shortened.
(6) scope is expanded wide
Utilize three-dimensional to join the model that mould generates, utilize its model characteristics, Virtual Construction, Digital manufacturing, quality can be extended to The aspects such as safety management, for construction management service.
(7) architecture information and the requirement of industrialization trend are met
Aluminum alloy mould plate is joined mould design and is realized by BIM technology, is consistent with the megatrend of construction industry development, embodies architecture information Change and industrialized feature, improve science decision and management level, promote fine-grained management.
Accompanying drawing explanation
By the detailed description made in conjunction with the following drawings, advantage of the present invention will be apparent from and be easier to reason Solving, these accompanying drawings the most schematically, are not limiting as the present invention, wherein:
Fig. 1 is the flow chart of the present invention;
Fig. 2 is Compound of the formworks schematic diagram;
Fig. 3 is that body of wall joins mould precedence diagram;
Fig. 4 is that support system joins mould precedence diagram;
Fig. 5 is that beam forms joins mould precedence diagram;
Fig. 6 is that floorboard joins mould precedence diagram;
Fig. 7 is that mould precedence diagram joined by stair.
Detailed description of the invention
Below in conjunction with specific embodiments and the drawings, a kind of based on Revit aluminum alloy mould plate of the present invention is joined mould method to enter Row describes in detail.
The embodiment recorded at this is the specific detailed description of the invention of the present invention, for the design of the present invention being described, all It is explanatory and exemplary, should not be construed as the restriction to embodiment of the present invention and the scope of the invention.Except record at this Outside embodiment, those skilled in the art can also based on the application claims and description disclosure of that use aobvious and Other technical scheme being clear to, these technical schemes include use to the embodiment recorded at this make any obviously The technical scheme of substitutions and modifications.
The accompanying drawing of this specification is schematic diagram, aids in illustrating the design of the present invention, it is schematically indicated the shape of each several part And mutual relation.Note that the structure of each parts for the ease of clearly showing the embodiment of the present invention, between each accompanying drawing Do not draw according to identical ratio.Identical reference marker is used for representing identical part.
Fig. 1 is the flow chart that a kind of aluminum alloy mould plate based on Revit joins mould method.One its specifically include following steps:
S1, uses Revit software, sets up parametrization building basal body structure model;
In this step, building basal body structure model is set up in the Revit groupware, including the absolute altitude of building, floor height, The primitive information such as axle net, wall, post, beam, plate, stair;And the employing of different structure component information is made a distinction without color, prominent Display aluminum alloy mould plate primitive information.
In this step, it includes that the secondary structure to building basal body structure model designs, and takes one-shot forming as far as possible Pour mode, to facilitate building engineering construction.
S2, uses Revit software, sets up parametrization aluminum alloy mould plate race file;
In this step, the parameter of aluminum alloy mould plate race file include the length of aluminum alloy mould plate, width, highly, material, aluminum close Gold template race file is set up on same benchmark job face.
The Revit groupware is set up, including arrange aluminum alloy mould plate length, width, highly, the major control such as material Parameter so that aluminum alloy pattern plate race file can drive template size according to its Parameters variation.
It addition, aluminum alloy mould plate race file need to be set up in same benchmark job face, as template pel at building base Location plane in body structural model.
S3, according to joining mould rule, ties aluminum alloy mould plate race file at building matrix according to engineering realistic simulation splicing On structure model, form simulation splicing component;
Aluminum alloy mould plate race file parametrization set up imports building basal body structure model, makes Prototype drawing unit according to benchmark work It is accurately positioned as face;Join mould rule according to aluminum alloy mould plate, adjust each template parameter information, the most at last each template pel Carry out assembly, form simulation splicing component.
In this step, join mould rule and include joining mould order and computation rule, be specifically related to aluminum alloy pattern plate, the joining of support system Mould.
Aluminum alloy formwork system includes template, support and accessory.
