WO2021128675A1 - Bim technology-based method for constructing underground continuous wall - Google Patents

Bim technology-based method for constructing underground continuous wall Download PDF

Info

Publication number
WO2021128675A1
WO2021128675A1 PCT/CN2020/087080 CN2020087080W WO2021128675A1 WO 2021128675 A1 WO2021128675 A1 WO 2021128675A1 CN 2020087080 W CN2020087080 W CN 2020087080W WO 2021128675 A1 WO2021128675 A1 WO 2021128675A1
Authority
WO
WIPO (PCT)
Prior art keywords
construction
project
bim
bim model
model
Prior art date
Application number
PCT/CN2020/087080
Other languages
French (fr)
Chinese (zh)
Inventor
施曙东
罗攀
岳国柱
庞晓明
李军代
李江峰
仕佳
张玮
姚凯
刘亚晴
袁帅
邱轶
邓国民
Original Assignee
上海浦东路桥(集团)有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 上海浦东路桥(集团)有限公司 filed Critical 上海浦东路桥(集团)有限公司
Publication of WO2021128675A1 publication Critical patent/WO2021128675A1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/05Geographic models

Definitions

  • the invention relates to a construction method, in particular to a construction method of an underground continuous wall based on BIM technology.
  • the construction of the underground continuous wall has the characteristics of strong construction technology periodicity, multiple soil layers, and large excavation depth of foundation pits.
  • Diaphragm wall is a kind of supporting structure of foundation pit.
  • Diaphragm wall is a foundation project that uses trenching machinery on the ground.
  • a long and narrow deep trench is excavated under the condition of mud protection.
  • the steel cage is hoisted in the trench.
  • the conduit method to fill the underwater concrete to build a unit trough section, so as to build a continuous reinforced concrete wall underground, as a water interception, anti-seepage, load-bearing, and water-retaining structure.
  • the construction of the underground diaphragm wall project usually still only relies on the traditional two-dimensional drawings. It is difficult to detect or discover the conflicts in the design and construction in advance. It is difficult to optimize the process, and the traditional underground
  • the continuous wall construction technology has problems such as low construction efficiency, high construction cost, low construction accuracy, and high construction risk.
  • the present invention provides an underground continuous wall construction method based on BIM technology, which realizes the integrated management of underground continuous wall construction information, three-dimensional visualization, model review, comparison and acceptance, and greatly improves the construction Quality and precision.
  • the technical scheme of the present invention is as follows:
  • the BIM technology-based underground continuous wall construction method disclosed in the present invention includes the steps: S1, according to the project BIM application standard, 3D modeling the underground continuous wall design and construction drawing to obtain the project BIM model; S2, based on the project BIM model , Carry out collision and error inspections among the underground diaphragm wall steel bars, lock pipes, and grouting pipes, and adjust and optimize the BIM model of the project according to the inspection results; S3, use the BIM model of the project to perform three-dimensional simulation to simulate construction Process; S4, in the on-site construction process, according to the project BIM model, three-dimensional visualization of the on-site construction personnel; S5, according to the project BIM model and construction process simulation, guide the on-site construction; S6, after the completion of the construction, Perform construction acceptance according to the BIM model of the project.
  • the step S2 specifically includes: S21, using Revit software to perform collision and error checking on the underground diaphragm wall reinforcement, the key pipe, and the grouting pipe in the project BIM model; or S22, the project BIM model Imported into Navisworks, through the Navisworks software, the underground diaphragm wall steel bar, the lock pipe, and the grouting pipe in the BIM model are checked for collision and error.
  • the project BIM model is the whole construction process model of the underground continuous wall construction project; the elevation and coordinate system adopted by the project BIM model are consistent with reality; and the information database of the project BIM model contains basic parameter information and Construction information.
  • the basic parameter information includes: spatial location parameter information and physical size information
  • the construction information includes: construction time information, model change information, construction material information, and acceptance information.
  • the construction method of the underground continuous wall based on the BIM technology further includes: S25, deriving the model data of the BIM model of the project to guide construction preparation; specifically including: deriving the engineering quantities of steel and concrete based on the BIM model of the project , Instruct the procurement of construction materials; and/or, import the steel cage model data of the BIM model of the project into automated equipment, and instruct the automated equipment to produce and process the steel cage; and/or, change the elevation of the project’s BIM model,
  • the coordinate system data is exported to the total station to guide the measurement and stakeout on site; and/or, based on the project BIM model, export a two-dimensional CAD drawing.
  • the step S3 specifically includes: S31, using Autodesk Revit to export the NWC and DAE files of the project BIM model, and import them into NavisWorks and Lumion software for construction simulation to form 3D, 4D, and 5D construction simulation videos.
  • the three-dimensional visualization presentation in step S4 specifically includes any one or more of BIM three-dimensional model presentation presentation, construction 4D, 5D simulation animation presentation, VR immersive experience presentation, and 3D printing physical presentation.
  • the step S6 specifically includes: S61, comparing the BIM model of the project with the actual appearance of the site; checking whether the appearance of the underground diaphragm wall is qualified; S62, comparing the BIM model data of the project with the actual measured data on the site , Check whether the quality of the underground diaphragm wall is qualified.
  • the on-site construction in step S5 includes: line measurement, guide wall construction, slurry preparation, trough excavation, foundation clearance, lock pipe hoisting, concrete pouring, lock extraction, and wall toe grouting .
  • the construction method of the underground continuous wall based on the BIM technology further includes the step: S7, after the acceptance is passed, the BIM model of the project is optimized and modified according to the acceptance information to form the construction completion model of the underground continuous wall.
  • the present invention introduces BIM technology into the construction process of the underground continuous wall, and uses BIM technology to guide the construction of the underground continuous wall, which can predict the problems in the construction, find the problems in advance, and solve the problems.
  • the construction management has been strengthened, and the construction quality has been greatly improved while reducing waste and shortening the construction period.
  • the present invention uses BIM technology to construct the project BIM model of the underground diaphragm wall project. Based on this model, it realizes the integrated management of underground diaphragm wall construction information, three-dimensional visualization, detailed processing and production of steel components, and model review and comparison acceptance, which greatly improves Improve the construction quality and precision.
  • the present invention uses BIM technology to construct a three-dimensional model, which is easier to accept than 2D plane construction drawings, improves the accuracy of each construction personnel's drawing recognition, and avoids construction errors caused by inaccurate drawing recognition, thereby ensuring construction Quality and cost saving.
  • the present invention uses BIM technology to perform construction simulation before construction, avoiding construction risks and hidden dangers.
  • construction simulation and construction simulation can also accurately reflect the existence of problems, so that corresponding rush or correction plans can be formulated according to the exposed problems, and the problems can be discovered and solved in time to avoid greater losses.
  • Fig. 1 is a flowchart of an embodiment of a construction method of an underground continuous wall based on BIM technology of the present invention
  • FIG. 2 is a flowchart of another embodiment of the construction method of underground continuous wall based on BIM technology of the present invention
  • Fig. 3 is a flowchart of another embodiment of a construction method of an underground continuous wall based on BIM technology of the present invention.
  • the invention discloses a construction method of an underground continuous wall based on BIM technology.
  • the embodiment is shown in Fig. 1 and includes the following steps:
  • the design and construction drawings are 3D modeling using Autodesk Revit software to obtain the project BIM model.
  • the project BIM model refers to the project BIM model of the underground continuous wall construction project, which contains the underground continuous wall construction station.
  • the models of the various components that need to be used, for example, the BIM model of the project includes: underground continuous walls, guide walls, reinforcement cages of underground continuous walls, trough forming machines, lock pipes, crawler cranes, construction sites, and so on.
  • Project BIM standards refer to the guidelines for the application of BIM technology in projects, and are the project BIM application guidelines. All participating parties should uniformly apply BIM technology in accordance with this standard.
  • Project BIM standards include: BIM application planning, BIM modeling standards, BIM delivery standards, sub-item split standards, BIM component naming rules, etc.
  • the model After the BIM model is built, it is necessary to perform collision check based on the constructed project BIM model, especially the collision and error check between the underground diaphragm wall reinforcement, the lock pipe, and the grouting pipe in the project BIM model. If errors are found, the model can be adjusted and optimized in time to prevent them.
  • the BIM three-dimensional live simulation technology is used to simulate the construction conditions of the underground diaphragm wall, which can discover possible problems in the construction in advance, and the construction personnel can formulate corresponding rush or correction plans according to the exposed problems, and find and solve them in time Problems, to avoid greater losses.
  • the use of BIM technology to simulate construction before construction also avoids construction risks and hidden dangers.
  • the BIM model of the project constructed using BIM technology is a visual three-dimensional model. Therefore, the on-site construction personnel can understand the specific plan more intuitively based on the model.
  • the BIM model of the project can also be used to make an animated video, so as to provide technical confession to the construction workers, which can be used as a supplement to the paper plan.
  • the construction personnel will be guided on-site construction.
  • BIM technology is introduced in the construction process of the underground continuous wall, and the BIM technology is used to guide the construction of the underground continuous wall, which can predict the problems in the construction, find the problems in advance, and solve the problems.
  • the construction management has been strengthened, and the construction quality has been greatly improved while reducing waste and shortening the construction period.
  • FIG. 2 Another embodiment of the present invention, as shown in FIG. 2, includes:
  • the project BIM model is the entire construction process model of the underground diaphragm wall construction project; the elevation and coordinate system adopted by the project BIM model are consistent with the actual situation; and the information database of the project BIM model contains basic parameter information and Construction information.
  • the basic parameter information includes: spatial location parameter information and physical size information;
  • the construction information includes: construction time information, model change information, construction material information, and acceptance information.
  • the informationized BIM technology is introduced, and the three-dimensional model and digital technology are used to form an information database consistent with the actual completed situation.
  • problems in construction can be predicted, problems can be discovered in advance, and problems can be solved in advance.
  • the construction management has been strengthened, and the construction quality has been greatly improved while reducing waste and shortening the construction period.
  • the collision and error check between the underground diaphragm wall reinforcement, the lock pipe, and the grouting pipe are carried out in Autodesk Revit software, and adjustment and optimization are carried out.
  • Autodesk Revit software we can also use Navisworks software for collision checking and other optimization work, but in the modeling phase, it is more convenient to directly use Revit's collision checking.
  • the biggest advantage of using Revit to check model collisions is that there is no need to guide NWC to check again, which is convenient and fast. It can be carried out during modeling, and problems can be found and adjusted immediately.
  • Navisworks is more professional and has more functions. It can export a more formal collision report, which contains information such as component ID number, location, and pictures, which is more intuitive and convenient. After modification, it can also be convenient for secondary inspection. Import the project BIM model into Navisworks, perform auxiliary inspection through the software, and check the model according to the report. Collect, categorize, and report all the problems in a unified manner, and finally modify and adjust the project BIM model according to the feedback information to obtain the final project BIM model.
  • the three-dimensional visualized presentation specifically includes: BIM three-dimensional model presentation presentation, construction 4D, 5D simulation animation presentation, VR immersive experience presentation, 3D printing physical presentation of any one or more.
  • the on-site construction includes: measurement and setting out, guide wall construction, mud preparation, trench excavation, foundation clearing, locking pipe hoisting, Concrete pouring, lock out, wall toe grouting.
  • the overall workflow is BIM modeling ⁇ data export ⁇ technical disclosure ⁇ on-site construction.
  • the on-site construction process is measuring line setting ⁇ guide wall construction ⁇ mud preparation ⁇ trough excavation ⁇ foundation clearance ⁇ lock pipe hoisting ⁇ steel cage hoisting ⁇ concrete pouring ⁇ lock pulling out ⁇ wall toe grouting ⁇ acceptance.
  • S62 Compare the BIM model data of the project with the actual measured data on site, and check whether the quality of the underground diaphragm wall is qualified.
  • This embodiment uses BIM technology to construct a project BIM model of an underground continuous wall project. Based on this model, it realizes integrated management of underground continuous wall construction information, three-dimensional visualization, model review and comparison and acceptance, which greatly improves construction quality and accuracy.
  • Another embodiment of the present invention on the basis of any of the foregoing embodiments, further includes after step S2 and before step S5:
  • the constructed project BIM model is used to exchange information and data with the automated processing equipment, and the relevant data can be directly imported into the automated equipment to directly produce the column steel template. Realize the refined processing and production of reinforced components.
  • the total station that is, the Electronic Total Station (Electronic Total Station), is a high-tech measuring instrument that integrates light, machine, and electricity.
  • the total station is the abbreviation of the total station electronic tachometer.
  • An optoelectronic instrument that combines an electronic theodolite, a photoelectric rangefinder and a microprocessor. Exporting the elevation data and coordinate system data in the project BIM model to the total station can guide the measurement and stakeout on site, which is efficient and fast, and is not easy to make mistakes.
  • FIG. 3 Another embodiment of the present invention, as shown in FIG. 3, on the basis of any of the above embodiments, after the acceptance is passed, the BIM model of the project is optimized and modified according to the acceptance information to form an underground continuous wall construction completion model, that is As-built model.
  • the project BIM model is used to perform three-dimensional simulation to simulate the construction process. In addition to simulating construction conditions, it can also perform construction schedule simulation and construction organization simulation.
  • Construction schedule simulation Simulation technology can make reasonable construction plans during the project construction process, accurately grasp the construction schedule in 4D, and optimize the use of construction resources. Construction is a highly dynamic process. As the scale of construction projects continues to expand, the complexity continues to increase, making Construction project management has become extremely complicated. By linking BIM with the construction schedule, and integrating spatial information and time information into a visual 4D (3D+Time) model, the construction process of the entire building can be reflected intuitively and accurately. The construction source and the scientific site layout, unified management and control of the construction schedule, resources and quality of the entire project, in order to shorten the construction period, reduce costs, and improve quality.
  • Construction organization simulation Through BIM, the key or difficult part of the project can be simulated for buildability, and the construction and installation plan can be analyzed and optimized on a monthly, daily, and hourly basis. For some important construction links or key parts and constructions that adopt new construction techniques Simulate and analyze construction guidance measures such as site layout to improve the feasibility of the plan. The construction party can further optimize and improve the original installation plan to improve the construction efficiency and the safety of the construction plan.