Aluminum alloy pattern plate includes plane template and corner formwork, and plane template includes wall column formwork, beam forms and accepts template, turns Angle formwork includes flooring internal corner formwork, flooring inner corner trim corner formwork, wall column internal corner formwork and external angle formwork;Support system includes early Dismantling device, adjustable steel support, early-dismantling device includes that early dismantling head at the bottom of early dismantling head at the bottom of beam, plate, monocline early tear aluminum beam open, diclinic early tears aluminum beam open And Quick Release bolt;Accessory includes pin, pin sheet, back cord, split bolt etc..
Fig. 2 is Compound of the formworks of the present invention order, and it is joined, and mould order joins mould for wall column formwork, adjustable steel support is joined Mould, beam-slab template join mould, stair template joins mould and other accessories join mould.
Fig. 3 is that body of wall joins mould precedence diagram, body of wall inside elder generation, then outside body of wall.Inner side body of wall, outside body of wall join mould order For: first joining wall Side Template, then join wall beam junction template, finally join mid portion, mid portion elder generation standard is the most nonstandard, last cloth Put back cord, split bolt, diagonal brace etc..
Body of wall joins mould principle: template is vertically main, and edge uses dedicated templates or angle mould, according to wall, post, depth of beam and top Plate thickness, in the case of meeting top and bottom interface template, uses standard size as far as possible, and one piece of template is to top, stitching position As far as possible in stress smaller part position;Wall, post both sides modulus configuration should be consistent, with ensure to the position drawing system;Casting formwork needs When connecing high, use standard edition traverse, it is impossible to when meeting, customization connects high template.
Support system joins mould precedence diagram, as shown in Figure 4.It is according to the sequence construction of first plate, girder, then secondary beam.Beam slab props up Support ensures that horizontal both direction is in a row, in column as far as possible;Wall, the first beam-slab bracing system on post limit should ensure that wall, column template remove sky Between;When isolated beam support is unsatisfactory for load, use dual-gripper form;The general supporting early dismantling head device of standard and adjustable of using Bracing members.
Fig. 5 is that beam forms joins mould precedence diagram, and it first configures beam internal corner formwork, then supports and aluminum beam, then at the bottom of configuration beam It is beam bottom mother plate, is followed by side template, last reinforcing beam formwork.
Floorboard joins mould precedence diagram, as shown in Figure 6.
The first step, internal corner formwork around the template of configuration bottom surface;Flooring corner design corner internal corner formwork, general employing turns Angle inner corner trim is 350-350(mm) template.
Configure the flooring internal corner formwork between two corner inner corner trims: first arrange an oblique angle inner corner trim, general employing C-600's Oblique angle inner corner trim;Arranging other inner corner trims again, the length kind of inner corner trim is the fewest.If occurring the situation at the bottom of beam base plate, the most not Internal corner formwork is set.
Second step, configuration early tears aluminum beam open
1) according to Support Position, arrange that middle morning tears aluminum beam open.The middle size early tearing aluminum beam open maximum is 1200mm, and middle morning tears open The dimension figure of aluminum beam should be integer.The middle kind early tearing aluminum beam open is avoided too much as far as possible.
2) arranging that edge early tears aluminum beam open, full-size 1100mm of aluminum beam is early torn on limit open, and the limit at two ends is early torn aluminum beam open and made as far as possible Obtaining size the same, the kind that aluminum beam is early torn on limit open is also unsuitable too many.
3rd step, configuration design soffit template
1) after laying and early tearing aluminum beam open, early tearing open between aluminum beam, the distance of vacancy is usually 1200mm, the length of end face template is little In 1200mm, it is ensured that the plate that floor template is 400 ~ 1200mm length of the overwhelming majority.
2) length of template is the multiple of 100mm as far as possible.
3) principle that the length and width direction of template is arranged: selection standard size template as far as possible, uses big-size formwork, subtracts Few formwork edge joint.
4) for there being the flooring encorbelmented, in the support that returns back to top that marginal position design of encorbelmenting is identical with flooring.
5) floorboard designed and wallboard, beam slab are integrated, check position, hole the most perfectly aligned.
6), after all flooring has designed, data all to flooring are added up, and according to statistical result to templating species And quantity is adjusted again.