Abstract

Disclosed is a BIM technology-based method for constructing an underground continuous wall. The method comprises the steps of: performing 3D modeling for an underground continuous wall design construction drawing according to a project BIM application standard so as to acquire a project BIM model; on the basis of the project BIM model, performing collision and error checking between a underground continuous wall steel bar, a locking pipe and a grouting pipe and adjusting and optimizing the project BIM model according to the result of the check; using the project BIM model to perform 3D simulation to simulate the construction process; during onsite construction, performing 3D visual disclosure for onsite construction workers according to the project BIM model; instructing the onsite construction according to the project BIM model and the construction process simulation; and once construction is complete, accepting the construction according to the project BIM model. By means of the present invention, the construction quality and accuracy of an underground continuous wall is improved, and construction progress is accelerated.

Description

一种基于BIM技术的地下连续墙施工方法A construction method of underground continuous wall based on BIM technology 技术领域Technical field
本发明涉及一种施工方法,尤其涉及一种基于BIM技术的地下连续墙施工方法。The invention relates to a construction method, in particular to a construction method of an underground continuous wall based on BIM technology.
背景技术Background technique
随着建筑施工技术日益更新和发展,传统的粗放式的建设模式,各项施工方法,施工工艺在工程的资源消耗、质量安全、环境保护等绿色施工方面劣势愈发明显。其中地下连续墙施工有施工工艺周期性强、穿越土层多、基坑开挖深度大等特点。With the ever-increasing update and development of building construction technology, traditional extensive construction modes, various construction methods, and construction techniques have become more and more inferior in terms of green construction such as project resource consumption, quality and safety, and environmental protection. Among them, the construction of the underground continuous wall has the characteristics of strong construction technology periodicity, multiple soil layers, and large excavation depth of foundation pits.
地下连续墙是基坑支护结构的一种。地下连续墙是基础工程在地面上采用挖槽机械,沿着深开挖工程的周边轴线,在泥浆护壁条件下,开挖出一条狭长的深槽,清槽后,在槽内吊放钢筋笼,然后用导管法灌筑水下混凝土筑成一个单元槽段,如此逐段进行,在地下筑成一道连续的钢筋混凝土墙壁,作为截水、防渗、承重、挡水结构。Diaphragm wall is a kind of supporting structure of foundation pit. Diaphragm wall is a foundation project that uses trenching machinery on the ground. Along the peripheral axis of the deep excavation project, a long and narrow deep trench is excavated under the condition of mud protection. After the trench is cleared, the steel cage is hoisted in the trench. , And then use the conduit method to fill the underwater concrete to build a unit trough section, so as to build a continuous reinforced concrete wall underground, as a water interception, anti-seepage, load-bearing, and water-retaining structure.
在传统的施工方法上,地下连续墙工程的施工各个环节通常仍然仅依靠传统的二维图纸,很难提前检测或发现设计、施工中存在的冲突问题,工艺优化难度较大,采用传统的地下连续墙施工工艺,存在施工工效低,施工成本高、施工精度低、施工风险大等等问题。In the traditional construction method, the construction of the underground diaphragm wall project usually still only relies on the traditional two-dimensional drawings. It is difficult to detect or discover the conflicts in the design and construction in advance. It is difficult to optimize the process, and the traditional underground The continuous wall construction technology has problems such as low construction efficiency, high construction cost, low construction accuracy, and high construction risk.
发明内容Summary of the invention
为了提高地下连续墙施工质量,加快施工进度,本发明提供一种基于BIM技术的地下连续墙施工方法,实现了地下连续墙施工信息集成管理、三维可视化交底、模型复核对比验收,大大提高了施工质量和精度。具体的,本发明的 技术方案如下:In order to improve the construction quality of the underground continuous wall and speed up the construction progress, the present invention provides an underground continuous wall construction method based on BIM technology, which realizes the integrated management of underground continuous wall construction information, three-dimensional visualization, model review, comparison and acceptance, and greatly improves the construction Quality and precision. Specifically, the technical scheme of the present invention is as follows:
本发明公开的基于BIM技术的地下连续墙施工方法,包括步骤:S1,根据项目BIM应用标准,对地下连续墙设计施工图进行三维建模,获取项目BIM模型;S2,基于所述项目BIM模型,对地下连续墙钢筋、锁口管、注浆管之间进行碰撞及错误检查,并根据检查结果对所述项目BIM模型进行调整优化;S3,利用所述项目BIM模型进行三维仿真,模拟施工过程;S4,在现场施工过程中,根据所述项目BIM模型,对现场施工人员进行三维可视化交底;S5,根据所述项目BIM模型及其施工过程模拟,指导现场施工;S6,施工完成后,根据所述项目BIM模型进行施工验收。The BIM technology-based underground continuous wall construction method disclosed in the present invention includes the steps: S1, according to the project BIM application standard, 3D modeling the underground continuous wall design and construction drawing to obtain the project BIM model; S2, based on the project BIM model , Carry out collision and error inspections among the underground diaphragm wall steel bars, lock pipes, and grouting pipes, and adjust and optimize the BIM model of the project according to the inspection results; S3, use the BIM model of the project to perform three-dimensional simulation to simulate construction Process; S4, in the on-site construction process, according to the project BIM model, three-dimensional visualization of the on-site construction personnel; S5, according to the project BIM model and construction process simulation, guide the on-site construction; S6, after the completion of the construction, Perform construction acceptance according to the BIM model of the project.
优选地,所述步骤S2具体包括:S21,采用Revit软件对所述项目BIM模型中的地下连续墙钢筋、锁口管、注浆管进行碰撞及错误检查;或S22,将所述项目BIM模型导入Navisworks中,通过所述Navisworks软件对所述BIM模型中的地下连续墙钢筋、锁口管、注浆管进行碰撞及错误检查。Preferably, the step S2 specifically includes: S21, using Revit software to perform collision and error checking on the underground diaphragm wall reinforcement, the key pipe, and the grouting pipe in the project BIM model; or S22, the project BIM model Imported into Navisworks, through the Navisworks software, the underground diaphragm wall steel bar, the lock pipe, and the grouting pipe in the BIM model are checked for collision and error.
优选地,所述项目BIM模型为地下连续墙施工项目的施工全过程模型;所述项目BIM模型采用的高程、坐标系统与实际一致;且所述项目BIM模型的信息数据库中包含基本参数信息及施工信息。Preferably, the project BIM model is the whole construction process model of the underground continuous wall construction project; the elevation and coordinate system adopted by the project BIM model are consistent with reality; and the information database of the project BIM model contains basic parameter information and Construction information.
优选地,所述基本参数信息包括:空间位置参数信息、物理尺寸信息;所述施工信息包括:施工时间信息、模型变更信息、施工材料信息、验收信息。Preferably, the basic parameter information includes: spatial location parameter information and physical size information; the construction information includes: construction time information, model change information, construction material information, and acceptance information.
优选地,所述基于BIM技术的地下连续墙施工方法还包括:S25,导出所述项目BIM模型的模型数据,指导施工准备;具体包括:基于所述项目BIM模型,导出钢筋及混凝土的工程量,指导施工材料采购;和/或,将所述项目BIM模型的钢筋笼模型数据导入自动化设备,指导所述自动化设备对钢筋笼的生产加工;和/或,将所述项目BIM模型的高程、坐标系统数据导出至全站仪,指导现场进行测量放样;和/或,基于所述项目BIM模型,导出二维CAD图纸。Preferably, the construction method of the underground continuous wall based on the BIM technology further includes: S25, deriving the model data of the BIM model of the project to guide construction preparation; specifically including: deriving the engineering quantities of steel and concrete based on the BIM model of the project , Instruct the procurement of construction materials; and/or, import the steel cage model data of the BIM model of the project into automated equipment, and instruct the automated equipment to produce and process the steel cage; and/or, change the elevation of the project’s BIM model, The coordinate system data is exported to the total station to guide the measurement and stakeout on site; and/or, based on the project BIM model, export a two-dimensional CAD drawing.
优选地,所述步骤S3具体包括:S31,采用AutodeskRevit导出所述项目BIM模型的NWC、DAE文件,并将其导入NavisWorks、Lumion软件进行施 工模拟,形成3D、4D、5D施工模拟视频。Preferably, the step S3 specifically includes: S31, using Autodesk Revit to export the NWC and DAE files of the project BIM model, and import them into NavisWorks and Lumion software for construction simulation to form 3D, 4D, and 5D construction simulation videos.
优选地,所述步骤S4中的三维可视化交底具体包括:BIM三维模型展示交底、施工4D、5D模拟动画交底、VR沉浸式体验交底、3D打印实物交底之中的任意一种或多种。Preferably, the three-dimensional visualization presentation in step S4 specifically includes any one or more of BIM three-dimensional model presentation presentation, construction 4D, 5D simulation animation presentation, VR immersive experience presentation, and 3D printing physical presentation.