Fig. 7 is that mould precedence diagram joined by stair, when stair template joins mould, should be noted following some:
For stair soffit base plate corner internal corner formwork, first according to bench base plate, at bench and wall, beam junction design base plate Corner inner corner trim;Base plate corner inner corner trim should use standard inner corner trim to be welded.This inner corner trim should be unsuitable with the contact length of bench base plate Too short, with mortar leakage prevention.
For stair soffit template, bench base plate should be made as far as possible to join the wide on-gauge plate of 400mm, facing sky side if having, facing sky side Use on-gauge plate wide for 200mm to be supported as far as possible;Template is unsuitable with length A of stair inclined floor mating part wide, to the greatest extent Amount controls within 300mm, to ensure the intensity of template.
When stair base plate joins mould design, it is important to note that the design at cleat stanchion, ladder beam, landing beam etc. and bench node, prevent Spillage;Consider and have remaining template of matching relationship with base plate mould so that it is complementary modul board size is integer, in order to use standard Plate;Bottom surface template uses 200mm, 400mm on-gauge plate, standard inner corner trim, standard oblique angle inner corner trim as far as possible.Standard inner corner trim length is not more than 2000mm.As shaped piece need to be designed at bench and the ladder node such as beam, cleat stanchion, landing beam, following principle should be followed: shaped piece structure Other formwork structure should be made to simplify;Shaped piece structure should be easy to processing and mounting or dismounting.
For backplanes support, sky is faced in bench one side, it is necessary to add the support that support interval is not more than 1200mm;
Bench one side part faces sky, when part is body of wall, faces empty part and can ensure that safety processes;
For template of marking time, connecting plate of marking time is for connection to the template middleware with wall form of marking time;Template main molding table The size in face must be with stair step consistent size, and the structure of connecting plate of marking time should be easy to body of wall and joins mould.
The size of template " L " shape molded surface must be with stair step consistent size.Mark time and intersect with landing beam, cleat stanchion etc. Node at it is contemplated that use the template of marking time of long 300mm.Template of marking time should conveniently be passed through, and transports material.Step plate with mark time The connecting hole of plate is away from preferably taking 200mm, 300mm.When structure limits, it is allowed to spacing 100mm;Baffle plate of marking time is for connection at the bottom of bench The middleware of template die plate and template of marking time.Baffle arrangement of marking time should ensure that bench side is without spillage.It is easy to assembling, without interfering.Knot Structure meets requirement of strength.
Side wall template is faced for bench, prevents wearing template: when stair bench side is whole face wall body, cloth is set up defences and worn template, anti- Wear template width and preferably take 200mm;Trapezoidal plate: preferential employing 400mm width trapezoidal plate joins mould;Trapezoidal plate dual-side punches preferably from right angle While start;Triangle plate: bench faces side wall according to joining the needs of template, can join triangle plate.Triangle plate should meet structure and set Meter requirement, it is ensured that seam is good, without spillage;Sketch plate: according to joining mould needs, sketch plate can be joined.Sketch plate should meet structure and set Meter requirement, it is ensured that seam is good, without spillage.
For inner corner trim corner mould between wall, between wall, join mould principle with corresponding wallboard identical for inner corner trim length, but is not required to deduct ditch The height of aluminum;For wall external angle formwork, the external corner length of body of wall end, but it is not required to deduct the height of ground aluminum corner brace.
S4, checks whether simulation splicing component exists interference, and checks simulation splicing component and other cross-operation models Whether existence is interfered, depending on aluminum alloy mould plate race file being optimized design;
In this step, by Revit software collision detection function, dimension information and the conflict feelings of simulation splicing component are checked Condition, depending on being adjusted amendment.
First, the simulation splicing component completed is integrated in Revit model, clicks " observability/the figure in view option card Shape " order, change wall, post, beam, plate and the filling pattern color of aluminum alloy mould plate pel, it is accordingly required in particular to aluminum alloy pattern plate fills face Color highlights, and will not join mould position and forms sharp contrast with aluminum alloy mould plate, it is simple to looks into each detail treatment and lack benefit Leakage;
Then, model is directed in Naviswork, carries out collision detection, return in Revit model, adjust and have repetition, punching Prominent, the position relationship of embedded template;
Finally, according to joining the basic principle of mould, according to thin after the thickest, first in after outer order, the setting first checking for supporting is No meet the requirements, be then examined in slab form, wall column formwork, stair template join mould, be finally template stay bolt system, with Check, adjust in time.