优选地,所述步骤S6具体包括:S61,将所述项目BIM模型与现场实物外观进行对比;检查地下连续墙外观是否合格;S62,将所述项目BIM模型数据与现场实测实量数据进行对比,检查地下连续墙的质量是否合格。Preferably, the step S6 specifically includes: S61, comparing the BIM model of the project with the actual appearance of the site; checking whether the appearance of the underground diaphragm wall is qualified; S62, comparing the BIM model data of the project with the actual measured data on the site , Check whether the quality of the underground diaphragm wall is qualified.
优选地,所述步骤S5中的现场施工包括:测量放线、导墙施工、泥浆配制、槽段开挖、清基、锁口管吊放、砼浇注、锁口拔出、墙趾注浆。Preferably, the on-site construction in step S5 includes: line measurement, guide wall construction, slurry preparation, trough excavation, foundation clearance, lock pipe hoisting, concrete pouring, lock extraction, and wall toe grouting .
优选地,所述基于BIM技术的地下连续墙施工方法还包括步骤:S7,验收通过后,根据验收信息优化修改所述项目BIM模型,形成地下连续墙施工完成模型。Preferably, the construction method of the underground continuous wall based on the BIM technology further includes the step: S7, after the acceptance is passed, the BIM model of the project is optimized and modified according to the acceptance information to form the construction completion model of the underground continuous wall.
本发明至少包括以下一项技术效果:The present invention includes at least one of the following technical effects:
(1)本发明在地下连续墙的施工工艺中引入了BIM技术,采用BIM技术来指导地下连续墙的施工,可预判施工中出现的问题,提前发现问题,解决问题。强化了施工管理,在减少浪费缩短工期的同时,大大提高了施工质量。(1) The present invention introduces BIM technology into the construction process of the underground continuous wall, and uses BIM technology to guide the construction of the underground continuous wall, which can predict the problems in the construction, find the problems in advance, and solve the problems. The construction management has been strengthened, and the construction quality has been greatly improved while reducing waste and shortening the construction period.
(2)本发明利用BIM技术构建了地下连续墙项目的项目BIM模型,基于该模型实现了地下连续墙施工信息集成管理、三维可视化交底、钢筋构件精细化加工生产、模型复核对比验收,大大提高了施工质量和精度。(2) The present invention uses BIM technology to construct the project BIM model of the underground diaphragm wall project. Based on this model, it realizes the integrated management of underground diaphragm wall construction information, three-dimensional visualization, detailed processing and production of steel components, and model review and comparison acceptance, which greatly improves Improve the construction quality and precision.
(3)本发明利用BIM技术构建三维模型,相对于2D的平面施工图更易于接受,提高了各施工人员识图的准确性,避免因识图不准确而造成的施工误差,从而保证了施工质量,节约成本。(3) The present invention uses BIM technology to construct a three-dimensional model, which is easier to accept than 2D plane construction drawings, improves the accuracy of each construction personnel's drawing recognition, and avoids construction errors caused by inaccurate drawing recognition, thereby ensuring construction Quality and cost saving.
(4)本发明利用BIM技术在施工之前进行了施工模拟,规避了施工风险及隐患。此外,通过施工仿真及施工模拟还可准确反映出存在问题,便可根据暴露出的问题制定相应赶工或纠偏方案,及时发现并解决问题,避免造成更大损失。(4) The present invention uses BIM technology to perform construction simulation before construction, avoiding construction risks and hidden dangers. In addition, construction simulation and construction simulation can also accurately reflect the existence of problems, so that corresponding rush or correction plans can be formulated according to the exposed problems, and the problems can be discovered and solved in time to avoid greater losses.
附图说明Description of the drawings
为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简要介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域的普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。In order to explain the technical solutions in the embodiments of the present invention more clearly, the following will briefly introduce the drawings needed in the description of the embodiments. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained from these drawings without creative labor.
图1为本发明基于BIM技术的地下连续墙施工方法的一个实施例的流程图;Fig. 1 is a flowchart of an embodiment of a construction method of an underground continuous wall based on BIM technology of the present invention;
图2为本发明基于BIM技术的地下连续墙施工方法的另一实施例的流程图;2 is a flowchart of another embodiment of the construction method of underground continuous wall based on BIM technology of the present invention;
图3为为本发明基于BIM技术的地下连续墙施工方法的另一实施例的流程图。Fig. 3 is a flowchart of another embodiment of a construction method of an underground continuous wall based on BIM technology of the present invention.
具体实施方式Detailed ways
以下描述中,为了说明而不是为了限定,提出了诸如特定系统结构、技术之类的具体细节,以便透彻理解本申请实施例。然而,本领域的技术人员应当清楚,在没有这些具体细节的其他实施例中也可以实现本申请。在其他情况中,省略对众所周知的系统、装置、电路以及方法的详细说明,以免不必要的细节妨碍本申请的描述。In the following description, for the purpose of illustration rather than limitation, specific details such as a specific system structure and technology are proposed for a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application can also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to avoid unnecessary details from obstructing the description of this application.
应当理解,当在本说明书和所附权利要求书中使用时,术语“包括”指示所述描述特征、整体、步骤、操作、元素和/或组件的存在,但并不排除一个或多个其他特征、整体、步骤、操作、元素、组件和/或集合的存在或添加。It should be understood that when used in this specification and appended claims, the term "comprising" indicates the existence of the described features, wholes, steps, operations, elements and/or components, but does not exclude one or more other The existence or addition of features, wholes, steps, operations, elements, components, and/or collections.
为使图面简洁,各图中只示意性地表示出了与本发明相关的部分,它们并不代表其作为产品的实际结构。另外,以使图面简洁便于理解,在有些图中具有相同结构或功能的部件,仅示意性地绘出了其中的一个,或仅标出了其中的一个。在本文中,“一个”不仅表示“仅此一个”,也可以表示“多于一个” 的情形。In order to make the drawings concise, the drawings only schematically show the parts related to the present invention, and they do not represent the actual structure of the product. In addition, in order to make the drawings concise and easy to understand, in some drawings, only one of the components with the same structure or function is schematically drawn, or only one of them is marked. In this article, "a" not only means "only this one", but can also mean "more than one".
还应当进一步理解,在本申请说明书和所附权利要求书中使用的术语“和/或”是指相关联列出的项中的一个或多个的任何组合以及所有可能组合,并且包括这些组合。It should be further understood that the term "and/or" used in the specification and appended claims of this application refers to any combination and all possible combinations of one or more of the associated listed items, and includes these combinations .
另外,在本申请的描述中,术语“第一”、“第二”等仅用于区分描述,而不能理解为指示或暗示相对重要性。In addition, in the description of the present application, the terms "first", "second", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对照附图说明本发明的具体实施方式。显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图,并获得其他的实施方式。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the specific implementation manners of the present invention will be described below with reference to the accompanying drawings. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, without creative work, other drawings can be obtained based on these drawings and obtained Other embodiments.
本发明公开了一种基于BIM技术的地下连续墙施工方法,实施例如图1所示,包括如下步骤:The invention discloses a construction method of an underground continuous wall based on BIM technology. The embodiment is shown in Fig. 1 and includes the following steps:
S1,根据项目BIM应用标准,对地下连续墙设计施工图进行三维建模,获取项目BIM模型;S1, according to the project BIM application standard, carry out 3D modeling on the design and construction drawing of the underground diaphragm wall, and obtain the project BIM model;
具体的,根据项目BIM应用标准,对设计施工图利用AutodeskRevit软件进行三维建模,获取项目BIM模型,该项目BIM模型是指地下连续墙施工项目的项目BIM模型,里面包含了地下连续墙施工所需要用到的各部件的模型,比如,该项目BIM模型中包含有:地下连续墙、导墙、地下连续墙的钢筋笼、成槽机、锁口管、履带式起重机、施工场地等等。项目BIM标准指在BIM技术在项目中的应用指南,是项目BIM应用纲领,所有参与各方均应按照该标准统一进行BIM技术应用。项目BIM标准包括:BIM应用策划、BIM建模标准、BIM交付标准、分部分项拆分标准、BIM构件命名规则等。Specifically, according to the project BIM application standard, the design and construction drawings are 3D modeling using Autodesk Revit software to obtain the project BIM model. The project BIM model refers to the project BIM model of the underground continuous wall construction project, which contains the underground continuous wall construction station. The models of the various components that need to be used, for example, the BIM model of the project includes: underground continuous walls, guide walls, reinforcement cages of underground continuous walls, trough forming machines, lock pipes, crawler cranes, construction sites, and so on. Project BIM standards refer to the guidelines for the application of BIM technology in projects, and are the project BIM application guidelines. All participating parties should uniformly apply BIM technology in accordance with this standard. Project BIM standards include: BIM application planning, BIM modeling standards, BIM delivery standards, sub-item split standards, BIM component naming rules, etc.
S2,基于所述项目BIM模型,对地下连续墙钢筋、锁口管、注浆管之间进行碰撞及错误检查,并根据检查结果对所述项目BIM模型进行调整优化;S2, based on the project BIM model, check collisions and errors among the underground diaphragm wall steel bars, lock pipes, and grouting pipes, and adjust and optimize the project BIM model according to the inspection results;
具体的,构建好BIM模型后,还需基于构建的项目BIM模型进行碰撞检查,尤其是对项目BIM模型中的地下连续墙钢筋、锁口管、注浆管之间进行 碰撞及错误检查,一旦发现错误,便可及时对模型进行调整优化,防范于未然。Specifically, after the BIM model is built, it is necessary to perform collision check based on the constructed project BIM model, especially the collision and error check between the underground diaphragm wall reinforcement, the lock pipe, and the grouting pipe in the project BIM model. If errors are found, the model can be adjusted and optimized in time to prevent them.
S3,利用所述项目BIM模型进行三维仿真,模拟施工过程;S3, using the BIM model of the project to perform three-dimensional simulation to simulate the construction process;
具体的,采用BIM三维实况模拟技术对地下连续墙的施工工况进行模拟,可提前发现施工中可能存在的问题,施工人员便可根据暴露出的问题制定相应赶工或纠偏方案,及时发现并解决问题,避免造成更大损失。此外,利用BIM技术在施工之前进行了施工模拟,还规避了施工风险及隐患。Specifically, the BIM three-dimensional live simulation technology is used to simulate the construction conditions of the underground diaphragm wall, which can discover possible problems in the construction in advance, and the construction personnel can formulate corresponding rush or correction plans according to the exposed problems, and find and solve them in time Problems, to avoid greater losses. In addition, the use of BIM technology to simulate construction before construction also avoids construction risks and hidden dangers.
S4,在现场施工过程中,根据所述项目BIM模型,对现场施工人员进行三维可视化交底;S4, during the on-site construction process, according to the BIM model of the project, perform a three-dimensional visualization of the on-site construction personnel;
具体的,利用BIM技术构建的项目BIM模型为可视化三维模型,因此,根据该模型可让现场施工人员更直观的了解到具体的方案。此外,还可以利用该项目BIM模型,制作成动画视频,从而对施工工人进行技术交底,可作为对纸质方案进行交底补充。Specifically, the BIM model of the project constructed using BIM technology is a visual three-dimensional model. Therefore, the on-site construction personnel can understand the specific plan more intuitively based on the model. In addition, the BIM model of the project can also be used to make an animated video, so as to provide technical confession to the construction workers, which can be used as a supplement to the paper plan.
采用三维可视化交底的形式,施工人员会更容易理解,交底的内容也会进行的更彻底,对于一线施工管理人员质量控制点把控也更加便捷。Using the form of three-dimensional visual confession, construction personnel will be easier to understand, the content of the confession will be carried out more thoroughly, and it will be more convenient for front-line construction managers to control the quality control points.
S5,根据所述项目BIM模型及其施工过程模拟,指导现场施工;S5, according to the project BIM model and its construction process simulation, guide the on-site construction;
具体的,施工模拟优化后,根据优化后的项目BIM模型及施工模拟,指导施工人员现场施工。Specifically, after the optimization of the construction simulation, according to the optimized BIM model of the project and the construction simulation, the construction personnel will be guided on-site construction.
S6,施工完成后,根据所述项目BIM模型进行施工验收。S6: After the construction is completed, carry out construction acceptance according to the BIM model of the project.
本实施例在地下连续墙的施工工艺中引入了BIM技术,采用BIM技术来指导地下连续墙的施工,可预判施工中出现的问题,提前发现问题,解决问题。强化了施工管理,在减少浪费缩短工期的同时,大大提高了施工质量。In this embodiment, BIM technology is introduced in the construction process of the underground continuous wall, and the BIM technology is used to guide the construction of the underground continuous wall, which can predict the problems in the construction, find the problems in advance, and solve the problems. The construction management has been strengthened, and the construction quality has been greatly improved while reducing waste and shortening the construction period.
本发明的另一实施例,如图2所示,包括:Another embodiment of the present invention, as shown in FIG. 2, includes:
S1,根据项目BIM应用标准,对地下连续墙设计施工图进行三维建模,获取项目BIM模型;S1, according to the project BIM application standard, carry out 3D modeling on the design and construction drawing of the underground diaphragm wall, and obtain the project BIM model;
具体的,所述项目BIM模型为地下连续墙施工项目的施工全过程模型;所述项目BIM模型采用的高程、坐标系统与实际一致;且所述项目BIM模型 的信息数据库中包含基本参数信息及施工信息。其中,所述基本参数信息包括:空间位置参数信息、物理尺寸信息;所述施工信息包括:施工时间信息、模型变更信息、施工材料信息、验收信息。Specifically, the project BIM model is the entire construction process model of the underground diaphragm wall construction project; the elevation and coordinate system adopted by the project BIM model are consistent with the actual situation; and the information database of the project BIM model contains basic parameter information and Construction information. Wherein, the basic parameter information includes: spatial location parameter information and physical size information; the construction information includes: construction time information, model change information, construction material information, and acceptance information.
本实施例中,引入了信息化BIM技术,利用三维模型和数字化技术形成了与实际建成情况一致的信息库。通过该信息库,可预判施工中出现的问题,提前发现问题,解决问题。强化了施工管理,在减少浪费缩短工期的同时,大大提高了施工质量。In this embodiment, the informationized BIM technology is introduced, and the three-dimensional model and digital technology are used to form an information database consistent with the actual completed situation. Through this information database, problems in construction can be predicted, problems can be discovered in advance, and problems can be solved in advance. The construction management has been strengthened, and the construction quality has been greatly improved while reducing waste and shortening the construction period.
S21,采用Revit软件或Navisworks软件对所述BIM模型中的地下连续墙钢筋、锁口管、注浆管进行碰撞及错误检查,优化所述项目BIM模型。S21, using Revit software or Navisworks software to perform collision and error checking on the underground diaphragm wall steel bars, lock pipes, and grouting pipes in the BIM model, and optimize the project BIM model.
具体的,基于构建的项目BIM模型,在AutodeskRevit软件中进行地下连续墙钢筋、锁口管、注浆管间的碰撞及错误检查,并进行调整和优化。当然,我们还可采用Navisworks软件进行碰撞检查等优化工作,但在建模阶段,直接使用Revit的碰撞检查更为方便。采用Revit里检查模型碰撞最大的优势是:不用导NWC再去检查,方便快捷,在建模时就可进行,可以即时发现问题进行调整。Specifically, based on the constructed BIM model of the project, the collision and error check between the underground diaphragm wall reinforcement, the lock pipe, and the grouting pipe are carried out in Autodesk Revit software, and adjustment and optimization are carried out. Of course, we can also use Navisworks software for collision checking and other optimization work, but in the modeling phase, it is more convenient to directly use Revit's collision checking. The biggest advantage of using Revit to check model collisions is that there is no need to guide NWC to check again, which is convenient and fast. It can be carried out during modeling, and problems can be found and adjusted immediately.
不过,Navisworks相较于Revit软件显得更专业,功能更多些,可以导出比较正式的碰撞报告,里面有构件ID号,位置、图片等信息,比较直观方便,修改后还可便于二次检查。将项目BIM模型导入到Navisworks中,通过软件进行辅助检查,并根据报告反查模型。将所有问题收集、归类,统一上报,最后根据反馈信息对该项目BIM模型进行修改调整,得到最终项目BIM模型。However, compared to Revit, Navisworks is more professional and has more functions. It can export a more formal collision report, which contains information such as component ID number, location, and pictures, which is more intuitive and convenient. After modification, it can also be convenient for secondary inspection. Import the project BIM model into Navisworks, perform auxiliary inspection through the software, and check the model according to the report. Collect, categorize, and report all the problems in a unified manner, and finally modify and adjust the project BIM model according to the feedback information to obtain the final project BIM model.
S31,采用AutodeskRevit导出所述项目BIM模型的NWC、DAE文件,并将其导入NavisWorks、Lumion软件进行施工模拟,形成3D、4D、5D施工模拟视频。S31, using Autodesk Revit to export the NWC and DAE files of the BIM model of the project, and import them into NavisWorks and Lumion software for construction simulation to form 3D, 4D, and 5D construction simulation videos.