S5, statistics aluminum alloy mould plate is joined mould model information, and is generated model component detail list, puts down, stands, cuts open three-view diagram and mould Plate manuscript.
In this step, by the detail list statistical function of Revit software, each template size, quantity, area are carried out intelligence Can add up, and generate list of templates;By the published picture sexual function of Revit software, generate flat deep cutting three-view diagram and complex node Three-dimensional construction diagrams is constructed for guide field.
The aluminum alloy mould plate based on Revit that the present invention provides joins mould method, has certain application scalability.It is permissible Threedimensional model is utilized to carry out aluminum dipping form construction animation and progress simulation and identification of dangerous source.
(1) use the Revit model of aluminum dipping form, model is imported Navisworks software, utilizes Animator instrument, arrange Scene and animation collection, fabrication and installation, dismounting analog video, derive video file, carry out later stage process with video software.Build continuously The structural model of vertical at least three layers, imports Navisworks software by model, simulates needs according to construction speed arrangement and 4D Precision establishment Project file, after importing Project file is arranged, carries out 4D simulation, finally derives 4D video, can be clear Show whole floor aluminum alloy mould plate construction overall process and the condition of construction of different time.
(2) BIM model can be utilized to carry out identification of dangerous source, identify horizontal hole, high-supported formwork equivalent risk source intuitively, To formulate corresponding countermeasure.
In embodiment shown in Fig. 1, it is applicable to ordinary residence index bed (within floor height 3.3m) aluminum alloy mould plate and joins mould Design, thin portion Deepen Design, quantities calculation and visualization of presence such as are told somebody what one's real intentions are at many-sided the use.Other are more than the knot of 3.3m floor height Structure layer aluminum alloy mould plate is joined mould and is referred to this engineering method, and conceptual design and safety check result in conjunction with aluminum dipping form carry out three-dimensional and join Mould.
The aluminum alloy mould plate based on Revit that the present invention provides joins mould method, defines aluminum alloy mould plate and joins the standard of mould Work flow, more traditional Auto CAD joins mould method, no longer depends on the three dimensions visionary of operator unduly, joins mould Accurately, efficiently, shorten the process-cycle of aluminum alloy mould plate, ensured the construction period of architectural engineering, specifically had the advantage that
(1) present invention utilizes the characteristic of three-dimensional visualization that Revit software realizes, completes two dimension drawing to threedimensional model, three-dimensional After the visual design again from three-dimensional to two dimension conversion, make to join mould flow process more three-dimensional, directly perceived, accurate, it is achieved complexity join mould joint The accurate embodiment of point, improves the efficiency joining mold process, publish picture the most convenient accurately;Especially after setting up component race, different The joining mould and can directly invoke of engineering.
(2) present invention utilizes the aluminum alloy mould plate three-dimensional information model of Revit software arrangements, and component is deposited during organizational system Store up relevant information, by information is extracted, the statistics of aluminum alloy mould plate specification, size, quantity, area can have been carried out, can With the sound field bill of materials, it is simple to the management to construction material.
(3) present invention utilizes structure, the aluminum dipping form model having built up, can expansive approach further, it is achieved Maximum Value Change.
The present invention is not limited to above-mentioned embodiment, and anyone can draw other various forms under the enlightenment of the present invention Product, no matter but in its shape or structure, make any change, every have same as the present application or akin technical side Case, within all falling within protection scope of the present invention.

Claims (8)

1. an aluminum alloy mould plate based on Revit joins mould method, it is characterised in that comprise the following steps:
S1, uses Revit software, sets up parametrization building basal body structure model;
S2, uses Revit software, sets up parametrization aluminum alloy mould plate race file;
S3, according to joining mould rule, splices aluminum alloy mould plate race file at building basal body structure mould according to engineering realistic simulation In type, form simulation splicing component;
S4, checks whether simulation splicing component exists interference, and checks whether are simulation splicing component and other cross-operation models Exist and interfere, depending on aluminum alloy mould plate race file being optimized design;
S5, statistics aluminum alloy mould plate joins mould model information, and generates model component detail list, puts down, stands, cuts open three-view diagram and template adds Work figure.
Aluminum alloy mould plate based on Revit the most according to claim 1 joins mould method, it is characterised in that in step sl, Building basal body structure model includes the absolute altitude of building, floor height, axle net, wall, post, beam, plate, stair.
Aluminum alloy mould plate based on Revit the most according to claim 1 joins mould method, it is characterised in that in step sl, Including the secondary structure design to building basal body structure model.
Aluminum alloy mould plate based on Revit the most according to claim 1 joins mould method, it is characterised in that in step s 2, The parameter of aluminum alloy mould plate race file include the length of aluminum alloy mould plate, width, highly, material.
Aluminum alloy mould plate based on Revit the most according to claim 1 joins mould method, it is characterised in that in step s 2, Aluminum alloy mould plate race file is set up on same benchmark job face.
Aluminum alloy mould plate based on Revit the most according to claim 1 joins mould method, it is characterised in that in step s3, Described mould rule of joining includes joining mould order and computation rule, described in join mould rule relate to aluminum alloy pattern plate, support system join mould.
Aluminum alloy mould plate based on Revit the most according to claim 6 joins mould method, it is characterised in that described aluminum alloy pattern plate Including plane template, corner formwork, wherein plane template includes wall column formwork, beam-slab template and accepts template;Described supporter System includes early-dismantling device, adjustable steel support.
8. join mould method according to the aluminum alloy mould plate based on Revit described in claim 6 or 7, it is characterised in that it is suitable that it joins mould Sequence is that wall column formwork joins mould, adjustable steel support joins mould, beam-slab template joins mould, stair template joins mould and other accessories join mould.
CN201610853427.5A 2016-09-27 2016-09-27 A kind of aluminum alloy mould plate based on Revit joins mould method Pending CN106284976A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610853427.5A CN106284976A (en) 2016-09-27 2016-09-27 A kind of aluminum alloy mould plate based on Revit joins mould method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610853427.5A CN106284976A (en) 2016-09-27 2016-09-27 A kind of aluminum alloy mould plate based on Revit joins mould method

Publications (1)

Publication Number Publication Date
CN106284976A true CN106284976A (en) 2017-01-04

Family

ID=57715272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610853427.5A Pending CN106284976A (en) 2016-09-27 2016-09-27 A kind of aluminum alloy mould plate based on Revit joins mould method

Country Status (1)

Country Link
CN (1) CN106284976A (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107729686A (en) * 2017-11-08 2018-02-23 江苏国泰新点软件有限公司 Component methods of exhibiting, device, electronic equipment and the storage medium of BUILDINGS MODELS
CN107859176A (en) * 2017-11-29 2018-03-30 湖北绿溪建筑科技有限公司 A kind of staggered floor construction in assembled architecture, improve the construction method of form cycling rate
CN108252519A (en) * 2018-03-14 2018-07-06 中铁八局集团第四工程有限公司 A kind of construction method of the house construction engineering template construction technique model based on BIM
CN108268707A (en) * 2017-12-31 2018-07-10 安徽马钢工程技术集团有限公司 A kind of transfer station standard form method for drafting and transfer station construction method based on REVIT
CN108280276A (en) * 2018-01-09 2018-07-13 上海大学 It is created and dosage statistical method based on Revit software stair model criterias
CN108491631A (en) * 2018-03-23 2018-09-04 中国十七冶集团有限公司 A kind of aluminum alloy mould plate construction method based on BIM technology
CN109424202A (en) * 2017-09-05 2019-03-05 中铁十局集团电务工程有限公司 A kind of secondary assembled wallboard building method
CN110378039A (en) * 2019-07-23 2019-10-25 广州优比建筑咨询有限公司 A kind of aluminum alloy pattern plate design method and system based on Revit