S4,在现场施工过程中,根据所述项目BIM模型,对现场施工人员进行三维可视化交底;S4, during the on-site construction process, according to the BIM model of the project, perform a three-dimensional visualization of the on-site construction personnel;
具体的,三维可视化交底具体包括:BIM三维模型展示交底、施工4D、 5D模拟动画交底、VR沉浸式体验交底、3D打印实物交底之中的任意一种或多种。Specifically, the three-dimensional visualized presentation specifically includes: BIM three-dimensional model presentation presentation, construction 4D, 5D simulation animation presentation, VR immersive experience presentation, 3D printing physical presentation of any one or more.
采用三维可视化交底,相对于2D的平面施工图更易于接受,提高了各施工人员识图的准确性,避免因识图不准确而造成的施工误差,从而保证了施工质量,节约成本。The use of three-dimensional visualization is easier to accept than 2D plane construction drawings, which improves the accuracy of each construction personnel's recognition of the drawings, avoids construction errors caused by inaccurate recognition of the drawings, thereby ensuring the quality of construction and saving costs.
S5,根据所述项目BIM模型及其施工过程模拟,指导现场施工;具体的,现场施工包括:测量放线、导墙施工、泥浆配制、槽段开挖、清基、锁口管吊放、砼浇注、锁口拔出、墙趾注浆。S5, according to the BIM model of the project and its construction process simulation, guide the on-site construction; specifically, the on-site construction includes: measurement and setting out, guide wall construction, mud preparation, trench excavation, foundation clearing, locking pipe hoisting, Concrete pouring, lock out, wall toe grouting.
整体来说,总体工作流程为BIM建模→数据导出→技术交底→现场施工。而现场施工流程为测量放线→导墙施工→泥浆配制→槽段开挖→清基→锁口管吊放→钢筋笼吊放→砼浇注→锁口拔出→墙趾注浆→验收。On the whole, the overall workflow is BIM modeling → data export → technical disclosure → on-site construction. The on-site construction process is measuring line setting → guide wall construction → mud preparation → trough excavation → foundation clearance → lock pipe hoisting → steel cage hoisting → concrete pouring → lock pulling out → wall toe grouting → acceptance.
S61,将所述项目BIM模型与现场实物外观进行对比;检查地下连续墙外观是否合格;S61: Compare the BIM model of the project with the physical appearance of the site; check whether the appearance of the underground diaphragm wall is qualified;
S62,将所述项目BIM模型数据与现场实测实量数据进行对比,检查地下连续墙的质量是否合格。S62: Compare the BIM model data of the project with the actual measured data on site, and check whether the quality of the underground diaphragm wall is qualified.
本实施例利用BIM技术构建了地下连续墙项目的项目BIM模型,基于该模型实现了地下连续墙施工信息集成管理、三维可视化交底、模型复核对比验收,大大提高了施工质量和精度。This embodiment uses BIM technology to construct a project BIM model of an underground continuous wall project. Based on this model, it realizes integrated management of underground continuous wall construction information, three-dimensional visualization, model review and comparison and acceptance, which greatly improves construction quality and accuracy.
本发明的另一实施例,在上述任一实施例的基础上,在步骤S2之后、步骤S5之前还包括:Another embodiment of the present invention, on the basis of any of the foregoing embodiments, further includes after step S2 and before step S5:
S25,导出所述项目BIM模型的模型数据,指导施工准备;具体包括:S25, export the model data of the BIM model of the project to guide construction preparation; specifically including:
(1)基于所述项目BIM模型,导出钢筋及混凝土的工程量,指导施工材料采购;如此,便可方便采购进行采购,及后续的造价成本分析。(1) Based on the BIM model of the project, the engineering quantities of steel and concrete are derived to guide the procurement of construction materials; in this way, it is convenient to purchase for procurement and subsequent cost analysis.
(2)将所述项目BIM模型的钢筋笼模型数据导入自动化设备,指导所述自动化设备对钢筋笼的生产加工;(2) Import the steel cage model data of the BIM model of the project into the automation equipment, and guide the production and processing of the steel cage by the automation equipment;
具体的,利用构建的项目BIM模型与自动化加工设备进行信息数据交换, 相关数据导入自动化设备后能够直接进行立柱钢模板的生产。实现了钢筋构件精细化加工生产。Specifically, the constructed project BIM model is used to exchange information and data with the automated processing equipment, and the relevant data can be directly imported into the automated equipment to directly produce the column steel template. Realize the refined processing and production of reinforced components.
(3)将所述项目BIM模型的高程、坐标系统数据导出至全站仪,指导现场进行测量放样;(3) Export the elevation and coordinate system data of the BIM model of the project to the total station to guide the site to carry out measurement and stakeout;
全站仪,即全站型电子测距仪(Electronic Total Station),是一种集光、机、电为一体的高技术测量仪器,全站仪是全站型电子速测仪的简称,是电子经纬仪、光电测距仪及微处理器相结合的光电仪器。将项目BIM模型内高程数据、坐标系统数据导出到全站仪,则可现场指导测量放样,高效快捷,且不容易出错。The total station, that is, the Electronic Total Station (Electronic Total Station), is a high-tech measuring instrument that integrates light, machine, and electricity. The total station is the abbreviation of the total station electronic tachometer. An optoelectronic instrument that combines an electronic theodolite, a photoelectric rangefinder and a microprocessor. Exporting the elevation data and coordinate system data in the project BIM model to the total station can guide the measurement and stakeout on site, which is efficient and fast, and is not easy to make mistakes.
(4)基于所述项目BIM模型,导出二维CAD图纸,便于后续进行施工指导。(4) Based on the project BIM model, export two-dimensional CAD drawings to facilitate subsequent construction guidance.
本发明的另一实施例,如图3所示,在上述任一实施例的基础上,在验收通过后,根据验收信息优化修改所述项目BIM模型,形成地下连续墙施工完成模型,也就是竣工模型。Another embodiment of the present invention, as shown in FIG. 3, on the basis of any of the above embodiments, after the acceptance is passed, the BIM model of the project is optimized and modified according to the acceptance information to form an underground continuous wall construction completion model, that is As-built model.
此外,在上述任一实施例的基础上,利用项目BIM模型,进行三维仿真,模拟施工过程,除了对施工工况等进行仿真模拟外,还可进行施工进度模拟和施工组织模拟。In addition, on the basis of any of the above-mentioned embodiments, the project BIM model is used to perform three-dimensional simulation to simulate the construction process. In addition to simulating construction conditions, it can also perform construction schedule simulation and construction organization simulation.
施工进度模拟:模拟技术可以在项目建造过程中合理制定施工计划、4D精确掌握施工进度,优化使用施工资建筑施工是一个高度动态的过程,随着建筑工程规模不断扩大,复杂程度不断提高,使得施工项目管理变得极为复杂。通过将BIM与施工进度计划相链接,将空间信息与时间信息整合在一个可视的4D(3D+Time)模型中,可以直观、精确地反映整个建筑的施工过程。施工源以及科学地进行场地布置,对整个工程的施工进度、资源和质量进行统一管理和控制,以缩短工期、降低成本、提高质量。Construction schedule simulation: Simulation technology can make reasonable construction plans during the project construction process, accurately grasp the construction schedule in 4D, and optimize the use of construction resources. Construction is a highly dynamic process. As the scale of construction projects continues to expand, the complexity continues to increase, making Construction project management has become extremely complicated. By linking BIM with the construction schedule, and integrating spatial information and time information into a visual 4D (3D+Time) model, the construction process of the entire building can be reflected intuitively and accurately. The construction source and the scientific site layout, unified management and control of the construction schedule, resources and quality of the entire project, in order to shorten the construction period, reduce costs, and improve quality.
施工组织模拟:通过BIM可以对项目的重点或难点部分进行可建性模拟,按月、日、时进行施工安装方案的分析优化,对于一些重要的施工环节或采用 新施工工艺的关键部位、施工现场平面布置等施工指导措施进行模拟和分析,以提高计划的可行性。施工方可以进一步对原有安装方案进行优化和改善,以提高施工效率和施工方案的安全性。Construction organization simulation: Through BIM, the key or difficult part of the project can be simulated for buildability, and the construction and installation plan can be analyzed and optimized on a monthly, daily, and hourly basis. For some important construction links or key parts and constructions that adopt new construction techniques Simulate and analyze construction guidance measures such as site layout to improve the feasibility of the plan. The construction party can further optimize and improve the original installation plan to improve the construction efficiency and the safety of the construction plan.
尽管已描述了本发明的优选实施例,但本领域内的技术人员一旦得知了基本创造性概念,则可对这些实施例作出另外的变更和修改。所以,所附权利要求意欲解释为包括优选实施例以及落入本发明范围的所有变更和修改。Although the preferred embodiments of the present invention have been described, those skilled in the art can make additional changes and modifications to these embodiments once they learn the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present invention.
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. In this way, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalent technologies, the present invention is also intended to include these modifications and variations.