CN110700583A (en) * 2019-05-28 2020-01-17 北京构力科技有限公司 Aluminum template pre-assembly system and method based on three-dimensional BIM technology
CN110704910A (en) * 2019-09-18 2020-01-17 山东新汉唐数据科技有限公司 Aluminum template matching method, system, computer readable storage medium and equipment
CN110716701A (en) * 2019-10-09 2020-01-21 周发喜 Method for quickly plotting detailed prefabricated convex window graph based on Revit software
CN111502246A (en) * 2020-04-29 2020-08-07 中铁二局第一工程有限公司 BIM technology-based design and optimization method for side wall unilateral template support system
CN111618528A (en) * 2019-02-27 2020-09-04 浙江树垚新材料科技有限公司 Production process of aluminum template for building
CN111832113A (en) * 2020-07-31 2020-10-27 河南五建第二建筑安装有限公司 Aluminum alloy template matching method based on BIM technology
CN112528357A (en) * 2019-08-31 2021-03-19 广东博越智慧建造科技有限公司 Prefabricated part and aluminum mold arrangement simulation construction method based on building information model
CN113378282A (en) * 2021-06-30 2021-09-10 中国二冶集团有限公司 BIM-based residential building template matching and collision inspection method and system
CN113550570A (en) * 2021-03-03 2021-10-26 中建八局发展建设有限公司 Aluminum alloy template deepened design and installation process
CN113609553A (en) * 2021-07-12 2021-11-05 广联达科技股份有限公司 Stair component creating method and device and electronic equipment
CN114065336A (en) * 2021-09-28 2022-02-18 广州优比建筑咨询有限公司 Revit-based high formwork region inspection method, device, medium and equipment
CN116446638A (en) * 2023-04-27 2023-07-18 中国建筑第二工程局有限公司 Construction method of ultra-high cast-in-situ wood form tower type early-dismantling support structure based on BIM

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109424202A (en) * 2017-09-05 2019-03-05 中铁十局集团电务工程有限公司 A kind of secondary assembled wallboard building method
CN107729686B (en) * 2017-11-08 2021-07-27 国泰新点软件股份有限公司 Building model component display method and device, electronic equipment and storage medium
CN107729686A (en) * 2017-11-08 2018-02-23 江苏国泰新点软件有限公司 Component methods of exhibiting, device, electronic equipment and the storage medium of BUILDINGS MODELS
CN107859176A (en) * 2017-11-29 2018-03-30 湖北绿溪建筑科技有限公司 A kind of staggered floor construction in assembled architecture, improve the construction method of form cycling rate
CN108268707A (en) * 2017-12-31 2018-07-10 安徽马钢工程技术集团有限公司 A kind of transfer station standard form method for drafting and transfer station construction method based on REVIT
CN108268707B (en) * 2017-12-31 2021-08-06 马钢集团设计研究院有限责任公司 ReVIT-based transfer station standard template drawing method and transfer station construction method
CN108280276A (en) * 2018-01-09 2018-07-13 上海大学 It is created and dosage statistical method based on Revit software stair model criterias
CN108280276B (en) * 2018-01-09 2022-02-08 上海大学 Revit software based stair model standard creation and usage statistical method
CN108252519A (en) * 2018-03-14 2018-07-06 中铁八局集团第四工程有限公司 A kind of construction method of the house construction engineering template construction technique model based on BIM
CN108491631A (en) * 2018-03-23 2018-09-04 中国十七冶集团有限公司 A kind of aluminum alloy mould plate construction method based on BIM technology
CN111618528A (en) * 2019-02-27 2020-09-04 浙江树垚新材料科技有限公司 Production process of aluminum template for building
CN110700583A (en) * 2019-05-28 2020-01-17 北京构力科技有限公司 Aluminum template pre-assembly system and method based on three-dimensional BIM technology
CN110378039A (en) * 2019-07-23 2019-10-25 广州优比建筑咨询有限公司 A kind of aluminum alloy pattern plate design method and system based on Revit
CN110378039B (en) * 2019-07-23 2022-04-19 广州优比建筑咨询有限公司 Revit-based aluminum template design method and system
CN112528357A (en) * 2019-08-31 2021-03-19 广东博越智慧建造科技有限公司 Prefabricated part and aluminum mold arrangement simulation construction method based on building information model
CN110704910A (en) * 2019-09-18 2020-01-17 山东新汉唐数据科技有限公司 Aluminum template matching method, system, computer readable storage medium and equipment
CN110704910B (en) * 2019-09-18 2023-06-23 山东新汉唐数据科技有限公司 Aluminum template matching method, system, computer readable storage medium and equipment