Claims (10)

  1. 一种基于BIM技术的地下连续墙施工方法,其特征在于,包括如下步骤:A construction method of underground continuous wall based on BIM technology is characterized in that it comprises the following steps:
    S1,根据项目BIM应用标准,对地下连续墙设计施工图进行三维建模,获取项目BIM模型;S1, according to the project BIM application standard, carry out 3D modeling on the design and construction drawing of the underground diaphragm wall, and obtain the project BIM model;
    S2,基于所述项目BIM模型,对地下连续墙钢筋、锁口管、注浆管之间进行碰撞及错误检查,并根据检查结果对所述项目BIM模型进行调整优化;S2, based on the project BIM model, check collisions and errors among the underground diaphragm wall steel bars, lock pipes, and grouting pipes, and adjust and optimize the project BIM model according to the inspection results;
    S3,利用所述项目BIM模型进行三维仿真,模拟施工过程;S3, using the BIM model of the project to perform three-dimensional simulation to simulate the construction process;
    S4,在现场施工过程中,根据所述项目BIM模型,对现场施工人员进行三维可视化交底;S4, during the on-site construction process, according to the BIM model of the project, perform a three-dimensional visualization of the on-site construction personnel;
    S5,根据所述项目BIM模型及其施工过程模拟,指导现场施工;S5, according to the project BIM model and its construction process simulation, guide the on-site construction;
    S6,施工完成后,根据所述项目BIM模型进行施工验收。S6: After the construction is completed, carry out construction acceptance according to the BIM model of the project.
  2. 根据权利要求1所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,所述步骤S2具体包括:The construction method of an underground continuous wall based on BIM technology according to claim 1, wherein the step S2 specifically includes:
    S21,采用Revit软件对所述项目BIM模型中的地下连续墙钢筋、锁口管、注浆管进行碰撞及错误检查;或S21, using Revit software to check the collision and error of the underground diaphragm wall steel bar, the lock pipe, and the grouting pipe in the BIM model of the project; or
    S22,将所述项目BIM模型导入Navisworks中,通过所述Navisworks软件对所述BIM模型中的地下连续墙钢筋、锁口管、注浆管进行碰撞及错误检查。S22: Import the project BIM model into Navisworks, and perform collision and error checking on the underground diaphragm wall steel bars, lock pipes, and grouting pipes in the BIM model through the Navisworks software.
  3. 根据权利要求1所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,所述项目BIM模型为地下连续墙施工项目的施工全过程模型;所述项目BIM模型采用的高程、坐标系统与实际一致;且所述项目BIM模型的信息数据库中包含基本参数信息及施工信息。The construction method of an underground continuous wall based on BIM technology according to claim 1, characterized in that the project BIM model is the whole construction process model of the underground continuous wall construction project; the elevation and coordinates used in the project BIM model The system is consistent with reality; and the information database of the project BIM model contains basic parameter information and construction information.
  4. 根据权利要求3所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,所述基本参数信息包括:空间位置参数信息、物理尺寸信息;所述施工信息包括:施工时间信息、施工进度信息、模型变更信息、施工材料信息、验收信息。The construction method of an underground continuous wall based on BIM technology according to claim 3, characterized in that, the basic parameter information includes: spatial position parameter information, physical size information; the construction information includes: construction time information, construction Progress information, model change information, construction material information, and acceptance information.
  5. 根据权利要求1所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,还包括:The construction method of an underground continuous wall based on BIM technology according to claim 1, characterized in that it further comprises:
    S25,导出所述项目BIM模型的模型数据,指导施工准备;具体包括以下任意一项或多项:S25, export the model data of the BIM model of the project to guide construction preparation; specifically including any one or more of the following:
    基于所述项目BIM模型,导出钢筋及混凝土的工程量,指导施工材料采购;Based on the BIM model of the project, derive the engineering quantities of steel and concrete, and guide the procurement of construction materials;
    将所述项目BIM模型的钢筋笼模型数据导入自动化设备,指导所述自动化设备对钢筋笼的生产加工;Import the steel cage model data of the BIM model of the project into the automation equipment, and guide the production and processing of the steel cage by the automation equipment;
    将所述项目BIM模型的高程、坐标系统数据导出至全站仪,指导现场进行测量放样;Export the elevation and coordinate system data of the BIM model of the project to the total station to guide the site to carry out measurement and stakeout;
    基于所述项目BIM模型,导出二维CAD图纸。Based on the BIM model of the project, a two-dimensional CAD drawing is derived.
  6. 根据权利要求1所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,所述步骤S3具体包括:The construction method of an underground continuous wall based on BIM technology according to claim 1, wherein the step S3 specifically includes:
    S31,采用AutodeskRevit导出所述项目BIM模型的NWC、DAE文件,并将其导入NavisWorks、Lumion软件进行施工模拟,形成3D、4D、5D施工模拟视频。S31, using Autodesk Revit to export the NWC and DAE files of the BIM model of the project, and import them into NavisWorks and Lumion software for construction simulation to form 3D, 4D, and 5D construction simulation videos.
  7. 根据权利要求1所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,所述步骤S4中的三维可视化交底具体包括:BIM三维模型展示交底、施工4D、5D模拟动画交底、VR沉浸式体验交底、3D打印实物交底之中的任意一种或多种。The construction method of an underground continuous wall based on BIM technology according to claim 1, wherein the three-dimensional visualization presentation in step S4 specifically includes: BIM three-dimensional model presentation presentation, construction 4D, 5D simulation animation presentation, VR Any one or more of immersive experience confession and 3D printing physical confession.
  8. 根据权利要求1所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,所述步骤S6具体包括:The construction method of an underground continuous wall based on BIM technology according to claim 1, wherein the step S6 specifically includes:
    S61,将所述项目BIM模型与现场实物外观进行对比;检查地下连续墙外观是否合格;S61: Compare the BIM model of the project with the physical appearance of the site; check whether the appearance of the underground diaphragm wall is qualified;
    S62,将所述项目BIM模型数据与现场实测实量数据进行对比,检查地下连续墙的质量是否合格。S62: Compare the BIM model data of the project with the actual measured data on site, and check whether the quality of the underground diaphragm wall is qualified.
  9. 根据权利要求1所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,所述步骤S5中的现场施工包括:测量放线、导墙施工、泥浆配制、槽段开挖、清基、锁口管吊放、砼浇注、锁口拔出、墙趾注浆。The construction method of an underground continuous wall based on BIM technology according to claim 1, characterized in that, the on-site construction in step S5 includes: measuring and setting out, guide wall construction, mud preparation, trench excavation, cleaning The foundation and the lock pipe are hoisted, concrete is poured, the lock is pulled out, and the wall toe is grouted.
  10. 根据权利要求1-9任一项所述的一种基于BIM技术的地下连续墙施工方法,其特征在于,还包括步骤:The construction method of an underground continuous wall based on BIM technology according to any one of claims 1-9, characterized in that it further comprises the steps of:
    S7,验收通过后,根据验收信息优化修改所述项目BIM模型,形成地下连续墙施工完成模型。S7: After the acceptance is passed, the BIM model of the project is optimized and modified according to the acceptance information to form a completion model of the underground continuous wall construction.
PCT/CN2020/087080 2019-12-24 2020-04-26 Bim technology-based method for constructing underground continuous wall WO2021128675A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201911343356.4A CN111062081A (en) 2019-12-24 2019-12-24 Underground continuous wall construction method based on BIM technology
CN201911343356.4 2019-12-24