CN110716701A (en) * 2019-10-09 2020-01-21 周发喜 Method for quickly plotting detailed prefabricated convex window graph based on Revit software
CN111502246A (en) * 2020-04-29 2020-08-07 中铁二局第一工程有限公司 BIM technology-based design and optimization method for side wall unilateral template support system
CN111832113B (en) * 2020-07-31 2023-10-10 河南五建第二建筑安装有限公司 Aluminum alloy template matching method based on BIM technology
CN111832113A (en) * 2020-07-31 2020-10-27 河南五建第二建筑安装有限公司 Aluminum alloy template matching method based on BIM technology
CN113550570A (en) * 2021-03-03 2021-10-26 中建八局发展建设有限公司 Aluminum alloy template deepened design and installation process
CN113378282A (en) * 2021-06-30 2021-09-10 中国二冶集团有限公司 BIM-based residential building template matching and collision inspection method and system
CN113609553A (en) * 2021-07-12 2021-11-05 广联达科技股份有限公司 Stair component creating method and device and electronic equipment
CN113609553B (en) * 2021-07-12 2023-12-22 广联达科技股份有限公司 Stair component creation method and device and electronic equipment
CN114065336A (en) * 2021-09-28 2022-02-18 广州优比建筑咨询有限公司 Revit-based high formwork region inspection method, device, medium and equipment
CN116446638B (en) * 2023-04-27 2023-12-05 中国建筑第二工程局有限公司 Construction method of ultra-high cast-in-situ wood form tower type early-dismantling support structure based on BIM
CN116446638A (en) * 2023-04-27 2023-07-18 中国建筑第二工程局有限公司 Construction method of ultra-high cast-in-situ wood form tower type early-dismantling support structure based on BIM

Similar Documents

Publication Publication Date Title
CN106284976A (en) A kind of aluminum alloy mould plate based on Revit joins mould method
CN110569621B (en) BIM technology-based multi-dimensional curved surface glass curtain wall design processing and installation method
CN108763710B (en) BIM-based forward deepening design method for assembled building
WO2021128675A1 (en) Bim technology-based method for constructing underground continuous wall
CN108491631A (en) A kind of aluminum alloy mould plate construction method based on BIM technology
CN107273607A (en) A kind of steel-structure factory building pre-assembly method based on BIM
CN105956257A (en) BIM-based aluminum alloy template deep design method
CN110287513A (en) A kind of built-in fitting construction method based on BIM technology
JP5048962B2 (en) Architectural plan change method and architectural plan change device using three-dimensional laser scanner
CN103336856A (en) Virtual steel structure pre-assembly method based on visual model
KR101425576B1 (en) Method for acquiring and processing a three-dimensional data to product a precise wide-area scale model
CN109684662A (en) A kind of construction method of intellectual assembled architecture
KR20130016620A (en) 3d process management method for bim(building information modeling)
CN105468796A (en) Method for establishing temporary support moulding bed system for steel structure assembly
CN107590334A (en) A kind of complex object stay in place form construction method
CN105551077B (en) The construction method and device of panel beating three-dimensional process model
Lee et al. Automated system for form layout to increase the proportion of standard forms and improve work efficiency
CN109025319A (en) A kind of prefabricated components butt joint interface quality testing and method of disposal
CN110378039A (en) A kind of aluminum alloy pattern plate design method and system based on Revit
KR101301716B1 (en) Method of manufacturing mold for free form architecture
CN108428032B (en) Method and device for making component production plan
CN203863813U (en) Die special for housing industrialization pre-cast concrete component stair
Maboudi et al. Current surveying methods for the integration of additive manufacturing in the construction process
CN112814146A (en) BIM technology-based wall green construction method
KR20120009237A (en) Support Modeling & Drawing creation system and method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170104

RJ01 Rejection of invention patent application after publication