Publications (1)

Publication Number Publication Date
WO2021128675A1 true WO2021128675A1 (en) 2021-07-01

Family

ID=70302677

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/087080 WO2021128675A1 (en) 2019-12-24 2020-04-26 Bim technology-based method for constructing underground continuous wall

Country Status (2)

Country Link
CN (1) CN111062081A (en)
WO (1) WO2021128675A1 (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111062081A (en) * 2019-12-24 2020-04-24 上海浦兴路桥建设工程有限公司 Underground continuous wall construction method based on BIM technology
CN111945706B (en) * 2020-07-10 2021-08-27 上海市隧道工程轨道交通设计研究院 Distribution algorithm for single-side stressed steel bars of underground continuous wall adopting two types of steel bars
CN111663783B (en) * 2020-07-16 2021-09-07 广州城建职业学院 Assembly type building concrete pouring device based on BIM
CN111794364A (en) * 2020-07-16 2020-10-20 中建八局科技建设有限公司 Double-layer plate fine plain concrete construction method
CN112252301A (en) * 2020-10-10 2021-01-22 无锡市市政设施建设工程有限公司 Method for realizing underground continuous wall groove jumping construction based on BIM
CN112252302A (en) * 2020-10-10 2021-01-22 无锡市市政设施建设工程有限公司 Method for realizing split hoisting of underground continuous wall special-shaped steel reinforcement cage into groove based on BIM
CN112487541A (en) * 2020-12-17 2021-03-12 中建一局集团建设发展有限公司 Underground continuous wall reinforcement cage manufacturing and hoisting construction method
CN114673139A (en) * 2020-12-25 2022-06-28 马超 Water conservancy construction pipe pile installation construction process
CN112966326A (en) * 2021-03-09 2021-06-15 金华电力设计院有限公司 Method for simulating electric power construction
CN113094782A (en) * 2021-03-18 2021-07-09 上海市水利工程设计研究院有限公司 Deep foundation pit quality supervision method
CN113221209A (en) * 2021-04-08 2021-08-06 中国电建集团华东勘测设计研究院有限公司 Undercurrent wetland BIM model creation method and undercurrent wetland construction method
CN113269411A (en) * 2021-05-08 2021-08-17 成都亲生命科技有限公司 Decoration system based on internet technology assembly decoration construction and convenient for customer quality inspection
CN113553644A (en) * 2021-07-13 2021-10-26 中国二冶集团有限公司 Method for optimizing excavation and support of subway station foundation pit based on BIM simulation
CN114266087A (en) * 2021-10-14 2022-04-01 中国建筑第二工程局有限公司 Thin-shell structure formwork system construction method and management system based on BIM technology
CN114622545A (en) * 2022-03-10 2022-06-14 中交第二航务工程局有限公司 Closed-width underground continuous wall reinforcement cage matching manufacturing method
CN114840899B (en) * 2022-05-17 2022-12-13 中国建筑第二工程局有限公司 BIM-based three-dimensional scanning earthwork balance analysis method and device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN106381866A (en) * 2016-08-31 2017-02-08 中铁二局工程有限公司 Construction method of ultra-deep underground diaphragm wall in water-rich soft-soil area
CN109972609A (en) * 2019-04-09 2019-07-05 西南林业大学 A kind of railway traffic engineering construction method of underground continuous wall
CN110080114A (en) * 2019-05-20 2019-08-02 上海浦东路桥建设股份有限公司 A kind of visualization prefabricated stand column construction method based on BIM technology
CN111062081A (en) * 2019-12-24 2020-04-24 上海浦兴路桥建设工程有限公司 Underground continuous wall construction method based on BIM technology

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN106381866A (en) * 2016-08-31 2017-02-08 中铁二局工程有限公司 Construction method of ultra-deep underground diaphragm wall in water-rich soft-soil area
CN109972609A (en) * 2019-04-09 2019-07-05 西南林业大学 A kind of railway traffic engineering construction method of underground continuous wall
CN110080114A (en) * 2019-05-20 2019-08-02 上海浦东路桥建设股份有限公司 A kind of visualization prefabricated stand column construction method based on BIM technology
CN111062081A (en) * 2019-12-24 2020-04-24 上海浦兴路桥建设工程有限公司 Underground continuous wall construction method based on BIM technology

Also Published As

Publication number Publication date
CN111062081A (en) 2020-04-24

Similar Documents

Publication Publication Date Title
WO2021128675A1 (en) Bim technology-based method for constructing underground continuous wall
CN106202723A (en) A kind of BIM subway work method
CN109785436A (en) A kind of management method of the reinforcing bar information Life cycle based on BIM technology
Zhou et al. Utilizing IFC for shield segment assembly in underground tunneling
CN109885966A (en) The method of the conflict of sliding slot section of jurisdiction and preferred arrangement based on BIM technology
CN108416162A (en) A kind of construction method of the spiral formula reinforced concrete structure based on BIM
CN110080114A (en) A kind of visualization prefabricated stand column construction method based on BIM technology
KR20130016620A (en) 3d process management method for bim(building information modeling)
CN111950067B (en) BIM-based earth and rockfill dam construction progress dynamic visual simulation method
CN109583149A (en) Super large lid rolling stock section in-depth modernization system and its construction method based on BIM management
CN110990914A (en) BIM technology-based large boiler installation method
CN109183785A (en) A kind of Construction of Engineering Pile method based on BIM
CN110909407A (en) Cave laboratory and vertical shaft BIM model creation method based on BIM
CN109933900A (en) A kind of construction three dimensional field cloth modeling method based on BIM technology
CN114997584A (en) BIM visualization-based high arch dam construction full life cycle dynamic simulation analysis method
CN111125820B (en) BIM+GIS-based construction site space virtual construction method
CN111597625A (en) Foundation pit support excavation quality control method based on BIM
Rui et al. Construction project management based on building information modeling (Bim)
CN110634186A (en) Arch cover method underground excavation construction method based on BIM
CN108984876A (en) A kind of service sleeve automation modeling method and system based on BIM
CN209486723U (en) A kind of construction management application platform based on BIM technology application
CN116070311A (en) BIM forward design method for long and large bridge
CN115577422A (en) BIM (building information modeling) forward design method for unequal-depth foundation pit group of near-operation subway
Tian et al. Research on the application of BIM technology in bridge engineering
Yang Application of BIM during lean construction of high-rise buildings

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20908268

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20908268

Country of ref document: EP

Kind code of ref document: A1